Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
© Heathrow Airport Limited 2019
Volume 1, Chapter 3
DCO Project alternatives
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
© Heathrow Airport Limited 2019
CONTENTS
3. DCO Project Alternatives 3.1
3.1 Introduction 3.1
3.2 Strategic alternatives 3.2
3.3 Component alternatives 3.3 Aviation 3.4 Roads 3.4 Displacements and Land Use 3.4
3.4 Aviation 3.9 Overview 3.9 Runway 3.10 Taxiways 3.12 Terminals, satellites and aprons 3.14 Aviation fuel supply, storage and distribution 3.16 Cargo 3.19 Maintenance, repair and overhaul facilities 3.21 Car parking facilities 3.22
3.5 Roads 3.26 M25 alignment 3.26 M25 junctions 3.29 A4 diversion 3.32 A3044 diversion 3.35
3.6 Displacements and land use 3.38 River diversions and flood storage 3.38 Drainage and pollution control 3.44 Utility diversions 3.48 Wastewater treatment 3.51 Home office immigration removals centre 3.53 Airport supporting development 3.55 Landscape Design and Green Infrastructure 3.58 Earthworks 3.59 Construction Support Sites 3.61
TABLE OF GRAPHICS
Graphic 3.1 Masterplan Assembly Process 3.6 Graphic 3.2: Indicative locations of runway options 3.11 Graphic 3.3: Indicative locations of taxiway options 3.13 Graphic 3.4: Indicative locations for terminal and apron growth 3.15 Graphic 3.5: Indicative locations of fuel storage facility options 3.17 Graphic 3.6: Indicative locations of truck park options 3.20 Graphic 3.7: Example of the consolidated car parking strategy 3.23 Graphic 3.8: Example of the semi-dispersed car parking strategy 3.24 Graphic 3.9: Example of the dispersed car parking strategy 3.25 Graphic 3.10: Indicative locations of M25 alignment options 3.28 Graphic 3.11: Indicative locations of M25 junction options 3.31 Graphic 3.12: Indicative locations of A4 diversion options 3.34 Graphic 3.13: Indicative locations of A3044 diversion options 3.37 Graphic 3.14: Indicative locations of flood storage site options 3.42
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
© Heathrow Airport Limited 2019
Graphic 3.15: Indicative locations of treatment facility options 3.46 Graphic 3.16: Indicative locations of substation relocation options 3.50 Graphic 3.17: Indicative locations of IRC replacement options 3.54 Graphic 3.18: Indicative locations of ASD opportunity sites 3.57 Graphic 3.19: Indicative locations of borrow pit site options 3.60 Graphic 3.20: Indicative locations of construction support site options 3.64
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.1 © Heathrow Airport Limited 2019
3. DCO PROJECT ALTERNATIVES
3.1 Introduction
This chapter considers the reasonable alternatives to the DCO Project. It sets out
why the preferred design has been selected over alternative options and explains
the environmental and other considerations which have been taken into account.
By way of context, it is a requirement of The Infrastructure Planning
(Environmental Impact Assessment) Regulations 2017 (the ‘EIA Regulations’) that
the Environmental Statement (ES) submitted with the application for development
consent should include:
“a description of the reasonable alternatives studied by the applicant, which are relevant to
the proposed development and its specific characteristics, and an indication of the main
reasons for the option chosen, taking into account the effects of the development on the
environment” (regulation 14(2)(d)).
This requirement is reiterated in the Airports National Policy Statement (ANPS)
(paragraph 4.28). However, with regard to the Preliminary Environmental
Information Report (PEIR), PINS Advice Note Seven explains that:
“There is no prescribed format as to what PEI[R] should comprise and it is not expected to
replicate or be a draft of the ES … the level of detail and type of PEI[R] may vary” (para.
7.4-7.5).
The information provided in this chapter will be updated for inclusion in the ES in
accordance with the EIA Regulations as the design of the DCO Project evolves
and other alternatives are considered.
Due to the scale of the DCO Project and extensive evaluation of alternatives
undertaken, this chapter focuses on the key alternatives that have been assessed
and the justification for their selection in relation to environmental effects. Context
for the components included in this chapter is set out in the Updated Scheme
Development Report (Updated SDR), which also forms part of the Airport
Expansion Consultation (June 2019). The Updated SDR explains in detail the
progress made to date in developing key components of the expanded Airport and
its supporting facilities in accordance with the scheme development process set
out in the Masterplan Scheme Development Manual (the Manual).
The level of detail provided for each alternative option in this chapter reflects the
extent of the relevant environmental consequences. It is clearly noted where all
options would have a similar environmental effect and thus the information
provided in that section is more limited. In such cases, feedback provided by other
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.2 © Heathrow Airport Limited 2019
evaluation disciplines was typically the determining factor in identifying the
preferred options.
This chapter also sign posts to where further information is available. It should be
noted that the labelling of options in this chapter does not necessarily reflect the
names used in the Updated SDR and Component Option Reports as, where
relevant, options have been grouped to explain similar environmental
consequences.
It should be noted that this chapter does not seek to repeat detail set out in the
Manual and Updated SDR but is focused on those alternative options that have
environmental consequences.
3.2 Strategic alternatives
In order to address long term airport capacity problems in London and the South-
East, the Government set up the Airports Commission in 2012, its purpose being
to determine how the UK could maintain its position as Europe’s most important
aviation hub and to examine the scale and timing of any requirement for additional
capacity.
