High-rise Building Micro-hydro Pumped-storage and PV Micro-grid Proposal with Shanghai Jinmao Tower as a Case Study Jianmin Zhang 1 , Qianzhi Zhang 2 1 Hangzhou Dianzhi University, Hangzhou, China; 2. Schl. of Elect., Comput., and Energy Engi., Arizona State University, USA Electrical load is centralized in city, especial in high-rise building which not only has PV or Wind generation resource but also has a ignored great gravity potential. The building above 50 meters are everywhere in city, there are 17383 buildings above 90 meters in the world. Water is also a necessary resource that city should have; water storages in the roof, or water bodies in waist, and water tanks underground of a building or a building group, are not difficult to build them, in fact, water systems including pump system have already been implemented in those buildings for water drink, sanitation, swim pool, fire control, water drain, etc. The hydro pumping storage will only add some new spaces, weight- bearings, new mini hydro pumping systems, etc. A micro-grid development scheme of mini-hydro pumping with PV or others is surveyed and it seems feasible from technical as well as economic point of view. Prof. Jianmin Zhang, Col.of Automation, Hangzhou Dianzi Univ., Hangzhou 310018 China, [email protected] Mr. Qianzhi Zhang, Research Assistant, MSEE , Schl. of Elect., Comput., and Energy Engi., Arizona State Univ., Tempe, AZ 85287- 5706, USA [email protected] US Standard: ASCE-2005 Minimum Design Loads for Buildings and Other Structures promenade purposes 2.87 kN/m 2 Roofs used for roof gardens or assembly purposes 4.79 kN/m 2 China Standard: GB 50009-2012 Load code for the design of building structures promenade purposes 2.0 kN/m 2 Roofs used for roof gardens or sport purposes 3.0 kN/m 2 High Rise Building Resources in the World Introduction Top 20 City Rank of Number of Building over 90 m Top 20 High Rise Building in the World Top Water Tank & Bottom Water Tank & Pumping for General High Rise Buildings Blvd Parameters: Height:420.5m Section Area: 100m*100m Electrical Parameters (Top Reliability): Volt: 35kV/6.3kV/380/220V Incoming: 2*35kV Independent Lines Main Transformers: 4*10MVA Static Load:10MVA, so 3 Transf backup Emer.Standby Gen: 6*1094 kW Oil Parameters of Shanghai Jinmao Building Present Shanghai Electricity Price Table Contact information Feasibility & Optimization Software Photovoltaic+ Pumped-hydro Storage + Sensitive Load Isolated Operation Mode The survey of high rise building in the world for using its ignored potential resource The discovery of such scheme in its grid-tied operation as well as isolated operation The discovery of its technical solution as well economic evaluation Shanghai Jinmao case study shows its great return for tied into bulk grid as well as its backup capacity for emergence source and isolation operation as micro-grid 2014 Symposium on Microgrids Tianjin, China, Nov. 13 - 14, 2014 PV Generation R(t),T(t) Convertor ηI Ppv(t) AC-MOTOR-PUMP Pp(t) Roof Water Tank Z1(t));Area1,ZH1(t) Qu(t) Down Water Tank Z2(t);Area2,ZH2(t) Mini Hydro Qd(t) Switch Box Ph(t)=9.81*Qd(t)*ηg*(Z1(t)-Z2(t)) Ps(t) Pumping Control Local Load Grid connected Switch Roof Tank Water Level Measure. Pgd(t) LoLD(t) Hydro Valve Control 0.4kV Distribution Grid Insolation R and PV temperature T Measurement AC- MOTOR PUMP Turbine Generator ηg Controller Generation Control Local Load Measurement Grid connection control Precipitation Measurement RA(t) Sunshine R(t) Rain clouds RA(t) DC AC system DC system Mechanical Electric Control Down Tank Water Level Measurement Lift Head= Waterhead =Z1(t)-Z2(t) Z1(t+1)=Z1(t)+Qu(t)*Δt/Area1+RA(t)*Area1; ZH(t)=Z(t)-Z10 ZH(t)<=Heigh1 Z2(t+1)=Z2(t)+Qd(t)*Δt/Area2; ZH2(t)=Z2(t)-Z20 ZH2(t)<=Heigh2 Water system 50 100 150 200 250 300 350 400 450 500 550 0 500 1000 1500 2000 2500 3000 3500 4000 4500 Meter kW Max HydrFw/PumpFw vs. Height of Bld Max HydrFw vs. Height of Bld PumpFw vs. Height of Bld A 50m*50m*3m Water Tank on Roof, how much power can generated and how much power needs for pump? 0 1000 2000 3000 4000 5000 6000 7000 Numbers of Blvd above 90m of Country over 100 Blvds World total 173830 500 1000 1500 2000 2500 3000 3500 Numbers of Blvd above 90m of top 20 Cities 0 100 200 300 400 500 600 700 800 900 Height, No.1: 828m, No.20 : 385m Wooden New York roof top tanks (1)water for domestic purposes (2) fire-fighting. (3) Pump: If water level in the tank drops below a certain level, the float switch engages the pump, refilling the tank. Roof Live Loads Standard (USA, China) Valley 22pm – 5am 0.273Ave 6-7, 11-12am/15-17, 21pm 0.719Peak 8-10 am/13-14, 18-20pm 1.202, Turbine efficiency 0.9Generator efficiency 0.92 Pump efficiency 0.8Global Efficiency 0.6624. Turbine/Pipe/Generator/Pump Efficiency Hydro-Pump Parameters Optimal Selection for grid-tied operation under weight bearing of roof garden standard Shanghai Electricity Price TopTankWaterLevel: s420.05m, e420.0m BotTankWaterLevel: s1.95m, e1.9818m Generation.Curve vs Pump Curve Power Gen:7783 kWh, Pump:12002 kWh Roof Garden Burden: Typical Operation Mode , 3 turns of pump-generating (40*40*2 TopTank) Gen.Return vs Pump Paid: Net Return 2797 RMB Gen.Flow vs. Pump Flow: Max Flow:0.7m 3 /s Hydro capacity:2400kW37% of the standby oil gen.setsPump capacity:3600 kW. Total investment: 40.00k Daily return: 2800 , Annual 10.22k , 4 Years return. a very good investment. Economic Evaluation for Roof Garden Burden ( 40*40*2 TopTank) Results for weight bearing over the garden standard under Top Water Tank bottom section in 50m*50m 4. Energy Efficiency from pump to generation vs. Top tank height vs. Max flow 2. Max hydro power vs. Top tank height vs. Max flow 3. Max hydro power vs. Top tank height vs. Max flow 1Daily Return vs.Top tank height vs Max flow Case Study: Shanghai Jinmao Building, 420.5 m New York City Vancouver, B.C Hong Kong PV Curve: Total Gen. 4470 kWh Pump Power Curve: Total. 2951.72kWh Hydro Power Curve: Total Gen. 1988.46 kWh Hydro+PV Curve: Total Gen. 6458.46kWh Sens.Load Curve: Total 3730 kWh Pump+Load Curve: Total. 6681.72kWh Mismatch : Shortage of Power Supply: 223.26 kWh, 5%

