HIT7300 Installation Procedure

HIT7300 Installation Procedure ICON+ Project

Embed Size (px)

Citation preview

Page 1: HIT7300 Installation Procedure ICON+ Project

HIT7300 Installation Procedure

Page 2: HIT7300 Installation Procedure ICON+ Project

i

TABLE OF CONTENT 1. Objective.................................................................................................................. 1 2. Work Preparation.................................................................................................... 1 2.1 Installation Tools Preparation .......................................................................... 2 2.2 As Plan Document ............................................................................................ 2 3. Pre Installation Check ............................................................................................ 2 3.1 CME RFI Check................................................................................................ 2 3.2 Material arrival and material check in field ....................................................... 2 3.3 Unpacking equipment from the box .................................................................. 3 4. Equipment Installation .......................................................................................... 3 4.1 DWDM Equipment Installation ......................................................................... 3 4.2 Power and Cabling Installation ......................................................................... 6 5. Work Completion ................................................................................................... 9 5.1 Installation Final Check..................................................................................... 9 5.2 Red Correction.................................................................................................. 9

Page 3: HIT7300 Installation Procedure ICON+ Project

ii

Figure List: Fig. 3.2 Box indicator.............................................................................................. 3 Fig. 4.1.b Rack Horizontal level adjustment.............................................................. 3 Fig. 4.1.c Rack fixed to the floor................................................................................ 4 Fig. 4.1.d Rack fixed to indoor tray ........................................................................... 4 Fig. 4.1.e Rack grounding ......................................................................................... 4 Fig. 4.1.f Electronic Bonding Point (EBP) jack ......................................................... 5 Fig. 4.1.g LC/PC and FC/PC cable ........................................................................... 5 Fig. 4.1.h.1 Inter module cable connection .................................................................. 5 Fig. 4.1.h.2 Cabling plan from as plan document......................................................... 6 Fig. 4.1.h.3 Cable connected through cable compartment and labeled....................... 6 Fig. 4.2.b.1 DC connection on PDP ............................................................................. 7 Fig. 4.2.b.2 Inner cable connection .............................................................................. 7 Fig. 4.2.c MCB usage................................................................................................ 7 Fig. 4.2.d.1 DC power cable position with cable ties.................................................... 8 Fig. 4.2.d.2 Cable path on indoor tray.......................................................................... 8 Fig. 4.2.e Patchcord cable installed on conduit through cable tray inside ODF rack 9 Fig. 5.2 Red Correction Flow Chart........................................................................ 10

Page 4: HIT7300 Installation Procedure ICON+ Project

iii

Table List: Tab. 2.1 Installation tool list .......................................................................................... 2 Tab. 3.1 CME RFI Checklist ......................................................................................... 2 Tab. 5.2 Red correction picture list............................................................................... 10

Page 5: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 1 of 10

1. Objectives Tujuan This document is intended to be used as a reference to guide the HIT7300 installation, so the HIT7300 installation will be similar. It contains all description of procedure to install the equipment. Dokumen ini ditujukan untuk membuat suatu petunjuk acuan dalam instalasi HIT7300, sehingga didapatkan instalasi HIT7300 yang seragam. Dokumen ini mencakup seluruh rincian prosedur instalasi perangkat 2. Work Preparation Persiapan Pekerjaan 2.1 Installation Tools Preparation Persiapan Peralatan Instalasi List of complete installation tools required is listed in below table Daftar dari alat kerja yang lengkap terdapat pada table berikut

NO Tool Name QTY 1 Drilling Machine for Steel and Concrete 1 2 Drill Bit for Steel/ HSS 1 set 3 Drill Bit for Concrete Dia 5mm, 6mm, 8mm, 10mm, 13mm 2 pcs/ Each 6 Open End Spanner No. 7-8 (Vanadium Chrome) 2 pcs 7 Open End Spanner No.24-27 (Vanadium Chrome) 2 pcs 8 Open End Spanner & Ring No.10 (Vanadium Chrome) 2 pcs 9 Open End Spanner & Ring No.13 (Vanadium Chrome) 2 pcs

