148
Massachusetts Water Resources Authority Metropolitan Tunnel Redundancy Off-Site Meeting History of the Water System October 6, 2016 Frederick A. Laskey Executive Director

History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Massachusetts Water Resources Authority

Metropolitan Tunnel RedundancyOff-Site Meeting

History of the Water System

October 6, 2016

Frederick A. LaskeyExecutive Director

Page 2: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Early Boston Water System

• Early Bostonians relied on local wells, rain barrels and a spring on Boston Common for their water

• In 1795 wooden pipes made from tree trunks delivered water from Jamaica Pond to Boston

• By the 1840s, Jamaica Pond was too small and too polluted to provide water to Boston’s 50,000 residents

• The pattern of moving continually westward in search of larger water sources began

Page 3: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Cochituate System

• After 20 years of study, the Cochituate System was chosen

• In 1845 construction began on a new distribution system

• The Sudbury River was impounded and Lake Cochituate was formed 14.5 miles from Boston

• The Cochituate Aqueduct transported water to the Brookline Reservoir, which supplied smaller reservoirs all over the City

• Lake Cochituate provided 2 billion gallons of storage and 10 million gallons per day

Page 4: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Long Pond was renamed Lake Cochituate Reservoir

• The system flowed by gravity through a series of distribution reservoirs

The The CochituateCochituate System

Lake Cochituate Intake

Page 5: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

CochituateCochituate Reservoir and Aqueduct

5

Page 6: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Cochituate System

• Water from Lake Cochituate flowed into the Frog Pond on Boston Common in 1848 at a dedication ceremony that drew 100,000

Page 7: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

But Boston Needed More Water

• By the early 1890s, Boston’s water supply was deemed unsafe and inadequate

• Governor Russell proposed a water district including the development of a large water supply for a number of communities

• In 1895, the Metropolitan Water Act called for the taking of water from the south branch of the Nashua River, the Boston Waterworks at Chestnut Hill and Spot Pond

• This system would supply water to the cities and towns within 10 miles of the State House that wanted it

Page 8: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Metropolitan Water District

Page 9: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

The Sudbury System

Page 10: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Sudbury System

• In 1878, the Sudbury River, 18 miles from Boston, was diverted through the Sudbury Aqueduct to the Chestnut Hill Reservoir

• By 1898, the Fayville Dam and the Sudbury Reservoir were completed

Page 11: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

A Regional Solution Was Needed

• Boston continued to grow rapidly in the 1880s and 1890s

• And planners had not foreseen the advent of indoor plumbing

• New water sources were considered: the Nashua River, the Merrimack River, Lake Winnipesaukee and Sebago Lake

Page 12: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

WachusettReservoir Wachusett

Aqueduct

The Wachusett Reservoir The Wachusett Reservoir -- 1897

Page 13: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Wachusett Reservoir

• Chief Engineer Frederick Stearns planned a water source that would be gravity-operated and not require filtration

• The Nashua River was impounded by the Wachusett Dam, 38 miles from Boston

Page 14: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Wachusett Reservoir

• At the time it was constructed, the Wachusett Reservoir was the largest man-made water supply reservoir in the world

• Its 65 billion gallons supplied 118 million gallons per day

Page 15: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Wachusett Aqueduct

15

• The Wachusett Aqueduct was constructed to bring water from the Wachusett Reservoir to Sudbury Reservoir

Page 16: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

WachusettReservoir Wachusett

Aqueduct

The Quabbin Reservoir

Page 17: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Quabbin Reservoir

• Construction of the Quabbin required the impoundment of the Swift River and the takings of four towns

• The Quabbin Reservoir, 60 miles from Boston, was another source that could be gravity-operated and not require filtration

Enfield

Page 18: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Quabbin Aqueduct

• Construction of the Wachusett-Colebrook Tunnel (now the Quabbin Tunnel) began in 1926, carrying surplus flow from the Ware River to the Wachusett Reservoir

• In the 1930s, the Tunnel was extended to the Swift River

• This two-way tunnel carries flows east and west, depending on time of year

• In 1936, construction of the reservoir began

was extended to the Swift

Page 19: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Quabbin Reservoir

• The reservoir was filled with water from the Swift River and the Ware River

• Filling began in 1939 and was completed in 1946

• At the time, the 412 billion gallon reservoir was the largest man-made reservoir in the world

Road still visible beneath surface of water

Page 20: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

WachusettReservoir Wachusett

Aqueduct

ChicopeeValley

Aqueduct

The Chicopee Valley Aqueduct The Chicopee Valley Aqueduct -- 1949

Page 21: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The Chicopee Valley Aqueduct

21

• The Chicopee Valley Aqueduct is a 14.8 mile, 4-foot diameter steel and concrete pipeline that supplies Chicopee, South Hadley FD 1 and Wilbraham from the Quabbin Reservoir

