HORNSBY KU-RING-GAI HOSPITAL REDEVELOPMENT - STAGE 2
COMMUNITY NEWSLETTER | JULY 2020 | ISSUE #7
WWW.NSLHD.HEALTH.NSW.GOV/HOSPITALS/HORNSBY
A MOMENT IN TIMEPAGE 2
NEW PATIENT
CHECK-IN KIOSKSPAGE 2
PHOTOGRAPHERS WANTEDPAGE 3
HKH STAGE 2 REDEVELOPMENT COMMUNITY NEWS | ISSUE 7| JULY 20202
PATIENTS TRIAL A NEW ARRIVAL SYSTEMA new program designed to improve patient flow is being piloted in the Bernard Curran Rehabilitation Unit, the first of its kind within the Northern Sydney Local Health District.The redevelopment has created an opportunity to build an integrated outpatient service, centrally managed from a common reception desk near the new entrance foyer of the hospital.
The Patient Queue Management System (PQMS) pilot, which was implemented recently, will allow the system to be tried and tested prior to the move to the new building.
Patient arrival kiosks and calling screens will be installed and a new application will be used by clinicians and clerical staff to manage the patient journey. Patients with pre-booked appointments will register their arrival and confirm their details using the touchscreen on the patient arrival kiosk. A ticket will be produced with the patient’s appointment times and clinician details.
Patients can also opt to receive updates regarding their appointment via SMS. The patient may choose to stay in the waiting room or wait elsewhere and return when they are called back to the clinic.
When the redevelopment is completed patients will have the
TIME CAPSULE UNEARTHED A time capsule from the 1930s has been unearthed.The glimpse into the past was found when building 2 was demolished to make way for the Stage 2 redevelopment.Inside the capsule were floor plans of the original hospital, six annual reports and two newspapers dated 8 December 1932.Redevelopment Transition Manager Adrienne Stern said the capsule was placed in copper guttering and attached to the plaque that was laid on 10 December 1932 by Minister for Health and Secretary for Public Works, Reginald Weaver.“It is a wonderful find especially as we are building a hospital for the future,” Ms Stern said.The redevelopment team is looking to place the contents of the time capsule into a box frame for display in the new building.
option to enjoy the retail space, florist & coffee shop while they wait for their appoinment in the new building. Wayfinding will be available on the arrival kiosk to help patients navigate through the new facility. Patients will also have the ability to provide feedback of their visit at the kiosk. The kiosk has been programed with the top five languages for the Hornsby Ku-ring-gai area as identified through NSW Census data.
WWW.NSLHD.HEALTH.NSW.GOV.AU 3
FOLLOW US:@hornsbyhospital
Thank you for your patienceThe redevelopment project team thanks you for your patience while we build the community a new state-of-the-art hospital.
For enquiries or feedback, contact [email protected]
Ph: 9978 5999
WWW.NSLHD.HEALTH.NSW.GOV.AU
CALLING ALL PHOTOGRAPHERSPicture yourself a photographer?
We are inviting amateur
photographers to contribute to the
permanent art collection for the new
Clinical Services Building.
We want photos that show what
inspires you about living and/or
working in the Hornsby Ku-ring-gai
community. We would like to see
images of the amazing bushland,
plant and bird life. The first prize
winner will receive a $250 Westfield
voucher and finalists will have their
photographs displayed in the new
building.
The competition is open to all staff,
patients and the community.
Visit www.nslhd.health.nsw.gov.au/
hospitals/hornsby for information on
how to enter.
Northern Sydney Local Health District
youtubeThe 30,000sqm building is taking
shape with the eastern facade now
fully exposed.
The building is being fitted with
plumbing and airconditioning,
while ceilings and flooring is being
installed.
The new Pharmacy Department
is progressing with staff looking
forward to moving in later in the
year.
Work is also underway on the
expansion of the Emergency
Department.
Visitors and patients will notice a
change to the location of the cafe,
which will move to the foyer of the
STAR building from mid-August.
The current building where switch
and the cafe are located will be
demolished to make way for the
new entrance to the hospital.
The cafe will be relocated in
August to the STAR building
foyer, while the switchboard has
temporarily moved to the Lumby
building.
STAGE 2 REDEVELOPMENT CONSTRUCTION UPDATE
FOLLOW US:@nthsydhealth
HKH STAGE 2 REDEVELOPMENT COMMUNITY NEWS | ISSUE 7 | JULY 20204
Above: Aerial view of Hornsby Ku-ring-gai Hospital stage 2 redevelopment from Palmerston Rd. Taken June 2020
Above: Aerial view of Hornsby Ku-ring-gai Hospital stage 2 redevelopment from Derby Rd Taken June 2020