The Airports Commission initially considered 52 proposals, with three options
developed by the Airports Commission itself.
Three schemes were shortlisted by the Airports Commission in its Interim report
(December 2013):
1. A new north-west runway at Heathrow Airport (the DCO Project)
2. A westerly extension of the northern runway at Heathrow Airport
3. A new runway at Gatwick Airport.
Studies of the proposal for a new hub airport in the inner Thames Estuary were
also continued beyond this date, but the Airports Commission concluded in
September 2014 that there were substantial disadvantages that collectively
outweighed its potential benefits and that it therefore did not represent a credible
option for shortlisting.
The Airports Commission’s Final Report was informed by a robust, integrated and
transparent process to assess the three shortlisted options, considering a range of
economic, social and environmental factors.
In light of this assessment, the Commission unanimously concluded in its final
report (July 2015) that of the three strategic alternatives, the proposal for a new
north-west runway at Heathrow Airport, in combination with a significant package
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.3 © Heathrow Airport Limited 2019
of measures to address its environmental and community impacts, presented the
strongest case.
Following a period of review and further analysis, the Government announced a
new north-west runway at Heathrow as its preferred scheme and location for
expanding airport capacity in the South-East. The ANPS was subsequently
designated in June 2018 confirming that there is a need for a third runway at
Heathrow Airport. Paragraphs 2.32-2.33 of the ANPS states that:
“Having reviewed the work of the Airports Commission and considered the evidence put
forward on the issue of airport capacity, the Government believes that there is clear and
strong evidence that there is a need to increase capacity in the South East of England by
2030 by constructing one new runway …
… the Government has identified the most effective and appropriate way to address the
overall need for increased airport capacity, and maintain the UK’s hub status, while
meeting air quality and carbon obligations and identifies that the Northwest Runway at
Heathrow is the Government’s preferred scheme”.
Paragraph 1.15 of the ANPS further confirms that:
“The Secretary of State will use the Airports NPS as the primary basis for making
decisions on any development consent application for a new Northwest Runway at
Heathrow Airport, which is the Government’s preferred scheme”;
“The policies in the Airports NPS will have effect in relation to the Government’s preferred
scheme, having a runway length of at least 3,500m and enabling at least 260,000
additional air transport movements per annum”;
“It will also have effect in relation to terminal infrastructure associated with the Heathrow
Northwest Runway scheme and the reconfiguration of terminal facilities in the area
between the two existing runways at Heathrow Airport”.
At a strategic level, the principle of the delivery of a new north-west runway at
Heathrow Airport (rather than elsewhere) is therefore firmly established within
national planning policy.
3.3 Component alternatives
Whilst the ANPS has established the need for the DCO Project, it does not fix the
design of the scheme. Rather it states that:
“While the Government has decided that a Northwest Runway at Heathrow Airport is its
preferred scheme to deliver additional airport capacity (an illustrative masterplan is at
Annex B of the Airports NPS), this does not limit variations resulting in the final scheme for
which development consent is sought” (paragraph 4.11).
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.4 © Heathrow Airport Limited 2019
In 2016, Heathrow Airport commenced a Scheme Development Process to inform
the selection of the preferred design for the DCO Project. For each component a
series of potentially feasible design alternatives were subject to a detailed
evaluation in combination with engagement with external stakeholders. Design
options were considered for the following key components of the DCO Project.
Aviation
1. Runway
2. Taxiway System
3. Terminals, satellites and aprons
4. Aviation fuel
5. Cargo
6. Maintenance
7. Car parking
Roads
1. M25 and junctions
2. Local roads.
Displacements and land use
1. River diversions and flood storage
2. Drainage and pollution control
3. Utility diversions
4. Wastewater treatment
5. Immigration Removals Centre
6. Airport supporting development
7. Landscape mitigation
8. Earthworks
9. Construction site options.
A long list of component option alternatives was considered and was reported in
the SDR which formed part of the suite of material consulted on as part of Airport
Expansion Consultation One (please refer to Chapter 1: Introduction for an
overview of Consultation One). The Consultation 1 feedback on options for each of
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.5 © Heathrow Airport Limited 2019
the components has informed further design development and the SDR has been
updated accordingly and published as part of the Airport Expansion Consultation
(June 2019).
An overview of the process and methodology that has been followed for identifying
and evaluating design options and selecting the preferred design for the DCO
Project for presentation in the Airport Expansion Consultation (June 2019), is
described below and illustrated in Graphic 3.1.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.6 © Heathrow Airport Limited 2019
Graphic 3.1 Masterplan assembly process
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.7 © Heathrow Airport Limited 2019
The four main stages of the evaluation process undertaken further to the
requirements of the Manual are summarised as follows:
1. Stage 1 – Strategic definition: the purpose of this stage was to set the
objectives for the DCO Project and define the key inputs in the process.
Examples of these inputs include: The Strategic Brief, which sets the strategic
vision of an expanded airport and formed part of the background material for
Airport Expansion Consultation One; the Evaluation Criteria Handbook, which
outlines the criteria used for evaluating the evolving component and preferred
masterplan options; and the Requirements Register, which captures the
requirements for an expanded airport from Heathrow and stakeholders
2. Stage 2 – Component options development: The components, some of which
are key to defining the shape of the design and the associated land required for
the DCO Project, have gone through a design development process. This
involved creating a longlist of all options to be considered, reducing the number
of options under consideration through the application of discontinuation rules
where there was a high degree of confidence that a component would not meet
the requirements, and evaluating the remaining options against the evaluation
criteria which were defined in Stage 1. Full details of the evaluation criteria can
be found in the Manual. The component options that were developed in this
stage were consulted upon in Airport Expansion Consultation One. The
preferred options for each component were taken forward to Stage 3 and the
feedback from the consultation was used to improve the options
3. Stage 3 – Masterplan options development: In this stage, preferred options
from the key components were combined to create assembly options.