Page 22: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Cumulative Water Supply Capacity

0

50

100

150

200

250

300

350

400

450

500

1848 1870 1872 1908 1946

Page 23: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

HultmanAqueduct

WachusettReservoir Wachusett

Aqueduct

ChicopeeValley

Aqueduct

The The HultmanHultman Aqueduct Aqueduct -- 1940

Page 24: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The The HultmanHultman Aqueduct

• In 1936, the Legislature approved the construction of a two high-pressure aqueducts to deliver water to the greater Boston area

• The two aqueducts would carry water from the Wachusett Reservoir to the new Norumbega Reservoir in Weston

Page 25: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The The HultmanHultman Aqueduct

• One barrel of the aqueduct system - the Hultman Aqueduct - was completed

• But work on the second barrel did not resume after World War II

• Until 2003, 85% of Boston’s water supply was provided without redundancy

Page 26: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• By the 1950s, tunnels were used to bring better pressure deeper into the distribution system

The Metropolitan Tunnel System

21

Page 27: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

HultmanAqueduct

CityTunnel

WachusettReservoir Wachusett

Aqueduct

ChicopeeValley

Aqueduct

The City Tunnel The City Tunnel -- 1950

Page 28: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

The City Tunnel

28

• The City Tunnel is a 12-foot deep rock tunnel that goes from Shaft 5 in Weston to Shaft 7/7B in Brighton

• It was constructed to meet increased demand, followed by the City Tunnel Extension to the north and the Dorchester Tunnel to the south

Page 29: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

HultmanAqueduct

CityTunnel

CityTunnel

Extension

WachusettReservoir Wachusett

Aqueduct

ChicopeeValley

Aqueduct

The City Tunnel Extension The City Tunnel Extension -- 1963

Page 30: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

City Tunnel Extension

3030

• The City Tunnel Extension is a 10-foot diameter deep rock tunnel that goes from Shaft 7 north to Shaft 9A in Malden

Page 31: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

HultmanAqueduct

CityTunnel

CityTunnel

Extension

WachusettReservoir Wachusett

Aqueduct

CosgroveTunnel

ChicopeeValley

Aqueduct

The Cosgrove Tunnel

Page 32: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Cosgrove Tunnel Cosgrove Tunnel -- 1967

32

• The Cosgrove Tunnel carries water eight miles from the Wachusett Reservoir to the Carroll Treatment Plant

• It is 14 feet in diameter and was constructed to replace the Wachusett Aqueduct with a pressurized tunnel

Page 33: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

HultmanAqueduct

CityTunnel

CityTunnel

Extension

DorchesterTunnel

WachusettReservoir Wachusett

Aqueduct

CosgroveTunnel

ChicopeeValley

Aqueduct

The Dorchester Tunnel

Page 34: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Dorchester Tunnel Dorchester Tunnel -- 1976

34

• The Dorchester Tunnel is a 10-foot diameter deep tock tunnel that was needed to serve the Southern High and Southern Extra High zones when the Sudbury Reservoir system no longer met water quality standards

Page 35: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

HultmanAqueduct

CityTunnel

CityTunnel

Extension

DorchesterTunnel

WachusettReservoir Wachusett

Aqueduct

CosgroveTunnel

MetroWestTunnel

ChicopeeValley

Aqueduct

The MetroWest Water Supply Tunnel The MetroWest Water Supply Tunnel -- 2003

Page 36: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

MetroWest Water Supply Tunnel

• The 17.6 mile, deep rock MetroWest Water Supply Tunnel was brought on-line in November 2003

• By March 2004, the Tunnel was being fully utilized allowing the shutdown of the HultmanAqueduct for repair

Page 37: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Since 2013, for the first time since originally planned in the 1930s, the Metropolitan Water System has redundancy for the Hultman Aqueduct from Marlborough to Weston

Hultman Aqueduct Rehabilitation

37

Page 38: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

ChicopeeValley

Aqueduct

SudburyAqueduct

SudburyReservoir

ChestnutHill

Reservoir

Quabbin Aqueduct

QuabbinReservoir

HultmanAqueduct

CityTunnel

CityTunnel

Extension

DorchesterTunnel

WachusettReservoir Wachusett

Aqueduct

CosgroveTunnel

MetroWestTunnel

ChicopeeValley

Aqueduct

Fells

Spot Pond

Blue Hills

LoringRoad

Norumbega

Nash Hill

Carroll

Covered Water Storage Covered Water Storage -- 19921992-1992-2015

Page 39: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Norumbega Covered Storage Facility

• The tank was completed in May 2004

• It provides 115 million gallons of storage for metropolitan Boston

Page 40: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

MWRA Metropolitan Area Storage Capacity Over Time

Page 41: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

New Wachusett Aqueduct Pump Station Under Construction

41

• Will provide redundancy for the Cosgrove Tunnel, from the Wachusett Reservoir to the Carroll Treatment Plant

