19
HIGH VOLTAGE ELECTRIC NETWORKS CJSC ARMENIA REHABILITATION AND EXPANSION OF HAGHTANAK SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN March 2014

HIGH VOLTAGE ELECTRIC NETWORKS CJSC ARMENIA · substation of High Voltage Electric Networks CJSC ... Poor equipment condition sometimes leads to ... Labor safety Traumatism and accidents

  • Upload
    trandat

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

HIGH VOLTAGE ELECTRIC NETWORKS CJSC

ARMENIA

REHABILITATION AND EXPANSION OF HAGHTANAKSUBSTATION

ENVIRONMENTAL MANAGEMENT PLAN

March 2014

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

2

CONTENTS

1. BACKGROUND ................................................................................................................ 3

2. PROJECT DESCRIPTION ................................................................................................... 3

3. LEGISLATION .................................................................................................................. 5

4. PUBLIC CONSULTATIONS ................................................................................................ 6

5. POTENTIAL IMPACTS AND MITIGATION MEASURES ....................................................... 6

6. RESPONSIBILITIES AND INSTITUTIONAL ARRANGEMENTS .............................................. 7

ENVIRONMENTAL MANAGEMENT PLAN ............................................................................ 9

ENVIRONMENTAL MONITORING PLAN ............................................................................ 15

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

3

1. BACKGROUND

Additional Financing for Electricity Supply Reliability Project (ESRP AF), requested by theGovernment of Armenia, intends to increase the reliability and capacity of the transmissionnetwork through rehabilitation/replacement of key transmission assets. To achieve thisobjective, the ESRP AF would include complete rehabilitation and expansion of Haghtanaksubstation of High Voltage Electric Networks CJSC (HVEN). The substation wascommissioned in 1988 and has not been rehabilitated since then. The key equipment andsupporting structures need replacement because of lack of maintenance parts and erosionof concrete foundations and steel supports. Poor equipment condition sometimes leads tounnecessary outages due to equipment failure. As part of the preparatory work forrehabilitation and expansion of Haghtanak substation, an Environmental Management Plan(EMP) is required.

2. PROJECT DESCRIPTION

Location and Site description

Haghtanak substation is located in the Western part of the capital city of Yerevan. Yerevan issituated in the north-eastern part of Ararat Valley, to the center-west of the Armenia. Theupper part of the city is surrounded with mountains on three sides while it descends to thebanks of the Hrazdan River at the south. It borders with Aragatsotn, Kotayk, Ararat andArmavir marzes of RA. The city's elevation ranges between 865 to 1390m above sea level.

The climate of Yerevan is a humid continental semi-arid climate, with hot and dry summersand cold and snowy winters. The average temperature in July is 25.8 C, and the absolutemaximum temperature is 42 C. The average temperature in January is -3.6 C, and theabsolute minimum temperature is -28 C. The average annual temperature is 11.9 C; averageannual relative humidity is 61%; average annual precipitation is 291-353mm.

Being located in a developed area, there is no wildlife within the area of constructionactivities. The substation is constructed within the re-cultivated territory of a closed tuffquarry. The construction site has flat topography and is surrounded by small-scale vineyardsto the south and south-east and by small production units to the west and south-west. Thevineyards are owned by the residents of neighboring rural communities and are cultivatedby them for personal use. An undeveloped land is located to the north of the substation.The closest residential area is about 300 m. There is a small water stream in 7 m distancefrom the southern fencing of the site.

The public road near the SS entrance will be used to access the site from the north. Thereare also access roads around SS fencing. Using of access roads will not restrict access toagricultural lands. All construction machinery and equipment will be parked inside the

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

4

fencing area. The project implementation will not have any temporary or permanentimpacts on neighboring production units.

The substation has: (a) two 220 kV overhead transmission lines (OTLs), (b) two 220 kV maintransformers (MTRs); and (c) three 10 kV feeder bus sections. One of the MTRs is220/(35)/10 kV 20 MVA transformer and the other is 220/10/(6) kV 63 MVA transformer.

