Architecture Design and Construction 

Project Review and Approval Process 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Issued 11 Oct 2012 

(L0046791) (L0046829) (L0046857) 

Page 2: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Contents 

 

CONTENTS 

Section  Page No. 

Introduction  1 

General Requirements  2 

Design Review and Approval Process  4 

Project Meetings  7 

New Construction  9 

Conversions  17 

 

Appendices 

 

Appendix A – Preliminary Plan Submission   

Appendix B – Design Development (50%) Plans and Specifications Submission   

Appendix C – Final (100%) Plans and Specification Submission   

Appendix D – Shop Drawings and Other Submissions   

Appendix E – Acceptance Protocol (Management Agreement)   

Appendix E – Acceptance Protocol (Franchise Agreement) 

 

   

 

   

   

   

Page 3: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 1 

 

INTRODUCTION 

Purpose of this Document 

The purpose and objective of this document is to supplement the approval and review process requirements 

set  out  in  the  relevant  Franchise  Agreement  and/or  Management  Agreement  and/or  Technical  Services 

Agreement relating to the relevant hotel (the “Operating Agreement”) regarding the design, construction, pre‐

opening and opening phases of a new or conversion hotel development and to set out the framework around 

which those reviews and approvals are conducted. 

The  following  procedures  are  to  be  read  in  conjunction with  the  relevant  Operating  Agreement. Nothing 

contained in this document relieves any of the parties of any obligations or contractual responsibilities under 

the relevant Operating Agreement and  in the event of any conflict between this document and the relevant 

Operating Agreement the latter shall prevail. References in this document to “Hilton Worldwide” means Hilton 

Worldwide  Inc  and/or  its  affiliates  that  are  party  to  a  relevant  Operating  Agreement.  References  in  this 

document to “Owner” mean the counterparty to the relevant Operating Agreement that has an obligation to 

construct, renovate, fit out, equip and decorate the hotel subject to such Operating Agreement. 

All  of  these  pages  and  the  relevant  Hilton Worldwide  architecture,  design  and  construction  standards  (of 

which  this document  forms part) applicable  to  the brand under which  the hotel which  is  the subject of  the 

Operating Agreement shall operate (the “Hilton Worldwide Architecture, Design and Construction Standards”) 

will apply to all of the following situations: 

1. New construction hotels. 

2. Conversion of non‐Hilton Worldwide branded hotels to Hilton Worldwide branded hotels. 

3. Renovation and refurbishment works to re‐licensed Hilton Worldwide branded hotels 

The Role of Hilton Worldwide Architecture, Design & Construction 

Hilton Worldwide’s Architecture, Design  and Construction  team  (the  “A,D&C  Team”) has  experience  in  the 

design  and management  of  the  branding,  refurbishment,  extension  and  construction  of  Hilton Worldwide 

hotels. The A,D&C Team covers a diverse range of construction and design disciplines and will provide a range 

of assistance to the Owner’s Professional Team including in relation to procurement, architecture and interior 

design, service installation design and costs throughout the hotel development process.  

Hilton Worldwide Project Director 

For every development opportunity a Project Director will be nominated  from within  the A,D&C  team  (the 

“Hilton Worldwide  Project Director”).  The Hilton Worldwide  Project Director will  be  the  principle  point  of 

contact during the entire hotel development process from inception to opening.  The Hilton Worldwide Project 

Director is there to assist the Owner’s Professional Team achieve the smooth and trouble‐free delivery of the 

highest  quality  hotel  product  that  incorporates  the  following  fundamental  components  of  any  Hilton 

Worldwide hotel from an architecture and construction perspective: 

Cost effective architecture, design and construction that is compliant with relevant Hilton Worldwide 

Architecture, Design and Construction Standards and any other relevant brand standards;  

   

Page 4: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 2 

 

INTRODUCTION – CONT’D 

Project Management – Cont’d 

Operational efficiency; 

Architectural and interior design excellence; 

Energy efficiency and sustainability through construction and in operation. 

Design 

The role of Hilton Worldwide’s Global Design Services group is to provide design guidance for key areas of the 

hotel,  including optimising  the  spatial  requirements and operational  relationships  in both  front and back of 

house areas of the hotel.  Interior design excellence is a key factor in all Hilton Worldwide hotels and the team 

provide both design direction and assistance in this area and are happy to recommend relevant interior design 

consultants for each project.  

Within  the Global Design  Services  group  is  a  dedicated  FF&E  group.  This  group  provides  guidance  on  the 

compilation of FF&E and OSE schedules  for  the hotel project and constantly works with Hilton Worldwide’s 

internal sourcing team and supply chain to ensure that product selection  is always current and relevant, and 

seeks to deliver value for Owners. 

All of this culminates in Hilton Worldwide’s overall objective helping Owners to deliver exceptionally designed 

hotels whilst remaining cost effective and operationally efficient. 

Engineering Support 

The Engineering Support group (within the A,D&C Team) will provide guidance on all mechanical, electrical and 

plumbing installations and advice on the delivery of a hotel that conforms to Hilton Worldwide’s overall global 

environmental and sustainability initiatives and targets.  

   

Page 5: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 3 

 

GENERAL REQUIREMENTS 

Generally 

The following sections shall apply to all new construction and conversion projects in whatever form. 

Approval of Owner’s Professional Team  

Hilton Worldwide will only accept the use of qualified professionals  that have gained relevant experience  in 

the design and construction of quality hotel operations. This will include all professionals who form part of the 

professional  team  for  the  project  (“Owner’s  Professional  Team”)  including,  but  not  limited  to,  architects, 

project managers, MEP  engineers,  structural  engineers,  interior  designers,  kitchen  consultants,  landscape 

architects and other specialist consultants. The relevant Operating Agreement may specify  those mandatory 

consultants that must be engaged on the project and that are subject to Hilton’s approval.  

In  order  to  assist with  the  selection  of  appropriate  consultants,  the  A,D&C  Team will  provide  a  preferred 

consultant panel for these mandatory consultants, when requested.  

Prior to the commencement of the design, planning and approval process, the A,D&C Team must be furnished 

with  contact  information  and  relevant  hotel  experience  for  all  of  the Owner’s  Professional  Team  that  the 

Owner is intending to retain on the project and will review and confirm in writing its approval or rejection of 

those proposed parties within the project team. 

Appointment of Owner’s General Contractor 

Where  requested,  the A,D&C Team will provide details of general contractors  they consider appropriate  for 

inclusion on the Owner’s tender list. 

Access to the Hilton Worldwide Architecture, Design & Construction Standards 

Access  to or distribution of  the  relevant Hilton Worldwide Architecture, Design and Construction Standards 

manuals will be arranged by the Hilton Worldwide Project Director. The Hilton Worldwide Project Director will 

liaise with the Owner and the Owner’s Professional Team as to the  implementation of these standards. The 

access to this  information will generally be subject to the project being at an appropriate stage and a signed 

and legally binding unconditional Operating Agreement being in place. 

   

Page 6: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 4 

 

DESIGN REVIEW PROCESS GENERALLY 

Design Elements 

Competition in today’s hotel market makes protecting Hilton Worldwide’s brands essential for the success of 

the hotel for the benefit of all parties. Design elements contained  in Hilton Worldwide’s brand hotels enable 

guests  to  associate  Hilton Worldwide’s  services  with  the  high  standards  of  quality  that  Hilton  strives  to 

provide. For  that  reason, Owners acknowledge  that  it  is  in all parties’  interests  to develop a design  for  the 

hotel project which is consistent with Hilton Worldwide’s overall design intent. Accordingly, Owner agrees that 

Hilton shall have final design approval of all finishes, colours and materials within the hotel project. 

Design Review Workshops 

Whilst the formal design review process requires specific information (as described later in this document), in 

order  to  foster  an  open  and  ongoing  process  of  communication  regarding  design  elements,  it  is  strongly 

recommended that separate informal design review workshops are conducted for all areas of the hotel and for 

all design disciplines during the course of the design development phase of the project.  

Experience has  shown  that not only  is  the  time period  required  for  formal approval  significantly  reduced  if 

these design workshops are held prior to formal submissions being made, but also the quality of the hotel  is 

enhanced and abortive design and/or construction work is potentially avoided.  

All reviews shall be arranged by the Owner and Hilton Worldwide.  Ideally, all  information to be discussed at 

the  workshop  should  be  supplied  seven  (7)  calendar  days  prior  to  any meeting  where  feedback may  be 

required. 

Owner  attendees  shall  include  those  individuals  necessary  to  provide  a  full  presentation  of  the  design 

elements being reviewed and to be approved by Hilton Worldwide. Hilton Worldwide attendees shall include 

those  individuals with  decision‐making  authority  regarding  the  design  elements  to  be  approved  by  Hilton 

Worldwide.  