Feedback received during Airport Expansion Consultation One, together with
the ongoing technical engagement with stakeholders, was used to review,
improve and endorse, or change the preferred component options for inclusion
in preferred masterplan assembly. The resulting masterplan options went
through a similar process to that outlined at the Component Options
Development stage, in that the list of options was reduced by applying
discontinuation rules and the remaining options were evaluated. This stage has
recently concluded with the selection of the Preferred Masterplan which we are
now consulting on as part of the Airport Expansion Consultation (June 2019)
4. Stage 4 – Masterplan Finalisation: in this stage, the Preferred Masterplan
selected in Stage 3 will be developed further, supported by further stakeholder
engagement and the feedback from this Airport Expansion Consultation (June
2019), which consults on the Preferred Masterplan along with the alternatives
which were considered and rejected. The Preferred Masterplan will be refined
in light of on-going environmental assessment, including definition of
appropriate environmental measures to avoid or reduce the likely significant
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.8 © Heathrow Airport Limited 2019
effects of the DCO Project on communities and the environment. This stage
will conclude with the submission of the DCO application in Summer 2020.
The selected and alternative options were evaluated based upon criteria set out in
the Manual. The seven evaluation disciplines comprise:
1. Operations and Service, which includes: airfield performance, airspace
performance, passenger experience, security, hub connectivity, baggage
performance, surface access, cargo and logistics, aviation fuel infrastructure
and implications for those working at the Airport
2. Delivery, which includes: construction complexity and programme implications
3. Sustainability which includes: carbon and climate change, landscape, historic
environment, biodiversity, water, air quality, land quality, socio-economics,
noise and waste
4. Community, which includes: in-combination effects and impacts on community
facilities
5. Planning, which includes policy fit
6. Property, which includes land requirements
7. Business Case, which includes: cost, viability, commercial income, capacity
and affordability of infrastructure and viability and financeability of the case.
The evaluation process has included input provided by Delivery and Operations
disciplines, enabling each component to be assessed against criteria relevant to
the construction of the DCO Project and its future operation. As the scheme
developed, it was also necessary to evaluate aspects of construction as
components. This includes consideration of Construction Support Sites (to
facilitate delivery of the DCO Project) and potential sites at which borrow pits could
be established to source the fill material.
This preliminary DCO Project Alternatives chapter presents the reasonable
alternatives with respect to the key physical components of the Preferred
Masterplan and elements of construction which directly influence the land which
may be required to deliver the DCO Project. However, the options for how we
operate three runways in the future have also been considered and have been
subject of a process of detailed evaluation. This has included options for: runway
alternation, to manage noise and provide regular breaks from planes flying directly
over local communities (respite); directional preference, which relates to how we
choose which direction the aircraft approach and depart Heathrow; and night flight
management, the options for introducing the 6.5hr ban on scheduled night flights.
Details of the ongoing process to determine our preferred package of operational
respite measures are set out within Document 5 of the Updated SDR, as is our
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.9 © Heathrow Airport Limited 2019
initial preferred package. Furthermore, other proposed operational noise mitigation
measures are described in Chapter 18 of this PEIR and in the Future Runway
Operations document also published as part of the AEC.
While this chapter is focused on the environmental effects of each component,
other considerations are also set out where relevant to explain how the selected
component option has been selected in a balanced way considering all the criteria.
Where appropriate, the requirements that relate to an individual component are
referred to below, in particular where a requirement has negated the need to
consider alternatives that would not be acceptable. A more comprehensive
description of requirements for each component can be found in the Updated
SDR.
3.4 Aviation
Overview
The DCO Project encompasses development that will lie within the expanded
Airport’s operational boundary, as well as development beyond this boundary
which is associated with the Airport’s expansion.
The critical infrastructure necessary to operate at least an additional 260,000 Air
Transport Movements (ATMs) at Heathrow Airport will comprise:
1. North West Runway and supporting taxiway network to link with the rest of the
Airport
2. Works to the existing northern runway (the future central runway)
3. New terminal and apron capacity to enable processing of the additional
passengers and aircraft, including new passenger and baggage connectivity to
link the terminals
4. Ancillary infrastructure – for example aircraft maintenance facilities, aviation
fuel infrastructure, and cargo facilities – to enable the expanded Airport to
operate
5. Car parking facilities to enable access to Heathrow Airport, both for passengers
and colleagues.
The requirements associated with these components primarily relate to those
which are essential to operate an airport. Relative to other components, there is
limited flexibility in how these components can be arranged and consequently the
number of alternative options is less than for other components and the extent of
the difference between the environmental effects of alternative options is generally
reduced.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.10 © Heathrow Airport Limited 2019
Runway
Introduction
The North West runway design developed by Heathrow for the Airports
Commission process sat between the communities of Colnbrook and Brands Hill
to the west, Sipson to the east and Harmondsworth to the north. Other
communities are also located nearby. It is recognised that the precise positioning
of the runway is important to Heathrow’s neighbours and the options evaluation
therefore included consideration of the potential local effects and environmental
effects associated with the runway, to understand the consequences of locational
choices.