Wachusett Aqueduct Pump Station

Page 42: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

We’ve Come A Long Way

4242

Page 43: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Massachusetts Water Resources Authority

Special Meeting of the Board of Directors

on

Metropolitan Tunnel Redundancy

October 6, 2016

Page 44: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

2

Status of Existing Transmission System Facilities

Page 45: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

MWRA Water Transmission System

3

1. Chicopee Valley Aqueduct 2007 Improvements2. Quabbin Aqueduct Inspection planned3. Cosgrove Tunnel / Wachusett Aqueduct Project underway4. MetroWest Tunnel / Hultman Aqueduct 2003/2013 Improvements5. Metropolitan Tunnels Significant Needs

3 52

1

Page 46: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Metropolitan Tunnel System

4

NorumbegaTank City Tunnel

City Tunnel Extension

Dorchester Tunnel

Carroll Treatment Plant

Shaft 5/5A

Shaft 7

Page 47: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Service Provided to a Large Percentage of MWRA Customers

5

Approximately 60% of total system flow is carried through the Metropolitan Tunnel System

Page 48: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Tunnel system:– Concrete-lined deep rock tunnels– Steel and concrete vertical shafts– Surface pipe, valves and

appurtenances

• Little maintenance required for tunnels and shafts. Little risk of failure.

• Pipe, valves and appurtenances need maintenance, replacement, rehabilitation

Condition of Metropolitan Tunnel System

6

Page 49: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Valves that don’t work

• Valves we can’t exercise

Valve Reliability Concern

7

Cone Valve at Shaft 7B

54-inch Shaft 7 Valve 20-inch Shaft 7 Valve

Page 50: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Valves that don’t work

• Valves we can’t exercise

Valve Reliability Concern

8

Cone Valve at Shaft 7B

60-inch gate valve Shaft 5

Gear box on valve at Shaft 8

Page 51: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Valves that don’t work

• Valves we can’t exercise

Valve Reliability Concern

9

Location?Location?

Shaft 8 PRV Chamber

Shaft 8

Shaft 8

Page 52: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Access Can Be Difficult

10

• High ground water table• Standing water in some chambers• Corrosion is a concern

Chamber at Shaft 7CChamber at Shaft 7D

Shaft 7C connection to Section 58

Page 53: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Access Can Be Difficult

11

• High ground water table• Standing water in some chambers• Corrosion is a concern

Shaft 7D located near salt marsh at Neponset River Reservation

Shaft 7D connecting pipe air valve chamber

Shaft 8 near Storrow Drive and the Charles River

Page 54: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Small pipe failures can lead to shut downs

Appurtenances Can Be Liabilities

12

Shaft 8 PRVs Top of Shaft 8

Page 55: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Appurtenances Can Be Liabilities

13

Control piping at Shaft 8

• Small pipe failures can lead to shut downs

Air valve at Shaft 9A Shaft 8 PRV Chamber

Page 56: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Appurtenances Can Be Liabilities

14

• Small pipe failures can lead to shut downs

< 1”

250 MGD flow at Shaft 5 break…. …came from a small gap in the pipe

Page 57: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Replace corroded bolts• Metal thickness evaluation• Wrap or coat pipe segments• Replace air valves• Cathodic protection• Heat tracing

Shaft Pipeline Improvements to Reduce Risk

15

Page 58: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Six 54-inch hydraulically actuated Dow Disc valves• Junction point of all three tunnels• Valve operability uncertain• Small diameter piping and valves

Location of Concern Location of Concern –– Shaft 7

16

Page 59: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Flooding of Boston College

Shaft 7 Shaft 7 –– Boston College

17

Shaft 7

Shaft 7B / Chestnut Hill Emergency Pump Station

Page 60: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Impacts to Chestnut Hill reservoir to Shaft 7B and Cleveland Circle

Shaft 7 Shaft 7 –– Boston College

18

Shaft 7

Shaft 7B / Chestnut Hill Emergency Pump Station

Page 61: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Located at tunnel depth for the purpose of dewatering tunnels• Access extremely difficult• High pressure bronze pipes connect tunnel to dewatering pumps• Smaller diameter piping from hydraulic valve actuators to surface

Location of Concern Location of Concern –– Shaft 5 & 9 Pump Chambers

19

Page 62: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Shaft 9 Pump Chamber

20

Page 63: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Shaft 9 Pump Chamber

21

• Shaft 9 also has a hydraulically actuated tunnel isolation valve• Access shaft and pump chamber have been submerged for decades

Valve control piping still present in both shaft buildings Shaft 9 access shaft is full of water

Page 64: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Shaft 9 Pump Chamber

22

Page 65: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Shaft 9 Pump Chamber

23

Page 66: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Couplings on pipeline located between tunnel shaft and isolation valves