Presentation materials  shall  include  renderings,  colour boards  and  technical  specification books,  as well  as 

material, fabric and carpet samples where relevant.  

Formal Design Approvals 

Prior  to  commencing  any  works  on  site  all  documents  and  drawings  describing  any  proposed  new 

construction, refurbishment and/or alterations to the hotel must be provided to and approved by the A,D&C 

Team. 

The formal plan review process is designed to ensure the timely submittal of the necessary and relevant plans 

and information required to enable a considered review, give appropriate feedback, and finalise any required 

amendments to and/or agreement of such plans or project information. This will ensure that all parties have a 

clear and mutual understanding of what  information  is required, what  is being proposed, what feedback has 

been given, what actions are required and what is approved.  

The Owner shall submit full‐size, reproducible drawings of all proposed submittals to Hilton Worldwide for its 

approval as detailed in the following pages.   

   

Page 7: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 5 

 

DESIGN REVIEW PROCESS GENERALLY – CONT’D 

Formal Design Approvals – Cont’d 

Hilton Worldwide  shall provide either written approval or disapproval of  the Plans  formally  submitted. Any 

items disapproved by Hilton Worldwide will be returned to the Owner with a written explanation detailing the 

reasons for such disapproval. Promptly following any Hilton Worldwide notice of disapproval, the Owner and 

Hilton Worldwide shall attempt to reach a satisfactory and agreeable resolution of the disapprovals submitted 

by Hilton Worldwide. The Owner shall incorporate any agreed upon modifications in a revised submission and 

resubmit these to Hilton Worldwide. 

Review Criteria 

The criteria applied by Hilton Worldwide during the formal design review process are to assess the designs and 

their compliance against the following general criteria (which are set out in no particular order of priority):  

(i) the agreed scope of the project; 

(ii) any relevant Hilton Worldwide Architecture, Design & Construction Standards; 

(iii) accepted industry standards; 

(iv) the design narrative for the relevant Hilton Worldwide brand; and 

(v) any other relevant Hilton Worldwide Brand Standards. 

Design Revisions and Changes 

All Hilton Worldwide’s comments or modifications to all plans and specifications, to the extent necessary to 

assure that the hotel project meets the Hilton Worldwide Architecture, Design & Construction Standards, shall 

be implemented by the Owner. In the event the Owner is aware of any deviation, change or departure in the 

actual  design,  development,  construction,  engineering,  planning,  equipping,  fixturing,  furnishing,  or 

completion of the hotel project, the Owner shall so advise Hilton Worldwide promptly  in writing of any such 

deviation, change or departure  in sufficient detail and with sufficient time to allow Hilton Worldwide to fully 

evaluate and approve or disapprove the deviation, change or departure.  

Review Basis 

Hilton Worldwide will be working in an advisory capacity but it is noted that any approval by Hilton Worldwide 

shall  not  be  deemed  or  construed  to  imply  any  representation  or warranty  as  to  the  item  or matter  so 

approved. 

Equally,  Hilton  Worldwide  shall  not  be  responsible  for  the  adequacy  or  coordination  of  any  plans  and 

specifications or for the structural soundness or integrity of any part of the project, or for the sufficiency of any 

mechanical and/or electrical systems. This all remains the sole and exclusive responsibility of the Owner.  

   

Page 8: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 6 

 

DESIGN REVIEW PROCESS GENERALLY – CONT’D 

Review Basis – Cont’d 

No review, comment, sanction, agreement, consent or other approval, recommendation (including in respect 

of the members of the Owner’s Professional Team), advice or inspection by or on behalf of Hilton Worldwide 

or any failure or delay by Hilton Worldwide in making or giving the same shall: 

(i) relieve  the Owner  (or any  third party engaged by  the Owner)  in whole or  in part of any of  its 

obligations or liabilities under the Operating Agreement;  

 

(ii) render Hilton Worldwide responsible or liable to the Owner or to any other person for the project 

(or any part thereof) or for any delay relating thereto; and 

 

(iii) be  relied  upon  by  any  person  other  than  the  Owner,  and  then  only  by  the  Owner  for  the 

purposes set out in the Operating Agreement. 

 

   

Page 9: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 7 

 

PROJECT MEETINGS 

Kick‐Off Meeting 

A kick‐off meeting will take place to introduce all of the key contacts from the Owner’s Professional Team and 

the Hilton Worldwide A,D&C  Team.  It  is  a  forum  that will  enable Hilton Worldwide  to  communicate  to  all 

parties  the  intent  of  the  Hilton Worldwide  Architecture,  Design &  Construction  Standards which must  be 

followed. It will help the Owner’s Professional Team understand the key areas of information that is required. 

This meeting  should  be  attended  by  the  following:  Owner/Developer/Investor  and  consultants;  Architect, 

Designer,  Project Manager, MEP  Consultant  and  from  Hilton Worldwide;  representatives  from  the  A,D&C 

Team and from Development plus any other relevant Hilton Worldwide parties. 

Pre‐Construction Meetings 

Pre‐construction meetings shall take place on a basis that enables regular updates on the design process and 

approval status. They should be at least every 2 months and the agenda should be similar to that of the kick off 

meeting. An update  shall be produced by  the Owner  for both  the design programme and  the  construction 

programme. A  schedule  of  all  outstanding  items must be  produced  and  reviewed  to  keep  a  record  of  the 

approval status and general content.  

Pre‐Construction Meeting Minutes  

The Owner  shall  arrange  for minutes,  in  English,  to  be  prepared  and  distributed  to  all meeting  attendees 

promptly  following each review session. These minutes shall reflect specifically which design elements were 

approved and which design elements were rejected by Hilton Worldwide and the steps which need to be taken 

in order to obtain Hilton Worldwide’s full approval of all design elements. The accuracy of the minutes shall be 

verified by the Hilton Worldwide Project Director.  

Construction Progress Meetings and Reports 

The Hilton Worldwide Project Director and the members of the Owner’s Professional Team shall be available 

via telephone conference or by attendance at meetings, as agreed between the Owner and Hilton Worldwide 

from time to time. The schedule of telephone conference calls and meetings shall be periodically reviewed by 

the Owner and Hilton Worldwide as and when required.  

Until  completion of  the hotel  there  shall be  regular monthly  technical meetings  relating  to  the design  and 

building works arranged for that purpose between the Owner, the Owner’s Professional team, and the General 

Contractor to review the progress of the building works. The Owner shall give to Hilton Worldwide appropriate 

notice of and copies of the agenda of all such meetings. 

The Owner shall provide to Hilton Worldwide the following in English: 

a. Reasonable notice of and an invitation to all relevant meetings (including site, design, team, or project 

meetings) and the minutes of all such meetings. 

b. Contractor’s monthly reports produced in connection with the project. 

   

Page 10: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 8 

 

PROJECT MEETINGS – CONT’D 

Construction Progress Meetings and Reports – Cont’d 

c. Monthly  reports  identifying  all  relevant material  issues  relating  to  the  project  including  without 

limitation:  

(i) Monthly  programme  status  of  overall  project  and major  construction  items  including  any 

planned measures to recover delays when measured against the initial project programme;  

(ii) Digital photographs showing the general level of progress;  

(iii) Schedule of any outstanding information required from Hilton Worldwide; and 

(iv) Formal design submission approval status by Hilton Worldwide. 

Construction Meeting Minutes  

The Owner  shall  arrange  for minutes,  in  English,  to  be  prepared  and  distributed  to  all meeting  attendees 

within five (5) calendar days following each progress/monthly meeting. These minutes shall reflect specifically 

which design elements were approved and which design elements were rejected by Hilton Worldwide and the 

steps which need to be taken  in order to obtain Hilton Worldwide’s full approval of all design elements. The 

accuracy of the minutes shall be verified by the Hilton Worldwide Project Director. 

 The Owner shall keep Hilton Worldwide informed of the progress of the project as related to the development 

program and the dates by which the Owner intends to and does issue all or any part of the project for tender.  

 

   

Page 11: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 9 

 

NEW CONSTRUCTION 

Generally 

All of  the  requirements  set out  in  the preceding  sections of  this Project Review and Approvals Process will 

apply to new constructions. The formal design submittals for a new construction project are described below. 

Project Brief 

Information  required  at  this  stage  is  to  communicate a basic  summary of  the proposal  to ensure  that  it  is 

aligned  with  the  requirements  of  the  relevant  Hilton  Worldwide  Architecture,  Design  and  Construction 

Standards  and  the  relevant  Hilton Worldwide  Brand  Standards.  It  must  include  a  project  brief,  facilities 

schedule, development program and concept design.  

