Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Henderson Ave. Complete Streets Project
� Meeting Purpose� To finalize
conceptual components of project prior to proceeding with preliminary engineering
� www.dallascompletestreets.wordpress.com
Meeting Agenda
� Presentation (40 minutes)
� Project background and schedule
� Summary of preferences from workshop #2
� Overview of conceptual design options
� Q and A (20 minutes)
� Voting Exercise (20 minutes)
� www.dallascompletestreets.wordpress.com
Project Background
� 2012 Complete Street bond budget: $1.3 Million
� Resurfacing budget $750,000 (Ross to Willis)
� DWU Improvements $45,000
� Project Limits: US 75 to Ross St. (1.1 miles)
� ROW Width: 50 feet (approx.)
� www.dallascompletestreets.wordpress.com
Interdisciplinary Project Team
� Planning & Neighborhood Vitality
� Strategic Planning
� City Design Studio
� Transportation Planning
� Public Works
� Streets Services
� DART
� Storm Water Management
� www.dallascompletestreets.wordpress.com
Project Schedule
� September 2014 - Public workshop #1: Preliminary design priorities
� April 2015- Public workshop #2: Conceptual design options:
� Bike Lane Option� Median Option
� September 2015 – Public workshop #3: Finalize Corridor Concept
� Spring 2016 (tentative) - Public workshop #4: Preliminary engineering design
� January 2017 (tentative) – Begin construction
� www.dallascompletestreets.wordpress.com
Conceptual Design Stage
� Focus on overall street design concept and general location of key design elements
� No specific styles, fixtures or materials selected yet
� Rough cost estimates to provide a general sense of budget allocation to various design components
� www.dallascompletestreets.wordpress.com
Community Priorities Key Themes From April 2015 Public Workshop
� General lack of support for bike lanes due to limited roadway width and safety issues
� Little support for median option. Most community members saw limited benefit
� On street parking is a priority
� Popular elements� Traffic Calming
� Lighting
� Extended median north of Willis
� Crosswalk upgrades
� Resurfacing
� Don’t use resurfacing funds for complete streets components
� www.dallascompletestreets.wordpress.com
Community Priorities Key Themes From April 2015 Public Workshop
� Explore Traffic Signal at Willis @ Henderson
� Explore left turn at Willis @ Henderson
� Explore possibility of stop signs
� www.dallascompletestreets.wordpress.com
Two Conceptual Design Options Proposed Corridor Concept Highlights
• 8’ Parallel Parking Lane in Select Locations
• 11’ Traffic Lanes (Narrowed lanes to slow traffic and accommodate bicycles)
• Net gain of about 70 parking spaces throughout corridor
• Landscaped bumpouts throughout corridor (xeriscape)
• Pedestrian lighting between US 75 and Richard
• Sidewalk reconstruction where needed
• Refreshed Crosswalks throughout corridor
• Repaving & Restriping (Willis to Ross)
• Landscaping (where ROW exists)
• Tree Plantings
• ADA compliant curb ramps (all intersections throughout corridor)
• Decorative Paving (Willis and Richard Ave)
• Bike Racks (Commercial/retail blocks)
• Gateway markers/Wayfinding
• No Bike Lanes
New Parallel Parking Areas
Willis to Homer (North Side)
Mission to Manett (South Side)
Capitol to Glencoe (South side)Glencoe to McMillan (North side)
McMillan to Lewis (North side)
Knig
ht
Thro
ckm
ort
on
� www.dallascompletestreets.wordpress.com
US 75 to Willis Cross-section (Configuration Unchanged)
55’ ROWExisting Median to be Extended South
Explore option to convert 90 degree parking to 60 degree angle parking
Henderson Ave. Typical Section (Parallel parking on north side of street)
8’11’ 11’
Henderson Ave. Typical Section(Parallel parking on south side of street)
8’ 11’ 11’
30’ Curb to Curb
50’ ROW
For Remainder of Blocks in Median Option
3’ Shoulder 3’ Shoulder
Henderson Ave. Typical Section (Sections without Parallel Parking)
Consolidate Curb Cuts
Vegetated Bumpout& Continental Crosswalks
Note: This is an example only. No style, material or detailed design choices have been made.
Bumpout with Parallel ParkingNote: This is an example only. No style, material or detailed design choices have been made.
Decorative Pavement Example
Note: This is an example only. No style, material or detailed design choices have been made.
Landscaping Examples
Xeriscape Bumpouts
Note: This is an example only. No style, material or detailed design choices have been made.
Landscaping Examples
Landscaped Buffer
Note: This is an example only. No style, material or detailed design choices have been made.
Pedestrian Light Examples
Note: This is an example only. No style, material or detailed design choices have been made.
Gateway Marker Example
Note: This is an example only. No style, material or detailed design choices have been made.
Proposed New Crosswalks
� New Crosswalks proposed at intersections of:
� Richard
� Homer
� Mission (one existing, another proposed)
� Capitol
� Glencoe
� Lewis
� www.dallascompletestreets.wordpress.com
Potential For New Stop Signs
� Traffic counts showed volumes do not justify stops at:
� Richard
� Homer
� Mission Capitol
� Glencoe
� Lewis
Willis Intersection (Traffic Signal)
• Community requested traffic control/traffic calming
• Traffic counts show sufficient volumes to warrant signal
• 4 way stop signs not recommended due to traffic queuing close to US 75
• Signal Installation Cost: About $300,000
• Options: • Build utilities/foundation as part of complete streets project
(about $25,000) and fund/install signal at later time• Fund & install complete signal as part of Complete Streets
project
Willis Intersection
(Dedicated Left Turn)
• Dedicated left turn requested by community in lieu of existing dedicated right
• Would require widening Henderson south of Willis to allow for straighter traffic movement from right lane of Henderson
• Impacts:• ROW acquisition• Stormwater inlet
relocation• Roadway widening• Loss of off-street
parking spaces on private property (about 5)
Inlet
Maintenance
� City will seek to partner with community on maintenance of some design elements:
� Soft landscape (Trees & Shrubs)
� Bike racks, benches, trash receptacles
� Gateway markers
� Landscaped Bumpouts
Vickery Park Sidewalk (Proposed Concept)
• Sidewalk inaccessible due to parallel parking in public ROW• Removal of 3 existing parallel spaces & 7 existing perpendicular spaces• Will be replaced with sidewalk & 10 on-street parallel parking spaces
within existing ROW (no parking loss on block)• Will reduce traffic conflicts and improve pedestrian safety
Before
After
8’11’11’
Milk and Honey Sidewalk (Proposed
Concept)
• Sidewalk narrowed to about 3’-4’ due to parallel parking in public ROW
• Wider sidewalk would be rebuilt with vegetative buffer• On-street parking spaces in public ROW to be replaced 1 for 1 (no
parking loss)• Will improve pedestrian safety
Before
After
11’ 11’ 8’
Instant Polling
� Did we capture your vision for Henderson Ave?
� Gain consensus on amenities
� Finalize the complete streets concept
� www.dallascompletestreets.wordpress.com