8
HERA •Week 50 •Nov-Dec Running •Shut-down at the end of the year •Startup in January •January-February Running

HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

Embed Size (px)

Citation preview

Page 1: HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

HERA

•Week 50

•Nov-Dec Running

•Shut-down at the end of the year

•Startup in January

•January-February Running

Page 2: HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

HERA Week 50

Machine Studies

Luminosity Runs

40mA p

Proton filework

Luminosity Run

40mA p

Technical problemsSEDAC,

SC RF

Background Studies

Page 3: HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

November Running

lumi32%

p-inj30%

e-inj20%

no beam7%

lumi tuning9%

no e2%

December 02

December Running

Lumi Tuning4%

No e beam6%

other2%

Lumi27%

P-inj25%

e-Inj22%

no beam14%

December Running

Page 4: HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

Schedule Week 51Fri Jan 3 - Mo Jan 6 start Up

Tu Dec 23- Thu Jan 2 shut down

Mo Dec 23 shutting down

So December 22 N high lumi / warm up GO/GGS high lumi F high lumi

Sa December 21 N MD: bb beta beat vs p bunch intensity S MD: test phase trombone F MD: lumi preparations

Fr December 20 N MD: Invest. of Synchro betatron resonancesS MD: Invest. of Synchro betatron resonances F MD: Invest. of Synchro betatron resonances

Th December 19 N MD: long e run S MD: high intensity e+ F MD: high intensity e+

We December 18 N luminosity operation S luminosity operation F luminosity operation

Tu December 17 N luminosity operation S luminosity operation F luminosity operation

Page 5: HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

Short Shut Down

Proposal:

• Do not break IR Vacuum North

• Warm up GO/GG beam pipes to room temp.

• Pump the warm pipes for 10 days

• Activate neg pumps

• Cool down

Page 6: HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

January Running

Continuous running without interruption by machine studies or background studies

Machine stdies en bloc in February

Page 7: HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

Machine Shut Down Activities• IR Survey before and after installations• Exchange bellows in the IR by bellows with SR shield• Add pumping ports to GA 30L? (not decided yet)• Install SR absorbers to protect rf screens in rotator area• Exchange Absorber 4• Install movable collimator at absorber 1 ?• Install movable collimator at L60m• Realignment of East Rotator• Repair wire alignment system• Replace electronics of e BPM monitors• Install bipolar chopper VO• Install fast injection kickers• Repair p-BPM• Repair vacuum leak, damaged windows, insulation SC cavities• Improve QR cooling

Page 8: HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running

Restart in July

• Start to close tunnel 4 weeks before shut down ends for ps tests (West, East, South)

• 3 weeks of start up with beams