18
Historical Power Plant Closures Jim Lingle Senior Project Manager EPRI Plant Closure Workshop November 12, 2009

Historical Power Plant Closures

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Historical Power Plant Closures

Historical Power Plant Closures

Jim Lingle Senior Project Manager

EPRI Plant Closure WorkshopNovember 12, 2009

Page 2: Historical Power Plant Closures

2© 2009 Electric Power Research Institute, Inc. All rights reserved.

Lakeside Power Plant

• 1921: began operation with 20 boilers

• 1968: converted to natural gas• 1983: plant decommissioned• 1985: property sold, demo began • 1994: Environmental Assessment• 1996: Soil Closure Report for

petroleum area, Addendum to Site Investigation Report, Capping Plan for ash area on northern parcel

• 1997 Groundwater monitoring plan

Page 3: Historical Power Plant Closures

3© 2009 Electric Power Research Institute, Inc. All rights reserved.

Lakeside Power Plant

Page 4: Historical Power Plant Closures

4© 2009 Electric Power Research Institute, Inc. All rights reserved.

Lakeside Property

Page 5: Historical Power Plant Closures

5© 2009 Electric Power Research Institute, Inc. All rights reserved.

Lakeside Environmental Issues

• Asbestos• Lead paint• PCB impacted equipment• Petroleum in fuel storage and truck unloading area• Ash in ponds• Ash in northern parcel• Coal and ash on western T-line & trolley property• PAHs in sediments in pond• Bluff stabilization

Page 6: Historical Power Plant Closures

6© 2009 Electric Power Research Institute, Inc. All rights reserved.

Solutions to Environmental Challenges

• Power plant foundation used as a licensed landfill for asbestos and demo debris

• Paint dried and disposed of as a solid waste• Oil-filled equipment tested for PCBs, drained and disposed of

according to regulations• Petroleum containing soils excavated• EPRI ROAM modeling of PAH behavior in groundwater• Well point samples in lake showed SO4 and B not above standards

(sulfate reducing bacteria)• PAH in pond sediments from Milwaukee Harbor• Ash relocated and used as structural fill for parking lot• Coal deposits burned at another plant• Negotiations, negotiations, negotiations

Page 7: Historical Power Plant Closures

7© 2009 Electric Power Research Institute, Inc. All rights reserved.

Demolition of the Lakeside Turbine Room

Page 8: Historical Power Plant Closures

8© 2009 Electric Power Research Institute, Inc. All rights reserved.

Developer’s Plan for Substation Area

Figure from: www.mandelgroup.com

Page 9: Historical Power Plant Closures

9© 2009 Electric Power Research Institute, Inc. All rights reserved.

Current Conditions

Northern Area Power Plant

Southern Area Substation

Page 10: Historical Power Plant Closures

10© 2009 Electric Power Research Institute, Inc. All rights reserved.

Port Washington Power Plant

• 1935-1950: 6 unit 341 MW plant

• 2003 Unit 4, 5 & 6 demolished

• 2004 Unit 1, 2, & 3 demolished

• Recycle– 22,000 tons of

structural steel– 3000 tons of

specialty metals– 12,000 tons of

concrete• Landfill

– <10% land filled

Page 11: Historical Power Plant Closures

11© 2009 Electric Power Research Institute, Inc. All rights reserved.

Environmental Issues

• Wastewater treatment ponds• Coal pile runoff basins • Asbestos (siding, window glazing, roofing, stack coating,

etc.)• Lead paint flaking from metal• Oil filled equipment• PCBs (switch house sump and transformer yard)• Exit signs (tritium)• Chromium containing firebrick

Page 12: Historical Power Plant Closures

12© 2009 Electric Power Research Institute, Inc. All rights reserved.

Environmental Issues

• Lab chemicals• Paint• Coal pile runoff • Coal dock abandonment• Regulatory limits

– PCBs <1 ppm in soil– Trace metals in wastewater

• Be <0.11 ug/l• Hg <1.3 ng/l

Page 13: Historical Power Plant Closures

13© 2009 Electric Power Research Institute, Inc. All rights reserved.

Solutions

• NR 213 evaluation of wastewater treatment ponds– Geoprobe soil samples, piezometer, and surface water

• PCB pre-treatment system• PCB soil excavation - EPA Self-Implementing Cleanup• Trailer for temporary PCB equipment storage• Baker tanks/micron filter bags for treatment of asbestos

containing wastewater• Hazardous waste disposal of firebrick• Coal dock soil excavation, capping, stormwater control• Inspection, inspection, inspection

Page 14: Historical Power Plant Closures

14© 2009 Electric Power Research Institute, Inc. All rights reserved.

Switchyard Cleanup

Page 15: Historical Power Plant Closures

15© 2009 Electric Power Research Institute, Inc. All rights reserved.

Demolition of Coal Crusher House

Page 16: Historical Power Plant Closures

16© 2009 Electric Power Research Institute, Inc. All rights reserved.

Unit 1 Complete (545 MW Gas-fired)

Page 17: Historical Power Plant Closures

17© 2009 Electric Power Research Institute, Inc. All rights reserved.

Potential Plans for Public Use of Coal Dock

Page 18: Historical Power Plant Closures

18© 2009 Electric Power Research Institute, Inc. All rights reserved.

Completed Two-Unit Gas-Fired Plant