High-rise Building Contact informationmicrogrid-symposiums.org/wp-content/uploads/2014/12/... · 2014-12-10 · Conclusion New York City High-rise Building Micro-hydro Pumped-storage

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: High-rise Building Contact informationmicrogrid-symposiums.org/wp-content/uploads/2014/12/... · 2014-12-10 · Conclusion New York City High-rise Building Micro-hydro Pumped-storage

Conclusion

High-rise Building

Micro-hydro Pumped-storage and PV Micro-grid Proposal

with Shanghai Jinmao Tower as a Case Study

Jianmin Zhang1, Qianzhi Zhang2

1 Hangzhou Dianzhi University, Hangzhou, China; 2. Schl. of Elect., Comput., and Energy Engi., Arizona State University, USA

Electrical load is centralized in city, especial

in high-rise building which not only has PV

or Wind generation resource but also has a

ignored great gravity potential. The

building above 50 meters are everywhere in

city, there are 17383 buildings above 90

meters in the world. Water is also a

necessary resource that city should have;

water storages in the roof, or water bodies in

waist, and water tanks underground of a

building or a building group, are not difficult

to build them, in fact, water systems

including pump system have already been

implemented in those buildings for water

drink, sanitation, swim pool, fire control,

water drain, etc. The hydro pumping storage

will only add some new spaces, weight-

bearings, new mini hydro pumping systems,

etc. A micro-grid development scheme of

mini-hydro pumping with PV or others is

surveyed and it seems feasible from

technical as well as economic point of view.

•Prof. Jianmin Zhang, Col.of Automation,

Hangzhou Dianzi Univ., Hangzhou 310018

China, [email protected]

•Mr. Qianzhi Zhang, Research Assistant,

MSEE , Schl. of Elect., Comput., and Energy

Engi., Arizona State Univ., Tempe, AZ 85287-

5706, USA [email protected]

US Standard: ASCE-2005 Minimum Design Loads for

Buildings and Other Structures promenade purposes : 2.87 kN/m2

Roofs used for roof gardens or assembly purposes 4.79 kN/m2

China Standard: GB 50009-2012 Load code for the

design of building structures promenade purposes : 2.0 kN/m2

Roofs used for roof gardens or sport purposes :3.0 kN/m2

High Rise Building Resources in the World

Introduction

Top 20 City Rank of Number of Building over 90 m

Top 20 High Rise Building in the World

Top Water Tank & Bottom Water Tank & Pumping for

General High Rise Buildings Blvd Parameters:

Height:420.5m

Section Area:

100m*100m

Electrical Parameters (Top Reliability):