As part of the Scheme Development Process, the length and precise location of
the runway was considered. At Stage 2, options were included for a shorter
runway than the selected option (as short as 2,295m). However, upon the
designation of the ANPS, in particular paragraph 4.3 which established a
requirement for the North West Runway to be at least 3,500m in length, it was
necessary to remove the shorter alternative options from consideration.
To permit independent parallel approaches and full runway alternation, there is a
requirement to have a minimum separation distance of 1,035m between the North
West Runway and the existing northern runway. More detail can be found in
Document 2, Chapter 1 of the Updated SDR.
Options
The following 3,500m runway options were considered (see Graphic 3.2):
1. The eastern end of the runway is fixed at a point to the west of the village of
Sipson (Family A)
2. The western end of the runway is fixed at a point to the east of the M25, with
the runway extending eastwards. This runway option does not cross the M25
(Family B)
3. The eastern end of the runway is fixed at a point to the west of the village of
Harlington, with the runway extending westwards. This option is similar to
Option 2 and explored the effects of moving the runway further eastwards
(Family C)
4. The eastern end of the runway is fixed at a point immediately to the west of the
M4 Spur motorway, with the runway extending westwards. This option explored
the effects of moving the runway approximately 300m further to the east than
Option 1, but not as far east as the Option 2 and 3, both of which extend
beyond the M4 spur (Family D).
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.11 © Heathrow Airport Limited 2019
Graphic 3.2: Indicative locations of runway options
Evaluation summary
Family A (Option 1) is the selected option. This meets the requirements of the
ANPS. It is consistent with the runway position included in the Airports
Commission scheme.
The selected option will facilitate the provision of respite from noise for local
communities, through full alternation of runway modes. It is the most preferable in
terms of the wider effects of air noise. Specifically, its location further west of the
London than other options will reduce noise effects associated with aircraft
movement across the Capital, relative to the alternatives. Unlike those alternative
options which would align the runway further to the east, the selected option would
not result in the demolition of further properties in Sipson. The selected option
does however extend to the west of the existing M25 motorway, demanding
realignment and lowering of the existing motorway. This introduces greater
complexity from a delivery perspective and is discussed further in Section 3.5:
Roads.
Option 2 and Option 3 would reduce interaction between the runway and the
existing M25 alignment and therefore have some benefits from a cost and delivery
perspective. However, these options were discontinued on environmental,
community, planning and property grounds. These options extend further east
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.12 © Heathrow Airport Limited 2019
than the selected option, would result in the additional property loss and
exacerbate noise and air quality effects at retained properties. This includes
properties in Harlington, given the proximity of these runway options to this
community.
Option 4 would cross the existing M25 alignment and introduce similar delivery
and delivery complexities as the selected option. However, as with Option 2 and
Option 3, it would also require additional demolitions of property in Sipson, whilst
not delivering any material benefits from a noise, air quality and community
perspective.
Taxiways
Introduction
Taxiways will be required to serve the new north-west runway and connect it with
the existing Airport. The system must provide efficient and safe links that deliver
predictable journey times for passengers and lower operating costs for airlines.
The taxiway system must ensure capacity and resilience can be optimised.
Some parts of the taxiway system are dependent on the terminal and apron layout.
Other sections of the taxiway network have been designed as separate
components and are therefore discussed in this section. These include:
1. The section of the taxiway system which allows aircraft to travel around the
west side of the western apron
2. The section of the taxiway system which allows aircraft entry and exit to what
will become the central runway, from north and south
3. The section of the taxiway system which allows aircraft to travel between the
new north-west runway and the existing airfield.
Based upon the need to optimise capacity, around the end taxiways (ATET) were
considered, which involve separate taxiways routed around either or both ends of
the runway, enabling aircraft to move without constraining runway operations.
Options
The following taxiway options were considered during component evaluation (see
Graphic 3.3):
1. Provision of ATETs at the eastern end of the central runway, 3 sub-options
were considered to accommodate either Code C, E or F aircraft
2. Provision of ATETs at the western end of the central runway, again 3 sub-
options were considered to accommodate either Code C, E or F aircraft
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.13 © Heathrow Airport Limited 2019
3. Provision of a Western Bypass Taxiway to the west of the Terminal 5 campus.
Following consideration of these taxiway options, an additional taxiway layout was
also identified during masterplan assembly (Stage 3):
4. Provision of a north-east taxiway to the north and east end of the central
runway.
Graphic 3.3: Indicative locations of taxiway options
Evaluation summary
As described in further detail in Document 2, Chapter 2 of the Updated SDR, a
combination of taxiway options has been selected.
Twin ‘Code F’ ATETs at the western end of the central runway have been
selected, which will enable independent operation of the central runway while
aircrafts are taxiing. This will maximise the runway throughput, avoiding taxiway
and runway congestion. Alternative Code options that are closer to the existing
runway could only accommodate smaller aircraft and would not operate as
efficiently, counter to the aim of providing an efficient airfield layout which reduces
potential fuel burn and associated emissions.
Locating the ATETs at the western end would position the taxiways nearer to the
NWR. It would also reduce the risk of associated air quality and noise effects by
virtue of locating the taxiways further away from existing communities. Specifically,
the alternative eastern ATET options would locate taxiway infrastructure
significantly closer to receptors north of the A4 Bath Road.
