4
Homer Public Safety Building Grubstake Avenue Homer, Alaska 99603 Date Fri 12/20/2019 Job # 1809-2 Prepared By Carl Brinkerhoff 12/20/19 | 04:38PM 12/20/19 | 04:38PM 12/20/19 | 04:38PM 12/20/19 | 04:38PM 12/20/19 | 04:38PM 12/20/19 | 04:38PM 12/20/19 | 04:38PM 12/20/19 | 04:38PM Weather 6:00 AM 25° Clear Wind: 9 MPH | Precipitation: .0'' | Humidity: 64% 12:00 PM 24° Clear Wind: 7 MPH | Precipitation: .0'' | Humidity: 64% 4:00 PM 24° Mostly Cloudy Wind: 6 MPH | Precipitation: .0'' | Humidity: 60% Work Logs Name Description Quantity Hours Hours To Date Accel Fire 0 0 38 Alasco Insulation 0 0 91 Consolidated Roofing 0 0 477 Duct or Sheet Metal Three workers onsite installing ducting mains at upper level in squad room and detectives offices. Carl Brinkerhoff | 12/20/19 | 06:53PM 3 8 91 East Road Services 0 0 944 Eayrs Plumbing Onsite working at upper level continuing domestic water rough in. Carl Brinkerhoff | 12/20/19 | 06:54PM 1 8 633 Matt Hanson, Ron Frazier, Tanner Stengel, Chad Albertsons, Ryan Fox, Jim Pollack, Tod Sharp Supervision, coordination and documentation. Completed interior shear diaphragm sheeting at upper level. Installed Sheetrock at janitors closet behind roof access ladder, installed ladder. Used Dimond blade on grinder to provide caulk joint space around detention frames and control joints for pick proof caulk. Framed additional openings for duct work through partition walls not previously lay out. Furred down women’s detention ceilings Carl Brinkerhoff | 12/20/19 | 07:07PM 7 8 392 Puffin Electric 2 journeyman and an apprentice onsite continuing rough in at upper level. Met with Pat McNary to discuss work at existing police station regarding generator move. Also discussed work required to get permanent power here at this site. 3 8 1145.5 1 of 4 | Homer Public Safety Building

Homer Public Safety Building · 2020. 1. 9. · Homer Public Safety Building: Grubstake Avenue Homer, Alaska 99603 Name Description Quantity Hours Hours To Date 1.Puffin Electric

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Homer Public Safety Building · 2020. 1. 9. · Homer Public Safety Building: Grubstake Avenue Homer, Alaska 99603 Name Description Quantity Hours Hours To Date 1.Puffin Electric

Homer Public Safety BuildingGrubstake Avenue Homer, Alaska 99603

Date Fri 12/20/2019 Job # 1809-2 Prepared By Carl Brinkerhoff

12/20/19 | 04:38PM12/20/19 | 04:38PM 12/20/19 | 04:38PM12/20/19 | 04:38PM 12/20/19 | 04:38PM12/20/19 | 04:38PM 12/20/19 | 04:38PM12/20/19 | 04:38PM

  Weather6:00 AM

25° Clear

Wind: 9 MPH  |  Precipitation: .0''  |  Humidity: 64%

12:00 PM

24° Clear

Wind: 7 MPH  |  Precipitation: .0''  |  Humidity: 64%

4:00 PM

24° Mostly Cloudy

Wind: 6 MPH  |  Precipitation: .0''  |  Humidity: 60%

  Work Logs

Name Description Quantity Hours Hours To Date

Accel Fire  0 0 38

Alasco Insulation  0 0 91

Consolidated Roofing  0 0 477

Duct or Sheet Metal  Three workers onsite installing ducting mains at upperlevel in squad room and detectives offices.Carl Brinkerhoff | 12/20/19 | 06:53PM

3 8 91

East Road Services  0 0 944

Eayrs Plumbing  Onsite working at upper level continuing domestic waterrough in.Carl Brinkerhoff | 12/20/19 | 06:54PM

