22
Heavy Water Components Test Reactor (HWCTR) Update Savannah River Site Citizens Advisory Board Facility Disposition and Site Remediation Committee -1- Presentation By Candice O. Freeman Deputy Federal Project Director Office of the Assistant Manager for Infrastrcture and Environmental Stewardship Department of Energy Savannah River Operations Office October 25, 2011

Heavy Water Components Test Reactor (HWCTR) Update

  • Upload
    vominh

  • View
    223

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Heavy Water Components Test Reactor (HWCTR) Update

Heavy Water Components Test Reactor (HWCTR) Update

Savannah River Site Citizens Advisory BoardFacility Disposition and Site Remediation Committee

-1-

Presentation By

Candice O. Freeman

Deputy Federal Project Director

Office of the Assistant Manager for Infrastrcture and Environmental Stewardship

Department of Energy

Savannah River Operations Office

October 25, 2011

Page 2: Heavy Water Components Test Reactor (HWCTR) Update

Agenda

• Heavy Water Components Test Reactor (HWCTR)

Background

• Completion Objectives

2

• Scope

• Accomplishments

• Photo Gallery

• Conclusion

Page 3: Heavy Water Components Test Reactor (HWCTR) Update

List of Acronyms

• ARRA American Recovery and Reinvestment Act

• D&D Deactivation and Decommissioning

• EE/CA Engineering Evaluation/Cost Analysis

3

• EE/CA Engineering Evaluation/Cost Analysis

• HWCTR Heavy Water Components Test Reactor

• KPP Key Performance Parameters

• M Million

• RSER Removal Site Evaluation Report

Page 4: Heavy Water Components Test Reactor (HWCTR) Update

Purpose

To provide a status update on the Heavy Water

Components Test Reactor (HWCTR) to the Facilities

4

Components Test Reactor (HWCTR) to the Facilities

Disposition and Site Remediation Committee

Page 5: Heavy Water Components Test Reactor (HWCTR) Update

HWCTR Location on the Savannah River Site

5

Page 6: Heavy Water Components Test Reactor (HWCTR) Update

Background

HWCTR was built to test the concept of heavy water

moderated reactors for the civilian power industry

(circ 1960)

6

Page 7: Heavy Water Components Test Reactor (HWCTR) Update

Background continued

• 1965

– Retired in place with controlled access

• 1975-1976

– Decommissioning plans considered

7

– Decommissioning plans considered

– Postponed due to budget constraints

• 1994-1997

– Second attempt to D&D

– Budget constraints again

– Auxiliary buildings removed

– Placed in extended surveillance mode

2009

Page 8: Heavy Water Components Test Reactor (HWCTR) Update

Background - Panorama view showing inside of HWCTR at Ground Level

8

Page 9: Heavy Water Components Test Reactor (HWCTR) Update

Completion Objectives

Achieve Human Health and Environmental

Protectiveness by removing approximately 99%

contamination

Meets standards for industrial worker

9

Meets standards for industrial worker

Final Decommissioned End State

In-Situ Decommissioning with Reactor Vessel and 2 Steam

Generators removed and disposed E-Area trenches on site

Page 10: Heavy Water Components Test Reactor (HWCTR) Update

Scope

Major Work Activities

Drain all liquids and isolate all

hazardous energy

Remove and dispose the metal dome

Remove and dispose the reactor vessel

Remove and dispose the two steam

10

Remove and dispose the two steam

generators

Grout the spent fuel pool

Grout the below-grade areas of the

building, including remaining piping

and equipment

Install a concrete cover over the

remaining grouted structure

Page 11: Heavy Water Components Test Reactor (HWCTR) Update

Scope - Conceptual Site Model of In-Situ Decommissioning with Reactor Vessel and Steam Generators Removal

11

Page 12: Heavy Water Components Test Reactor (HWCTR) Update

Photo Gallery

12

Photo Gallery

Page 13: Heavy Water Components Test Reactor (HWCTR) Update

Block Removal

13

Page 14: Heavy Water Components Test Reactor (HWCTR) Update

Crane Assembly

14

Page 15: Heavy Water Components Test Reactor (HWCTR) Update

Dome Removal

15

Page 16: Heavy Water Components Test Reactor (HWCTR) Update

Steam Generator Removal

16

Page 17: Heavy Water Components Test Reactor (HWCTR) Update

Reactor Vessel Removal

17

Page 18: Heavy Water Components Test Reactor (HWCTR) Update

Relocation of Transfer Coffin

18

Page 19: Heavy Water Components Test Reactor (HWCTR) Update

Dome and Wall Shearing

19

Page 20: Heavy Water Components Test Reactor (HWCTR) Update

Completed HWCTR Concrete Cap

20

Page 21: Heavy Water Components Test Reactor (HWCTR) Update

Conclusion

Work has been performed safely

Projects are mechanically completed and completed ahead of

schedule in July 2011 and below cost

21

Page 22: Heavy Water Components Test Reactor (HWCTR) Update

Cost Backup (Total Project Cost)

Original TPC ($ Million) Actual TPC ($ Million)

HWCTR Decommissioning

10.7 8.77

22