As required by the Operating Agreement or, if not specified then, within thirty (30) calendar days of the signing 

of the Operating Agreement, the Owner shall submit in English to the A,D&C Team, for the approval of Hilton 

Worldwide, the elements that are required as follows: 

a. An Area Programme  (Facilities  Schedule)  for  the project  showing public  areas, back of house,  and 

guestroom components including a summary page showing gross areas and total enclosed areas per 

key, gross area of meeting spaces per key, guestroom and suite ratios, and any other significant data 

unique to this project. 

b. The  Project  Brief  in  English which  includes  a written  design  narrative  from  the  Architect,  Interior 

Designer, and/or F&B Designer incorporating their comments and inspirations for the design. It must 

outline the key objectives, scope of work, design guidelines, the Owner’s Professional Team and other 

requirements relating to the hotel and the project and,  if applicable,  information on any mixed use 

development  identifying how the non‐hotel aspects of the mixed use development  impact or affect 

the hotel. 

c. The Development Programme shall be a timeline identifying all key activities affecting, relating to or 

required for completion of the project and opening date including, the duration and completion date 

for each key milestone, obtaining approvals, developing and completing  the concept design, design 

development (the final floor plans, building envelope and system designs for each design discipline on 

the consultant category  list), contract documents, design approvals, mock‐up and prototype rooms, 

tendering, procurement,  construction,  fit‐out,  test  and  commissioning,  completion of  construction, 

pre‐opening activities commencement, “soft opening” and, if applicable, an indicative timeline for the 

mixed use development indicating any impact on the hotel project.  

Key  timing  milestones  and  their  completion  dates  that  must  be  shown  on  the  Development 

Programme will include the following as a minimum:  

i. Project Brief; 

ii. Facilities Schedule/Area Programme; 

iii. Development Program; 

iv. Concept Design; 

   

Page 12: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 10 

 

NEW CONSTRUCTION – CONT’D 

Project Brief – Cont’d 

v. Appointment of the Owner’s Professional Team; 

vi. Preliminary Plan submission; 

vii. Design Development (50%) Plans and Specifications Submission; 

viii. Final (100%) Plans and Specifications Submission; 

ix. Mock‐up and Prototype/Control Room(s); 

x. Construction commencement; 

xi. Commissioning commencement;  

xii. Hotel construction completion date  

xiii. Handover of hotel to manager/management company; 

xiv. Hotel opening date. 

d. Concept design. 

e. Detailed Budget/Cost Plan for the project submitted in an elemental format. 

Preliminary Plans Submission 

As  required  by  the Operating  Agreement  or  if  not  specified  then, within  3 months  following  date  of  the 

Operating Agreement,  the Owner  shall prepare  and  submit  to Hilton Worldwide  for  the  approval of Hilton 

Worldwide, the Preliminary Plans Submission. A Preliminary Plans Submission must consist of the submission 

form set out in Appendix A hereto together with the information listed therein. 

The  submission  shall  also  include  a  comprehensive  list  of  all  of  all  the  facilities  of  the  hotel,  including 

architectural drawings at 1:100 scale of all floor plans, sections and elevations of the building and, if applicable, 

information on any mixed‐use development identifying how the non‐hotel aspects of the mixed development 

impact  or  affect  the  concept  design  of  the  hotel.    The  objective  of  this  submission  is  for  the  Owner  to 

demonstrate that, in principle, the basic brand requirements as set out in the relevant Hilton Worldwide Brand 

Standards and Hilton Worldwide Architecture, Design & Construction Standards can be achieved and each of 

Hilton Worldwide’s brand customer satisfaction and brand positioning goals are met and the submission will 

be reviewed by Hilton Worldwide in this context. 

Hilton Worldwide  shall  respond  to  this  submission with a written  schedule highlighting  in each  case where 

approvals have been granted or where conditions or standards have not been achieved. Advice on how these 

areas can be adapted to achieve an approved status may be given where appropriate.   

Page 13: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 11 

 

NEW CONSTRUCTION – CONT’D 

Design Development (50%) Plans and Specifications Submission 

As required by the Operating Agreement, or if not specified then, within six (6) calendar months of the date of 

the  Operating  Agreement  but  not  less  than  six  (6)  calendar  months  prior  to  the  proposed  construction 

commencement date, the Owner shall submit to Hilton Worldwide, for the approval of Hilton Worldwide, the 

Design Development  (50%)  Plans  and  Specifications  Submission.  The Design Development  (50%)  Plans  and 

Specifications Submission must consist of the submission form set out in Appendix B hereto together with the 

information listed therein. 

The Design Development (50%) Plans and Specifications consist of detailed information including MEP design. 

This submittal will be reviewed mainly for overall design co‐ordination and conformance. It must also include 

outline  specifications  of  all  the  areas  as  listed  in  the  Design  Development  (50%)  Plans  and  Specifications 

Submission, preliminary  interior design elements  including concepts,  image boards and materials  including a 

written description of the proposed design of the food and beverage concept.  

Hilton Worldwide  shall  respond  to  this  submission with a written  schedule highlighting  in each  case where 

approvals have been granted or where conditions or standards have not been achieved. Advice on how these 

areas  can  be  adapted  to  achieve  an  approved  status may  be  given where  appropriate. All  changes  to  the 

design  as  described  in  the  response  shall  be  incorporated  into  the  Final  (100%)  Plans  and  Specifications 

Submission. 

Final (100%) Plans and Specifications Submission 

As required by the Operating Agreement, or if not specified then within nine (9) calendar months of the date 

of the Operating Agreement the Owner shall submit to Hilton Worldwide for the approval of Hilton Worldwide  

the Final (100%) Plans and Specifications Submission.  

The  Final  (100%)  Plans  and  Specifications  Submission  shall  include  but  not  be  limited  to  layouts, working 

drawings, millwork details, design detailing, schedules and specifications and must consist of the submission 

form set out in Appendix C hereto together with the information set out therein. 

No construction shall commence prior to the approval of the Final (100%) Plans and Specifications Submission. 

In the case of a “Phased Design & Build” project this shall apply to each  individual element and no element 

shall commence construction prior to its approval by Hilton Worldwide in accordance with this document. 

This submittal will be reviewed for final design co‐ordination and conformance. Hilton Worldwide will provide 

a written  response  to  all  items  and  issued  as described  in  the previous  review process. All  changes  to  the 

design as described in the Plan Review shall be incorporated into the Final Plans Document Review Submittal.   

A Plan Review will be issued to the Owner with comments noted for incorporation into the final construction 

documents.  Final  approval will  be  issued  upon  receipt  of  a written  notification  by  the  owner  agreeing  to 

respond  to outstanding  items and describing  the method  in which these  items will be resolved.   Addendum 

drawings may be necessary. 

   

Page 14: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 12 

 

NEW CONSTRUCTION – CONT’D 

Shop Drawings and Other Submissions 

Construction submittals must also be provided by the Owner if not included elsewhere to Hilton Worldwide for 

review  and  approval  prior  to  purchasing  or  orders  being  placed.  Manufacturers’  technical  information, 

drawings and specifications should be provided by the Owner to Hilton Worldwide for all of the items set out 

in Appendix D hereto for conformity review. 

Format of all Submissions 

All submissions are to be made in Adobe Acrobat pdf format as a minimum, in local language and English. 

Mock‐Up Room 

The Owner shall build and prepare for design purposes and for the approval of Hilton Worldwide, a mock up 

room for each typical room type e.g. king room, double room or different décor. Such mock‐up rooms shall be 

completed and available for approval within any applicable periods specified in the Operating Agreement, or if 

not specified then: 

(i) In respect of a full service brand, six (6) months from the commencement of construction of the hotel; 

and 

(ii) In respect of a focused service brand, three (3) months from the commencement of construction of 

the hotel; 

and  in any event prior to the mechanical, electrical and fire protection first fix  (rough  in works) and prior to 

making  purchasing  commitments  for  FF&E  and  other  guestroom materials.  The mock  up  room(s) may  be 

provided on site or off site as determined by the Owner. 

All drawings, specifications and FF&E control books in connection to the mock‐up room must be submitted by 

the Owner  at  least 6 weeks prior  to  commencement of  the  construction of  the  room.  For  focused  service 

brands  this  may  be  waived  if  it  is  considered  there  are  no  material  or  significant  deviations  from  the 

prototypical design for the relevant Hilton Worldwide brand. 

For the purpose of clarity a mock‐up room  is a fully fitted‐out and decorated typical guest room(s)  including 

adjoining corridor and services riser mock up for the purposes of design and operational approvals including all 

FF&E, operating equipment,  functioning  furniture,  fully operating power points and other electrical services 

and an air conditioning fan coil in the bulkhead, together with all fixed wall, floor and ceiling finishes, fittings 

and  services  for  the  purpose  of  benchmarking,  quality  control  and  services  co‐ordination.  The  review will 

require  the  attendance  of  the  following  parties:  Hilton Worldwide  Project  Director  and  Hilton Worldwide 

Design Manager, Owner’s Designer, Owner  (or Representative), General Contractor and Owner’s Purchasing 

Agent (if applicable). 