Location of Concern Location of Concern –– Shaft 9A

24

Page 67: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Tunnel System Shut-downImpacts

Page 68: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Partially supplied communities use alternate supplies• Gillis Pump Station / Spot Pond Pump Station• Reconfigure Northern High piping• Pump from Open Spot Pond Reservoir (BOIL ORDER) 1-2 months

at average day demand; 1-3 weeks at high day demand• Replenish from Low Service supply lines (WATER RESTRICTIONS)

Planned Shut Down Planned Shut Down –– Service to the North

26

Page 69: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Partially supplied communities use alternate supplies• Chestnut Hill Emergency Pump Station• Surface Mains to Blue Hills Tanks (PRESSURE SWINGS / BREAKS)• Pump from Chestnut Hill Reservoir (BOIL ORDER)• Replenish from Sudbury Aqueduct

Planned Shut Down Planned Shut Down –– Service to the South

27

Page 70: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• text

Shut Down Sometimes Unplanned

28

• Flooding/damage/public safety concerns

• May not have time to set up back up systems

Page 71: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Extent of shut-down depends on failure• Numerous shaft locations to isolate / multiple valves at some• Some chambers require pumping• Valve turn counts / time to close on the order of 45 minutes each

ShutShut-Shut-down and Isolation Takes Time

29

Page 72: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Sudden shut down of Metropolitan Tunnel system

• Loss of supply to high service areas

• Pumped Service Areas lose supply as tanks empty

• Whole system would be on boil order

WideWide-Wide-Spread WideWideWideWide Spread Spread Spread Impact

Highlighted areas of high and pumped service areas that could lose supply

Page 73: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Daily Business Impact: $208 million• Daily Residential Impact: $102 million

• Economic Impact for Total Water Loss - One Day:• $310 million

• Economic Impact for Total Water Loss - Three Days:

• $930 million

Economic Impact Economic Impact –– Total Water Loss

31Analysis based on guidelines in FEMA Benefit-Cost Analysis Version 4 standard

Page 74: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Activate back-up supplies• Large areas of MWRA and community systems will need to be

refilled SLOWLY to avoid breaking lines• Flushing to remove air pockets could take days if not weeks• Water Quality Samples to assure public

Service Restoration

32

Page 75: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Daily Business Impact: $195 million• Daily Residential Impact: $102 million

• Economic Impact for Boil Order – One Week:• $2.1 billion

Economic Impact Economic Impact –– Boil Order

33Analysis based on guidelines in FEMA Benefit-Cost Analysis Version 4 standard

Page 76: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Water Quality Sample Locations

34

Page 77: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Break

Page 78: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Strategic Goals for Redundancy Improvements

Page 79: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Operating Goals:

– Protection of Public Health

– Providing Sanitation– Fire Protection

• Average day demand

• High day demand preferred– Longer shut downs

possible

Water System Operating Goals

37

150

200

250

300

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

20112012201320142015

Norumbega Daily Flows 2011 to 2015

Average Day

High Day

Page 80: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Emergency-Only Capability

– Utilize only if failure occurs– Does not allow planned maintenance– Decrease in level of service– Potential for damage to MWRA and community systems

• Planned Shut-Down Capability Preferred

– Allows maintenance of system– Maintenance reduces risk of failure– Meet customer expectations for excellent quality water– Minor impact on normal service

Strategic Goal for Redundancy Improvements

38

Page 81: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

National Guidance, Peer Organizations and Redundancy Planning at MWRA

Page 82: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

National Guidelines and Standards for Redundancy

• Recommended Standards for Water Works (“10 States Standards”):

– “Redundancy…should be incorporated into the design to eliminate single points of failure…”

• EPA Guidance 2011:

– “Reduce outage risk through system redundancy/resiliency and repair capabilities…”

40

Page 83: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Example Peer Organization Redundancy Programs:Example Peer Organization Redundancy Programs:Example Peer Organization Redundancy Programs:San Francisco

41

• $4.8 billion Water Supply Improvement Program

• Major Transmission and Storage Projects

• Cross Bay Tunnel

• High Day Design EnablesMaintenance of Either New or Old Tunnels

Replace with Transmission System Picture

41

Page 84: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Example Peer Organization Redundancy Programs:Example Peer Organization Redundancy Programs:Example Peer Organization Redundancy Programs:Seattle

42

• Two ways to convey water to all parts of their system

• Two separate supply and transmission systems

• Opposite sides of the city• Two different feed points• Two separate tanks• Looped Transmission

System

Replace with Transmission System Picture

42

Replace with Transmission System Picture

Page 85: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Example Peer Organization Redundancy Programs:Example Peer Organization Redundancy Programs:Example Peer Organization Redundancy Programs:New York City

