30
High-speed, High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 [email protected] EWI Project No. 56132GTH Welding Technology Panel Meeting September 19, 2017 Approved for Public Release: Distribution is Unlimited

High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 [email protected]

Embed Size (px)

Citation preview

Page 1: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

High-speed, High-quality Welding of

Copper-nickel Pipe Joints

Nick Kapustka

Senior Engineer, Arc Welding

EWI

614.688.5175

[email protected]

EWI Project No. 56132GTH

Welding Technology Panel Meeting

September 19, 2017

Approved for Public Release: Distribution is Unlimited

Page 2: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Acknowledgments

This project was funded by the National Shipbuilding Research Program – Advanced Shipbuilding Enterprise.

Fronius USA and OTC-Daihen supported this project by providing equipment and technical assistance.

Airgas provided assistance during shipyard trials at Vigor Industrial.

2

Page 3: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Introduction

Virtually all ship designs utilize copper-nickel alloys:

─ Fire mains and other seawater/fresh water piping.

─ Tanks, penetrations, mask emitters, rope guards, deck drains.

Most pipe joints are welded with manual gas tungsten arc welding (GTAW) at an approximate travel speed of 4 ipm.

Gas metal arc welding (GMAW) can operate at travel speeds of 12 to 18 ipm and fewer passes are typically required compared to GTAW.

The goal of this project was to develop GMAW procedures to provide enhanced welding of copper-nickel systems resulting in higher speeds, higher quality welds, lower heat input, reduced distortion, and minimal rework.

3

Page 4: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Objectives

To provide the GMAW welding procedures needed for the range of applications selected by the project team.

To disseminate the project results to the U.S. shipbuilding community.

4

Page 5: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Project Team

EWI (prime):─ Nick Kapustka (PI), Harvey Castner (PM)

Nassco: ─ Mike Sullivan

Vigor:─ Ken Johnson

5

Page 6: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Approach

Task 1 – Project Initiation and Kickoff Meeting:

─ Identify candidate applications and acceptance criteria.

Task 2 – Procedure Development and Feasibility Demonstration:

─ Develop semi-automatic and/or mechanized GMAW procedures for each application.

─ Produce procedure qualification weldments for each application and evaluate in accordance with NAVSEA Tech Pub 248.

Task 3 – Identification of the Qualification Test Matrix:

─ Determine tests required for procedure qualification in accordance with NAVSEA Tech Pub 248 for each application.

Task 4 – Shipyard Process Demonstrations:

─ Arrange equipment and materials for shipyard demonstration.

─ Fabricate mock-ups for each application using the procedures developed in Task 2.

─ Subject mock-ups to tests identified by the project team.

Task 5 – Technology Transfer and Reporting

─ Briefings at NSRP meetings.

─ Final written report.

6

Page 7: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Application 1

Butt Joint with Backing

Butt joint, welded on permanent backing ring, V-groove, P-3:

─ Figure 35 in MIL-STD-22D.

─ 90/10 Cu-Ni pipe, 6.625-in. OD, 0.134-in. nominal wall thickness.

─ MIL-RN-67 wire, 0.035 or 0.045-in. Ø.

─ 5G position using semi-automatic welding is preferred (pipe fixed).

Welding procedures:

─ Pulsed GMAW (GMAW-P) mode.

─ Two layers required.

7

Page 8: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Application 2

Fillet-welded Coupling Joint

Fillet-welded slip on coupling, P-13: ─ Figure 45 in MIL-STD-22D.

─ 90/10 Cu-Ni pipe, 6.625-in. OD, 0.134-in. nominal wall thickness.

─ 90/10 Cu-Ni coupling ring.

─ MIL-RN-67 wire, 0.035 or 0.045-in. Ø.

─ 5F position using semi-automatic welding is preferred.

Welding procedures:─ GMAW-P mode.

─ Two layers required.

8

Page 9: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Accomplishments

Application Position Location System

Semi-

Automatic/

Mechanized

Accomplishments

Butt Joint with Backing 5G EWI Fronius TPS 5000 Semi-automatic Procedures identified that pass VT, but not RT (0729-1).

Butt Joint with Backing 1G-R EWI Fronius TPS 5000 MechanizedWeldment 0809-1: Meets procedure qualification requirements

of Tech Pub 248 everywhere except the start/stop.

