15
CERN klystron test stand – CLIC Workshop, Oct. 2008 page 1 F. Peauger High-Power RF Test Areas: Design & Planning Progress of the CERN Klystron Test Area CLIC WORKSHOP 2008 1. Objectives 2. Layout 3. Modulator purchase status 4. SLED2 Pulse compressor 5. BOC Pulse compressor 6. Milestones and deliverables

High-Power RF Test Areas: Design & Planning Progress of the CERN Klystron Test Area

  • Upload
    wenda

  • View
    42

  • Download
    0

Embed Size (px)

DESCRIPTION

High-Power RF Test Areas: Design & Planning Progress of the CERN Klystron Test Area. CLIC WORKSHOP 2008. Objectives Layout Modulator purchase status SLED2 Pulse compressor BOC Pulse compressor Milestones and deliverables. Objectives. Objectives: - PowerPoint PPT Presentation

Citation preview

Page 1: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 1F. Peauger

High-Power RF Test Areas: Design & Planning Progress of the

CERN Klystron Test Area

CLIC WORKSHOP 2008

1. Objectives

2. Layout

3. Modulator purchase status

4. SLED2 Pulse compressor

5. BOC Pulse compressor

6. Milestones and deliverables

Page 2: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 2

Objectives

Objectives:

1) Collaborate with CERN for the development and construction of a 12 GHz Klystron based Test Stand at CERN

2) Get an experience on critical components for a future additional test stand at CEA Saclay in the SYNERGIUM accelerator test area (352 MHz, 704 MHz and 1.3 GHz power sources already exist)

CEA Participation to the CERN Test Stand:

1. High voltage modulator

- Procurement, installation and tests with a 12 GHz klystron

In the framework of exceptional contribution of France to CERN

2. RF Pulse Compressor

- Design, fabrication and installation

3. RF Components

- Procurements of loads or dir. couplers

Page 3: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 3F. Peauger

Layout with SLED2 pulse compressor (baseline)

Page 4: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 4F. Peauger

1) 1st Phase of Call for tender : Pre-selection of candidates

done in June 2008

3 companies pre-selected

2) 2nd phase of Call for tender :

o Technical specification and commercial documents submitted to the 3 candidates

o 45 days of delay for technical and commercial answer

3) Choice of the company

4) Adjudication of the contract

HV Modulator: Call for tender

We miss now the 12 GHz klystron characteristics to finalize the modulator technical specification (perveance, gun mechanical configuration, nb of power

supplies…)

Page 5: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 5F. Peauger

Preliminary specification:

Pulse repetition rate = 50 Hz but with an indication from the candidate if it is possible to provide a

100 Hz system

Peak voltage = 460 kV, Peak current = 310 A Pulse length = 1.5 µs (flat top), 2.3 µs (at FWHM).

Scope of the delivery:

High voltage pulsed power supply, auxiliary power supply (klystron focus magnet, filament, ion

pump), high voltage oil tank, X-ray shielding, control-command system

Scope of the services:

Fabrication of the system, acceptance tests at factory, installation and acceptance tests on-site

with a 12 GHz klystron from SLAC (delivered by CERN).

HV Modulator: Pre-selection criteria

Options:

Option 1 – realization of a second modulator with the same specification (for CEA Saclay Test Stand)

Option 2 – One additional year of maintenance

Delay : 12 months from the date of contract adjudication → may become the critical path of the schedule

Again, we need the 12 GHz klystron characteristics to be able to start the 2nd phase of modulator call for tender

Page 6: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 6F. Peauger

Parameters Values units

Frequency 11.9942 GHz

Multiplication factor 2.5 min -

Input power 50 min MW

Output power 150 min MW

Input pulse length 1.5 µs

Output pulse length 300 ns

Vacuum level 1.10-8 max mbar

Pulse compressor specifications

Bandwidth

Time to reach the nominal vacuum level

RF pulse amplitude ripple

RF pulse phase ripple

Pulse to pulse stability (amplitude)

Pulse to pulse stability (phase)

Thermal stability

Cooling circuit

RF leakage

X-ray radiation

Preliminary specifications

Complementary specifications to be discussed and defined

Ability to vary the pulse amplitude

Ability to vary the pulse length

Ability to vary the slope

In order to study different philosophies of conditioning

Page 7: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 7F. Peauger

0

20

40

60

80

100

120

140

160

0 200 400 600 800 1000 1200 1400 1600 1800

0

20

40

60

80

100

120

140

160

180

200

Pinc (Ampl)

Pinc (Phase)

0

20

40

60

80

100

120

140

160

0 200 400 600 800 1000 1200 1400 1600 1800

Ptrans (Ampl)

Time (ns)

Time (ns)

Output PC power amplitude (MW)

Input PC power amplitude (MW)Input PC power phase (deg)

SLED2: Pulse waveform after compression

2

2012

2 '

2 a

pCTL d

L : Length of the delay line

Td :Time delay = 2L/vg = length of output compressed pulse

C : Light velocity

ω = 2πF with F operating frequency

p’01 : 1st root of J’0 the derivative of J0 the bessel function of kind p’01 = 3.832

a : circular waveguide diameter

-

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

- 100 200 300 400 500

30

45

90

150

Length of delay line (m)