The Substation occupies the fenced area of 2.6 ha with various` buildings having thefollowing external dimensions (L×W×H):

Control and dispatching building (including offices and battery room):41.7×12.05×5m;

10 kV feeder bus sections and two associated buildings:

36.7×9.1×5m and 15.9×5.18×5m each; and

Checkpoint: 6×3×4m.

The west side of the substation is currently used as decommissioned materials andequipment storage.

Project scope of work

The rehabilitation and expansion of the substation will involve the following:

replacement of two 220 kV main transformers (MTRs);

complete replacement of 220kV open switch-yard (OSY);

construction of new 110kV OSY with four bays for overhead transmission lines(OTLs);

demolition of existing and construction of new control and dispatching building;

replacement of Alternating Current and Direct Current (AC/DC) systems, includingdistribution system, chargers, invertors, and batteries;

installation of SCADA system and replacement of protection relay equipment;

replacement of 10 kV cubicles and the associated building;

reconstruction of grounding system;

reconstruction of oil spill collection system;

construction and reconstruction of roads and walkways;

rebuilding of cable trenches;

installation of fire alarm and fire localization system;

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

5

construction of external water drainage and reconstruction of sewerage system;and

restoration of outdoor lighting.

All of these activities will take place in the area of an already existing substation (as shownin Figure 1) and all impacts will be confined to the existing substation yard.

Figure 1: Site Plan

3. LEGISLATION

The following Armenian legislation defines a legal framework applicable to project activities:

Law on Atmospheric Air Protection of RoA (1994)

The purpose of Law on Atmospheric Air Protection is to define main principles of the RoA,directed to provision of purity of atmospheric air and improvement of air quality, preventionand mitigation of the chemical, physical, biological and other impacts on air quality andregulation of public relation.

According to this law, contractor shall undertake demolition and construction activities aswell as transportation and temporary storage of wastes the way to minimize dust and otheremissions to the air.

Law on Waste of RoA (2004)

The law provides the legal and economic basis for collection, transportation, disposal,treatment, re-use of wastes as well as prevention of negative impacts of waste on natural

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

6

resources, human life and health. The law defines the roles and responsibilities of the stateauthorized bodies as well as of waste generator organizations in waste managementoperations.

According to this law, the waste generated by the demolition, construction, dismantling andinstallation activities should be recycled as appropriate, or disposed of in designatedlocations.

Law on Environmental Impact Assessment of RoA (1995)

The law defines type of activities which are subject to environmental impact assessmentand ecological expertise.

According to this law, works planned at Haghtanak substation are not subject to theecological expertise.

Law on Urban Development of RoA (1998)

According to this law, works planned at Haghtanak substation require obtaining of theconstruction permit.

4. PUBLIC CONSULTATIONS

The neighboring communities of Haghtanak substation are considered to be the affectedparties during the construction and operational phases. EMP will be disclosed on the HighVoltage Electric Networks CJSC website. Brief information on the planned works and contactinformation for addressing questions and grievance will be placed at the work site and/or inits immediate surroundings/municipality.

5. POTENTIAL IMPACTS AND MITIGATION MEASURES

The EMP covers environmental and social impacts that may arise from the projectimplementation and provides mitigation measures to cover typical impacts from upgradingequipment and installing new equipment at substations, including workers’ health andsafety, earthworks, and solid and hazardous waste management. EnvironmentalManagement Program containing management and monitoring plans by project phase andactivity is provided in Annex 1.

Waste management is the most challenging task of the environmental mitigation plandeveloped for the project. The main types of wastes expected at the construction phase are:(i) non-hazardous - demolition debris; other types of non-hazardous construction waste;excess material from excavation; obsolete equipment; and (ii) hazardous - lead batteries andbattery acids; used transformer oils; used tires, filters, and oils of construction machineryand vehicles.