Butt Joint with Backing 5G EWI Fronius TPS 5000 Mechanized

Weldment 1031-1: Meets the Class 1 procedure qualification

requirements of Tech Pub 248 for PT, RT, mechanical testing.

Meets Class 2 & 3 requirements for VT due to a 0.05-in. long

area with undercut between 1/64 and 1/32 in.

Fillet-welded Coupling

Joint2F-R EWI Fronius TPS 5000 Mechanized

Weldment 0906-1: Meets procedure qualification requirements

of Tech Pub 248 everywhere except the start/stop.

Butt Joint with Backing 1G-R VigorOTC-Daihen Welbee

P400Semi-automatic

Weldment 0202-5: Meets procedure qualification requirements

of Tech Pub 248 at all locations.

Butt Joint with Backing 1G-R VigorOTC-Daihen Welbee

P500LMechanized

Weldment 0203-1: Meets NDE requirements of Tech Pub 248

at all locations, mechanical testing is in process.

0729-1, EWI, 5G, Semi-Auto

0809-1, EWI, 1G-R,

Mechanized

1031-1, EWI, 5G,

Mechanized0906-1, EWI, 2F-R,

Mechanized

0202-5, Vigor, 1G-R

Semi-Auto

0203-1, Vigor, 1G-R

Mechanized

9

Page 10: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Mechanized Trials at EWI

Evaluated mechanized welding in the 1G-R and 5G positions for the butt joint and the 2F-R position for the coupling joint.

Equipment:

─ ABB IRB 1600 robot

─ ABB 2-axis positioner (1G-R, 2F-R positions)

─ Jetline Engineering positioner (5G position, not-rotating)

─ Fronius TPS 5000 power supply

─ Fronius VR7000 wire feeder

─ Fronius Robacta Drive torch

10

5G

2F-R1G-R

Page 11: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0809-1 – 1G Butt Joint

Goal: ─ Produce a butt joint that meets the procedure

qualification requirements.

Approach:─ Mechanized welding in the 1G-R position.

─ Each pass is 360 degrees.

─ MIL-RN-67 wire.

─ GMAW-P.

─ Travel angle: 0 degree (neutral).

Evaluation:─ VT, PT, RT, two tensiles, four bends, macro.

11

Pass

Work

Angle

(deg)

Travel

Speed

(ipm)

Weave/

Stringer

WFS

(ipm)Wire Alignment

1 0 10.0 Weave 325 Center of groove

2 8 10.0 Stringer 250 Edge of the wire at the bevel wall

3 0 10.0 Stringer 250 – 270 Edge of wire at the bevel wall

Page 12: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0809-1 – Results

No dressing of the completed weldment prior to NDE.

Start/stop location was not included in NDE testing:

─ Procedures for start/stop location can be developed in the future.

VT:

─ Main weld region meets Class 1 requirements of MIL-STD-2035, provided that excess reinforcement is removed.

─ Reinforcement is about 3/32 in. (1/16 in. max for Class 1 welds).

PT and RT:

─ Main weld region meets the PT and RT requirements of MIL-STD-2035.

12

Page 13: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0809-1 – Results

All bend test specimens passed.

Both tensile test specimens met the requirements of NAVSEA Tech Pub 248:

─ Fracture faces of both specimens extended from the fusion line/near heat-affected zone (HAZ) into the HAZ/base metal.

─ Minimum ultimate tensile test strength specified by MIL-T-16420k is 38 ksi for 90/10 copper nickel.

─ Tensile test specimens had tensile strength of 38.4 and 42.6 ksi.

13

Page 14: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

1031-1 – 5G Butt Joint

Pass

Work

Angle

(deg)

Travel

Speed

(ipm)

Wire AlignmentWFS

(ipm)

Stringer or

Weave

1 0 5.8 – 10.0 Center 200 – 325 Weave

2 8 8.0Edge of wire is aligned with the

toe of Pass 1200 Weave

3 0 6.3Wire is centered on the

exposed face of Pass 1200 Weave

Goal:─ Produce a butt joint that meets the procedure

qualification requirements.

Approach:─ Mechanized welding in the 5G position (pipe is fixed).

─ Each pass is 360 degrees.

─ MIL-RN-67 wire.

─ GMAW-P.

─ Travel angle: 0 degree (neutral).

Evaluation:─ VT, PT, RT, two tensiles, four bends, macro.