Following  the mock‐up  room  review meeting,  the Hilton Worldwide Project Director will distribute minutes 

confirming  the  status  of  all  the  items,  approved  or  rejected,  and  any  recommendations  considered 

appropriate. 

Approval must be obtained from Hilton Worldwide prior to any of these works being carried out on the actual 

hotel site and/or materials, products being ordered.  

   

Page 15: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 13 

 

NEW CONSTRUCTION – CONT’D 

Sample/Control Room 

Hilton Worldwide  requires a sample/control  room  to be made available  for  the purposes of quality control. 

This room must include all the proposed finishes and furnishings in the proposed guestroom to be constructed 

for review and approval by Hilton Worldwide. 

The  review will  require  the  attendance  of  the  following  parties: Hilton Worldwide  Project Director, Hilton 

Worldwide  FF&E Manager,  Hilton Worldwide  Design Manager,  Hilton Worldwide  Operations Manager  (in 

hotels managed by Hilton Worldwide), Owner’s Designer, Owner (or Representative), General Contractor and 

Owner’s Purchasing Agent (if applicable). 

Following  the  review meeting  the Hilton Worldwide Project Director will distribute minutes  confirming  the 

status of all the items, approved or rejected and any recommendations considered appropriate. All items must 

be resolved prior to the commencement of any fit out of guest rooms and corridors on the actual hotel site. If 

the  requirements of both  the mock‐up  room(s)  and  the  sample/control  room  can be  accomplished by  the 

construction of only one room this must be completed on site.   

Page 16: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 14 

 

NEW CONSTRUCTION – CONT’D 

Final Inspection, Project Completion and Handover 

The Hilton Worldwide Project Director  is responsible for co‐ordinating with all Hilton Worldwide functions  in 

order to verify that: 

(i) the hotel has been constructed and fitted out in accordance with Hilton Worldwide Architecture, 

Design and Construction Standards; and 

(ii) the hotel has been completed in terms of physical condition to such an extent as to be capable of 

being  operated  to  the  requirements  of  the  relevant  brand  and  is  ready,  in  terms  of  physical 

condition  only,  for  full  opening  to  the  public  in  accordance  with  the  terms  of  the  relevant 

Operating Agreement. 

For  the  avoidance of doubt,  the Hilton Worldwide Project Director’s  representations  relate  to  the physical 

condition of the hotel only and not to the operational readiness of the hotel. The opening of the hotel will only 

be permitted once  approval  is  given  to both  its physical  condition  and operational  readiness. As  such,  the 

following  conditions  only  relate  to  the  completion  of  the  physical  condition  of  the  hotel  and  not  to  its 

operational readiness.  

Completion  (and  in  the  case  of  hotels which  are  to  be managed  by Hilton Worldwide  handover  to Hilton 

Worldwide)  of  the  hotel  is  defined  in  and  governed  by  the  Operating  Agreement  and  shall  include  the 

following conditions which will be co‐ordinated by the Hilton Worldwide Project Director:  

1. 100% of the guestrooms must be complete in every detail and ready for habitation.  

2. 100% of  the public areas must be complete and  ready  for guest use,  including  the swimming pool 

and congruent areas (if applicable). 

3. Site construction must be totally complete. Construction trailers and equipment must be off site and 

away from guest view. 

4. All roadways and paved areas must have been swept and be free of any dirt or debris. 

5. The hotel must have  in place all consents, permits and  licenses required to operate all areas of the 

hotel  including but not  limited  to  the hotel’s  restaurant(s), bar(s), elevators,  swimming pools, etc. 

and  including but not  limited to the  licences etc. set out  in appendix 7 to the Acceptance Protocol 

Document (the form of which is set out in Appendix E). 

6. All  terms  of  the  Operating  Agreement must  be  fulfilled  on  or  before  the  date  specified  in  any 

conditional  opening  approval  letter  served  by  Hilton  Worldwide  which  relate  to  the  physical 

condition of the hotel. 

7. Evidence of  insurance  coverage must have been provided  to Hilton Worldwide as  required  in  the 

Operating Agreement.  

8. Full inspection by an independent third party inspector of all fire life safety systems and acceptance 

by Hilton Worldwide.  

   

Page 17: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 15 

 

NEW CONSTRUCTION – CONT’D 

Final Inspection, Project Completion and Handover – Cont’d 

The following information is required during the final inspection: 

1. The  date  when  practical  completion  (where  relevant)  under  the  Owner’s  building  contract  has 

occurred. 

2. Delivery of all operating and maintenance manuals to the hotel. 

3. Delivery to the hotel of all original consents, permits and licenses required to operate all areas of the 

hotel.  

4. Satisfactory completion of all the items as required by the Acceptance Protocol Document (the form 

of which is set out in Appendix E).   

5. The delivery of  the hotel  completion documentation as  specified  in  the Operating Agreement but 

which will generally comprise the following (relevant for Management Agreements only) : 

(i) a computer disk or CD of a complete set of final construction  issue drawings of the project 

(including  all works  constructed  in  connection  with  the  same,  the  route  and  connection 

points of all services to and from the same and details of any services re‐routed retained or 

disconnected) suitable for reproduction and record purposes;  

 

(ii) a  full  set  of  technical  specifications,  operation manuals  and maintenance  and  guarantee 

documentation  complete with  commissioning data  records  and  certificates  relating  to  any 

plant and machinery or any mechanical, electrical or electronic or other systems forming part 

of the project; 

(iii) details of all manufacturers and suppliers of specialist or proprietary materials or products 

used in the project which carry a supplier's or manufacturer's guarantee and details of such 

guarantee;  

(iv) any other additional information required by applicable  laws (for example, health and safety 

file information);  

(v) three (3) full sets of the “as built” drawings in hard copy and CAD format (*.dwg, *.dwf, etc.). 

   

Page 18: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 16 

 

NEW CONSTRUCTION – CONT’D 

Fire Life Safety 

Written  approval  of  the  plans  for  required  fire  safety  systems  must  be  obtained  from  the 

government/regulatory  authority  having  jurisdiction  prior  to  installation  of  the  fire  safety  system  and 

subsequently prior  to handover of  the hotel by Hilton Worldwide  (in  the case of a hotel managed by Hilton 

Worldwide) and/or hotel opening. 

The  form  of  written  approval  may  vary  by  government/regulatory  authority.  For  the  purposes  of  this 

document,  this  shall  be  defined  as  a  certificate,  letter  of  approval,  permit,  stamp  of  approval,  or  other 

approval method as used by the relevant government/regulatory authority.  

Written certification that the required fire safety systems have been installed according to the plans approved 

by Hilton Worldwide by a licensed contractor and are fully operational, tested and approved by the authority 

having jurisdiction must be obtained from the installation contractor.  

 

 

   

Page 19: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 17 

 

CONVERSIONS  (OF  A  NON‐HILTON WORLDWIDE  BRANDED  HOTEL  TO  A  HILTON WORLDWIDE  BRANDED 

HOTEL)  OR  RENOVATIONS  AND  REFURBISHMENT  WORKS  FOR  A  RE‐LICENSED  HILTON  WORLDWIDE 

BRANDED HOTEL 

A conversion Product Improvement Plan (“PIP”) will be prepared prior to signing an Operating Agreement for 

any new development deal where a non‐Hilton Worldwide brand hotel will convert into one of the brands of 

Hilton  Worldwide.  This  will  be  required  and  must  be  undertaken  prior  to  execution  of  the  Operating 

Agreement. A copy of the PIP will be appended to the Operating Agreement. 

The Hilton Worldwide Project Director will assist  the Owner  in  the  following areas during  the course of  the 

conversion process: 

1.   Compliance with the PIP. 

2.   Compliance with  the  relevant Hilton Worldwide Brand Standards and Hilton Worldwide Design and 

Construction Standards. 

3.  Compliance with the relevant brand design narrative. 

Conversion PIP 

Where the PIP requires minor re‐design and/or renovation of existing facilities, design drawings of guestrooms 

and  public  areas  furnishings  and  layouts  and  interior/exterior  elevations  shall  be  submitted  for  Hilton 

Worldwide  review  and  approval.  This  submittal  is  to  be  sent  to  the  A,D&C  Team  and  shall  include  colour 

renderings or photographs if requested by the A,D&C Team in line with the section of this document headed 

“Design Review Process Generally – Design Elements”. 

