36
Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to proceeding with preliminary engineering www.dallascompletestreets.wordpress.com

Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Henderson Ave. Complete Streets Project

� Meeting Purpose� To finalize

conceptual components of project prior to proceeding with preliminary engineering

� www.dallascompletestreets.wordpress.com

Page 2: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Meeting Agenda

� Presentation (40 minutes)

� Project background and schedule

� Summary of preferences from workshop #2

� Overview of conceptual design options

� Q and A (20 minutes)

� Voting Exercise (20 minutes)

� www.dallascompletestreets.wordpress.com

Page 3: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Project Background

� 2012 Complete Street bond budget: $1.3 Million

� Resurfacing budget $750,000 (Ross to Willis)

� DWU Improvements $45,000

� Project Limits: US 75 to Ross St. (1.1 miles)

� ROW Width: 50 feet (approx.)

� www.dallascompletestreets.wordpress.com

Page 4: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Interdisciplinary Project Team

� Planning & Neighborhood Vitality

� Strategic Planning

� City Design Studio

� Transportation Planning

� Public Works

� Streets Services

� DART

� Storm Water Management

� www.dallascompletestreets.wordpress.com

Page 5: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Project Schedule

� September 2014 - Public workshop #1: Preliminary design priorities

� April 2015- Public workshop #2: Conceptual design options:

� Bike Lane Option� Median Option

� September 2015 – Public workshop #3: Finalize Corridor Concept

� Spring 2016 (tentative) - Public workshop #4: Preliminary engineering design

� January 2017 (tentative) – Begin construction

� www.dallascompletestreets.wordpress.com

Page 6: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Conceptual Design Stage

� Focus on overall street design concept and general location of key design elements

� No specific styles, fixtures or materials selected yet

� Rough cost estimates to provide a general sense of budget allocation to various design components

� www.dallascompletestreets.wordpress.com

Page 7: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Community Priorities Key Themes From April 2015 Public Workshop

� General lack of support for bike lanes due to limited roadway width and safety issues

� Little support for median option. Most community members saw limited benefit

� On street parking is a priority

� Popular elements� Traffic Calming

� Lighting

� Extended median north of Willis

� Crosswalk upgrades

� Resurfacing

� Don’t use resurfacing funds for complete streets components

� www.dallascompletestreets.wordpress.com

Page 8: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Community Priorities Key Themes From April 2015 Public Workshop

� Explore Traffic Signal at Willis @ Henderson

� Explore left turn at Willis @ Henderson

� Explore possibility of stop signs

� www.dallascompletestreets.wordpress.com

Page 9: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Two Conceptual Design Options Proposed Corridor Concept Highlights

• 8’ Parallel Parking Lane in Select Locations

• 11’ Traffic Lanes (Narrowed lanes to slow traffic and accommodate bicycles)

• Net gain of about 70 parking spaces throughout corridor

• Landscaped bumpouts throughout corridor (xeriscape)

• Pedestrian lighting between US 75 and Richard

• Sidewalk reconstruction where needed

• Refreshed Crosswalks throughout corridor

• Repaving & Restriping (Willis to Ross)

• Landscaping (where ROW exists)

• Tree Plantings

• ADA compliant curb ramps (all intersections throughout corridor)

• Decorative Paving (Willis and Richard Ave)

• Bike Racks (Commercial/retail blocks)

• Gateway markers/Wayfinding

• No Bike Lanes

Page 10: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

New Parallel Parking Areas

Willis to Homer (North Side)

Mission to Manett (South Side)

Capitol to Glencoe (South side)Glencoe to McMillan (North side)

McMillan to Lewis (North side)

Page 11: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Knig

ht

Thro

ckm

ort

on

� www.dallascompletestreets.wordpress.com

US 75 to Willis Cross-section (Configuration Unchanged)

55’ ROWExisting Median to be Extended South

Explore option to convert 90 degree parking to 60 degree angle parking

Page 12: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Henderson Ave. Typical Section (Parallel parking on north side of street)