10 Open End Spanner No.17-19 (Vanadium Chrome) 2 pcs 11 Open End Spanner No.30-32 (Vanadium Chrome) 1 12 Adjustable Spanner 6" (Vanadium Chrome) 1 13 Adjustable Spanner 15" (Vanadium Chrome) 1 14 Socket Wrench Set till to 13mm 1 set 15 Screw Driver (-) 3mm (Vanadium Chrome-Insulated) 1 16 Screw Driver (-) 5mm (Vanadium Chrome-Insulated) 1 17 Screw Driver (-) 7mm (Vanadium Chrome-Insulated) 1 18 Screw Driver (+) 3mm (Vanadium Chrome-Insulated) 1 19 Screw Driver (+) 5mm (Vanadium Chrome-Insulated) 1 20 Screw Driver (+) 7mm (Vanadium Chrome-Insulated) 1 21 Hexagonal Key (Vanadium Chrome) 1 set 22 Torx Key With Hole (Vanadium Chrome) 1 set 23 Hammer 1 24 Center Punch 1 25 Standard Iron Saw 1 28 Precision Cutting Pliers (Small) 1 29 Cutting Pliers 1 30 Combination Pliers 1 31 Long Nose Pliers 1 33 Utility Knife 1 35 Square 1 36 Metal Brush 1 39 Scissor (Stainless Steel) 1 42 Cable Scraper 1 44 Digital multi meter 1 46 AC Cable Junction 1

Page 6: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 2 of 10

47 Anti Static Strap 1 49 Flash Light 1 50 Labeling Tool 1

Tab. 2.1 Installation tool list 2.2 As Plan Document Dokumen As Plan As plan document consists of site and equipment information and as plan drawing. All installation should be finished according to the as plan Dokumen As plan berisi informasi site dan perangkat dan gambar as plan site. Seluruh hasil pekerjaan instalasi harus mengacu kepada gambar as plan 3. Pre Installation Check Pengecekan Awal Sebelum Instalasi 3.1 CME RFI Check Pengecekan RFI CME

CME RFI completeness is a mandatory requirement for installation. Subcontractor is responsible to check these CME RFI items listed in below table Kesempurnaan CME RFI adalah merupakan persyaratan wajib untuk instalasi. Subcontractor berkewajiban untuk mengecek beberapa item CME RFI yang terdapat pada tabel berikut

No No

Item to be Checked Item yang di Check

Requirement Persyaratan

1 Indoor tray Indoor tray

Completely installed Terpasang lengkap

2 Shelter Shelter

Completely installed Terpasang lengkap

3 PLN PLN

Connected to AC power source Terhubung ke sumber catuan

4 Grounding System Sistem pertanahan/grounding

Completely installed and connected to main grounding Terpasang lengkap dan terhubung ke grounding utama

5 Lightning Arrester Rod Penangkal Petir

Installed and connected to main ground Terpasang dan terhubung ke grounding utama

Tab. 3.1 CME RFI Checklist 3.2 Material arrival and material check in field Penerimaan dan pemeriksaan material di lapangan Every material is delivered with a Dispatch Note. When receiving the material from the mover, Subcontractor must check the following items; Setiap pengiriman material disertai dengan Dispatch Note. Ketika menerima material dari mover, Subcontractor harus memeriksa beberapa hal berikut; a. Check the correctness of site address. Material is delivered to correct site

Periksa kebenaran alamat site. Material dikirim ke alamat site yang benar

b. Check material correctness. All material sent are correct Periksa kecocokan material. Semua material yang dikirim benar

c. Check the box condition Periksa kondisi peti/box.

d. Check the condition of shock and level of indicator box Periksa kondisi shock indicator dan level indicator box.

Page 7: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 3 of 10

Fig 3.2. Box indicator

e. Check material completeness. No missing material (check the content of each box!) Periksa kelengkapan material. Tidak ada material yang hilang (periksa isi dari setiap box!)

3.3 Unpacking equipment from the box Pembongkaran barang dari box a. Open the box carefully and check for every material in the boxes.