A Western Bypass Taxiway is also included in the preferred Masterplan. Taxiway
modelling confirmed that its removal would increase ground interactions by 25%
and average taxi delay by up to 18%, both of which are beyond an acceptable
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.14 © Heathrow Airport Limited 2019
level for operations. The inclusion of the western bypass taxiway supports efficient
operations, reducing potential fuel burn and associated emissions.
The preferred Masterplan does not include a north-east taxiway. Airfield modelling
has indicated that it is not essential and would not outweigh property and
environmental effects. As with the eastern ATETs options, a north-east taxiway
would exacerbate noise and air quality effects at receptors to the north of the A4
Bath Road.
Terminals, satellites and aprons
Introduction
Growth in passenger throughput up to and beyond 130 million passengers per
annum (mppa) will be met by a combination of physical extension and
intensification of existing terminals and satellites and development of new
terminals and satellites. More detail can be found in Document 2, Chapter 3 of the
Updated SDR.
Options
The following alternative options for the terminals (see Graphic 3.4) were
considered:
1. North: a new northern apron would be necessary to serve the expanded Airport
but there are choices for the size of that apron and location of the associated
terminal capacity, which must be on the public transport spine. A large northern
apron could result in less apron infrastructure west of Terminal 5 and retain use
of junction 14a of the M25, as well as providing an opportunity to locate airport
supporting development in this space
2. West: An enlarged western apron between Terminal 5 and the M25 motorway
could result in a smaller northern apron
3. East: Expansion of the eastern apron would require relocation of airfield
taxiway and aircraft maintenance infrastructure, which benefits from using the
existing Airport efficiently but requires significant time to build
4. Centre: The centre apron will be considered for modification to achieve higher
land use efficiency.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.15 © Heathrow Airport Limited 2019
Graphic 3.4: Indicative locations for terminal and apron growth
Evaluation summary
Environmental considerations were not the primary determining factor in
identifying the preferred option but were considered in combination with the
performance of options against the criteria of the other evaluation disciplines,
including phasing and cost-effective delivery, airfield performance and efficiency,
passenger experience, security and baggage handling. From an environmental
perspective, the combination of expansion to the centre, north and west is
preferable over the alternative of a significantly enlarged western apron with
reduced capacity in the north, which would have more extensive effects on road
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.16 © Heathrow Airport Limited 2019
and river infrastructure to the west of Terminal 5 outside the existing Airport
boundary.
An alternative option relying on significant expansion to the east was not preferred
on the basis that it would not be on the public transport spine and would require
the relocation of the existing maintenance infrastructure, including the loss of the
Grade II Listed Technical Block A.
The combination of the three areas (north, west and centre) would also result in
less development of terminal and airfield infrastructure to the south west of Sipson,
in close proximity to existing communities.
Aviation fuel supply, storage and distribution
Introduction
An expanded Heathrow will require additional facilities for receiving, distributing
and storing fuel. The storage facilities need to hold adequate volumes of fuel to
feed the Airport in case of supply disruption. Alternative locations for fuel storage
in and around the Airport were considered.
The existing fuel railhead at Bath Road, Poyle, cannot remain in its current
location, because the proposed runway bisects the existing rail spur to the fuel
railhead. To maximise rail freight, increase fuel supply resilience and optimise the
Colnbrook branch line in the future, a fuel railhead will be required. The railhead
replacement will be provided on a like for like basis. The Colnbrook Branch Line
was considered the only suitable active railway line for the fuel railhead relocation.
More detail can be found in Document 2, Chapter 4 of the Updated SDR.
Options
The following alternative options for the fuel storage facilities (shown in Graphic
3.5) were considered:
1. Expanded Perry Oaks site: land within the existing Airport boundary which
already has connections to the existing supply pipelines and the Airport
hydrant, it is secure, and by locating the new facility immediately adjacent to
the existing site, most of the current facilities can be utilised
2. Grass Area 17a: land within the existing Airport boundary
3. Northern Apron sites: land within the expanded Airport boundary
4. Esso West London: land outside, to the south, of the Airport boundary currently
in use and adjacent to a current fuel storage facility
5. Gypsum site: land outside, to the north, of the existing Airport boundary
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.17 © Heathrow Airport Limited 2019
6. South of Esso West London: land outside, to the south, of the Airport boundary
currently in use and adjacent to a current fuel storage facility
The following alternative options for the fuel railhead replacement facility on the
Colnbrook Branch Line were considered:
1. Goodman’s Site (Colnbrook)
2. Gypsum Site at Thorney Mill Lane
Graphic 3.5: Indicative locations of fuel storage facility options
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.18 © Heathrow Airport Limited 2019
Evaluation summary
The selected option is to provide supplementary fuel storage on the northern
apron site and the expanded Perry Oaks site (Option 1 and Option 3). These sites
are within the boundary of the expanded Airport, which limits the risk of adverse
effects on landscape and townscape and views. The land would already form part
of the DCO Project and therefore the loss of agricultural land (northern apron)
would occur irrespective of this particular component. Environmental
considerations were not, however, the only determining factor in the selection of
these two sites, with other evaluation disciplines strongly supporting the case for
airside locations for reasons including, security and resilience, reduced operational
complexity, ease of delivery, and compliance with local plan designations.
Similar environmental benefits could be secured through the use of Grass Area
17a due to its location within the expanded Airport boundary. However, the use of
this site for fuel storage would displace or constrain the provision of other key
Airport infrastructure and so it was discontinued.
Outside of the Airport boundary, the alternative sites are generally more sensitive
with regards to landscape and townscape aspects due to the juxtaposition with
surrounding uses. The exception to this is the Esso West London site, where the
proposed use would be compatible with the existing site. This site has not been
progressed, however, due to the flood risk and ground instability.
