Upload
lydang
View
214
Download
0
Embed Size (px)
Citation preview
HIGH PERFORMANCECONCRETE
by
John J. Roller
CTLGroup
Early Louisiana HPC Research
Law & Rasoulian (1980)
Adelman & Cousins (1990)
Bruce, Russell & Roller – (1990-1993)
Law & Rasoulian (1980)
Concrete strengths of 6,500 psi and higher could be achieved using regionally available materials.
High strengths could best be achieved through use of crushed limestone aggregate.
Adelman & Cousins (1990)A mix design was developed that consistently yielded 28-day compressive strength in excess of 10,000 psi.
Measured MOR values compared well with results reported in other literature.
Measured MOE values represented the upper bound for the range of values reported in other literature.
Increasing design compressive strength from 6,000 psi to 10,000 psi resulted in an approximate 10% increase in span length and 5% decrease in superstructure cost.
Bruce, Russell & Roller (1990-93) With special attention to quality control, HPC with compressive strengths of 10,000 psi can be produced in a precast plant environment using regionally available materials.
HPC structural members performed in a manner that would be conservatively predicted using current AASHTO design provisions.
AASHTO provisions for estimating prestress loss due to creep and shrinkage may be too conservative for HPC with high compressive strengths.
Feasibility Study – RecommendationsUse of HPC with compressive strengths up to 10,000 psi should be considered by the Louisiana DOTD.
The effects of steam curing on the properties of high-strength HPC should be investigated further.
A HPC quality control training program should be developed for regional fabricators.
HPC with compressive strength up to 10,000 psi should be implemented in a bridge. This bridge should be instrumented.
Early Louisiana HPC Implementation
1988 – Specifying 8,000 psi concrete for a bridge project.
1992 – Successfully fabricating, shipping and driving a 130-ft long prestressed pile with concrete compressive strength of 10,450 psi.
1993 – Utilization of AASHTO Type IV girders with 8,500 psi compressive strength in Shreveport Inner Loop Expressway.
Implementation Project -Charenton Canal Bridge
(2001)
Charenton Canal Bridge - Section
Charenton Canal Bridge -Research Plan
Measure prestress force levels in selected strands during fabrication of girders for Span 3.
Measure concrete temperatures during initial curing of girders fabricated for Span 3.
Measure early-age and long-term concrete strains in girders and bridge deck slab for Span 3.
Measure early-age and long-term mid-span deflections for girders incorporated in Span 3.
Perform material property testing program for Span 3.
Charenton Canal Bridge -Conclusions
Reduction in prestress force occurring between the time of initial stress and release were greater than the PCI QC Manual tolerance and calculated steel relaxation prestress loss.
Concrete temperatures along the length of prestressed girders were not uniform during initial curing. In addition, curing temperatures measured in field-cured cylinders were considerably less than those measured in the girders. The consequence of this temperature variation was evident in the measured concrete compressive strengths.
Measured early-age and long-term prestress losses were considerably less than the design loss calculated using provisions of the AASHTO Standard Specification.
Measured early-age girder camber agreed well with the calculated design values. However, the calculated design values (with the appropriate PCI multipliers applied) did not provide a reliable estimate of long-term camber after the deck slab was cast.
Charenton Canal Bridge -Conclusions
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
0 12 24 36 48 60 72Time Since Pretensioning Strands, hours
Ave
rage
Str
and
Load
, lbf
ConcreteCastingCompleted
Steam Appliedfor Approx. 2.5Hours
StrandsReleased
StrandsTensioned
Measured Prestress Force
50
60
70
80
90
100
110
120
130
140
150
0 10 20 30 40 50
Time Since Casting Concrete, hours
Con
cret
e Te
mpe
ratu
re, °
F
Bottom Flange @ Mid-Span
Bottom Flange @ End
6 x 12 in. Cylinder
Temperature Variations
Compressive Strength
Concrete
Age,
Days
Initial
Curing
Method
Concrete
Compressive
Strength, psi
28Field 9,610
Match 10,570
90Field 10,670
Match 11,950
Prestress LossesPrestress
LossComponent
MeasuredLoss,
psi
DesignLoss,
psi
Elastic - ES 14,336 16,234
Relaxation - CRs - 1,805
Creep - CRc 18,589 25,686
Shrinkage - SH 5,750
Total 39,925 49,475
Girder Camber
Event(Time After
Release, days)
MeasuredCamber,
In.
CalculatedCamber,
In.
After Release (0.01) 1.00 1.41
Before Shipping (271) 2.40 2.51
After Casting Deck (303) 1.61 1.64
Final Reading (631) 1.58 0.87
Charenton Canal Bridge -Recommendations
Louisiana DOTD should continue specifying HPC on all bridges where its use is beneficial and economical.