Buka box dengan hati-hati dan periksa setiap material yang ada di box masing-masing. b. Check arrival material quantities and make a report if there is any

incomplete/damage/missing material. Periksa jumlah material yang diterima dan buat report bila ada yang tidak lengkap/rusak/hilang.

c. Make material request if there are any less material or wrong shipment to NSN

supervisor. Buat request material bila ada kekurangan material atau kesalahan kirim ke supervisor NSN.

4. Equipment Installation Instalasi Perangkat 4.1 DWDM Equipment Installation

Instalasi Perangkat DWDM a. Locate the position of ETSI rack according to site layout described in as plan

Tempatkan ETSI rak di shelter sesuai dengan layout yang terdapat pada as plan

b. Put ETSI rack in level position, by using spirit level Posisikan agar ETSI rack pada posisi datar, gunakan spirit level

Fig.4.1.b. Rack Horizontal level adjustment

Page 8: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 4 of 10

c. Fix ETSI rack to the floor tightly by using screw bolt and fisher ETSI rack harus disekrup kelantai dengan kencang menggunakan baut ulir dan fisher

Fig.4.1.c. Rack fixed to the floor

d. Fix ETSI rack to indoor tray by using tray support as follow Kencangkan ETSI rack ke tray indoor menggunakan penyangga tray seperti berikut

Fig.4.1.d. Rack fixed to indoor tray

e. Install ground ETSI rack cable and should be connected to busbar

ETSI rack harus digrounding (terhubung dengan grounding bar / busbar dibawah FEP di dalam shelter)

Fig.4.1.e. Rack grounding

Fix ETSI rack to the floor tightly by using screw bolt and fisher

Page 9: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 5 of 10

f. Use ESD (Wrist strap) equipment while working with module Gunakan Peralatan ESD (Wrist strap) saat bekerja dengan module.

Fig.4.1.f. Electronic Bonding Point (EBP) jack

g. Check the completeness of patchcord cables, LC/PC – LC/PC for internal HIT7300 modules and LC/PC – FC/PC for ODF termination Cek kelengkapan kabel patchcord yang akan digunakan, LC/PC – LC/PC untuk antar module HIT7300 dan LC/PC – FC/PC untuk terminasi ke ODF.

Fig.4.1.g. LC/PC and FC/PC cable

h. Check all patchcord cables connection based on as plan document. All cables should be labeled and connected through cable compartment. Cek semua koneksi kabel patchcord sesuai dengan dokumen as plan. Semua kabel harus dilabel dan terkoneksi melewati kabel kompertemen

Fig.4.1.h.1. Inter module cable connection

Plug the wristband cable into the Electronic Bonding Point (EBP) jack

Page 10: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 6 of 10

Fig.4.1.h.2. Cabling plan from as plan document

Fig. 4.1.h.3. Cable connected through cable compartment and labeled

4.2. Power and Cabling Installation

Instalasi Power dan pengkabelan

a. Measure the distance between Power Distribution Panel (PDP) on ETSI rack and DCPDB, than cut the power cable to the required length. Tentukan jarak antara penghubung Power Distribution Panel (PDP) di rak ETSI dan DCPDB, kemudian potong kabel power sesuai dengan panjang yang diperlukan.

b. Set power cable into PDP connector, remove the insulation of the cable approx 1cm and make sure that power supply was OFF before connecting the power cable to PDP terminal. The wire/ inner cable must properly insert and tighten on terminal. Pasang kabel power ke konekor di PDP, lepaskan pembungkus DC kabel kurang lebih 1cm dan pastikan power supply dalam kondisi mati sebelum dihubungkan ke PDP termainal. Kabel inti harus dimasukkan secara benar dan kencang kedalam terminal.

Page 11: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 7 of 10

Fig.4.2.b.1. DC connection on PDP

Fig.4.2.b.2. Inner cable connection

c. Connect power cable into 32A MCB on DCPDB. Measure the voltage from DCPDB

with Voltmeter before connected to PDP, voltage value should between –40.5 and –75 VDC.