At the Gypsum Site the fuel storage facilities would be surrounded by surface
water features, increasing the risk of pollution incidents and would also have the
potential for socio-economic and community effects. The site would also require
additional security features.
The selected location for the railhead replacement facility is the Goodman’s site
(Option 1). The alternative site (Option 2) was discontinued, primarily due to its
designation as a strategic freight site, however, its distance to the Airport would
also have resulted in a significant increase to local traffic on local roads and
consequently risks were identified regarding the likely air quality and noise effects
of the additional traffic.
The fuel distribution system from the storage location to the Airport hydrant system
will be developed during the next stages of the Preferred Masterplan design. Any
new distribution pipework, as with the existing pipework, will be below ground,
limiting the risk of adverse environmental effects.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.19 © Heathrow Airport Limited 2019
Cargo
Introduction
To enable a doubling in freight handling capacity at the Airport it will be necessary
to overhaul the existing facilities and make improvements to transit facilities and
transhipment zones.
New truck park facilities have also been considered to address existing issues on
the route network and in the cargo area. The provision of a purpose-built truck
park forms part of the Heathrow cargo strategy to reduce congestion within the
cargo area, the local road system and prevent the nuisance to the local
community. More detail can be found in Document 2, Chapter 5 of the Updated
SDR.
Options
The following opportunities to enhance the cargo facilities were considered:
1. Intensification or redevelopment of existing shed facilities within the Airport
boundary
2. Provision of additional shed capacity on and adjacent to the Airport
3. Intensification or provision of dedicated transhipment facilities closer to the
aprons in order to reduce journey times and maximise utilization of cargo
facilities.
The following locations for new cargo facilities were considered:
1. Grass Area 17a, within the airport boundary
2. Gate Gourmet site, within the airport boundary
3. Terminal 4, within the airport boundary assuming demolition of Terminal 4
4. Cargo Gateway, adjacent to the airport boundary.
The following opportunities for new truck park facilities are all outside of the Airport
boundary (shown in Graphic 3.6):
1. North of new north-west runway
2. West of the M25 junction 14
3. West of the existing cargo centre
4. South of Beacon Roundabout.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.20 © Heathrow Airport Limited 2019
Graphic 3.6: Indicative locations of truck park options
Evaluation summary
To support future cargo needs, a combination of all solutions will be required in
addition to the provision of a new truck park.
The intensification of existing cargo facilities is supported on the basis that it will
reduce the pressure on other sites within the Airport, including those in close
proximity to more sensitive receptors, and it will release land for alternative uses.
The consideration of high mechanised and low mechanised options did not raise
materially different environmental consequences.
Additional cargo provision will be located on Airport at Grass Area 17 (Option 1), in
close proximity to the existing cargo area. This site being within the Airport
boundary, reduces the potential for effects on visual receptors, as characteristics
of the view are unlikely to materially change when compared with the existing
appearance of the airfield. In comparison, an alternative site off-airport (Option 4),
would have a greater effect on visual receptors. The use of land outside of the
Airport boundary would also increase the risk of freight movements near sensitive
receptors and the loss of land used for community uses.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.21 © Heathrow Airport Limited 2019
Although important to the selection of the preferred option, environmental reasons
were not the primary reason for choosing between cargo sites within the Airport
boundary. Other considerations included other competing uses for land and the
phasing of development while seeking to maintain existing cargo capacity.
The development of new transhipment facilities within the Airport boundary has
been selected to manage freight movements on the surrounding road network.
The alternative of intensifying existing facilities could result in a significant uplift in
the volume of vehicle movements on the road network as the quantum of cargo
passing through the control posts increases.
The selected truck park option is a variation of Option 3, located to the west of the
cargo centre on the Southern Perimeter Road close to the cargo centre, enabling
efficient access to the cargo facilities and reducing potential congestion. This
location utilises existing routes on the road network, but is in close proximity to
sensitive receptors, including the Stanwell Conservation Area and will have a
greater effect on visual receptors than other sites which are further from such
receptors.
The alternative site to the north of the runway (Option 1) is remote from the cargo
area and would be likely to introduce additional freight movements on local roads,
in turn increasing the risk of noise and air quality effects at adjacent receptors. The
distance from the cargo area would also have significant implications for efficiency.
It was not selected for this combination of reasons.
To the west of the cargo centre, Option 2 would utilise land already used as a
truck park and so freight movements may not increase significantly from today.
The site also benefits from good access to the motorway network. However, it is
also in close proximity to the Wraysbury Reservoir and vehicles movements would
not be as efficient as the selected option, given the need to traverse Junction 14
multiple times when accessing cargo facilities. Option 4, which is further from the
motorway network, would also be less efficient than the selected option requiring
vehicle movements past the cargo centre in order to access the truck park.
For the reasons set out above, the sites to the north of the runway, to the west of
the cargo centre and to the south of the Airport cargo centre, were not selected for
cargo (truck park) use.
Maintenance, repair and overhaul facilities
Introduction
Today, the Maintenance, Repair and Overhaul (MRO) facilities are located on the
eastern side of the Airport, with the sites split into an East Base and a West Base.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.22 © Heathrow Airport Limited 2019
Discussions with airlines have highlighted the opportunity to intensify the use of
the existing facilities but also increase their flexibility by increasing hangar size
rather than the number of hangar bays. More detail can be found in Document 2,
Chapter 6 of the Updated SDR.
