Upload
others
View
10
Download
1
Embed Size (px)
Citation preview
HORIZONTAL
RAISE BORING
Topics
Overview of methods and technology
Common aplications
Project-specific experiences
Hitting the target
Raiseboring concept
The pilot hole is (normally) drilled down to a lower level, diameter 250 – 310mm
A reamer with a larger diameter than the pilot hole is attached to the drill string
The pilot hole is then reamed to the final diameter
Raiseboring equipment
Drillsite
Tri-cone pilot bit and drill pipe (drill string)
Stabilizers
Bit Reamer Stabilizer
Six-Rib Stabilizer
Reamer, cutter and cutter
housing (saddle)
Technology and methods
The raiseboring machine provides thrust and rotation for crushing the rock
During pilot hole drilling, the materials (cuttings) are removed by flushing water through the hollow core (4 ¾”) of the drill string, forcing them out the annular space between the drill string and the rock wall
During reaming, the materials fall by gravity, or are flushed out with water on horizontal/low angle holes or mecanical scraper
The raiseboring method is only for use in rock, hard or soft
Equipment Capacities
Our company’s machines can drill up to 600 meters (+)
We have reamer sizes from 440 mm to 3100 mm
Machines can be set up to drill in any angle, from vertical to horizontal
Our machines can be dissassembled and transported by helicopter
Equipment is heavy: drill string weighs 200 kg/meter, machine from 9 - 13 tonnes,
”Blind hole” drilled for nuclear storage facility
Nuclear power station, Aspo
Oscarshamn, Sweden.Horizontal tunnel for deposit of
nuclear waste.
Inclination: 1,8 grader
Diameter: 1,8 meter
Length: 95 meter and 15 meter
The drifts are situated 220 m
below the surface.
Project site without road accessSauda Hydro Power Project, Istjønna.L=410m Ø=1060mm Inclination=2%
Drilling river intakes for small hydro power projects
Directional guidance to hit the target
Advanced survey instruments are used to track the position of the pilot hole
By using special drill pipes (stabilizers), regulating thrust and rotation, and amount of bailing water, the vertical direction of the pilot hole can be controlled to minimize deviation from the target
Horizontal deviation cannot be controlled when using traditional raise boring equipment. Deviations of 0-2% of the length can be experienced.
Combination of drilled tunnel and D&B tunnel:
Pilot hole is completed before D&B tunnel, pilot hole location is surveyed, and D&B tunnel direction is adjusted to meet the pilot hole
Directional drilling…?
If the target requirements are very stringent, the pilot hole can be drilled with a directional drilling system
Different methods
Directional core drilling, that is in turn reamed to larger diameter
Use of mud motor with bent sub (North-Sea drilling)
Advanced stabilizers
Stringent target requirements adds significant costs and completion times to the project:
Pilot hole is drilled in several steps
More than one drill rig
Success of any directional drilling method is dependent on rock type, hardness, stratification, weak zones, etc.
More economical to have less stringent target requirements
Landfall, Faroe Island
Pilot hole drilling
Shore Aproach/Landfall Faroe Island
Reaming Process
Removal of cuttings/muck disposal methods
Water flushing with high pressure pump
Flow: 2000-5000 l/min, system pressure: 20bar.
Scraper system.
Auger system
Drilled Landfall from a rock tunnel into the North Sea, Norway
Location: Karstø area at the coast of Norway
Project: Oil pipeline from Åsgard oil field in the North Sea, to Kårstø Refinery
Client: Statoil
Drilling contractor: Entreprenørservice AS, Norway
Drilling equipment: Indau R90H, raise boring machine
Reaming head: Sandvik ø 1600 mm
The drilling operation: Time consumtion: 6 weeks.
Drilled Landfall from a rock tunnel into the North Sea, Norway
Drilled Landfall from a rock tunnel into the North Sea, Norway
Drilled Landfall from a rock tunnel into the North Sea, Norway
Horizontal, Drilling, Skien, NorwayØ2,44m, L= 42m
Flesland Airport and Hammerfest water supply
Flesland Airport
Runway Runway
L= 480m
Ø1800mm
Hammerfest, Water supply Water reservoar
L=390m
Ø660mm
Why use raiseboring for small tunnel projects?
Environmentaly Friendly
Little or no visible impact during and after drilling operations
”Tailored” cross-sectional area of tunnels, no over-break
Smooth tunnel walls; low surface roughness (<5 mm)
Rock support (anchor bolts, concrete lining) inside tunnel is rarely needed, circular tunnels are inherently stable
Road access to drill site not necessary
Safe and clean working environment for the operators (no fumes, dust)
Clean water only is used for removal of cuttings. Water can be recycled by using on-site settlement basins/containers
Very little noise from the equipment (electrically/hydraulically driven)
Environmentaly friendly…
Summary
The raise boring method is well suited for drilling water tunnels for small power projects
”Tailored” cross-sectional area, little or no need for rock support
Low surface roughness
Environmentaly friendly, very little visible impact, little noise and dust during construction
Customized equipment and experienced crew can drill tunnels in most conditions
Equipment can be transported to sites with no road access