43

• Tunnel #3 - Designed for Full Redundancy to Tunnels 1 & 2

• Stage 1 and 2 Completed – 27 miles of 24’ tunnel

• $4.7 billion through 2013

• $ 1 billion of Supply, Treatment, and Transmissionprojects will enable taking NYC’s largest aqueduct and supply off line for a 2.5 mile Bypass Tunnel and Repairs

43

Page 86: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

44

AMWA Survey of Redundant Water Sources and/or Treatment AMWA Survey of Redundant Water Sources and/or Treatment AMWA Survey of Redundant Water Sources and/or Treatment Systems AMWA Survey of Redundant Water Sources and/or Treatment Systems Systems -AMWA Survey of Redundant Water Sources and/or Treatment AMWA Survey of Redundant Water Sources and/or Treatment AMWA Survey of Redundant Water Sources and/or Treatment

-- 2016

• 22 Systems Nationwide representing populations of 100K to 1.8 million

8 designed for redundant max day /summer demand

3 designed for most of summer peak

7 designed for at least winter or average day

3 systems can only handle less than an average day

1 system with no redundancy

• MWRA in Lower 25%

Page 87: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Redundancy examples in our water system since 1800s:– Two basins of Chestnut Hill Reservoir– East and West Spot Pond Supply Mains– Hultman Aqueduct planned to have two barrels

Redundancy Redundancy –– It’s Always Been a Goal for MWRA Water System

45

Future Hultman Aqueduct connection at Shaft 4 (1940)

Future Hultman Aqueduct connection at Shaft 4 WASM 1 and 2 Pipe Yard (1915)

Page 88: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Paired Pump Stations Provide Redundancy

46

Brattle Court Pump Station (1907) Spring Street Pump Station (1958) redundancy to Brattle Courtto Brattle Court

Gillis Pump Station (1899) Spot Pond Pump Station (2015) redundancy to Gillis Station

Page 89: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Other MWRA Redundancy Projects

47

• CVA pipeline redundancy• Hultman interconnections / MetroWest tunnel• Northern Intermediate High Pipe Loop

New valve chamber connecting MWWST and Hultman Aqueduct at Shaft 5 (2013)

Night work on 36-inch NIH pipeline in Woburn (2016)

Night work on 36-inch NIH pipeline in Woburn

Page 90: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Southern Extra High Pipe Loop to provide redundant supply to Boston, Norwood, Canton, Stoughton, and Dedham/Westwood

• Wachusett Aqueduct Pump Station to Provide Redundancy to Cosgrove Tunnel between Wachusett Reservoir and Carroll Treatment Plant

Other MWRA Redundancy Projects

48Wachusett Aqueduct Pump Station

Page 91: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

49

Previous Redundancy Evaluations

• 1938 Plan – Tunnel Loop

Page 92: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• 1990 Plan – MetroWest Tunnel followed by Northern Tunnel Loop

50

Previous Redundancy Evaluations (continued)

Page 93: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• 2011 Plan – Surface piping with Northern and Southern Components

51

Previous Redundancy Evaluations (continued)

Page 94: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

52

Difficulties Carrying Out 2011 Plan

Page 95: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

2011 Redundancy Plan

53

• 14 alternatives evaluated

• 2011 Proposed Redundancy Plan included

– 7 miles of 72-inch pipeline construction to the north– 4 miles of 84-inch steel pipe slip-lining Sudbury Aqueduct to

Chestnut Hill area – 4 miles of tunnel or large diameter surface pipe from

Norumbega or Shaft 5 area to the Sudbury Aqueduct

Page 96: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

2011 Plan 2011 Plan –– Surface piping with Northern and Southern 2011 Plan 2011 Plan 2011 Plan Surface piping with Northern and Southern Surface piping with Northern and Southern Components

54

Page 97: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Traffic– Street Closures & Detours– Congested City Streets/Gridlock

• Business Disruption– Access Disruption– Loss of Business

• Permitting & Approval– Multiple Environmental and Agency Permits– Street Opening Approvals & Fees

• Community Disruption– Noise– Dust– Detours– Long Period of Impacts Over Large Areas– Mitigation

Impacts of Surface Pipeline

55

Page 98: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Newton Street Newton Street -- Waltham

56

Page 99: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Main Street (Route 20) Waltham

57

Page 100: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

TrapeloTrapelo Road at Pleasant Street Road at Pleasant Street -- Belmont

58

Page 101: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Felton Street Felton Street -- Waltham

59

Page 102: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Felton Street Felton Street -- Waltham

60

Page 103: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Construction of 72Construction of 72-Construction of 72-inch Spot Pond Pipeline

6161

Page 104: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

565656-56-Inch Concrete Pipe Inch Concrete Pipe –– South Boston CSO Project

62

Page 105: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Washington Suburban Sanitary District– 5.3 mile tunnel was constructed in 2015 to avoid construction

impacts of a surface pipe

• East Bay Municipal Utility District (MUD)– 4 mile tunnel to avoid construction impacts to neighborhoods