Options
The following alternative approaches to MRO have been considered, all of which
are located within the Airport boundary:
1. Family A: all MRO at Heathrow is consolidated in a single zone at the eastern
end of the airfield
2. Family B: MRO is dispersed across the aprons to be closer to terminal
operations
3. Family C: MRO is centralised in one location, but with a degree of
decentralisation, such as a Forward Maintenance Unit (FMU) near the apron of
a home-based operator. This option family safeguards facilities for a new
home-based entrant.
Evaluation summary
Due to the nature of the works undertaken in an MRO facility, which can potentially
be very disruptive, a requirement to ensure that options do not create
unacceptable environmental effects, such as ground noise due to the location of
ground run pens, traffic generation and air quality was agreed prior to evaluating
the component options. As a consequence, the alternative options do not result in
materially different environmental effects.
The selected option (Family C) would make provision for the growth and
redevelopment of existing MRO facilities in the existing location on the eastern
side of the Airport. Some hangars will be retained, with new facilities delivered
alongside. A site on the northern apron would provide a new FMU nearer to the
aprons. The primary determining factors in selecting this option related to
efficiency of operations and delivery.
Car parking facilities
Introduction
There are several key requirements that have been identified that will influence the
provision of car parking at Heathrow in association with the DCO Project.
The precise parking numbers in the expanded Airport are still subject to change as
they are directly related to the development of the Surface Access Strategy (SAS),
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.23 © Heathrow Airport Limited 2019
modelling and forecast parameters which are still subject to refinement and
development. More detail can be found in Document 2, Chapter 7 of the Updated
SDR.
Options
Three strategies for car parking have been considered (examples shown in
Graphic 3.7, Graphic 3.8, and Graphic 3.9):
1. Consolidated – existing car parking is consolidated into a single parking site to
serve each of the terminal complexes.
2. Semi-dispersed – The merging of Heathrow’s existing dispersed parking into a
maximum of two parking sites to serve each of the terminal complexes
3. Dispersed – The scattered distribution of parking across the Airport.
The option to utilise underground levels to reduce massing has been considered
with all options.
Graphic 3.7: Example of the consolidated car parking strategy
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.24 © Heathrow Airport Limited 2019
Graphic 3.8: Example of the semi-dispersed car parking strategy
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.25 © Heathrow Airport Limited 2019
Graphic 3.9: Example of the dispersed car parking strategy
Evaluation summary
The selected option comprises two consolidated car parks referred to as the
Northern and Southern Parkways, as well as additional car parking spaces at
Terminal 4 and within the Central Terminal Area and the retention of car parking in
the western campus. There will also be additional coach and lorry parking areas.
The proposed parkway concept enables consolidation of parking spaces in a small
number of highly accessible locations. The efficiencies in the scale of development
reduces land take in sensitive locations – this includes reducing the loss of Green
Belt. It is also considered to reduce the potential for circulating vehicle movements
on the road network around the airport perimeter. However, the Parkways require
massing of such a scale that there is a significant risk of adverse effects on the
surrounding landscape and neighbouring visual receptors. Environmental effects,
outweighed by the opportunity to provide convenient and cost-effective access to
the terminals, were not the primary reason for selecting the consolidated
Parkways.
The alternative approaches (dispersed and semi-dispersed) assume reduced
density in the Parkways. However, this would increase the requirement for
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.26 © Heathrow Airport Limited 2019
additional land, including within the Green Belt. Alternatively, land within the
expanded Airport boundary could be used, but it would subsequently displace
other uses to land outside of the Airport boundary (likely to be within the Green
Belt and other sensitive landscapes).
The opportunity to reduce the massing of multi-storey car parks by providing levels
below ground was considered. This option was preferred, on balance, by the
environmental discipline for the reduced visual effects, notwithstanding the
requirement for major earthworks. It was not progressed due to the high cost of
construction and maintenance and potential delays to the delivery programme.
The selected Parkway locations – close to major transport routes – will reduce the
potential for congestion on local roads and associated air quality effects. In
contrast, the alternative locations for dispersed car parking further away from the
Airport would need to be accessed using local roads, which would risk additional
congestion and the associated air quality effects.
Two options for the Northern Parkway were considered, one either side of the M4
Spur. The selected site, to the east of the M4 spur and west of Harlington, was
considered, on balance, to be a more appropriate location within the Green Belt
(both sites were in the Green Belt but this site was considered less damaging to it)
for a Parkway. The selected site will result in the partial loss of community
facilities, which will need to be replaced. The alternative, to the west of the M4
Spur, would have resulted in the Parkway being in closer proximity to designated
heritage assets in Harmondsworth and compromise habitat connectivity between
the Colne and Crane valleys.
Two options for the Southern Parkway were also considered, one with the diverted
rivers to the north of the Parkway and one with the rivers to the south. The rivers
passing to the south was selected on the basis that it would create a wider buffer
between the local community and the Parkway, reducing the effect on sensitive
receptors and providing greater opportunities for appropriate landscaping
measures.
3.5 Roads
M25 alignment
Introduction
As set out in Section 3.4, the selected runway is 3500m in length and is positioned
immediately to the west of the village of Sipson, extending beyond the existing
alignment of the M25. The runway would therefore necessitate either a crossing of
the motorway infrastructure, or diversion of the motorway alignment to avoid this
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.27 © Heathrow Airport Limited 2019
interface. More detail can be found in Document 3, Chapter 1 of the Updated
SDR.