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

7

Non-hazardous - demolition debris and other as well as excess material from excavation willbe disposed to the formally designated locations. Permission for disposal from the YerevanMunicipality shall be obtained by Construction Contractor prior to disposal.

Obsolete equipment will be stored at Haghtanak SS site before being sold or possible reuseby HVEN. A separated outdoor area in west side of the SS plot will be used asdecommissioned equipment storage.

The maintenance of construction machinery and vehicles will be performed at specializedservice centers, which also accept used tires, filters, and oils.

Transformer oils at Haghtanak SS were assessed by the Waste Research Center SNCO of theMinistry of Nature Protection of RoA in 2010 using DEXSIL L2000 DX analyser. According toassessment results, the transformer oils at Haghtanak SS do not contain PCBs. Since atpresent there is no local licensed recycling facility, the used oils will be transported 3 kmnorth-east to Shahumyan-2 SS of HVEN and stored there in appropriate oil storage beforerecycling by a licensed contractor. Used oils will be transported in closed and sealedcontainers or tanks properly covered and immobilized by secure attachment totransportation trucks. Trucks will carry signage warning of hazardous cargo.

Since the disposal of decommissioned lead batteries and battery acid in a landfill isprohibited, while at present there is no local licensed recycling/neutralization facility in thecountry, the acid containing batteries must be transported 3.5 km north-east to MainBranch of HVEN and appropriately stored in warehouse building after removal of acid untilsuch kind of facilities will be established. Batteries should be protected against short circuitand secured from movement during transportation in an enclosed vehicle. The storageconditions will include locked and ventilated room with non-permeable floor material andthe shelves for placement of batteries. Acid will be stored in proper tanks having secondarycontainment. The trained HVEN staff will prepare the batteries and acid for storage. Properpersonal protection gear will be used by personnel when handling acid.

The EMP establishes a critical link between the management and mitigation measuresspecified in this report and the proper implementation and management of the measuresduring the construction and operation phases of the project. It provides details on themeasures responsibilities to mitigate these impacts; the costs of mitigation; and, the ways inwhich implementation and effectiveness of the measures will be monitored and supervised.

6. RESPONSIBILITIES AND INSTITUTIONAL ARRANGEMENTS

HVEN is responsible for the implementation of the EMP. The environmental managementplan table, extracted from this EMP, will be included into the tender package and will beincorporated into the contract for the provision of works, so that contractor is aware of the

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

8

mitigation measures to be applied, can properly cost them and include into the bill ofquantities, and is obligated to adhere to the EMP alike any other terms of the contract.

Responsibilities of Construction Contractor

HVEN shall obtain Construction Permit for the designed works. If any additional licenses,permits, consents required (e.g. waste disposal etc.) construction company shall obtain suchlicense, permits, and consents within its capacity.

Monitoring of EMP implementation

HVEN carries overall responsibility for the implementation of EMP and for organizingenvironmental monitoring of works. Environmental monitoring of works shall be undertakenaccording to the Environmental Monitoring Plan presented in this report and the outcomesof monitoring shall be documented in monthly environmental supervision reports.

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

9

ANNEX 1: ENVIRONMENTAL MANAGEMENT PROGRAM

ENVIRONMENTAL MANAGEMENT PLAN

Activity Potential Impact Mitigation Measure Indicator of Mitigation Cost of Mitigation Responsibilityfor Mitigation

CONSTRUCTION PHASE

1. Labor safety Traumatism and accidentsat work site

- Provision of constructionworkers with uniforms andPPE;

- Strict compliance with therules of constructionequipment operation andusage of PPE.

- Construction workersfound wearing uniformsand adequate protectivegear during inspections;

- No violations ofequipment operation anduse instructions registeredduring inspections.