Where  the  PIP  requires major  refurbishment  works  and/or  construction  of  additional  facilities,  complete 

design and specifications are to be submitted to and approved by the A,D&C Team prior to commencement of 

construction in line with the previous section of this document relating to New Construction. 

Active Conversion PIP 

Once a PIP is activated, the process is managed by the A,D&C Team.  

Various specialist reports are required such as but not limited to an IT, engineering (including any outstanding 

maintenance issues), FLS report, acoustics , asbestos and fire stopping (where requested). 

Any proposed extensions or deviations from relevant Hilton Worldwide Brand Standards and Hilton Worldwide 

Design and Construction Standards will be sent to the appropriate Hilton Worldwide brand team for approval.  

The  design  and  construction  programme  must  be  approved  by  Hilton  Worldwide  and  issued  prior  to 

commencement of any works. Design review submittals will be handled by the A,D&C Team. Thirty  (30) day 

progress  reports  and  photographs  must  be  sent  to  the  A,D&C  Team  after  every  monthly  site  meeting. 

Outstanding works must be tracked on a monthly basis.  

The  meeting  process  and  requirements  shall  follow  the  same  as  set  out  in  this  document  for  a  New 

Construction. Minutes must  be  in  English  and  issued within  seven  (7)  calendar  days  and must  include  the 

proposed design programme and construction programme.  

Page 20: Hilton Worldwide Architec 1352468850

Architecture Design & Construction Project Review and Approvals Process 

Date : 11 Oct 2012  (L0046791)  Page No. 18 

 

CONVERSIONS  (OF  A  NON‐HILTON WORLDWIDE  BRANDED  HOTEL  TO  A  HILTON WORLDWIDE  BRANDED 

HOTEL)  OR  RENOVATIONS  AND  REFURBISHMENT  WORKS  FOR  A  RE‐LICENSED  HILTON  WORLDWIDE 

BRANDED HOTEL – CONT’D 

Active Conversion PIP – Cont’d 

A mock‐up room and sample control room    (in accordance with the requirements of the previous section of 

this document relating to New Construction) shall be constructed, fitted out and made available for approval 

by Hilton Worldwide when the  PIP includes  the addition of new facilities or where there is refurbishment of 

guestrooms. 

Hilton Worldwide  requires  a  final  report of  compliance and photos  to be  submitted by  the Owner  at  least 

fifteen (15) calendar days prior to opening of the hotel.    

Page 21: Hilton Worldwide Architec 1352468850

APPENDIX A PRELIMINARY PLANS SUBMISSION 

Date : 11 Oct 2012    Page No. 1 

Site Name :   

Brand :   

Site Address :   

Owner/Developer :   

Contact :   

 

The  following  list  comprises  the  information  required  for  the  Hilton Worldwide  Design  and  Construction Department to conduct a formal review of the Preliminary Plans in connection with the above project. 

Please submit this form with the information listed. 

Plans and documents to be submitted to the Hilton Worldwide Project Director at least (20)  calendar days before any sign‐off meeting. 

1. An Area Programme  (Facilities  Schedule)  for  the project  showing public  areas, back of house,  and guestroom components.  Include a summary page showing gross areas and  total enclosed areas per key, gross area of meeting spaces per key, guestroom and suite ratios, and any other significant data unique to this project. 

2. Vicinity Map/Location Plan which must include adjacent properties (existing and planned), associated roads and the like. Minimum scale 1:1250. 

3. Site Plan with building, car parking (quantity and size of spaces of aisles to be provided), landscaping and  recreational  area  outlined.  Indicate  satellite  dish  location  (if  provided),  signage  locations  and refuse/storage building location. Minimum scale 1:500 plans of all areas. 

4. Floor Plans of all areas at a minimum scale of 1:100 with all key dimensions noted and including the following information : 

(i) No. of guestrooms per floor; 

(ii) Gross building area in square metres; 

(iii) Name of all internal spaces; 

(iv) Larger scale detail of all typical guestroom layouts including dimensions; and 

(v) Seating layouts showing capacity of all F&B areas and meeting and conference rooms. 

Note : For additions, all floor plans and exterior elevations must show the relationship to the existing building(s). 

5. A section through the building at a minimum scale of 1:100 showing all floor to ceiling heights. 

6. Exterior  elevations  indicating  proposed materials  and  the  positions  of  building  signage. Minimum scale 1:100. 

 

 

Page 22: Hilton Worldwide Architec 1352468850

APPENDIX A PRELIMINARY PLANS SUBMISSION 

Date : 11 Oct 2012    Page No. 2 

 

7. Narrative  description  and  design  brief  for  all  mechanical,  electrical  and  plumbing  installations, including sprinklers (where relevant). Outline scope of works identifying all elements of the following disciplines; mechanical (including design criteria), electrical (including design criteria), plumbing,  lifts (including lift traffic analysis), building energy performance and sustainable elements included in the design  and  single  line  schematic diagrams  for  key  systems  such  as HV/LV distribution,  ventilation, chilled water, domestic hot water, heating and plumbing. 

8. Outline Fire Strategy including all local codes and design principles for the project. 

9. Drawing Register of attached  information  including a  list of all drawings  to be  reviewed  (including revision number) and a list of any other documents to be reviewed. 

10. Project Brief  

11. Concept Design  

Please provide all sheet numbers, sheet names, scales, current date and a note in the drawing border that indicates “PRELIMINARY PLANS’. 

Review and approval of the Preliminary Plans must be secured prior to submission of the Design Development (50%)  Plans and Specifications. 

 

 

Page 23: Hilton Worldwide Architec 1352468850

APPENDIX B DESIGN DEVELOPMENT (50%) PLANS AND SPECIFICATIONS SUBMISSION 

Date : 11 Oct 2012    Page No. 1 

Site Name :   

Brand :   

Site Address :   

Owner/Developer :   

Contact :   

 

The following list comprises the information required for Hilton Design and Construction to conduct a formal review of the Design Development (50%) Plans and Specifications in connection with the above project. 

Please submit this form with the information listed. 

Plans and documents to be submitted to the Hilton Worldwide Project Director at least (20) CALENDAR days before any sign‐off meeting. 

1. A Site Plan at a minimum scale of 1:500 showing dimensioned parking and  roadways, all proposed materials, signage locations, external lighting and landscaped zones. 

2. Floor plans at a minimum scale of 1:100 showing  final room designations and numbers, wall  types, room dimensions, FF&E and  fixed  furniture  layouts,  floor  to ceiling heights  in each zone,  floor, wall and ceiling finishes and fire and acoustic ratings of walls and floors. 

3. Large scale floor plans of the following specific areas (scale as shown) : 

(i) Individual guestroom and bathroom types including millwork and elevations (1:20); 

(ii) Kitchen layouts (1:50); 

(iii) Adminstration Offices (1:50); 

(iv) Business Centre (1:50); 

(v) Meeting rooms and conference rooms (1:50); 

(vi) Public toilets (1:50); and 

(vii) Recreational areas. 

4. Building elevations at a minimum scale of 1:100 showing all finishes, colours of materials and finishes, window types and operational details, vertical dimensions and signage locations. 

5. Building  sections  at  a minimum  scale  of  1:50  showing  all  overall  vertical  dimensions,  clear  ceiling heights,  longitudinal and  traverse  sections  through  the whole building and  fire  rating of  floors and roof structures. 

 

 

 

Page 24: Hilton Worldwide Architec 1352468850

APPENDIX B DESIGN DEVELOPMENT (50%) PLANS AND SPECIFICATIONS SUBMISSION 

Date : 11 Oct 2012    Page No. 2 

 

6. Mechanical,  electrical  and  plumbing  engineering  plans  (showing  plant  and  equipment  locations (minimum scale 1:100), single  line drawings  for all piped and ducted services, detailed service  riser layout  between  guestrooms,  electrical  power  and  lighting  layouts  and  air  balance  calculations)  as follows : 

(i) Mechanical design including : plans showing plant and equipment locations (minimum scale 1:100),  single  line  drawings  for  all  piped  and  ducted  services, make  up  air  and  exhaust calculations, main plant locations and indoor unit locations for all piped and ducted systems including  outline  plant  ratings,  BMS  schedule  of  included  items,  heat metering  strategy, building  energy  calculations  and  proposed  building  rating,  supporting  calculations  for justification on plant selection and design criteria for all areas. Detailed service riser  layout between guestrooms and typical room details and air balance calculations. 

(ii) Fire Life safety design  including: fire strategy report, fire strategy drawings (minimum scale 1:100), list of applicable codes used to develop and support the proposal. 

