How Can I Make Our Weekly Maintenance Scheduling Meetings More Productive

Embed Size (px)

Citation preview

  • 8/22/2019 How Can I Make Our Weekly Maintenance Scheduling Meetings More Productive

    1/1

    7/22/13 How can I make our weekly maintenance scheduling meetings more productive? :: Planning & Scheduling :: Resource Library :: Life Cycle Engineering

    www.lce.com/How_can_I_make_our_weekly_maintenance_scheduling _meetings_more_productive_518-item.html 1/1

    http://www.lce.com/How_can_I_make_our_weekly_maintenance_scheduling_meetings_more_productive_518-item.html

    Articles Index >> Planning & Scheduling

    How can I make our weekly maintenance scheduling meetings more productive?

    By Tim Kister, CMRP, Life Cycle EngineeringAs appeared in the June Edition ofRxToday

    Q: We have a weekly scheduling meeting to establish our maintenance schedule for the following week. This meeting doesnt seem to be as productive as

    we feel it should be. How long should this meeting take and who should attend?

    A: There are several factors to consider. First, you need to clearly define the objective of the meeting. This meeting is for final schedule negotiations that

    consider operations ability to grant access to equipment for which maintenance has identified ready work and sufficient labor to complete the work. This

    meeting does not address planning issues.

    Second, the meeting should last one hour or less, based on all parties coming to the meeting fully prepared. This meeting is not to start the scheduling

    process but to finalize the schedule.

    Third, only those individuals that have specific responsibilities in the scheduling process should attend the meeting. They would include Planner/Schedulers,

    Maintenance supervision and an Operations representative. The Operations representative must have knowledge of the production schedule, the

    authorization to grant equipment/process downtime and the support of Operations management to back his decisions. Typically this position is called anOperations/Maintenance Coordinator (OMC). Any additional attendees are only on an as-needed support role basis .

    Tim Kister, CMRP, is a well-recognized leader in the field of Planning & Scheduling. A dedicated educator, Tim has facilitated over 100 workshops and

    seminars focused on maintenance management and planning & scheduling and has co-authored the book, Maintenance Planning and Scheduling

    Handbook; Streamlining Your Organization for a Lean Environment. As Planning & Scheduling Subject Matter Expert for Life Cycle Engineering (LCE), Tim

    helps clients recognize opportunities for improvement that enable rapid optimization of business processes and long-term sustainability. You can reach Tim

    at [email protected].

    2011 Life Cycle Engineering, Inc.

    ForMore Information

    843.744.7110 | [email protected]

    2013 Life Cycle Engi neering Al l rights reserved. | 4360 Corporate Road, Charleston, SC 29405 | 843.744 .7110

    http://www.lce.com/How_can_I_make_our_weekly_maintenance_scheduling_meetings_more_productive_518-item.htmlmailto:[email protected]://www.lce.com/http://www.lce.com/http://www.lce.com/http://www.lce.com/mailto:[email protected]:[email protected]://www.lce.com/eNewsletters_62.htmlhttp://www.lce.com/Planning_Scheduling_Articles_337.html?cat=Planning+%26+Schedulinghttp://www.lce.com/Articles_59.htmlhttp://www.lce.com/How_can_I_make_our_weekly_maintenance_scheduling_meetings_more_productive_518-item.html