Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
SEWC Utility Advisory Group Bruce Rew, Vice President Operations
2
Wind Capacity Installed by Year
3
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 0
2000
4000
6000
8000
10000
12000
14000
80 438 341 80 626 207 266 644 1176 837 561
2171
0 1146
3827
80 518 859 939 1565 1772 2038
2682 3858
4695 5256
7427 7427
8573
12400
Wind Installed Wind Capacity
Current MWs By Fuel Type
• Wind Totals 12,400 MWs � NDVer 6,634 MWs � DVer 5,766 MWs
• Solar 50 MWs • Nuclear 2,635 MWs • Natural Gas 35,692 MWs • Coal 28,916 MWs
� Generic Coal 21,368 MWs � Lignite Coal 2,899 MWs � Subbituminous 4,649 MWs
• Hydro 3,427 MWs • Other Fuel Types (Oil, Agricultural Byproducts, Municipal Solid
Waste) 1,659 MWs
4
0
5000
10000
15000
20000
25000
30000
35000
40000
12400 6634 5766
50 2635
35692 28916
21368
2899 4649 3427 1659
MW's By Fuel Type
Renewables impacts to SPP • Peak Wind Penetration level: 45.1% March 7, 2016
• Peak instantaneous Wind output: 10,738 MW (36.9% pen.)
• High impact on congestion and loading of the transmission system
• Wind can cause capacity issues by � Not showing up during times of high demand, contributing to
capacity shortages � Showing up too high during times of low demand, contributing to
“Min Gen” issues
• Short-term, intra-hour changes in wind also require reserves to maintain balance between generation and obligations
• Wind forecast is crucial for SPP to have the right generation online at the right time, while maintaining the reliability and economic efficiency of the regional transmission grid.
5
Operational Planning • Multi-Day Reliability Unit Commitment (RUC)
studies starting 7 days out � Identify potential capacity or transmission issues that may
need to be mitigated days in advance of the Operating Day
• Day-Ahead RUC � Run after Day Ahead Market (financial) results are posted � Ensures adequate resource capacity for the Operating Day
• Intra-Day RUC (same function as Day-Ahead RUC) � Begin running the night before and throughout the
Operating Day � Run at least every four hours, usually more frequently
• *NEW* Short-Term RUC � Run every 15 minutes, provides more granular look at
ramping obligations and transmission requirements
6
7
OD - 7
Multi-Day RUC studies, utilizing Long- and Mid-
Term wind forecast
OD - 1 Operating Day
Real-Time
Day Ahead RUC, run after Day Ahead
Market results posted
Short-term wind forecast used in Pre-RTBM and
RTBM; estimates uncurtailed potential
Intra-Day and Short-Term
RUCs
Wind Forecast in SPP
High wind/low load capacity
8
Dispatchable Range
At times we are using DVER wind to meet down-ramping obligation
RTBM redispatch of wind during down-ramping periods
9
NDVER actual wind
Market dispatches more wind down after evening load peak, when system load is
dropping and we need to ramp down
DVER actual wind
Real-time usage of wind • SPP implements a controlled release of DVERs
after curtailment � Ramp constraint provides controlled release � Allows the market to reevaluate before full release � Provides a safety net for wind forecast error � Optimize the reliable and economic solution with
many resources at once
• DVERs can offer in to clear down-regulation service � Only a handful of DVERs have cleared Reg Down
in the past � Allows wind farms to provide products other than
energy � Helpful when system wind is increasing, load is
decreasing and we are constrained on down ramp for conventional fuel resources
10
2015 Average Regulation Requirement contributors (Up direction)
11
0
50
100
150
200
250
300
350
400
450
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
MW
Hour of Day
Average of Load Magnitude Componet Average of Load Variability Component
Average of Wind Magnitude Component Average of Wind Variability Component
“Wind Variability” component creates higher requirement on average during morning hours, as wind is typically ramping down during this time (expected use of Regulation Up during this time
November 26-28, 2015 Extreme Weather Event
12
Timeline of Events Overview • Operations Impacts Beginning at Approx. 4:30 on
11/26 � Cold conditions and icing begin affecting wind resources � Footprint wide output of wind resources begins to come
up significantly short of forecasted output � Excess Capacity Reduced System Wide
• Early Morning into Midday 11/27 � Difference between 24 Hour Ahead Forecast and Actual
Wind Output greater than 6000 MW � Significant Increase in Number of Self, IDRUC, and QS Unit
Commitments � Limited Additional Capacity Available
• Reduced Operational Impacts Continue on 11/28
13
Impact on SPP’s Wind Forecast
14
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
SPP
Win
d M
W
Wind vs Forecast
Forecast 24 hours out Forecast 4 hours out Forecast 8 hours out Actual Wind
Storm moving in late Thursday 11/26
WF Outages/Derates in CROW
15
0
500
1000
1500
2000
2500
3000
3500
11-26-15 00:00
11-26-15 12:00
11-27-15 00:00
11-27-15 12:00
11-28-15 00:00
11-28-15 12:00
11-29-15 00:00
11-29-15 12:00
11-30-15 00:00
11-30-15 12:00
12-01-15 00:00
OOS Derate
Managing the Event • SPP Operators Adjusted for Loss of Resources/Capacity
Efficiently
• SPP RUC Operators Committed Additional Resources Appropriately Given Information Available as Events Unfolded
• WF Operators Informed SPP of Resource Status
16
Lessons Learned and Potential Improvements Identified from Event • Potential Icing Impacts as a Component of SPP’s Wind Forecast
• Improving the Timeliness and Accuracy of WF Availability Information in CROW
• Anticipating Capacity Needs in Preparation for Similar Events � Day-Ahead Preparations � Balancing Economic and Reliability Considerations
17
SPP Wind Integration Summary • Market is adjusting to high levels of wind � Some LMP prices driven negative � Wind farms voluntarily curtailing due to price
• Operations responding to wind impacts � Forecasting continues to improve � SPP is blessed with large number of quick start units � DVER policies and experience from EIS market greatly
helped in Integrated Marketplace
• Wind futures… � Wind capacity continues to increase, expect another
4,000 MW within 2 years � Expect to hit >50% penetration level in April 2016 � Studying higher wind penetration level impacts to
maintain reliable operations
18
Bruce Rew, PE Vice President, Operations [email protected] 501-614-3214