(iii) Electrical design  including  : plans  showing plant  and  equipment  locations  (minimum  scale 1:100),  single  line  drawings  for  HV  and  LV  installations  including  outline  load  summary, lighting, coordinated riser diagrams, typical guestroom requirements, fire alarm / voice alarm schematic,  CCTV  system  locations  brief  scope  and  schematic,  generator  supported  loads, emergency  lighting  outline  design,  TV  distribution  schematic,  lightning  protection, music systems, lighting controls, energy metering strategy and AV systems. 

(iv) Audio Visual design must include: scope of works, schematics outline proposals.  

(v) Plumbing design including: (minimum scale 1:100), single line drawings for all piped services including  systems  such  as  rain  water,  grey  water,  detailed  service  riser  layout  between guestrooms, main gulley locations (minimum scale 1:100). 

(vi) Mechanical handling design including: Lift traffic analysis’, Lifts proposed and manufacturer, escalators proposed and manufacturer, dock  levellers, scissor  lifts, dumb waiters, hoists. All details of performance criteria must be submitted with a list of suppliers.  

7. Kitchen  and  laundry  layouts  at  a  minimum  scale  of  1:50  together  with  preliminary  equipment schedules. 

8. Outline  specifications  including  finishes,  fittings,  general  construction  standards  and  MEP installations. 

9. Location of satellite dish (if provided). 

10. Building and ground signage proposals including any associated electrical requirements. 

11. Drawing Register of attached  information  including a  list of all drawings  to be  reviewed  (including revision number) and a list of any other documents to be reviewed. 

Please provide all sheet numbers, sheet names, scales, current date and a note in the drawing border that indicates “DESIGN DEVELOPMENT (50%) PLANS AND SPECIFICATIONS’. 

Review and approval of the Preliminary Plans and Design Development (50%) Plans and Specifications must be secured prior to submission of the Final (100%) Plans and Specifications. 

 

 

Page 25: Hilton Worldwide Architec 1352468850

APPENDIX C FINAL (100%) PLANS AND SPECIFICATIONS SUBMISSION 

Date : 11 Oct 2012    Page No. 1  

Site Name :   

Brand :   

Site Address :   

Owner/Developer :   

Contact :   

 

The following list comprises the information required for Hilton Design and Construction to conduct a formal review of the Final (100%) Plans and Specifications in connection with the above project. 

Please submit this form with the information listed. 

Plans and documents to be submitted to the Hilton Worldwide Project Director at least (20)  Calendar days before any sign‐off meeting. 

Complete working drawings and specifications, properly sealed and signed by the architects and engineers of record, when  required by government  regulations, are  to be  submitted and approved by Hilton Worldwide before construction begins. For Design and Build conditions, drawings and specifications must be submitted at key milestones for approval as the project progresses. 

The drawings and specifications must include the following : 

1. Complete  and  indexed  civil,  architectural, mechanical,  plumbing  (including  detailed  fire  protection drawings),  electrical  and  structural  drawings.  All  drawings  should  include  definitions  of  all abbreviations and symbols used within each discipline.  

2. All room finishes, door and hardware schedules.  

3. Identification of exterior signage drawings showing location and design of all high level, low level and external directional signage.  

4. Room  layouts for all guestroom types  indicating room dimensions,  furnishings, electrical, telephone and  television  outlets.  Interior  elevations  of  all  guestroom  types  are  also  required,  together with details of all finishes and artwork locations and details.  

5. An  interior design package prepared by a professional  interior design firm experienced  in hospitality interior design. The format of the following submittals must be an A4 2‐ring binder with project name, location and date clearly identified on the front cover and spine. Each finish, fabric and cut sheet must be inserted in a clear A4 sleeve placed in the binder. A Hilton Worldwide approved specification sheet must accompany each finish, fabric or cut sheet.  

The submission must include :  (i) Floor plans, including ceiling plans, at 1:50 scale, showing all guestroom types and all public 

areas. FF&E, ceiling heights,  lighting and floor finishes must also be denoted. Specifications for each item of furnishing and all interior finishes must also be submitted.  

(ii) Scaled elevations of all  interior walls of  the public  spaces. All  finishes must be noted  and artwork locations identified along with the size of artwork and subject matter. 

 

Page 26: Hilton Worldwide Architec 1352468850

APPENDIX C FINAL (100%) PLANS AND SPECIFICATIONS SUBMISSION 

Date : 11 Oct 2012    Page No. 2  

  

(iii) Samples of all finishes and fabrics, together with cut sheets of all public area and guestroom furniture.  All  samples  and  cut  sheets  must  be  clearly  labelled  and  identified  as  to  the proposed use and location.  

 

(iv) Submissions for conversions must include colour photographic documentation of the existing conditions.  It must  include the exterior, public area and guestroom types and be  identified on a  location plan. The  location plan must  identify  the  location of the photograph and  the direction of the photograph. 

 

(v) A sample and schedule of the proposed interior signage. 

(vi) Specialist lighting schemes; details of all lighting and proposed control. 

6. A  full  mechanical,  electrical  and  plumbing  design  package  incorporating  the  following  systems information : 

(i) Final mechanical design including but not restricted to all main system schematics, methods of  air  distribution,  hot  water,  chilled  water,  potable  water,  gas  distribution,  heat  loads, cooling  loads,  fresh  air  requirements,  design  temperatures,  air  supply  and  extract calculations, make up air and exhaust calculations, all methods of air distribution, equipment specifications and  locations, all controller  locations  including sample pictures, BMS system, heat  metering  strategy,  building  energy  calculations  and  proposed  building  rating, specifications and proposed plant manufacturers.  

(ii) Final  Fire  Life  safety  design  including:  fire  strategy  report,  fire  strategy  drawings,  list  of applicable codes used to develop and support the design, sprinkler design and calculations, fire  alarm design  scope and drawings,  voice  alarm design  scope  and drawings, emergency lighting  layouts  and  calculations  and  description  on  system,  kitchen  suppression,  IT suppression,  UPS  design,  dry/wet  risers,  smoke  extract/clearance,  stair  ventilation/ pressurisation, generator supported loads, hose reels, fire alarm matrix. All system drawings and manufacturers must be provided to support the overall strategy. 

(iii) Final electrical design  including :  lighting and coordinated reflected ceiling plans, HV and LV installations including load calculations, small power, lighting, equipments specifications and locations,  coordinated  riser  diagrams,  thermostat  locations,  fire  alarm  systems,  CCTV systems,  intruder  alarm  systems,  access  control  and  full  layouts  of  coordinated  reception panels,  security  lodge  panels  and  services,  IT  rooms  services  and  equipment,  including elevations  of  equipment,  generator  supported  loads,  emergency  lighting,  TV  distribution, lightning protection, music systems, lighting controls and energy metering strategy. 

(iv) Audio  Visual  design must  include:  scope  of works,  detailed  drawings  including  plans  and elevations  showing  equipment  finishes,  schematics,  manufacturer  of  products  including pictures, power and heat output requirements, maintenance and warranty.  

(v) Final plumbing design  including:  all piping,  connections,  sizing,  riser diagrams  and  fixtures schedule. 

(vi) Final Mechanical handling design  including:  Lift  traffic analysis’  from chosen manufacturer, detail  drawings  of  all  lifts  proposed  by  manufacturer,  detail  drawings  of  all  escalators proposed  by manufacturer,  dock  levellers,  scissor  lifts,  dumb waiters,  hoists. All  drawings must be submitted from the chosen manufacturer and installer. Details of maintenance and warranties.  

 

Page 27: Hilton Worldwide Architec 1352468850

APPENDIX C FINAL (100%) PLANS AND SPECIFICATIONS SUBMISSION 

Date : 11 Oct 2012    Page No. 3  

 

7. Kitchen  and  laundry  layouts  at  1:50  scale  showing  equipment  locations  and  specifications  and  all mechanical, electrical and plumbing connections and requirements. 

8. IT and communications design (where not included in electrical drawings). 

9. Bar, service station and pantry equipment  locations and specifications and all mechanical, electrical and plumbing connections and requirements. 

10. Drawing Register of attached  information  including a  list of all drawings  to be  reviewed  (including revision number) and a list of any other documents to be reviewed. 

Please provide all sheet numbers, sheet names, scales, current date and a note in the drawing border that indicates “FINAL (100%) PLANS AND SPECIFICATIONS’. 

Review and approval of the Preliminary Plans and Design Development (50%) Plans and Specifications must be secured prior to submission of the Final (100%) Plans and Specifications. 

 

 

 

 

 

 

 

Page 28: Hilton Worldwide Architec 1352468850

APPENDIX D SHOP DRAWINGS AND OTHER SUBMISSIONS 

Date : 11 Oct 2012    Page No. 1  

Site Name :   

Brand :   

Site Address :   

Owner/Developer :   

Contact :   

 

The following list comprises the information required for Hilton Design and Construction to conduct a formal review of the Shop Drawing and Other Submissions in connection with the above project. 

