Hells Gates Dam &Big Rocks Weir

Business Case Update

Townsville Enterprise Limited

Page 2: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

BIG ROCKS WEIR BUSINESS CASE

Page 3: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

• The proposed Big Rocks Weir is located approximately 26 km north-west of Charters Towers, capable of storing up to 10,000 ML of water.

• The proposed purpose of the weir is for water supply for irrigation, industrial development and urban water supply.

• Project includes mass concrete gravity weir and associated infrastructure including saddle dam, outlet works, fishway and access track.

Page 4: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Reference Design

Big Rocks Weir – digital visualisation from upstream of the weir looking south

• Reference Design

• Approvals Processes

• Environmental Assessment

• Capital cost estimate -$59.82m (P90 – 38% contingency)

Page 5: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Site overview

Site location

Big Rocks Weir, Charters Towers

Page 6: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

• 20,000 ML of unallocated water currently available under the Water Plan (10,000ML strategic reserve and 10,000ML general reserve)

• Yield modelling undertaken indicates BRW could provide 10,000 ML at 100% reliability

• More than 10,000ML could be made available, but would be expected to be deliver less reliability

• Final amount of water to be made available subject to DNRME consideration

Big Rocks Weir Public Meeting, Charters Towers

Water availability and agricultural production

Page 7: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Big Rocks Weir Public Meeting, Charters Towers

Economics

BCR - 7%

10,000ML of water 1.38

15,000ML of water 1.80

20,000ML of water 2.14

Benefits

• Approximately 172 full-time equivalent (FTE) positions

directly supported during the construction peak in 2022.

• Additional economic activity and employment

opportunities associated with the operations of BRW and

use of the additional water supplied by the weir.

• At full production, an additional $35 million per annum in

additional agricultural revenue, and 117 FTEs each year will

be directly supported by the additional agricultural

production associated with BRW (10,000 ML of water).

• Reliability of water supply for Charters Towers during

extended dry periods.

Page 8: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Business Case21 August 2020

IAR31 January 2021

Construction2021/22

Milestones

Page 9: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

NEXT STEPS:

➢$30m funding committed by Commonwealth Government

➢Seeking matching funding contribution from Queensland Government

➢Progress detailed design

➢Charters Towers Regional Council as proponent to construct, own and deliver Big Rocks Weir.

Page 10: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

HELLS GATES DAMPROJECT UPDATE

Page 11: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Hells Gates Dam project overview

➢ 2,100 Gigalitre (GL) Hells Gates Dam

➢ 50,000 ha irrigation area

➢ 25,000 ha approx. of inundated area

➢ Dam height at 75 m

➢ 3 x weir pools

Page 12: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Location120 Kilometres north of Charters Towers and north west of Townsville.

Page 13: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Project update

HELLS GATES DAM:

➢Important project for the region

➢Delivery in accordance with Building Queensland guidelines

➢Coordinated project with Office of Coordinated General

➢Environmental Impact Assessment January 2022

Page 14: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water
Page 15: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Milestones

Business CaseApril 2022

Environmental Impact AssessmentJanuary 2022

Construction20??

Page 16: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

DAM, WEIR’S and IRRIGATION

Page 17: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Power link will investigate connecting 850MW of pumped hydro generation into the Ross Substation at Townsville.

Pumped Hydrology Storage

Page 18: Hells Gates Dam & Big Rocks Weir Business Case Update · 2020. 9. 18. · Big Rocks Weir Public Meeting, Charters Towers Economics BCR - 7% 10,000ML of water 1.38 15,000ML of water

Pumped Hydrology Storage