Hospital Revitalization Grant Hospital Revitalization Grant Infrastructure Performance Review : Western Cape Infrastructure Performance Review : Western Cape
April-September 2010April-September 2010
Presentation to Select Committee Presentation to Select Committee on Appropriationson Appropriations
20 October 201020 October 2010
Hospital Revitalization GrantPresentation Outline
1. Programme Overview2. Budget spending for first two quarters3. Expected Budget Performance for year4. Inter-departmental Reporting and Co-
ordination 5. Performance of Contractors &
Consultants6. Project Monitoring and Co-ordination7. Capacity to implement HRP Grant
programme
Hospital Revitalization GrantProgramme Overview
• 3 Projects completed (in retention, final account)
• 7 Projects under construction
• 3 Projects in planning
Hospital Rationalization Grant: Budget spending
for first two quarters 2010/11
INSTITUTE SERVICE2010/11 BUDGET
Apr-SeptEXP.
PRED. EXP.
COMMENTS
R m R m R m
1 George Hospital Upgrade Phase 3 28,750 13,271 26,885 Construction 44% Complete
2 Khayelitsha Hospital New Hospital 191,103 109,597 245,616 Construction 50% Complete
3 Mitchells Plain Hospital New Hospital 120,500 32,989 92,251 Construction 10% Complete
4 Paarl Hospital Hospital Upgrade 90,000 61,232 88,688 Construction 94% Complete
5 Paarl Hospital New Psychiatric Block 2,000 0 1,830 Planning Stage 1
6 Paarl TC Newman Hosp CHC Upgrade 16,000 12,127 18,685 Construction 80% Complete
7 Valkenberg Hospital Hospital Upgrading 6,500 0,085 2,665 Planning Stage 1
8 Valkenberg Hospital Emergency Repairs to Admin 1,500 3,207 3,207 Retention / Final Account
9 Vredenburg Hospital Phase 1B - Internal Work 0,020 0,266 288 Retention / Final Account
10 Vredenburg Hospital Phase 2A - Upgrading 11,000 6,726 13,858 Construction 78% Complete
11 Vredenburg Hospital Phase 2B - Upgrading 8,000 2,158 4,282 Planning (Stage 3)
12 Worcester Hospital Phase 3 - Upgrading 0 0,924 2,624 Retention / Final Account
13 Worcester Hospital Phase 4 - Upgrading 30,000 11,637 30,936 Construction 45% Complete
Total 505,373 255,509 533,106R27.7m projected over- expenditure
Roll-over funds of R42,8m excluded
Hospital Revitalization GrantExpected Budget Performance for 2010/11
Budget R 505 573 000
Predicted over-expenditure
R 27 733 000
Roll-over(to be confirmed)
R 42 774 000
Predicted under-expenditure (roll-over included)
R 15 041 000
Hospital Revitalization GrantInter-departmental Reporting and Co-
ordination
Projects• Site visits by DTPW project team at least once a
month• Monthly project site meetings (DTPW, DoH,
Contractor and Consultants) • Rational Programme Management (RPM) system for
recording project
Programme• Monthly progress meetings information and progress
between DTPW, DoH and Treasury• Daily informal contact• Monitoring by Treasury with reports to National
Hospital Revitalization GrantPerformance of Contractors and
Consultants
• Good contractor performances in general– Quality – strictly controlled– Adherence to programme – mostly on schedule - Khayelitsha and Mitchell’s Plain: early completion
- Vredenburg Ph 2A: slight delay expected - Worcester Ph 4: lagging - JV seems to be problematic
• Consultants generally competent– Input / guidance required from DTPW
professionals varies across disciplines and projects
Hospital Revitalization GrantProject Monitoring and Co-ordination
• Co-ordination between Principal Agent (or Project Manager on larger projects) and internal Project Co-ordinator
• DoH Project Manager• Clerk of Works provides daily on site quality
control and co-ordination with DoH Project Manager and Principal Agent
Hospital Revitalization GrantProgramme Implementation Capacity
• Sufficient capacity for HRP Programme• Large number of capital projects places professional staff under high work
load stress.
• Micro-structure being finalised- IDIP assessment of capacity requirements- HR Plan Developed to increase built sector professional staff
• Architectural –Fully staffed • Quantity Surveying – fully staffed• Electrical Engineering – two vacant posts• Mechanical Engineering – two vacant posts • Civil & Structural – two vacant posts
• Number of built sector professionals have been appointed additional to the establishment in order to attend to the internal capacity
BUILT SECTOR PROFESSIONALS
CATEGORY OF EMPLOYMENT QUANTITY TOTAL
Architects Permanent RegisteredContract RegisteredCubanRetired Professional registered Consultant Registered
4 3121
11 FULL CAPACITY
Quantity Surveyors Permanent RegisteredPermanent CandidateContract CandidateCubansRetired Professional ConsultantQs In Training Student Candidate
3 4 1 0001
9 FULL CAPACITY
Electrical Engineers Permanent RegisteredContract Registered As Candidate EngineerCubanRetired Professional Registered EngineerConsultant Registered Engineer
12111
6 2 VACANT ELECTRICAL ENGINEERS POST
Mechanical Engineers Permanent Registered Engineer Contract Registered As Candidate EngineerCubanRetired Professional Registered Engineer Consultant Registered Technician
14111
8 2 VACANT MECHANICAL ENGINEERS POST
Civil &Structural Engineers Permanent Registered EngineerContract Registered As Candidate EngineerCubanRetired Professional Registered EngineerConsultant
11130
6 2 VACANT CIVIL & STRUCTURAL ENGINEER POST
40 6 VACANT BUILT SECTOR PROFESSIONAL POST