14

Page 15: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

1031-1 – Results

Start/stop location was included in NDE testing.

VT:

─ Meets VT requirements for Class 2 & 3 welds

▪ Would meet Class 1 requirements, but there is undercut at 220 degrees that is about 0.05-in. long that is at the 1/64-in. max depth limit for Class 1 welds.

─ Reinforcement is 0.060 to 0.082 in. (max reinforcement for Class 1 welds is 0.062 in.).

PT and RT:

─ Meets PT and RT requirements for Class 1 welds the full length (including start/stop area).

15

Page 16: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

1031-1 – Completed Weldment

Photos of the completed weldment are shown.

16

Page 17: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

1031-1 – Mechanical Testing

Results

All bend test specimens passed.

Both tensile specimens met the requirements of NAVSEA Tech Pub 248:

─ Both specimens failed in the HAZ or the base metal.

─ Minimum tensile strength specified by MIL-T-16420k is 38 ksi for 90/10 copper nickel.

─ Tensile test specimens had tensile strength of 43.6 ksi and 44.2 ksi.

17

Page 18: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0906-1 – 2F Coupling Joint

Goal:

─ Produce a fillet-welded coupling joint that meets the procedure qualification requirements.

Approach:

─ Mechanized welding in the 2F position (pipe rolled).

─ Each pass is 360 degrees.

─ MIL-RN-67 wire.

─ GMAW-P.

─ Travel angle: 0 degree (neutral).

─ Stringer technique for all passes.

Evaluation:

─ VT and PT.

─ Four macro specimens removed 90 degrees apart.

18

Pass

Work

Angle

(deg)

Travel

Speed

(ipm)

Weave/

Stringer

WFS

(ipm)Wire Alignment

1 35 17.5 Stringer 350 1 Ø from joint

2 26 12.0 Stringer 300 1 Ø from toe of Pass 2

3 15 12.0 Stringer 300 Center between bevel wall and toe

of Pass 2

Page 19: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0906-1 – Results

No dressing of the completed weldment prior to NDE.

Start/stop location was not included in NDE testing:

─ Procedures for start/stop location can be developed in the future.

VT and PT:

─ Main weld region meets the VT and PT requirements of MIL-STD-2035.

─ Distance from the coupling wall to the horizontal toe is about 0.35 in. (requirement is 0.26 in.).

19

Page 20: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0906-1 – Met Sections

Metallographic sections:

─ Removed 45 degrees (M1), 135 degrees (M2), 225 degrees (M3), and 315 degrees (M4) from the start.

All four metallographic sections meet the requirements of Tech Pub 248:

─ Horizontal size and leg = 0.34 in.

▪ Required size is 1.75 T = 0.26 in.

─ Vertical size and leg = T = 0.146 in.

▪ Required size = T = 0.146 in.

20

Page 21: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Trials at Vigor

Evaluated semi-automatic and mechanized welding of butt joints in the 1G-R position.

Semi-automatic welding equipment:─ OTC Manual Welbee WB-P400 power supply

─ OTC CM-743 wire feeder

─ OTC BT3510-45UT torch, 4.5 m/15 ft

─ Jetline Engineering positioner

Mechanized welding equipment:─ OTC FD-V6L robot

─ OTC A2PF tilt and rotate positioner

─ OTC Welbee WB-P500L power supply

─ OTC AF-4012 wire feeder

─ OTC RTW5000H torch

21

Page 22: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0202-5 – 1G-R Semi-Auto Butt Joint

Goal:─ Produce a butt joint in the 1G-R position that

meets the procedure qualification requirements.

Approach:─ Semi-automatic welding in the 1G position (pipe

rolled).

─ Each pass is 360 degrees.

─ MIL-RN-67 wire.

─ Wave Pulse synergic line that was custom built by OTC for this project.

─ Travel angle: 0 degree.

─ Torch is aligned at 1:00 with a slight downhill progression.

Evaluation:─ VT, PT, RT, two tensiles, four bends, macro.

Pass

Travel

Angle

(deg)

Work

Angle

(deg)

Travel

Speed

(ipm)

Weave/

Stringer

Set WFS

(ipm)

Wave Pulse

Frequency

(Hz)

1 0 0 9.9 Weave 325 32

2 0 0 7.8 Weave 325 32

Roll

22

Page 23: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0202-5 – Results

Vigor performed VT, PT, and RT on the entire weldment.