When HPC is specified for a bridge, the Louisiana DOTD should consider conducting further research to investigate the early-age and long-term behavior of structural components. This objective could be accomplished by implementing instrumentation and testing programs similar to the one used for the Charenton Canal Bridge.
Fatigue & Shear Study (2000-2004) Tulane University; CTLGroup; HGR, Inc.
Provide assurance that 72-in. deep bulb-tee girders made with 10,000 psi compressive strength concrete will perform satisfactorily under fatigue and shear loading conditions.
Determine if a higher allowable concrete tensile stress can be used in design.
Investigate the use of welded-wire deformed shear reinforcement as an alternative to conventional bars.
Fatigue Endurance Tests
Test Matrix - Fatigue
SpecimenPeak
Extreme Fiber Tensile Stress, psi
Stress Range
Bottom Flange Status
Loading Frequency
BT6 6.0 HS-20 Pre-cracked 2.0 Hz
BT7 8.6 HL-93 Pre-cracked 1.9 Hz
BT8 7.5 HL-93 Pre-cracked 1.9 Hz
BT11 6.0 HL-93 Uncracked 1.0 Hz
BT12 7.5 HL-93 Uncracked 1.0 Hz
cf '
cf '
cf '
cf '
cf '
Fatigue Test Results
SpecimenBottom
Flange Status
Calculated Extreme Fiber Stress, psi *
Measured Steel
Stress Range, ksi
Fatigue Cycles
AchievedMax. Range
BT6 Pre-cracked 610 1,247 9.1 5,000,000
BT7 Pre-cracked 857 1,269 11.8 1,910,000
BT8 Pre-cracked 750 1,276 9.6 2,500,000
BT11 Uncracked 600 1,273 6.2 5,000,000
BT12 Uncracked 750 1,285 5.8 5,000,000
* Parameters calculated based on uncracked section properties.
Post-Fatigue Flexural Strength
Shear Strength Tests
Test Matrix - Shear
Specimen AASHTO Design
Deck Slab
Girder End
Test Region Reinforcement
BT6 Standard GGBFS (50%)
R No. 4 @ 10 in.
L D20 @ 12 in.
BT7 LRFDSilica Fume (5%)
R No. 4 @ 6.5 in.
L No. 4 @ 15 in.
BT8 LRFD Fly Ash (20%)
R D20 @ 8 in.
L D20 @ 12 in.
Shear Strength Test Results
0
100
200
300
400
500
600
700
BT6-L BT6-R BT7-L BT7-R BT8-L BT8-R
DesignMeasured
Test Specimen End
AppliedShear,kips
Fatigue & Shear Study -Conclusions
High-strength concrete girders incorporating mid-span flexural cracks can be expected to perform adequately under fatigue loading conditions when extreme fiber tensile stress is limited to the current allowable level.
Fatigue test results indicate that higher allowable tensile stresses for HPC can be used if the concrete remains uncracked. However, the potential for unanticipated cracking makes utilizing reserve strength a risky proposition.
Fatigue & Shear Study -Conclusions
Measured shear strengths for high-strength concrete girders exceeded the corresponding calculated strengths determined using current design provisions from either the AASHTO Standard Specifications or AASHTO LRFD Specifications.
The existing 60 ksi limit for the design yield strength of transverse reinforcement is conservative, and higher yield strength values can be conservatively utilized for deformed welded wire reinforcement.
Fatigue & Shear Study -Recommendations
The allowable concrete tensile stress used in flexural design of HPC girders should be limited to 6 .
The Louisiana DOTD may implement the use of 72-in. deep HPC bulb-tee girders designed in accordance with current AASHTO provisions with the knowledge that girder performance will be satisfactory.
Deformed welded wire reinforcement with a design yield strength of 75 ksi may be used as an alternative to conventional deformed bars.
cf '
- 62-Span Bridge- Total Length = 5,489 ft- HPC Incorporated in Two 131-ft Long Spans- HPC Spans Incorporate Four BT-78 Girders
Implementation Project –US 90 Rigolets Pass Bridge
(2007)
Overall Research Objective
Monitor the structural behavior of one of the two HPC spans in the Rigolets Pass Bridge for the purpose of obtaining additional data for the State’s growing HPC data base that will be useful in the development of specifications and designs for future HPC bridge structures.
Project Team
Tulane University
CTLGroup
Henry G. Russell, Inc.
Rigolets Pass Bridge –Research Plan
Measure prestress force levels in selected strands during fabrication of girders for Span 43.
Monitor early-age and long-term concrete strains in girders and bridge deck slab incorporated in Span 43.
Monitor early-age and long-term mid-span deflections for girders incorporated in Span 43.
Perform material property testing program for Span 43.
Install on-site automated data acquisition system with remote access capability and web-site presentation.
Instrumented Bridge Span(Span No. 43)
Design InformationStructural design per AASHTO Standard Specifications (Sixteenth Edition).
Design live load based on greater of MS-18 or HST-18(M).