No specific extra cost:common responsibilityof works contractor

ConstructionContractor

2. Demolition andconstruction

Air pollution with dust andemissions

- Keeping demolition debris incontrolled area and sprayingwith water mist to reducedebris dust;

- Suppression of dust duringpneumatic drilling/walldestruction by ongoing waterspraying and/or installingdust screen enclosures at site;

- Keeping the surroundingenvironment (sidewalks,roads) free of debris tominimize dust;

- Prohibiting open burning ofconstruction / waste materialat the site;

- Keeping construction vehiclesand machinery in adequatetechnical condition excludingexcessive emissions;

- No idling of constructionvehicles at sites.

- No demolition debrisfound in uncontrolled areaand unsprayed with water;

- No pneumatic drilling/walldestruction activitywithout suppression ofdust by ongoing wasterspraying and/or installingdust screen enclosures atsite;

- Surrounding environment(sidewalks, roads) foundfree of debris duringinspections;

- No open burning ofconstruction / wastematerial found at the siteduring inspections;

- During inspections,construction vehicles andmachinery foundoperating without

No specific extra cost:common responsibilityof works contractor

ConstructionContractor

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

10

Activity Potential Impact Mitigation Measure Indicator of Mitigation Cost of Mitigation Responsibilityfor Mitigation

excessive emissions;- No complaints from

nearby residents.Generation of noise - Respecting working hours;

- Closing the engine covers ofgenerators, air compressorsand other poweredmechanical equipment duringoperations, and placing ofequipment as far away fromresidential areas as possible;

- Fitting noise mufflers tomobile plant and equipment;

- Preventative maintenance ofequipment to minimize noise;

- Switching off unnecessary oridle equipment.

- No constructionequipment foundoperational out of workinghours;

- Construction equipmentfound in decent technicalcondition duringinspections;

- No switched onunnecessary or idleequipment found duringinspections;

- No complaints fromnearby residents.

No specific extra cost:common responsibilityof works contractor

ConstructionContractor

3. Provision of constructionmaterials

Delivery of substandardmaterials which may causerisks to the safety ofstructure and to health ofpeople

Purchase of constructionmaterials from the registeredproviders

Delivery of standard qualityconstruction materialscarrying relevant certificatesof origin

None ConstructionContractor

4. Transportation ofconstruction materialsand waste

Movement ofconstruction machinery

- Pollution due to poortechnical condition ofvehicles and movement ofuncovered truckloads;

- Nuisance to localresidents from noise anddust.

- Adequate technical conditionof vehicles and machinery;

- Confinement and protectionof truck loads with lining;

- Respect of the establishedhours and routes oftransportation.

- Vehicles and machineryfound in decent technicalcondition duringinspections;

- No uncovered truck loadsfound during inspections;

- No activity ongoing out ofworking hours which maybe disturbing for nearbypopulation;

- No complaints fromnearby residents.

No specific extra cost:common responsibilityof works contractor

ConstructionContractor

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

11

Activity Potential Impact Mitigation Measure Indicator of Mitigation Cost of Mitigation Responsibilityfor Mitigation

5. Operation ofconstruction equipmenton site

- Pollution of environmentwith emissions andleakages;

- Nuisance for nearbypopulation.

- Adequate technical conditionof construction equipment;

- No excessive exhaust;- No fuel and lubricant leakage;- Observation of working

hours.

- Vehicles and machineryfound in decent technicalcondition duringinspections;

- No heavy vehicles andmachinery foundoperational out of theestablished hours;

- No complaints fromnearby population.

No specific extra cost:common responsibilityof works contractor

ConstructionContractor

6. Maintenance ofconstruction equipment

- Pollution of ground waterand soil with oil productsdue to operation ofequipment;

- Damage in case of fire.

- Washing of cars andconstruction equipmentoutside the construction siteor on maximum distancefrom natural streams;

- Refueling or lubrication ofconstruction equipment atpredetermined fillingstations/service centers.

- No direct entry of runofffrom car-wash to waterbodies;

- No spillages of fuel andlubricants found on theground within and nearbythe construction site;

- Presence of basic fireextinguishing means onsite.