Please submit this form with the information listed. 

Plans and documents to be submitted to the Hilton Worldwide Project Director at  least (20) calendar days before any sign‐off meeting. 

1. Plumbing fixture and equipment cut sheets and trade literature. 

2. Light fixture cut sheets and trade literature. 

3. Door hardware cut sheets and schedule  including electronic  locks, proximity  readers and any other door locking systems. 

4. Roof material sample, cut sheet and trade literature. 

5. Exterior wall finish sample, cut sheet and trade literature. 

6. Fire sprinkler shop drawings. 

7. Lift & Escalator shop drawings 

8. Audio Visual shop drawings 

9. Specialist joinery shop drawings. 

10. Gym equipment cut sheets and trade literature. 

11. FF&E submittal including colour boards, cut sheets and specifications. 

12. Acoustic and background noise survey confirming compliance with the stated acoustic requirements. 

13. Drawing Register of attached  information  including a  list of all drawings  to be  reviewed  (including revision number) and a list of any other documents to be reviewed. 

Please provide all sheet numbers, sheet names, scales, current date and a note in the drawing border that indicates “SHOP DRAWINGS AND OTHER SUBMITTALS”. 

Review and approval of  the Preliminary Plans, Design Development  (50%) Plans and Specifications and Final (100%) Plans and Specifications must be secured prior to submission of the above submittals. 

Page 29: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

 [Insert name of hotel] Acceptance Protocol (Management Agreement) 

    Project:        [Insert name of hotel]        Nature of work:     New Build Construction  Date of this Acceptance Protocol:  xx/xx/xxxx    

 Operator            Owning Company       Hilton Worldwide          [insert name of Owning Company] Represented by:  xxxxxxxx        Represented by: xxxxxxxxx     Construction Works carried out by:  xxxxxxxxxxx    Represented by: xxxxxxxxx             

  

This Acceptance Protocol formalises that, subject to the terms set out herein: 

(i) the hotel has been constructed and fitted out in accordance with Hilton Worldwide Architecture, Design 

and Construction Standards; and 

(ii) the hotel has been completed in terms of physical condition to such an extent as to be capable of being 

operated to the requirements of the relevant brand and is ready, in terms of physical condition only, for 

full opening to the public in accordance with the terms of the Management Agreement dated (insert date) 

(as amended) (the “Management Agreement”). 

For the avoidance of doubt, this Acceptance Protocol relates to the physical condition of the hotel only and not to the operational readiness of the hotel. The opening of the hotel will only be permitted once approval is given to both  its  physical  condition  and  operational  readiness  in  accordance  with  the  terms  of  the  Management Agreement. 

 

Page 30: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

As  of  the  date  of  this  Acceptance  Protocol  and  subject  to  the  terms  of  this  Acceptance  Protocol  and  the Management  Agreement,  the Operator will  take  over  the Hotel  and  prepare  for  its  operational  readiness  as provided for in the Management Agreement.  1.  Scope  

This Acceptance Protocol relates to the Hotel as defined in the Management Agreement.  2.  Defects and works that are still to be done  

The following defects to be rectified and works still to be carried out have been identified as of the date of this Acceptance Protocol and accordingly are excluded from this Acceptance Protocol until such time as they have been rectified and/or carried out to the mutual satisfaction of the Owner and Operator 

 

A list of defects to be rectified signed by all parties or their representatives (appendix 2, page .. to 

..) (the “Snagging Works”) 

 

A list of the works still to be carried out signed by all parties or their representatives (appendix 3, 

page ... to ...) (the “Outstanding Works”) 

 3.  Handover of the Hotel  

Subject to the terms of this Acceptance Protocol and the Management Agreement the Operator will now take  over  the  Hotel  and  prepare  for  its  operational  readiness  as  provided  for  in  the  Management Agreement. 

 4.  Notification by the Operator of non‐compliance  

4.1  Operator hereby gives notice of the following deviations from the Hilton Worldwide Architecture, Design and Construction Standards identified as at the date of this Acceptance Protocol:  

 [insert details] 

 4.2  The Owner acknowledges receipt of the above notification without further comment at this time. 

 5.  Rectifying defects/carrying out the outstanding works  

5.1  The Owner will carry out the Outstanding Works with all reasonable diligence and shall complete them no later than (period of time to be entered once agreed upon), unless otherwise provided in Appendix 3. The Outstanding Works shall be carried out at times and in a manner approved by the Operator and  so as  to  cause as  little disturbance  as possible  to  the efficient management and operation of the Hotel.   

 5.2  The Owner  shall,  at  its  sole  cost  and  expense, undertake or procure  that  the  relevant original 

contractor undertakes the Snagging Works.   

Page 31: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

5.3  The Operator may, but shall have no obligation to, arrange for certain of the Snagging Works to be  carried  out  by  the  employees  of  the  Hotel  employed  in  the  engineering  department  (the “Engineering Employees”) and shall notify the Owner when this is done. Any costs and expenses incurred in carrying out such Snagging Works shall be at the sole cost and expense of Owner. Such assistance by  the Operator  shall not make  the Operator  responsible or  liable  for  the  Snagging Works or for any delay in the completion of the Snagging Works and the Owner shall continue to be responsible for any incomplete or defective Snagging Works.  

 5.4  The  Owner  will  notify  the  Operator  in  writing  when  any  of  the  Outstanding  Works  and/or 

Snagging Works have been completed and are ready for  inspection. The Operator will notify the Owner  in writing when any of the Snagging Works carried out pursuant to paragraph 5.3 above have been completed and are ready for inspection. The parties or their representatives will then jointly  inspect  the works and a  further report will be prepared and a  formal acceptance agreed upon once  the Operator and  the Owner have accepted  that  the works have been  satisfactorily completed  in  accordance  with  the  Hilton  Worldwide  Architecture,  Design  and  Construction Standards. 

 5.5  The handover of the Hotel under this Acceptance Protocol and the opening of the Hotel by the 

Operator shall not in any way relieve the Owner of any of its liabilities or obligations to cure any defects and deficiencies in the Hotel in accordance with the Management Agreement. 

 6.  Documentation and inventories 

 6.1  The training of the Hotel’s personnel in the operation of the equipment/installation/system took 

place on  [date  to be  inserted].     The  reports on  the  training were handed over  to  the Operator when the documentation for the building was handed over on [date to be inserted]. 

 6.2  The documents  required  to operate  the  equipment/installation/system  (operating  instructions, 

brochures,  equipment  specifications, maintenance  instructions,  spare  parts  lists, measurement forms,  consents,  acceptance  forms,  etc)  were  handed  over  to  the  Operator  on  [date  to  be inserted]. 

 6.3  The  details  missing  from  the  documentation  referred  to  above  will  be  handed  over  to  the 

Operator by (period of time to be entered once agreed upon).  7.  Post Handover defects  

If  any  further  errors,  omissions  or  defects  in  the works  are  noted  after  the  date  of  this  Acceptance Protocol  these  will  be  notified  in  writing  to  the  Owner.  This  relates  to  those  areas  covered  by  the construction warranties that currently exist (See Appendix 9).  It  is  agreed  that  these  items  will  be  logged  by  the  Operator  and  categorised  as  Critical;  requiring immediate  action  within  24  hours,  Urgent;  requiring  action  within  three  days  or  Normal;  requiring rectification within four weeks.   Critical  items will be those where there  is a danger to the Hotel guests, the staff and/or relate to Fire and Life Safety issues.  Urgent items will be those that relate to possible loss of revenue if repairs are not carried out and Normal items will be for all other matters.  

Page 32: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

It  is agreed and accepted that  if these response times are not achieved then the Operator will have the right  (but  not  the  obligation)  to  undertake  whatever  works  are  deemed  necessary  to  remedy  the deficiencies, pay for the works from the operating accounts of the Hotel and charge the costs back to the Owner by a deduction from the Owners Return.  