Volt: 35kV/6.3kV/380/220V

Incoming: 2*35kV Independent Lines

Main Transformers: 4*10MVA

Static Load:10MVA, so 3 Transf backup

Emer.Standby Gen: 6*1094 kW Oil

Parameters of Shanghai Jinmao Building

Present Shanghai Electricity Price Table

Contact information

Feasibility & Optimization Software

Photovoltaic+ Pumped-hydro Storage + Sensitive Load Isolated Operation Mode

•The survey of high rise building in the world for using its ignored potential resource •The discovery of such scheme in its grid-tied operation as well as isolated operation •The discovery of its technical solution as well economic evaluation •Shanghai Jinmao case study shows its great return for tied into bulk grid as well as its backup capacity for emergence source and isolation operation as micro-grid

2014 Symposium on Microgrids

Tianjin, China, Nov. 13-14, 2014

PV GenerationR(t),T(t)

ConvertorηI

Ppv(t)

AC-MOTOR-PUMP

Pp(t)

Roof Water TankZ1(t));Area1,ZH1(t)

Qu(t)

Down Water TankZ2(t);Area2,ZH2(t)

Mini Hydro

水 水

Qd(t)

Switch Box Ph(t)=9.81*Qd(t)*ηg*(Z1(t)-Z2(t))

Ps(t)

PumpingControl

Local Load

Grid connected Switch

Roof Tank Water Level Measure.

Pgd(t)LoLD(t)

Hydro Valve Control

0.4kV Distribution Grid

Insolation R and PV

temperature T Measurement

AC-MOTOR

PUMP Turbine Generatorηg

Controller

GenerationControl

Local Load Measurement

Grid connection control

Precipitation Measurement

RA(t)

SunshineR(t)

Rain cloudsRA(t)

DC

AC system

DCsystem

Mechanical

Electric Control

Down Tank Water LevelMeasurement

Lift Head=Waterhead

=Z1(t)-Z2(t)

Z1(t+1)=Z1(t)+Qu(t)*Δt/Area1+RA(t)*Area1;ZH(t)=Z(t)-Z10ZH(t)<=Heigh1

Z2(t+1)=Z2(t)+Qd(t)*Δt/Area2;ZH2(t)=Z2(t)-Z20ZH2(t)<=Heigh2

Watersystem

50 100 150 200 250 300 350 400 450 500 5500

500

1000

1500

2000

2500

3000

3500

4000

4500

Meter

kW

Max HydrFw/PumpFw vs. Height of Bld

Max HydrFw vs. Height of Bld

PumpFw vs. Height of Bld

A 50m*50m*3m Water Tank on Roof, how much power

can generated and how much power needs for pump?

0

1000

2000

3000

4000

5000

6000

7000

Numbers of Blvd above 90m of Country over 100 Blvds (World

total 17383)

0

500

1000

1500

2000

2500

3000

3500

Numbers of Blvd above 90m of top 20 Cities

0

100

200

300

400

500

600

700

800

900

Height, No.1: 828m, No.20 : 385m

Wooden New York roof top tanks

(1)water for domestic purposes

(2) fire-fighting. (3) Pump: If water level in the tank drops

below a certain level, the float switch

engages the pump, refilling the tank.

Roof Live Loads Standard (USA, China)

Valley 22pm – 5am :0.273;

Ave 6-7, 11-12am/15-17, 21pm :0.719;

Peak 8-10 am/13-14, 18-20pm :1.202,

Turbine efficiency :0.9;Generator efficiency :0.92

Pump efficiency :0.8; Global Efficiency :0.6624.

Turbine/Pipe/Generator/Pump Efficiency

Hydro-Pump Parameters Optimal Selection for grid-tied operation under weight bearing of roof

garden standard

Shanghai Electricity Price

TopTankWaterLevel: s420.05m, e420.0m

BotTankWaterLevel: s1.95m, e1.9818m

Generation.Curve vs Pump Curve

Power Gen:7783 kWh, Pump:12002 kWh

Roof Garden Burden: Typical Operation Mode , 3 turns of pump-generating (40*40*2 TopTank)

Gen.Return vs Pump Paid: Net Return 2797 RMB

Gen.Flow vs. Pump Flow: Max Flow:0.7m3/s

Hydro capacity:2400kW,37% of the standby oil gen.sets;

Pump capacity:3600 kW. Total investment: 40.00k ¥

Daily return: 2800 ¥, Annual 10.22k ¥, 4 Years return.

a very good investment.

Economic Evaluation for Roof Garden Burden ( 40*40*2 TopTank)

Results for weight bearing over the garden standard

under Top Water Tank bottom section in 50m*50m

4. Energy

Efficiency

from pump to

generation vs.

Top tank

height vs. Max

flow

2. Max hydro

power vs. Top

tank height vs.

Max flow

3. Max hydro

power vs. Top

tank height vs.

Max flow

1、Daily

Return vs.Top

tank height vs

Max flow

Case Study:

Shanghai

Jinmao

Building,

420.5 m

New York City

Vancouver, B.C

Hong Kong

PV Curve: Total Gen. 4470 kWh

Pump Power Curve: Total. 2951.72kWh Hydro Power Curve: Total Gen. 1988.46 kWh

Hydro+PV Curve: Total Gen. 6458.46kWh

Sens.Load Curve: Total 3730 kWh

Pump+Load Curve: Total. 6681.72kWh

Mismatch : Shortage of Power Supply: 223.26 kWh, 5%