No specific extra cost:common responsibilityof works contractor

ConstructionContractor

7. Earth works - Loss of vegetation due toground piling andminimization of pollutionof surface water bodywith particles.

- Topsoil removal andtemporary stockpiling for re-cultivation of the land;

- Temporary storage ofexcavated soil at determinedplaces;

- Backfilling of the excavatedground as needed anddisposal of the excess mass tothe places, approved inwriting.

- Excess material disposedat the agreed upon safepermanent storage siteswith no threat of erosionand no blocking ofwaterways;

- No remnants of excessmaterial at theconstruction site uponcompletion of works;

Contractor has toinclude the cost oftransportation ofexcess material to thesites of final disposalinto the bill ofquantities.

ConstructionContractor

8. Generation of non-hazardous constructionwaste

- Pollution of soil, surfacewater and ground water;

- Accidents at constructionsite due to scatteredfragments of construction

- Temporary storage ofconstruction waste inespecially allocated areaswithin the fenced area of SS;

- Written agreement on the

- Construction waste foundat the work site piled up indesignated locations;

- No excessive amount ofconstruction waste stored

Contractor shallinclude cost of wastetransportation/disposalinto the bill ofquantities.

YerevanMunicipality

ConstructionContractor

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

12

Activity Potential Impact Mitigation Measure Indicator of Mitigation Cost of Mitigation Responsibilityfor Mitigation

materials and debris;- Deterioration of esthetic

appearance ofconstruction site and itssurroundings.

disposal of excess materialand construction wasteobtained from Municipality ofYerevan;

- Timely disposal of wastes tothe formally designatedlocations.

on site.

9. Generation of non-hazardous liquid wastes

- Pollution of surface andground water;- Deterioration of sanitaryconditions at work site.

Arrangement and maintenanceof toilets in compliance withsanitation norms at theconstruction site.

Toilets provided at theconstruction site and foundin good sanitary condition

No specific extra cost:common responsibilityof works contractor

ConstructionContractor

10. Generation of waste fromthe removal of usedtransformer oils andobsolete equipment

- Pollution of soil, surfacewater and ground water;

- Accidents at constructionsite due to scattereddecommissioned;materials and equipment;

- Deterioration of estheticappearance ofconstruction site and itssurroundings.

- Temporary storage ofdecommissioned equipmenton the site of Haghtanak SS inespecially designatedlocations.

- Safe transportation oftransformer oils toShahumyan-2 SS;

- Safe storage of transformeroils at Shahumyan-2 SS.

- Decommissionedequipment found atHaghtanak SS sitecollected in designatedlocations;

- Replaced transformer oilsfound in proper storage atShahaumyan SS.

To be included in theSSs’ operation andmaintenance budget

ConstructionContractor

HVEN

11. Generation of toxic wastefrom replacement ofbatteries

- Pollution of soil, surfacewater and ground waterdue to leakage or spillageof acid from oldequipment;

- Health hazards toconstruction workers andother people which mayenter the constructionsite;

- Health hazards to workersand other people whichmay enter waste storingsite.

- Strict separation of toxicwaste (used batteries, batteryacid, etc.) from other types ofwaste generated at thesubstation;

- Preparation of toxic waste forstorage through placement incontainers and full labelling(details of composition,properties and handlinginformation);

- Preparation of premises forstorage of toxic waste(provision of non-permeable

- Hazardous waste found atthe work site separatedfrom other waste;

- Hazardous waste found atthe central branch ofHVEN stored in safecontainers labeled withdetails of composition,properties and handlinginformation.

To be included in theSS’s operation andmaintenance budget

ConstructionContractor

HVEN

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

13

Activity Potential Impact Mitigation Measure Indicator of Mitigation Cost of Mitigation Responsibilityfor Mitigation

flooring, shelves, ventilationsystems, security systems,etc.);

- Placement of toxic waste forstorage.

