1.0 HISE RISE TOWER
Start: Mon 3/16/15ID: 1
Finish: Fri 5/22/15 Dur: 50 days
Comp: 0%
1.1 MOBILIZATION ON SITE
Start: Mon 3/16/15ID: 2
Finish: Fri 3/20/15 Dur: 5 days
Comp: 0%
Page 1
Page 2
1.2 SITE PREPARATION
Start: Mon 3/23/15ID: 8
Finish: Tue 3/31/15Dur: 7 days
Comp: 0%
1.2.1 Clear and grub site
Start: Mon 3/23/15ID: 9
Finish: Mon 3/23/15Dur: 1 day
Res:
1.3 FOUNDATION
Start: Wed 4/1/15 ID: 16
Finish: Mon 4/20/15Dur: 14 days
Comp: 0%
1.3.1 Excavate foundations
Start: Wed 4/1/15 ID: 17
Finish: Wed 4/1/15Dur: 1 day
Res:
1.4 BASEMENT
Start: Tue 4/21/15 ID: 31
Finish: Thu 4/23/15Dur: 3 days
Comp: 0%
Page 3
Page 4
1.2.2 Stone site access and temporary parking area
Start: Tue 3/24/15 ID: 10
Finish: Tue 3/24/15Dur: 1 day
Res:
1.2.3 Rough grade site (cut and fill)
Start: Wed 3/25/15ID: 11
Finish: Wed 3/25/15Dur: 1 day
Res:
1.3.2 Excavate elevator pit
Start: Thu 4/2/15 ID: 18
Finish: Thu 4/2/15 Dur: 1 day
Res:
1.3.3 Form column piers and spread foundations
Start: Fri 4/3/15 ID: 19
Finish: Fri 4/3/15 Dur: 1 day
Res:
1.4.1 column
Start: Tue 4/21/15 ID: 32
Finish: Tue 4/21/15Dur: 1 day
Res:
1.5 FLOORS
Start: Fri 4/24/15 ID: 35
Finish: Mon 5/4/15Dur: 7 days
Comp: 0%
1.5.1 STRUCTURE- form and pour concrete floors and roof and strip form
Start: Fri 4/24/15 ID: 36
Finish: Fri 4/24/15 Dur: 1 day
Res:
1.6 ROOFING
Start: Wed 5/6/15 ID: 43
Finish: Tue 5/12/15Dur: 5 days
Comp: 0%
1.4.2 shear wall
Start: Wed 4/22/15ID: 33
Finish: Wed 4/22/15Dur: 1 day
Res:
Page 5
Page 6
1.2.5 Install exterior fire line and building fire riser
Start: Fri 3/27/15 ID: 13
Finish: Fri 3/27/15 Dur: 1 day
Res:
1.3.4 Rough-in electric and plumbing in elevator
Start: Mon 4/6/15 ID: 20
Finish: Mon 4/6/15Dur: 1 day
Res:
1.3.5 Form elevator pit wallS
Start: Tue 4/7/15 ID: 21
Finish: Tue 4/7/15 Dur: 1 day
Res:
1.4.3 slab
Start: Thu 4/23/15 ID: 34
Finish: Thu 4/23/15Dur: 1 day
Res:
1.5.2 ELEVATOR
Start: Mon 4/27/15ID: 37
Finish: Mon 4/27/15Dur: 1 day
Res:
1.5.3 CEILING
Start: Tue 4/28/15 ID: 38
Finish: Tue 4/28/15Dur: 1 day
Res:
1.6.1 Install flashing at parapet walls
Start: Wed 5/6/15 ID: 44
Finish: Wed 5/6/15Dur: 1 day
Res:
1.6.2 Pour lightweight concrete roof fill
Start: Thu 5/7/15 ID: 45
Finish: Thu 5/7/15 Dur: 1 day
Res:
1.7 LANDSCAPE
Start: Wed 5/13/15ID: 49
Finish: Fri 5/15/15 Dur: 3 days
Comp: 0%
1.7.1 Pour concrete driveway and sidewalks
Start: Wed 5/13/15ID: 50
Finish: Wed 5/13/15Dur: 1 day