• Metropolitan Water District of Southern California– 9 mile Tunnel in San Bernardino to avoid construction impacts

and seismic concerns

Other Utilities Have Constructed Tunnels to Avoid Surface Other Utilities Have Constructed Tunnels to Avoid Surface Other Utilities Have Constructed Tunnels to Avoid Surface Pipe Construction Impacts

63

Page 106: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

64

Evaluation of Alternatives

Page 107: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Due to the major impacts of miles of large pipe construction, additional tunnel alternatives were evaluated

• Previous and new alternatives were evaluated including pipelines, pumping and tunnels

– 13 alternatives to the north– 14 alternatives to the south

ReReRe-Re-evaluation of Alternatives

65

Page 108: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Six Categories of Alternatives

66

North

• No new pipes - Push northern system to its limits

• Replace WASM 3 with larger pipe or construct new pipe and/or add pump station

• Construct tunnel to north

South

• New tunnel or pipeline from Norumbega or Shaft 5 area to Chestnut Hill and upgrade Chestnut Hill Emergency Pump Station

• New pipe to southern surface mains with or without new Pump Station

• Tunnel to Dorchester Tunnel Shaft 7C

Page 109: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

67

Baseline Construction:

• Rehabilitate WASM 3• CHEPS Emergency

Generator• New Loring Road

pump connection• New Hultman valve• New 36” Waltham

pipeline

Cost to Complete:

$145M

(Midpoint of Construction)

Baseline Components For All Alternatives

Page 110: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Northern Component Northern Component –– Category 1 (one alternative)Northern Component Northern Component Northern Component Category 1 (one alternative)Category 1 (one alternative)Push Existing System to Its Limits

68

Convert part of WASM 4 and entire West Spot Pond pipeline to high service

• Cost: $10 million (one alternative)

• Cannot supply summer season demands

• Not reliable for planned maintenance shut down of tunnel system

• Could be used as contingency plan for emergency use while long term solution is being implemented

• Potential pipe replacement

Cost is midpoint of construction. Does not include WASM 3 baseline work

Page 111: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Northern Component Northern Component –– Category 2Northern Component Northern Component Northern Component Category 2Category 2Increase Capacity to North (Larger Pipe and/or Pump Station)

69

Construct larger diameter pipeline to the north

Construct pump station to force more flow through

pipeline

• Cost: $138 million - $473 million (six alternatives)

• Large diameter pipelines are extremely difficult to construct through congested urban areas

• Pump station could cause potential pressure surges in distribution system

Cost is midpoint of construction. Does not include WASM 3 baseline work

Page 112: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Northern Component Northern Component –– Category 2Northern Component Northern Component Northern Component Category 2Category 2Increase Capacity to North (Larger Pipe or Pump Station)

70

Alt 2N Alt 3N Alt 4N *

Alt 5N Alt 6N Alt 7N

Page 113: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Northern Component Northern Component –– Category 3Northern Component Northern Component Northern Component Category 3Category 3Increase Capacity to North (Tunnel)

71

Construct tunnel to the north

• Cost: $472 million - $1,292 million (six alternatives)

• Construction impacts would be limited to shaft construction sites and pipe connections

• Would provide redundancy to WASM 3 pipeline

• Meets redundancy goals under all demands

• Allows year round maintenance of tunnel system (in combination with a southern solution)

Cost is midpoint of construction. Does not include WASM 3 baseline work

Page 114: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Northern Component Northern Component –– Category 3Northern Component Northern Component Northern Component Category 3Category 3Increase Capacity to North (Tunnel)

72

Alt 8N * Alt 9N Alt 10N

Alt 11N Alt 12N Alt 13N

Page 115: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Southern Component Southern Component –– Category 1Southern Component Southern Component Southern Component Category 1Category 1Increase Capacity to Chestnut Hill (tunnel or pipeline)

73

Construct tunnel or pipeline to Chestnut Hill

Re-construct Chestnut Hill Emergency Pump Station

• Cost: $293 million - $629 million (nine alternatives)

• Large diameter pipelines are extremely difficult to construct through congested urban areas

• Pump station would cause higher pressures and potential surges in distribution system

Cost is midpoint of construction. Does not include WASM 3 baseline work

Page 116: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Southern Component Southern Component –– Category 1Southern Component Southern Component Southern Component Category 1Category 1Increase Capacity to Chestnut Hill (tunnel or pipeline)

74

Alt 5S Alt 6S Alt 7S

Alt 9S Alt 11S Alt 12S

Page 117: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Southern Component Southern Component –– Category 1 (continued)Southern Component Southern Component Southern Component Category 1 (continued)Category 1 (continued)Increase Capacity to Chestnut Hill (tunnel or pipeline)

75

Alt 15S *Alt 14S Alt 16S

Page 118: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Southern Component Southern Component –– Category 2 Southern Component Southern Component Southern Component Category 2 Category 2 Increase Capacity to South (pipeline with or without pump station)