12. Construction site re-cultivation andlandscaping

Loss of aesthetical value ofthe landscape due torehabilitation/expansion ofthe SS

- Dismantlement ofconstruction base (if any) andtemporary access roads tothe site (if any) andharmonization of the areaswith the landscape;

- Final cleaning of theconstruction site andpermanent access roads andlandscaping-greening of thearea.

- No remnants of a workcamp left behind afterdemobilization ofcontractor;

- Temporary access roadsharmonized withlandscape and enablingconditions provided fornatural regeneration ofvegetation;

- Construction sitelandscaped and greened.

Included inproject costs

ConstructionContractor

13. Traffic and PedestrianSafety

Direct or indirect hazards topublic traffic andpedestrians by constructionactivities

- Signposting, warning signs,barriers and traffic diversions;

- Traffic management systemand staff training, especiallyfor site access and near-siteheavy traffic. Provision of safepassages and crossings forpedestrians whereconstruction traffic interferes;

- Adjustment of working hoursto local traffic patterns, e.g.avoiding major transportactivities during rush hours;

- Active traffic management bytrained and visible staff at thesite, if required for safe andconvenient passage for thepublic.

- Properly securedconstruction site;

- Clearly visible site and thepublic warned of allpotential hazards;

- Regulated constructionrelated traffic.

Included inproject costs

ConstructionContractor

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

14

Activity Potential Impact Mitigation Measure Indicator of Mitigation Cost of Mitigation Responsibilityfor Mitigation

OPERATION PHASE

1. Generation of hazardouswaste (oily rags, oilcontaminated sand)

- Health hazards to SS staff;- Pollution of soil, surface

and ground water in SSarea and its surroundings.

- Separation of hazardouswaste from other types ofwaste generated atsubstation;

- Presence of appropriatelysealed and protected storagearea for hazardoussubstances;

- Arrangements in place withespecially licensed entities forregular out-transporting andrecycling/disposal ofhazardous waste incompliance with the nationallegislation and the bestnational practice.

Good sanitary conditions inand around SS

To be included in theSS’s operation andmaintenance budget

HVEN

2. Operation andmaintenance of SSequipment

Pollution of soil, surface andground water in substationarea and its surroundings

- Availability of spill kits on-sitefor the clean-up of spills andleaks of oil;

- Preventing leakage andspillage of oil duringoperation and maintenance;

- Timely cleaning any oilleakages and accidentalspillages.

Good sanitary conditions inand around SS

To be included in theSS’s operation andmaintenance budget

HVEN

3. Emergency preparedness Disruption of the Substationoperation causing nuisanceto the consumers

Presence of fire alarm and firelocalization system, andemergency back-up systems forpower supply

Smooth operation of theSubstation

To be included in theSubstation operationand maintenancebudget

HVEN

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

15

ENVIRONMENTAL MONITORING PLAN

ActivityWhat

(Is the parameter to bemonitored?)

Where(Is the parameter

to bemonitored?)

How(Is the parameterto be monitored?)

When(Define the

frequency / orcontinuous?)

Why(Is the parameter

being monitored?)

Who(Is responsible

formonitoring?)

CONSTRUCTION PHASE

1. Provision ofconstruction materials

Purchase of construction materialsfrom the registered providers

In the provider’soffice orwarehouse

Verification oflabels of thematerials and/orcertificates if any

During conclusion ofsupply contracts

Ensure reliability ofconstructionmaterials and theirsafety for humanhealth

HVEN

2. Transportation ofconstruction materialsand waste

Movement ofconstruction machinery

- Technical condition of vehiclesand machinery;

- Confinement and protection oftruck loads with lining;

- Respect of the established hoursand routes of transportation.

- Constructionsite;

- Routes oftransportationof constructionmaterials andwastes.

Inspection of roadsadjacent to the SSin the direction ofthe movementroute

Selectiveinspections duringwork hours

- Limit pollution ofsoil and air fromemissions;

- Limit nuisance tolocal communitiesfrom noise andvibration;

- Minimize trafficdisruption.