Res:
1.2.4 Install storm drainage
Start: Thu 3/26/15 ID: 12
Finish: Thu 3/26/15Dur: 1 day
Res:
Page 7
1.8 ROADS
Start: Mon 5/18/15ID: 53
Finish: Fri 5/22/15 Dur: 5 days
Res:
Page 8
1.2.6 Perform final site grading
Start: Mon 3/30/15ID: 14
Finish: Mon 3/30/15Dur: 1 day
Res:
1.2.7 Erect building batter boards and layout building
Start: Tue 3/31/15 ID: 15
Finish: Tue 3/31/15Dur: 1 day
Res:
1.3.6 Set reinforcing and anchor bolts
Start: Wed 4/8/15 ID: 22
Finish: Wed 4/8/15Dur: 1 day
Res:
1.3.7 Pour column piers and foundations
Start: Thu 4/9/15 ID: 23
Finish: Thu 4/9/15 Dur: 1 day
Res:
1.3.8 Pour concrete elevator walls
Start: Fri 4/10/15 ID: 24
Finish: Fri 4/10/15 Dur: 1 day
Res:
1.5.4 TOILET
Start: Wed 4/29/15ID: 39
Finish: Wed 4/29/15Dur: 1 day
Res:
1.5.5 MECH. ROOM
Start: Thu 4/30/15 ID: 40
Finish: Thu 4/30/15Dur: 1 day
Res:
1.5.6 ELECT. ROOM
Start: Fri 5/1/15 ID: 41
Finish: Fri 5/1/15 Dur: 1 day
Res:
1.6.3 Install seamless roofing material
Start: Fri 5/8/15 ID: 46
Finish: Fri 5/8/15 Dur: 1 day
Res:
1.6.4 Spread stone ballast on seamless roof
Start: Mon 5/11/15ID: 47
Finish: Mon 5/11/15Dur: 1 day
Res:
1.6.5 Set rooftop equipment
Start: Tue 5/12/15 ID: 48
Finish: Tue 5/12/15Dur: 1 day
Res:
1.7.2 Install boundary wall perimeter
Start: Thu 5/14/15 ID: 51
Finish: Thu 5/14/15Dur: 1 day
Res:
1.7.3 Sod and complete plantings
Start: Fri 5/15/15 ID: 52
Finish: Fri 5/15/15 Dur: 1 day
Res:
Page 9
Page 10
1.3.9 Cure elevator wall concrete
Start: Mon 4/13/15ID: 25
Finish: Mon 4/13/15Dur: 1 day
Res:
1.3.10 Cure piers and foundations
Start: Tue 4/14/15 ID: 26
Finish: Tue 4/14/15Dur: 1 day
Res:
1.3.11 Strip wall forms
Start: Wed 4/15/15ID: 27
Finish: Wed 4/15/15Dur: 1 day
Res:
1.5.7 EXTERIOR
Start: Mon 5/4/15 ID: 42
Finish: Mon 5/4/15Dur: 1 day
Res:
Page 11
Page 12
1.3.11 Strip column piers and foundation forms
Start: Thu 4/16/15 ID: 28
Finish: Thu 4/16/15Dur: 1 day
Res:
1.3.12 Install pneumatic tube in elevator pit
Start: Fri 4/17/15 ID: 29
Finish: Fri 4/17/15 Dur: 1 day
Res:
1.3.13 Prepare and pour concrete floor in elevator pit
Start: Mon 4/20/15ID: 30
Finish: Mon 4/20/15Dur: 1 day
Res:
Page 13
Page 14
Page 15
Page 16
Critical
Noncritical
Critical Milestone
Milestone
Critical Summary
Summary
Critical Inserted
Inserted
Critical Marked
Marked
Critical External
External
Project Summary
Highlighted Critical
Highlighted Noncritical
Page 17
Project: WBSchart1Date: Sat 3/21/15