Compressed pulse length (ns)

Circular waveguide diameter

L=42m, a = 90 mm

Propagation of the TE01 mode

140 MW, 300 ns

Page 8: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 8F. Peauger

SLED2: Vacuum short study

Cu OFHC

Pre-heating at 950°C under vacuum during 10h

bake out at 120°C

Design Level: 4E-9 Torr

Need at least 6 RF pumping ports, 3 ports on each delay line

Sensitivity to the waveguide diameter?

q = 1.8 x 10-9 Torr.L.s-1.m-1

Delay line length (m)

Delay line pressure (Torr)

Pumping port

Ion pump 30 L/s

Hybrid coupler + mode converter

Variable short circuit

Page 9: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 9

SLED-II concept was already demonstrated with NLCTA operation and runs routinely for high gradient research

S. Tantawi et al. Results:

With a single 50 MW klystron (1998)

With four 50 MW klystron and multimode PC (2005)

SLED2 at SLAC

Recommendations from SLAC for our system are welcome (vacuum, tolerances for fabrication, mechanical support and alignment…)

BUT: installation in CTF3 buildings may be problematic and cost could be high

→ Alternative solution: X-band Barrel Open Cavity (BOC)

Page 10: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 10F. Peauger

Layout with BOC pulse compressor (option)

Page 11: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 11

With = skin depth

F. Peauger

BOC: Preliminary RF design

Inner radius a

L2

L1

R1

Elliptic profile (ratio)

F0 = 11.9968 GHz

Q0 = 169465 with copper

a = 103.75 mm

L2 = 100 mm

L1 = 40 mm

R1 = 10 mm

ratio = 0.848

With a TM20,1,1 mode:

ΔF/Δa = -0.1182 GHz/mm

Other modes will be studied: Q0 = 200000 with a=130 mm, …

Simplification of the cavity profil

- Optimisation of H and ө for a given inner radius a… H

ө

a

Q 0

Page 12: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 12F. Peauger

-

20

40

60

80

100

120

140

160

0 200 400 600 800 1000 1200 1400

Ptrans. (Ampl)

Ptrans w ith 15% losses (Ampl)

-

10

20

30

40

50

60

0 200 400 600 800 1000 1200 1400

-

20

40

60

80

100

120

140

160

180

200

Pinc (Ampl)

Pinc (Phase)

BOC: Pulse waveform after compression

Time (ns)

Output PC power amplitude (MW)

Input PC power amplitude (MW)

Input PC power phase (deg)

Time (ns)

Q0 = 160000

β=Qx/Q0 = 8

Reflexion coef = 0.777

Filling time = 0.471 µs

Phase step of 1.3 rad and linear variation from 1.3 to π rad

Filling BOC: 1.3 µs

Slope phase step: 20ns

Flat top BOC: 255 ns

120 MW, 250 ns

not within spec (150MW - 300ns) but interesting first results

is worth being more studied and optimized

Page 13: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 13F. Peauger

BOC: Coupling

Quarter wavelength multi-hole coupler: TM20,1,1 → 20 x 4 = 80 holes (m=20)

Synchronism conditions between surrounding waveguide and cavity:

tx

Tz/2

R

Parameters Case 1 Case 2

Tx 2.95 mm 3.05 mm

Tz 3 mm 3 mm

R 1 mm 1 mm

β= Qx/Q0 8.45 6.43

2

0

0

21

2

w

m

wa

w

Δ

a

With wavelength = 24.995 mmF

C0

Page 14: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 14

Milestones and deliverables

• Participation in 12 GHz component review at CERN Oct. 2008

• Participation in component testing at SLAC Nov. 2009

• High-power testing at CERN Feb. to June 2010

• Preliminary Design Review : decision between SLED2 and BOC July 2009

• Delivery of the Pulse Compressor to CERN, installation and high

power tests with a SLAC klystron Feb 2010

• Participation in the klystron design review at SLAC Oct. 2008

• Tender for modulator purchase Nov. 2008

• Choice of the supplier in collaboration with CERN Jan. 2009

• Modulator production follow-up Feb 2009 to Feb 2010

• Delivery of the modulator to CERN, installation

and high power tests with a SLAC klystron Feb. 2010

1. High voltage modulator

2. Pulse compressor

3. RF Components

Page 15: High-Power RF Test Areas:  Design & Planning Progress of the CERN Klystron Test Area

CERN klystron test stand – CLIC Workshop, Oct. 2008 page 15F. Peauger

Acknowledgments for preliminary discussions and work:

G. Mcmonagle, K.M. Schirm, I. Syratchev

Conclusion

Interesting and challenging program with significant R&D effort

We are waiting for the klystron characteristics in order to finalize the modulator technical specifications and continue the call for tender which is planed in Nov. 08 for the end phase

Design studies have started for Pulse Compressor, with SLED2 as baseline and BOC as option → decision in July 2009

Preliminary Design Study started with Thales ED (S. Sierra) for the study and realization of an additional test stand at CEA Saclay (except the klystron): delivery in Nov. 08

Thank you for your attention