Hubungkan kabel power ke MCB 32 Ampere pada DCPDB. Ukur tegangan dari DCPDB dengan voltmeter sebelum dihubungkan ke PDP, nilai tegangan harus antara -40.5 dan -75 VDC

Fig.4.2.c. MCB usage

Put label on DCPDB

Page 12: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 8 of 10

d. Power cables installed on tray must be separated, not crossed over with patchcord

cable, and be tied using white ties. Instalasi kabel power yang melewati cable tray harus terpisah dan tidak bersilangan dengan kabel

patchcord dan diikat dengan cable ties

FRONT VIEW TOP VIEW

SIDE VIEWCable Ties

Fig.4.2.d.1. DC power cable position with cable ties

Conduit Cable

Grounding Cable

DC Power Cable

Conduit installed in right side of tray rack

DC cable + grounding installed in left side of tray rack

Rack back side

Fig.4.2.d.2. Cable path on indoor tray

Page 13: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 9 of 10

e. Patchcord cable installed inside conduit from top of HIT7300 rack to ODF, through cable tray inside ODF rack and continued using spiral cable Kabel patchcord dipasang didalam conduit dari atas rack HIT7300 sampai ke ODF melalui kabel tray didalam rack untuk ODF dan dilanjutkan dengan kabel spiral

AC outlet

ODF

DCPDB

GPA Alarm

HUB 8 Port & alarm Censor

Spiralconduit

Fig.4.2.e. Patchcord cable installed on conduit through cable tray inside ODF rack

5. Work Completion Penyelesaian Pekerjaan 5.1 Installation Final Check Pengecekan Instalasi Akhir

To ensure that all equipment installation is finished as quality standard, therefore the subcontractor must check the installation result and make sure all parts are properly installed. Untuk memastikan bahwa instalasi perangkat telah diselesaikan sesuai dengan standar kualitas, maka Subcontractor harus mengecek hasil pekerjaan instalasi dan memastikan semua bagian terpasang dengan benar 5.2 Red Correction Red Correction

There is a possibility that some installation item is not finished as planned due to unpredictable factor such as changed in actual space allocation, direct change request from customer, etc. To keep the site information is always updated; therefore the Red Correction activity is required, the document called as build document. Figure below explains the Red Correction process Terdapat kemungkinan bahwa hasil instalasi tidak sesuai dengan as plan yang disebabkan oleh factor yang tidak bisa diperkirankan sebelumnya seperti perubahan alokasi tempat, permintaan perubahan langsung dari

Page 14: HIT7300 Installation Procedure ICON+ Project

SE-TI-ICON-10-03 Nokia Siemens Network

Rev : 00

HIT7300 Installation Procedure Page 10 of 10

customer, dan lain lain. Untuk menjaga agar informasi site selalu update, maka diperlukan aktifitas Red Correction, dokumennya dinamakan dokumen as build. Gambar berikut menjelaskan proses Red Correction

Fig. 5.2 Red Correction Flow Chart In this activity, subcontractor will do: Di aktifitas ini, Subcontraktor akan melakukan:

1. Red Line, by providing “red mark” in former as plan document for any changes/differences found between as plan and actual installation result Red Line, dengan memberikan “red mark“ pada dokumen as plan sebelumnya jika ditemukan adanya perbedaan antara as plan dengan hasil instalasi ang sesungguhnya

2. Site Picture Record, by taking some necessary picture as listed in below table. Pengambilan Gambar Site, dengan mengambil beberapa gambar/foto yang terdapat pada tabel berikut.

No Picture 1 View to site 2 View to ETSI rack placement 3 View to ETSI rack floor mounting 4 View to ETSI rack tray mounting 6 View to ETSI rack grounding cable 7 View to bus bar grounding cable 8 View to patchcord installation (internal module) 9 View to patchcord installation (to ODF)

10 View to power cable installation in ETSI rack 11 View to patchcord, power and grounding cable path on indoor tray 12 View to open rack 19” placement 13 View to open rack 19” grounding cable 14 View to DCPDB on open rack 19” 15 View to AC outlet on open rack 19” 16 View to ODF

Tab. 5.2 Red correction picture list

Identify any changes

Red Line + Photo

Red Line Drawing

Site Picture Record

Installation Finished