76

• Cost: $363 million - $390 million (two alternatives)

• Large diameter pipelines are extremely difficult to construct through congested urban areas

• Pump station would cause potential damaging pressure surges in distribution system

Construct pipeline to southern system

Construct New Pump Station

Cost is midpoint of construction. Does not include WASM 3 baseline work

Page 119: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Southern Component Southern Component –– Category 2 Southern Component Southern Component Southern Component Category 2 Category 2 Increase Capacity to South (pipeline or pump station)

77

Alt 8S * Alt 10S

Page 120: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Southern Component Southern Component –– Category 3Southern Component Southern Component Southern Component Category 3Category 3Increase Capacity to South (Tunnel)

78

Construct tunnel to southern system

• Cost: $716 million - $1,034 million (three alternatives)

• Construction impacts would be limited to shaft construction sites and pipe connections

• Meets redundancy goals under all demands

• Allows year round maintenance of tunnel system (in combination with a northern solution)

Cost is midpoint of construction. Does not include WASM 3 baseline work

Page 121: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Southern Component Southern Component –– Category 3Southern Component Southern Component Southern Component Category 3Category 3Increase Capacity to South (Tunnel)

79

Alt 17S Alt 19SAlt 18S *

Page 122: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

80

Financial Considerations

Page 123: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Financial Considerations

• Preserve Sustainable and Predictable Rates at Water Utility level

• Ensure Adequate Capital is Available When Necessary

• Minimize Cost of Borrowing

Page 124: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Debt Service Profile

$0

$100

$200

$300

$400

$500

$600

$ in

mill

ions

Projected Debt Service

Page 125: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

1. CIP without Long –Term Redundancy Project

2. Lowest Cost Alternative - $729M midpoint of construction

3. Middle Cost Alternative - $1.47B midpoint of construction

4. Highest Cost Alternative -$2.3B midpoint of construction

Four Alternatives Modeled

83

Page 126: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Debt Service Pro Forma

$0

$100

$200

$300

$400

$500

$600

1990

1992

1994

1996

1998

2000

2002

2004

2006

2008

2010

2012

2014

2016

2018

2020

2022

2024

2026

2028

2030

2032

2034

2036

2038

2040

2042

2044

2046

2048

2050

2052

2054

2056

2058

2060

$ in

mill

ions

Projected Debt Service Pro FormaBased on Middle Cost Alternative

Page 127: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Combined Assessments

$600,000

$650,000

$700,000

$750,000

$800,000

$850,000

$900,000

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Amou

nt in

$00

0s

Combined Rate Revenue Requirement

Combined No LTR Combined Least Combined -Non Phased Combined -Max

Page 128: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Water Utility Assessments

$200,000

$250,000

$300,000

$350,000

$400,000

$450,000

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Amou

nt in

$00

0s

Water Utility Rate Revenue Requirement

Water No LTR Water Least Water - Non Phased Water -Max

Page 129: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Combined Rate Projections

-6%

-4%

-2%

0%

2%

4%

6%

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Annu

al ra

te

Rate of Change to Combined Assessments

Combined No LTR Combined Least Combined -Non Phased Combined -Max

Page 130: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Water Utility Projections

-6%

-4%

-2%

0%

2%

4%

6%

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Annu

al ra

te

Rate of Change to Water Utility Assessments

Water No LTR Water Least Water - Non Phased Water -Max

Page 131: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Staff Preferred Alternative

Page 132: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Staff Recommendation Staff Recommendation –– Interim Measures

90

• Take action now to reduce risk of failure/improve ability to respond:

– Tunnel-shaft pipeline improvements $ 7.5 million– Chestnut Hill Pump Station improvements

• Emergency power $ 10.9 million• Investigate feasibility of pump

output controls $ 22.5 million– WASM 3 rehabilitation $104.6 million– Commonwealth Avenue pump station

low service suction capability $ 8.0 million– Increase PRV capacity WASM 3 and WASM 4 $ 8.7 million– PRVs for East/West Spot Pond Supply Main

community connections $ 1.3 million

Total $ 163.5 million

Page 133: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Emergency and Planned Shut-Down Capability Preferred

– Allows maintenance of system– Maintenance reduces risk of failure– Meet customer expectations for excellent quality water– Minor impact on normal service

Strategic Goal for LongStrategic Goal for Long-Strategic Goal for Long-Term Redundancy

91

Page 134: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Need additional capacity to supply water to both the north and south

• Chestnut Hill Emergency Pump Station cannot reliably supply enough water to the south with the Dorchester Tunnel shut down

• Long distance large diameter surface pipelines in urban areas present significant implementation challenges

Findings of Alternatives Analysis

92

Page 135: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Preferred Alternative for LongPreferred Alternative for Long-Preferred Alternative for Long-Term Redundancy

93

• Two Tunnel Option Preferred

• Time to Complete: 17 - 23 years

• Tunnels begin in the Mass Pike/Route 128 vicinity

• Northern Tunnel 4.5 miles, connects to mid-point of WASM 3 in Waltham/Belmont area.