VT, PT, and RT:

─ Entire weldment meets the Class 1 requirements.

─ Reinforcement is just below 1/16 in.

23

Page 24: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0202-5 – Completed Weldment

Photos of the completed weldment are shown:─ Reinforcement is just below 1/16 in.

24

Page 25: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0202-5 – Results

All bend test specimens passed.

Both tensile test specimens met the requirements of NAVSEA Tech Pub 248:

─ Fracture faces are in the HAZ or the base metal.

─ Minimum ultimate tensile strength specified by MIL-T-16420k is 38 ksi for 90/10 copper nickel.

─ Tensile test specimens had tensile strength of 45.2 and 46.2 ksi.

25

Page 26: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0203-1 – 1G-R Mechanized Butt Joint

Goal:

─ Produce a butt joint in the 1G-R position that meets the procedure qualification requirements.

Approach:

─ Mechanized welding in the 1G position (pipe rolled).

─ Each pass is 360 degrees.

─ MIL-RN-67 wire.

─ Wave pulse synergic line (existing line from OTC).

─ Travel angle: 0 degree.

Evaluation:

─ VT, PT, RT, two tensiles, four bends, macro.

Pass

Travel

Angle

(deg)

Work

Angle

(deg)

Travel

Speed

(ipm)

Weave/

Stringer

Set

WFS

(ipm)

Wave Pulse

Frequency

(Hz)

Wave Pulse

Amplitude

(%)

1 0 0 7.9 Weave 320 32.0 50

2 0 0 7.9 Weave 320 32.0 50

26

Page 27: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

0203-1 – Results

Vigor performed VT, PT, and RT on the entire weldment.

VT, PT, and RT:

─ Entire weldment meets the Class 1 requirements.

─ Reinforcement is just below 1/16 in.

Mechanical testing is in progress.

27

Page 28: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Summary – GMAW of Cu-Ni Pipe

(1 of 2)

28

The feasibility of producing welds that meet the procedure qualification requirements was demonstrated at EWI for the following conditions:

─ Butt joint with backing, 1G-R, mechanized.

─ Butt joint with backing, 5G, mechanized.

─ Fillet-welded coupling joint, 2F-R, mechanized.

Procedures were developed at Vigor for producing a semi-automatic 1G-R butt joint that met the procedure qualification requirements:

─ Approval of PQR data by NAVSEA will result in Vigor having a qualified, implementable welding procedure for this condition.

Procedures were developed at Vigor for producing a mechanized 1G-R butt joint that met the NDE requirements:

─ Mechanical testing is in progress

─ Acceptable mechanical test results and approval of the PQR data by NAVSEA will result in Vigor having a qualified, implementable welding procedure for this condition.

Page 29: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

Semi-automatic procedures for the 5G butt joint were not completely developed:

─ Best procedures enabled welds that passed VT, but not RT.

Future work:

─ Determine semi-automatic procedures for producing butt joints in the 5G position and fillet-welded coupling joints in the 5F position that meet the procedure qualification requirements.

Summary – GMAW of Cu-Ni Pipe

(2 of 2)

29

Page 30: High-speed, High-quality Welding of Copper-nickel … High-quality Welding of Copper-nickel Pipe Joints Nick Kapustka Senior Engineer, Arc Welding EWI 614.688.5175 nkapustka@ewi.org

EWI is the leading engineering and technology organization in North America dedicated

to developing, testing, and implementing advanced manufacturing technologies for

industry. Since 1984, EWI has offered applied research, manufacturing support, and

strategic services to leaders in the aerospace, automotive, consumer electronic,

medical, energy, government and defense, and heavy manufacturing sectors. By

matching our expertise to the needs of forward-thinking manufacturers, our technology

team serves as a valuable extension of our clients’ innovation and R&D teams to

provide premium, game-changing solutions that deliver a competitive advantage in the

global marketplace.

Columbus, Ohio

EWI (Headquarters)

1250 Arthur E. Adams Drive

Columbus, OH 43221

614.688.5000

[email protected]

Buffalo, New York

Buffalo Manufacturing Works

847 Main Street

Buffalo, NY 14203

716.710.5500

[email protected]

Loveland, Colorado

Rocky Mountain Center for Innovation & Technology

815 14th Street SW

Loveland, CO 80537

970.635.5105

[email protected]

EWI FACILITIES AND LABS