Specified girder concrete compressive strength of 6,670 psi at release and 10,000 psi at 56 days.
Specified deck slab concrete compressive strength of 4,200 psi at 28 days.
Girder Fabrication Information
Girders fabricated by Gulf Coast PreStress, Pass Christian, Mississippi.
Each BT-78 HPC girder incorporated fifty-six 0.6-in. diameter, Grade 270, low-relaxation strands in lower flange.
Each strand in lower flange stressed to initial force of 43.95 kips (75% of specified minimum breaking strength).
GIRDERINSTRUMENTATION
& FABRICATION
Strand Load Cells
DEAD END VIEW
Vibrating Wire Strain Gages
DEAD END VIEW
Material Sampling
Camber Instrumentation
SPAN NO. 43CONSTRUCTION
Deck Slab VWSGs
Camber/Deflection Reference
Deck Concrete Placement
PRELIMINARY RESEARCH RESULTS
Girder Concrete Mix DesignMaterial Quantity per yd3
Portland Cement (Type III) 846 lbSilica Fume 100 lbFine Aggregate 1,149 lbCourse Aggregate - Limestone 1,866 lbWater 204 lbWater Reducer (ASTM C494, Type D) 38 ozHigh-Range Water Reducer (ASTM C494, Type F)
51 oz
Air Entrainment NoneWater/Cementitious Ratio 0.22
6,000
8,000
10,000
12,000
14,000
0 10 20 30 40 50 60 70 80 90 100
Concrete Age, days
ConcreteCompressive Strength, psi
Girder 43AGirder 43BGirder 43CGirder 43D
Girder Concrete Compressive Strength
MOE vs Compressive Strength
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000Compressive Strength, psi
ConcreteModulus
ofElasticity,
ksiAASHTO ExpressionPiles P1, P2, P3Girders BT1, BT2, BT3, BT5Charenton - MatchCharenton - FieldBT6, BT7, BT8BT11, BT12Girders 43A, 43B, 43C, 43D
MOR vs Compressive Strength
0
200
400
600
800
1,000
1,200
1,400
2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000Concrete Compressive Strength, psi
ConcreteModulus ofRupture, psi
Piles P1, P2, P3Girders BT1, BT2, BT3, BT5CharentonBT6, BT7, BT8Girders BT11, BT12Girders 43A, 43B, 43C, 43D
fr = 7.5 f 'c
fr = 10 f 'c
Creep Coefficient
0.00
0.50
1.00
1.50
2.00
2.50
3.00
0 100 200 300 400 500Concrete Age, days
CreepCoefficient
Age of Loading = 4 DaysAge of Loading = 100 days
Shrinkage
-50
0
50
100
150
200
250
300
350
400
0 100 200 300 400 500
Concrete Age, days
ConcreteShrinkage,
με
Age of Loading = 4 Days
Age of Loading = 100 days
Prestress Force Measurement
Girder Production
Run
Average Force After Stressing All
Strands
Average Force Prior to Release of
PrestressKips %
ReductionKips %
Reduction43 A and 43B 42.01 4.4 40.94 6.8
43C and 43D 41.80 4.9 40.04 8.9
Average 41.90 4.7 40.49 7.9
Specified 43.95 <5.0 - -
Measured Girder Concrete Strains
-200
0
200
400
600
800
1,000
1,200
0 100 200 300 400 500
Time Since Release, days
ConcreteStrain,με
Girder 43A-BF and TF Girder 43B-BF and TF
Girder 43C-BF and TF Girder 43D-BF and TF
Measured Prestress Loss
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
0 100 200 300 400 500
Time Since Release, days
PrestressLoss,
psi
Girder 43AGirder 43BGirder 43CGirder 43D
Prestress LossesPrestress
LossComponent
MeasuredLoss,
psi
DesignLoss,
psi
Elastic - ES 19,563 20,545
Relaxation - CRs - 908
Creep - CRc 6,720 34,993
Shrinkage - SH 5,750
Total 26,283 62,197
Measured Midspan Camber
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
0 100 200 300 400 500 600 700Time After Strand Release, days
MidspanCamber, in.
Girder 43A Girder 43B
Girder 43C Girder 43D
Girder CamberEvent
(Time AfterRelease, days)
MeasuredCamber,
In.
CalculatedCamber,
In.
After Release (0.01) 2.25 3.15
Before Shipping (110-118) 3.54 3.49
After Casting Deck (177-185) 1.86 1.93
6 Mo. After Deck Cast (364-372) 1.72 1.93
Final Reading (?) ? -
Measured Deck Slab Strain
-50
0
50
100
150
200
0 100 200 300 400 500 600
Time After Cast, days
CompressiveStrain @
Mid-Depth of Deck Slab,
με
43-S143-S243-S343-S443-S543-S643-S7
On-Site DAS w/Remote Access
Web-Based Data Posting
THANK YOU!