HVEN

Traffic Police

3. Dust Air condition on-site Construction siteand access road

Visual inspection Recurrent Reduce risks for thestaff and neighboringcommunities

HVEN

4. Noise - Observance of working hours- Technical condition of vehiclesand machinery- Noise levels (in case ofcomplaints)

Construction site - Visual inspection;- instrumentalmeasurement ofnoise levels (incase of complaints)

- Recurrent- Within 2 weeksfollowing acomplaint

Reduce nuisance forstaff and neighboringcommunities

HVEN

5. Maintenance ofconstructionequipment

- Washing of cars and constructionequipment outside theconstruction site or on maximumdistance from natural streams;

- Refueling or lubrication ofconstruction equipment at thepredetermined fillingstations/service centers.

Construction site Inspection ofactivities

Selectiveinspections duringwork hours

- Avoid pollution ofwater and soil withoil products due tooperation ofequipment;

- Timely localize fireand decreasepossible damage.

HVEN

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

16

ActivityWhat

(Is the parameter to bemonitored?)

Where(Is the parameter

to bemonitored?)

How(Is the parameterto be monitored?)

When(Define the

frequency / orcontinuous?)

Why(Is the parameter

being monitored?)

Who(Is responsible

formonitoring?)

6. Earth works - Topsoil removal and temporarystockpiling for re-cultivation ofthe land;

- Temporary storage of excavatedsoil at determined places;

- Backfilling of the excavatedground as needed and disposal ofthe excess mass to the places,approved in writing.

Construction site Inspection ofactivities

During earth works - Limit loss ofvegetation due toground piling andminimization ofpollution of surfacewater reservoirswith particles

- Limit pollution withcontaminated soilof surface andground waters

HVEN

7. Generation of non-hazardous constructionwaste

- Temporary storage ofconstruction waste in especiallyallocated areas within the fencedarea of SS;

- Timely disposal of wastes to theformally designated locations.

Construction site;Waste disposalsite

Inspection ofactivities

Periodically duringconstruction andupon its completion

- Prevent pollutionof soil, surfacewater and groundwater;

- Avoid accidents atthe SS site due toscatteredfragments ofconstructionmaterials anddebris;

- Retain estheticappearance of thesites area and itssurroundings.

HVEN

YerevanMunicipality

8. Production of liquidwastes

- Arrangement and maintenance oftoilets in compliance withsanitation norms at theconstruction site

Construction site Inspection ofactivities

Total period ofconstruction

- Reduce pollution ofsurface and groundwaters.

ConstructionContractor

9. Generation of wastefrom the removal ofobsolete equipment

- Temporary storage ofdecommissioned equipment inespecially designated location of

Land plot ofHaghtanak SS

Inspection ofactivities

Periodically duringconstruction andupon its completion

- Prevent pollutionof soil, surfacewater and ground

HVEN

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

17

ActivityWhat

(Is the parameter to bemonitored?)

Where(Is the parameter

to bemonitored?)

How(Is the parameterto be monitored?)

When(Define the

frequency / orcontinuous?)

Why(Is the parameter

being monitored?)

Who(Is responsible

formonitoring?)

Haghtanak SS. water;- Avoid accidents at

the constructionsite due toscattereddecommissionedmaterials andequipment;

- Retain estheticappearance of theSS area and itssurroundings.

10. Generation of wastefrom replacement oftransformer oils

- Transportation of oil toShahumyan-2 SS

- Storage conditions of oils atShahumyan-2 SS

- Transportationroute fromHaghtanak SS toShahumyan-2SS;

- Shahumyan-2SS.