1 8 633

Matt Hanson, RonFrazier, TannerStengel, ChadAlbertsons, Ryan Fox,Jim Pollack, TodSharp 

Supervision, coordination and documentation.Completed interior shear diaphragm sheeting at upperlevel. Installed Sheetrock at janitors closet behind roofaccess ladder, installed ladder. Used Dimond blade ongrinder to provide caulk joint space around detentionframes and control joints for pick proof caulk. Framedadditional openings for duct work through partition wallsnot previously lay out. Furred down women’s detentionceilingsCarl Brinkerhoff | 12/20/19 | 07:07PM

7 8 392

Puffin Electric  2 journeyman and an apprentice onsite continuing roughin at upper level.Met with Pat McNary to discuss work at existing policestation regarding generator move. Also discussed workrequired to get permanent power here at this site.

3 8 1145.5

1 of 4 | Homer Public Safety Building

Page 2: Homer Public Safety Building · 2020. 1. 9. · Homer Public Safety Building: Grubstake Avenue Homer, Alaska 99603 Name Description Quantity Hours Hours To Date 1.Puffin Electric

Carl Brinkerhoff | 12/20/19 | 06:58PM

Total 14 112 11802

  Time Cards No entry

  Materials No entry

  General Notes

1.  Went over for hardware inconsistencies between electrical drawings/ Siemens drawings and hardwareschedule with Puffin.Ordered materials for suspended gyp ceilings.Carl Brinkerhoff | 12/20/19 | 07:10PM

  Site Safety Observations

1.  Site safety protocols were observed onsite today.Carl Brinkerhoff | 12/20/19 | 07:10PM

  Quality Control Observations

1.  All materials and workmanship performed onsite today met or exceeded project specifications.Carl Brinkerhoff | 12/20/19 | 07:10PM

  Survey

Questions N/A No Yes Description

1. Any accidents on site today?

2. Any schedule delays occur?

3. Did weather cause any delays?

4. Any visitors on site? Pat McNary was on site today.Carl Brinkerhoff | 12/20/19 | 07:13PM

5. Any areas that can't be worked on?

Door 100A & 100B. Both types ofexterior siding. Permanent electricalpower to building which will delayelevator installationCarl Brinkerhoff | 12/20/19 | 07:13PM

6. Any equipment rented on site? All terrain scissor liftCarl Brinkerhoff | 12/20/19 | 07:13PM

  Attachments  

2 of 4 | Homer Public Safety Building

Page 3: Homer Public Safety Building · 2020. 1. 9. · Homer Public Safety Building: Grubstake Avenue Homer, Alaska 99603 Name Description Quantity Hours Hours To Date 1.Puffin Electric

12/20/19 | 04:38PM12/20/19 | 04:38PM 12/20/19 | 03:19PM12/20/19 | 03:19PM 12/20/19 | 02:40PM12/20/19 | 02:40PM 12/20/19 | 02:58PM12/20/19 | 02:58PM

I, Carl Brinkerhoff, have reviewed and completed this report.

Carl Brinkerhoff | 12/20/19 | 07:13PM

3 of 4 | Homer Public Safety Building

Page 4: Homer Public Safety Building · 2020. 1. 9. · Homer Public Safety Building: Grubstake Avenue Homer, Alaska 99603 Name Description Quantity Hours Hours To Date 1.Puffin Electric

SUBCONTRACTOR REPORTSFri 12/20/2019

Homer Public Safety Building: Grubstake Avenue Homer, Alaska 99603

Name Description Quantity Hours Hours To Date

1. Puffin ElectricNo Entry

0 0.0 0.0

2. Eayrs Plumbingand Mechanical

No Entry0 0.0 0.0

3. PEIDoor access control for doors 105, 107, 114A,and 126 was in question today for us because 3 24.0 160.0

Subtotal 3 24 160.0

Grand Total (Includes Cornerstone General Contractors Work LogTotal) 17 136 11962.0