• Southern Tunnel 9.5 miles, connects to Shaft 7C and southern surface mains

Page 136: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Meets Many Objectives:

• No boil order

• Flow and pressure for normal service and fire protection

• Ability to perform maintenance

• Additional benefit: Ability to meet high day demand. No seasonal restrictions.

Preferred Alternative for LongPreferred Alternative for Long-Preferred Alternative for Long-Term Redundancy

94

Page 137: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Midpoint of Construction Cost: $1,470 -$1,700 million

• Costs include:– 30% contingency

factor– 4% annual

escalation

• Cost does not include baseline / interim improvement costs.

Preferred Alternative for LongPreferred Alternative for Long-Preferred Alternative for Long-Term Redundancy

95

Page 138: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Could be built in phases

• Northern Tunnel– Redundancy for City

Tunnel Extension– Could shut City Tunnel

during periods of low demand and still feed south

• Southern Tunnel – Redundancy for

Dorchester Tunnel– Eliminates reliance on

the CHEPS

Construction in Phases Still Provides Benefit

96

Northern Tunnel

Southern Tunnel

Page 139: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• If a phased approach is a goal, staff would recommend that the Northern Tunnel be constructed first

• With Northern Tunnel in place– test valves at Shaft 7 – potentially address

Shaft 5, Shaft 9 or Shaft 9A concerns

Phased Construction of Preferred Alternative

9797

Shut down City Tunnel (winter only)

Supplement down City Tunnel Ext to Dorchester Tunnel

Supply through new Northern Tunnel & WASM 3

X XSupply with Chestnut Hill pump station from Boston Low

PS

Page 140: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Possible Schedule for Preferred Alternative

98

2 Years

3 Years

6.5 Years

11.5 Years

2 Years

3 Years

6.5 Years

3 Years

11.5 Years

Cost to Complete: $1,470 million (escalated to midpoint of Construction)

Cost to Complete: $1,700 million (escalated to midpoint of Construction)

Page 141: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

2 Preferred Alternatives Modeled

Description DurationCost

Mid-point of Construction

Non Phased 17yrs $1.47BPhased 23yrs $1.70B

Page 142: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Cash Flows

$-

$10,000

$20,000

$30,000

$40,000

$50,000

$60,000

$70,000

$80,000

$90,000

$100,000

Amou

nt in

$,0

00s

Cash Flows Non-Phased

$-

$10,000

$20,000

$30,000

$40,000

$50,000

$60,000

$70,000

$80,000

$90,000

$100,000

Amou

nt in

$00

0s

Cash Flows Phased

Page 143: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Cash Flows

$-

$10,000

$20,000

$30,000

$40,000

$50,000

$60,000

$70,000

$80,000

$90,000

$100,000

Amou

nts i

n $

000s

Cash Flows Compared

Phased $1.70B MPoC Non-Phased $1.47B MPoC

Page 144: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Combined Assessments

$600,000

$650,000

$700,000

$750,000

$800,000

$850,000

$900,000

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Amou

nt in

$00

0s

Combined Rate Revenue Requirement

Combined -Non Phased Combined -Phased

Page 145: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Water Utility Assessments

$200,000

$220,000

$240,000

$260,000

$280,000

$300,000

$320,000

$340,000

$360,000

$380,000

$400,000

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Amou

nt in

$00

0s

Water Utility Rate Revenue Requirement

Water - Non Phased Water-Phased

Page 146: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Combined Rate Projections

-6%

-4%

-2%

0%

2%

4%

6%

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Annu

al ra

te

Rate of Change to Combined Assessments

Combined -Non Phased Combined -Phased

Page 147: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

Water Utility Rate Projections

-6%

-4%

-2%

0%

2%

4%

6%

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Annu

al ra

te

Rate of Change to Water Utility Assessments

Water - Non Phased Water-Phased

Page 148: History of the Water System - MWRA - Home– Surface pipe, valves and appurtenances • Little maintenance required for tunnels and shafts. Little risk of failure. • Pipe, valves

• Redundancy for Metropolitan Tunnel system is necessary for maintenance and emergency response

• If we do nothing, failure will eventually occur• Extensive alternatives were identified and evaluated• Long distance large diameter pipeline alternatives present

significant implementation challenges• Operational reliability problems were identified with Chestnut Hill

Pump Station and other proposed pump stations

• Preferred tunnel alternatives meet service objectives and goals– Allows planned maintenance of 60+ year old infrastructure

that are beyond their useful life– Allows emergency response at normal level of service– Constructible

Meeting Summary

106