8’11’ 11’

Page 13: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Henderson Ave. Typical Section(Parallel parking on south side of street)

8’ 11’ 11’

Page 14: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

30’ Curb to Curb

50’ ROW

For Remainder of Blocks in Median Option

3’ Shoulder 3’ Shoulder

Henderson Ave. Typical Section (Sections without Parallel Parking)

Page 15: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to
Page 16: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to
Page 17: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to
Page 18: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Consolidate Curb Cuts

Page 19: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to
Page 20: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Vegetated Bumpout& Continental Crosswalks

Note: This is an example only. No style, material or detailed design choices have been made.

Page 21: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Bumpout with Parallel ParkingNote: This is an example only. No style, material or detailed design choices have been made.

Page 22: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Decorative Pavement Example

Note: This is an example only. No style, material or detailed design choices have been made.

Page 23: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Landscaping Examples

Xeriscape Bumpouts

Note: This is an example only. No style, material or detailed design choices have been made.

Page 24: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Landscaping Examples

Landscaped Buffer

Note: This is an example only. No style, material or detailed design choices have been made.

Page 25: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Pedestrian Light Examples

Note: This is an example only. No style, material or detailed design choices have been made.

Page 26: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Gateway Marker Example

Note: This is an example only. No style, material or detailed design choices have been made.

Page 27: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Proposed New Crosswalks

� New Crosswalks proposed at intersections of:

� Richard

� Homer

� Mission (one existing, another proposed)

� Capitol

� Glencoe

� Lewis

� www.dallascompletestreets.wordpress.com

Page 28: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Potential For New Stop Signs

� Traffic counts showed volumes do not justify stops at:

� Richard

� Homer

� Mission Capitol

� Glencoe

� Lewis

Page 29: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Willis Intersection (Traffic Signal)

• Community requested traffic control/traffic calming

• Traffic counts show sufficient volumes to warrant signal

• 4 way stop signs not recommended due to traffic queuing close to US 75

• Signal Installation Cost: About $300,000

• Options: • Build utilities/foundation as part of complete streets project

(about $25,000) and fund/install signal at later time• Fund & install complete signal as part of Complete Streets

project

Page 30: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Willis Intersection

(Dedicated Left Turn)

• Dedicated left turn requested by community in lieu of existing dedicated right

• Would require widening Henderson south of Willis to allow for straighter traffic movement from right lane of Henderson

• Impacts:• ROW acquisition• Stormwater inlet

relocation• Roadway widening• Loss of off-street

parking spaces on private property (about 5)

Inlet

Page 31: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Maintenance

� City will seek to partner with community on maintenance of some design elements:

� Soft landscape (Trees & Shrubs)

� Bike racks, benches, trash receptacles

� Gateway markers

� Landscaped Bumpouts

Page 32: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Vickery Park Sidewalk (Proposed Concept)

• Sidewalk inaccessible due to parallel parking in public ROW• Removal of 3 existing parallel spaces & 7 existing perpendicular spaces• Will be replaced with sidewalk & 10 on-street parallel parking spaces

within existing ROW (no parking loss on block)• Will reduce traffic conflicts and improve pedestrian safety

Page 33: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Before

After

8’11’11’

Page 34: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Milk and Honey Sidewalk (Proposed

Concept)

• Sidewalk narrowed to about 3’-4’ due to parallel parking in public ROW

• Wider sidewalk would be rebuilt with vegetative buffer• On-street parking spaces in public ROW to be replaced 1 for 1 (no

parking loss)• Will improve pedestrian safety

Page 35: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Before

After

11’ 11’ 8’

Page 36: Henderson Ave. Complete Streets Project · Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to ... (South Side) Capitol to

Instant Polling

� Did we capture your vision for Henderson Ave?

� Gain consensus on amenities

� Finalize the complete streets concept

� www.dallascompletestreets.wordpress.com