Visual inspection -Duringtransportation ofoils;

-Periodically duringstorage of oils

Avoid pollution ofsoil and water

HVEN

11. Generation of toxicwaste fromreplacement ofbatteries

- Strict separation of toxic waste(used batteries, battery acid, etc.)from other types of wastegenerated at the SS;

- Preparation of toxic waste for on-site storage through placement incontainers and full labeling(details of composition,properties and handlinginformation);

- Preparation of premises for on-site storage of toxic waste(provision of non-permeableflooring, shelves, ventilation

- Transportationroute fromHaghtanak SS tothe main branchof HVEN;- Premises of themain branch ofHVEN.

Visual inspection - Duringtransportation oftoxic waste;- Periodically duringstorage of toxicwaste.

Avoid pollution ofsoil and water

HVEN

Ministry ofNatureProtection

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

18

ActivityWhat

(Is the parameter to bemonitored?)

Where(Is the parameter

to bemonitored?)

How(Is the parameterto be monitored?)

When(Define the

frequency / orcontinuous?)

Why(Is the parameter

being monitored?)

Who(Is responsible

formonitoring?)

systems, security systems, etc.);- Safe placement of toxic waste for

storage.12. Construction site re-

cultivation andlandscaping

- Dismantlement of constructionbase (if any) and temporaryaccess roads to the site (if any)and harmonization of the areaswith the landscape;

- Final cleaning of the constructionsite and permanent access roadsand landscaping-greening of thearea.

Construction site,access roads

Inspection ofactivities

Final period ofconstruction

Reduce loss ofaesthetical value ofthe landscape due torehabilitation of theSS

HVEN

13. Workers’ health andsafety

- Construction workers wearinguniforms and PPE;

- Strict compliance with the rulesof construction equipmentoperation and usage of PPE.

Construction site Inspection ofactivities

Total period ofworks

Reduce probability oftraumas andaccidents toconstructors

HVEN

OPERATION PHASE1. Hazardous waste

management (oilyrags, oil contaminatedsand)

- Separation of hazardous wastefrom other types of wastegenerated at substation

- Presence of appropriately sealedand protected storage area forhazardous substances;

- Arrangements in place withespecially licensed entities forregular out-transporting anddisposal of hazardous waste incompliance with the nationallegislation and the best nationalpractice.

Premises of SS - Inspection of SS- Checking

presence andvalidity of wasteremoval anddisposalagreement witha licensed entity.

Total period ofoperation of the SS

- Maintenance ofgood sanitaryconditions at SS;

- Limitation of soil,surface and groundwater pollution.

Ministry ofNatureProtection

2. Operation andmaintenance of SS

- Availability of spill kits on-site forthe clean-up of spills and leaks of

SS area Inspection of SSpremises

Total period ofoperation of the

- Prevention ofhealth hazards to

Ministry ofNature

ENVIRONMENTAL MANAGEMENT PLAN HAGHTANAK SUBSTATION

19

ActivityWhat

(Is the parameter to bemonitored?)

Where(Is the parameter

to bemonitored?)

How(Is the parameterto be monitored?)

When(Define the

frequency / orcontinuous?)

Why(Is the parameter

being monitored?)

Who(Is responsible

formonitoring?)

equipment oil;- Preventing leakage and spillage

of oil during operation andmaintenance;

- Timely cleaning any oil leakagesand accidental spillages.

facility staff and otherpeople which mayenter the site;

- Avoid pollution ofwater and soil withoil products due tomaintenance andoperation ofequipment;

- Timely localize anddecrease expecteddamage in case offire.

Protection

Ministry ofEnergy andNaturalResources

3. Electric and MagneticField

Electric and Magnetic Fieldintensity

In the area ofoperation and atthe fence

Electro meter andGauss meter

Six monthly Reduce risks forthe staff andneighboringcommunities

HVEN

Ministry ofHealth

4. Emergencypreparedness

Presence of fire alarm and firelocalization system, and emergencyback-up systems for power supply

SS area Periodic check-ups Total period ofoperation of thefacility

- Reduce risks forthe staff andneighboringcommunities;

- Avoid disruption ofSS’s operation.

Ministry ofEnergy andNaturalResources

Ministry ofEmergencySituations