How to Streamline the Public Participation

Process

José Luis CáceresSACOG

(916) [email protected]

g

Anne JensenSCRTPA

(530) [email protected]

.ca.us

The Current PPP Process

• Maximizing efficiency

• Meeting requirements without excess procedure

Identifying where the PPP can be streamlined

• Shortening amendment time

• Appropriate length of public review period

SACOG’s Example

• Public review period can often be as little as 7 days

• SACOG model separates amendments into 5 types

Type 1: Administrative Modification

• No public review period required

• Requires only manager approval

Type 2: Formal Amendment due to Funding Changes

Funding change is greater than allowed per Caltrans’ administrative procedures.

• Public review period required is 7 days

• Requires manager approval only

Type 3: Formal Amendments of Exempt

ProjectsAmendment of an exempt or non-

capacity increasing project• e.g., add/delete exempt or non-

regionally significant project or project phases to/from the FTIP.

• Public review period is 7 days

• Requires manager approval only

Type 4: Formal Amendment requiring a

conformity determination

These amendments require conformity determination but rely on a previous Regional Emissions Analysis

• Public review period is 7 days

• Public hearing is required

• Require Board approval

Type 5: Formal Amendment requiring a

conformity determination and new

Regional Emissions Analysis

• Public review period is 30 days

• Requires a public hearing

• Requires Board approval

Interagency Consultation

• Circulate preliminary draft

• Federal and state agencies

• Keep in touch with stakeholders

Implementing Change• Amend your PPP (following public

outreach requirements)• Decide on a spectrum of options

with varying public review• Delegate approval as much as

possible• Decide what works best for your

region• Take advantage of Grouped Project

Listings

Possible Conflicts with Streamlining the PPP

• Board won’t delegate power

• Agency’s TIP history

• Level of difficulty in amending the PPP

Any questions?