8.  Signatures  

By signing this Acceptance Protocol the parties accept and agree its terms.    Signed on behalf of the Owner         Signed on behalf of the Operator (A&C Dept)      By [name to be inserted] on [insert date]    By [name to be inserted] on [insert date]    Signed on behalf of the Operator (Opps Dept)  

     

By [name to be inserted] on [insert date]      

 

Page 33: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol   Appendices  Appendix 1:  List of those present Appendix 2:  List of Snagging Works Appendix 3  List of Outstanding Works still to be completed Appendix 4:  Utility Meter and Sub‐meter readings Appendix 5:  List of handover documentation, O&M manuals and “As Built” drawings Appendix 6:  List of keys Appendix 7:  List of all permits and licences for opening the Hotel Appendix 8:  Building Permit Appendix 9:  Contract warranty periods  

Page 34: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol  Appendix 1 to acceptance report dated:  List of those present  Date:   No.  Company    Name        Telephone number    Signature      

Page 35: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel]                     Acceptance Protocol  Appendix 2 to acceptance report dated:  List of Snagging Works (See attached documents, pages …..to ……                 

Page 36: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol  Appendix 3 to acceptance report dated:  List of Outstanding Works  No.  Description of works    To be completed by    Comment on completion            

Page 37: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol  Appendix 4 to acceptance report dated:  Utility Meter and Sub‐meter readings    Water meter no.    Reading      Date         Electricity meter no.    Reading      Date        Other meters no.    Reading      Date      

Page 38: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol  Appendix  5 to acceptance report dated:  List of handover documentation, O&M manuals and “As Built” drawings    The attached list shows the contents of the O&M manuals and all other documentation for the building, together with a list of all of the “As Built Drawings” that have been handed over to the Operator by the Owner on [date to be inserted].       

Page 39: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol  Appendix 6 to acceptance report dated:  List of keys  

No  Room Number, Name and Location      Door Type    Locking Devices  Master Key Systems 

         

Page 40: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol  Appendix 7 to acceptance report dated:  List of all permits and licences for opening the Hotel which must have been received prior to acceptance.  

Sanitary certificates for all outlets  

 

Alcohol license for all outlets including minibar 

 

Public reproduction of music or TV programs (Author rights) 

 

Telecommunication (for public internet access) 

 

Registration of Radio and TV sets 

 

Labour & Sanitary inspection notification  

 

Final hotel classification certificate 

 

   

Page 41: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol  Appendix 8 to acceptance report dated:  Building Permit           

Page 42: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by Operator (A&C Dept)   

Initialled by Owner  Initialled by Operator (Opps Dept) 

 Date : 11 Oct 2012  (L0046829) 

[Insert name of hotel] Acceptance Protocol  Appendix 9 to acceptance report dated:  Contract warranty periods    

Page 43: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

 [Insert name of hotel] Acceptance Protocol (Franchise Agreement) 

    Project:        [Insert name of hotel]        Nature of work:     New Build Construction  Date of this Acceptance Protocol:  xx/xx/xxxx    

 Franchisor            Franchisee       Hilton Worldwide          [insert name of Franchisee Company] Represented by:  xxxxxxxx        Represented by: xxxxxxxxx     Construction Works carried out by:  xxxxxxxxxxx    Represented by: xxxxxxxxx             

  

This Acceptance Protocol formalises that, subject to the terms set out herein: 

(i) the Hotel  [applies on MA  version  too] has been  constructed  and  fitted out  in  accordance with Hilton 

Worldwide Architecture, Design and Construction Standards; and 

(ii) the Hotel [as above] has been completed in terms of physical condition to such an extent as to be capable 

of being operated to the requirements of the relevant brand and is ready, in terms of physical condition 

only, for full opening to the public in accordance with the terms of the Franchise Agreement dated (insert 

date) (as amended) (the “Franchise Agreement”). 

For the avoidance of doubt, this Acceptance Protocol relates to the physical condition of the Hotel [as above] only and not  to  the operational  readiness of  the Hotel  [as above]. The opening of  the Hotel  [as above] will only be permitted once approval is given to both its physical condition and operational readiness in accordance with the terms of the Franchise Agreement. 

    

Page 44: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

1.  Scope  

This Acceptance Protocol relates to the Hotel as defined in the Franchise Agreement.  2.  Defects and works that are still to be done  

The following defects to be rectified and works still to be carried out have been identified as of the date of this Acceptance Protocol and accordingly are excluded from this Acceptance Protocol until such time as they  have  been  rectified  and/or  carried  out  to  the  mutual  satisfaction  of  the  Franchisee  and  the Franchisor: [colon also for MA] 

 

A list of defects to be rectified signed by all parties or their representatives (appendix 2, page .. to 

..) (the “Snagging Works”) 

 

A list of the works still to be carried out signed by all parties or their representatives (appendix 3, 

page ... to ...) (the “Outstanding Works”) 

 3.  Notification by the Franchisor of non‐compliance  

3.1  The  Franchisor  hereby  gives  notice  of  the  following  deviations  from  the  Hilton  Worldwide Architecture,  Design  and  Construction  Standards  identified  as  at  the  date  of  this  Acceptance Protocol:  

 [insert details] 

 3.2  The Franchisee acknowledges receipt of the above notification without  further comment at this 

time.  4.  Rectifying defects/carrying out the outstanding works  

4.1  The  Franchisee  will  carry  out  the  Outstanding Works  with  all  reasonable  diligence  and  shall complete them no  later than (period of time to be entered once agreed upon), unless otherwise provided in Appendix 3. The Outstanding Works shall be carried out in a manner approved by the Franchisor.   

 4.2  The Franchisee shall, at its sole cost and expense, undertake or procure that the relevant original 

contractor promptly undertakes the Snagging Works.   

4.3  The Franchisee will notify  the Franchisor  in writing when any of  the Outstanding Works and/or Snagging  Works  have  been  completed  and  are  ready  for  inspection.  The  parties  or  their representatives will  then  jointly  inspect  the works and a  further  report will be prepared and a formal acceptance agreed upon once  the Franchisor and the Franchisee have accepted  that the works have been satisfactorily completed in accordance with the Hilton Worldwide Architecture, Design and Construction Standards. 

 

Page 45: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

4.4  The issuing of this Acceptance Protocol and the opening of the Hotel by the Franchisee shall not in any way  relieve  the  Franchisee  of  any  of  its  liabilities  or  obligations  to  cure  any  defects  and deficiencies in the Hotel in accordance with the Franchise Agreement. 

 5.  Documentation and inventories 

 5.1  The training of the Hotel’s personnel in the operation of the equipment/installation/system took 

place on [date to be inserted].     

5.2  The  Franchisee  has  retained  all  documents  required  to  operate  the equipment/installation/system  (operating  instructions,  brochures,  equipment  specifications, maintenance  instructions,  spare  parts  lists, measurement  forms,  consents,  acceptance  forms, etc). 

 6.  Post Handover defects  

If any further errors, omissions or defects in the works are noted by the Franchisor after the date of this Acceptance Protocol these will be notified in writing to the Franchisee.   It is agreed that these items will be logged  and categorised by the Franchisor and Franchisee as Critical; requiring  immediate  action  within  24  hours,  Urgent;  requiring  action  within  three  days  or  Normal; requiring rectification within four weeks.  Critical items will be those where there is a danger to the Hotel guests,  the  staff and/or  relate  to Fire and Life Safety  issues.   Urgent  items will be  those  that  relate  to possible loss of revenue if repairs are not carried out and Normal items will be for all other matters. The Franchisee  will  undertake  whatever  works  are  deemed  necessary  to  remedy  the  items  within  these response times.    

7.  Signatures  

By signing this Acceptance Protocol the parties accept and agree its terms.    Signed on behalf of the Franchisee      Signed on behalf of the Franchisor (A, D &C Dept)      By [name to be inserted] on [insert date]    By [name to be inserted] on [insert date]    

 

Page 46: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

[Insert name of hotel] Acceptance Protocol   Appendices  Appendix 1:  List of those present Appendix 2:  List of Snagging Works Appendix 3  List of Outstanding Works still to be completed Appendix 4:  List of all permits and licences for opening the Hotel Appendix 5:  Building Permit  

Page 47: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

[Insert name of hotel] Acceptance Protocol  Appendix 1 to acceptance report dated:  List of those present  Date:   No.  Company    Name        Telephone number    Signature      

Page 48: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

[Insert name of hotel]                     Acceptance Protocol  Appendix 2 to acceptance report dated:  List of Snagging Works (See attached documents, pages …..to ……                 

Page 49: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

[Insert name of hotel] Acceptance Protocol  Appendix 3 to acceptance report dated:  List of Outstanding Works  No.  Description of works    To be completed by    Comment on completion                        

Page 50: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

[Insert name of hotel] Acceptance Protocol  Appendix 4 to acceptance report dated:  List of all permits and licences for opening the Hotel which must have been received prior to acceptance.  

Sanitary certificates for all outlets  

 

Alcohol license for all outlets including minibar 

 

Public reproduction of music or TV programs (Author rights) 

 

Telecommunication (for public internet access) 

 

Registration of Radio and TV sets 

 

Labour & Sanitary inspection notification  

 

Final hotel classification certificate 

 

   

Page 51: Hilton Worldwide Architec 1352468850

APPENDIX E ACCEPTANCE PROTOCOL 

 Initialled by A, D&C Dept)    Initialled by Franchisee    Date : 11 Oct 2012  (L0046857) 

[Insert name of hotel] Acceptance Protocol  Appendix 5 to acceptance report dated:  Building Permit