Options
The following options (shown in Graphic 3.10) were considered:
1. Retention of the existing horizontal alignment. Two sub-options were
considered: either retaining both the current horizontal and vertical alignment
(minimising works to the carriageway); or retaining the current horizontal
alignment but lowering the carriageway to reduce the height of the runway.
2. Localised realignment of the horizontal alignment approximately 150m to the
west of the existing route and lowering of the carriageway, retaining Junction
15 in its current configuration. Two sub-options were considered: either with or
without the provision for dedicated collector-distributor roads.
3. A more extensive realignment of the M25 to the west, such that the
carriageway would be moved far enough to avoid conflicts with a 3,500m
runway, tying into the existing alignment north of Junction 15.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.28 © Heathrow Airport Limited 2019
Graphic 3.10: Indicative locations of M25 alignment options
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.29 © Heathrow Airport Limited 2019
Evaluation summary
Option 2 is the selected option. The Preferred Masterplan also includes collector-
distributor roads to run alongside the main through carriageways of the M25 to
serve turning traffic (such as that using the M25 to travel to / from the Airport,
communities to the west or the M4), with through traffic travelling on the central
carriageways. This is considered to support improvements in overall journey times,
increased resilience of the motorway and optimise safety and wayfinding for road
users.
Option 2 would allow the new section of carriageway and tunnel under the
proposed runway to be constructed largely offline from the existing alignment. This
significantly reduces the risk of traffic disruption and associated environmental
effects during the construction phase, such as those on local air quality. It also
provides greater opportunity to lower the vertical alignment of the carriageway
than Option 1. This facilitates the optimal balance between highway geometry and
runway height, the latter of which influences both the amount of earthworks fill
required and the potential landscape and visual impacts of the runway.
Option 1 would require temporary diversion of the motorway to undertake the
works necessary to bridge over the existing carriageway. Online construction
would therefore increase complexity, due to the need to maintain traffic flows on
this section of the motorway. This is likely to result in greater disruption than the
selected option. Retaining the vertical alignment of the carriageway would result in
the elevation of the runway being approximately 4-5m greater than the selected
option, increasing the volume of earthworks and risk of adverse effects on the
surrounding landscape and neighbouring visual receptors. The gradient is also
unlikely to be achievable for operational reasons.
Option 3 would require the motorway alignment to be diverted sufficiently far to the
west to avoid interaction with the runway. To facilitate such an alignment,
additional properties demolitions within the Poyle, Colnbrook and Richings Park
would be required. Retained properties would be subject to adverse traffic noise,
air quality and visual effects. Other likely effects include loss of additional habitat,
greater interaction with landfill sites and additional water course crossings. Due to
the likely environmental effects, associated costs, construction complexity and
planning risks, this Option 3 was discontinued.
M25 junctions
Introduction
The western expansion of the airfield interacts directly with the existing layout of
Junction 14A (J14A) of the M25, and, to a lesser extent, Junction 14 (J14). There
is also a relationship with the M25 alignment options discussed in the previous
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.30 © Heathrow Airport Limited 2019
section and these junctions. Specifically, in the absence of collector-distributor
roads (which segregate turning traffic), to reduce risks associated with weaving
traffic, the removal of J14A was considered. This would in effect move the merge
point on the northbound carriageway south to J14. As such, it would provide a
greater distance for turning traffic utilising J14 or J15, and through traffic
continuing north/south, to orientate themselves in the correct carriageways.
The other key factor influencing the M25 junction arrangements is the projected
distribution of additional passengers across the expanded Airport. This is likely to
result in re-distribution of Airport-related traffic, which could result in changes in
traffic flow through both J14 and J14A. More detail can be found in Document 3,
Chapter 1 of the Updated SDR.
Options
The following key options (shown in Graphic 3.11) were considered:
1. Removal of J14A and substantial upgrade to J14 in its existing location. Were
J14A removed, upgrading of J14 would be required to improve junction
performance and enhance capacity, necessitating construction of additional
grade separated flyover structures. These flyover carriageways would provide
access to the western campus and proposed southern parkway, extending east
of J14, running parallel to the existing alignment of the A3113
2. Removal of J14A and re-configuration of J14 to the south of the existing
junction location. A number of sub-options were considered, all of which
involved shifting J14 approximately 500m further south and utilising land to the
east and west of the existing M25 alignment. Reconfiguration of the junction to
the south would require multiple grade separated carriageways. The A3113
would also require realignment to the south of the existing route to tie into the
relocated junction.
3. Retention of the two existing M25 junctions with minimal alteration and without
lane segregation (collector-distributor roads). This option would involve minimal
alteration to the existing motorway junction layout.
4. Retention of the two M25 junctions, supplemented by a collector-distributor
system between J14 and J15. The existing J14 layout is largely retained, with
extension of the existing roundabout to the west to accommodate a junction
with the realigned A3044. Given the interface with the expanded Airport
boundary, western terminal area and re-aligned Twin Rivers, amendments
would be required to J14A.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.31 © Heathrow Airport Limited 2019
Graphic 3.11: Indicative locations of M25 junction options
Evaluation summary
Option 4 is the selected option. As discussed in relation to the M25 alignment, the
preferred masterplan includes collector-distributor roads to segregate turning
traffic utilising the M25 junctions from through traffic, optimising capacity,
resilience, safety and wayfinding. Option 4 would retain much of the existing
Junction 14 and 14A infrastructure and therefore reduces the extent of upgrade
works to these junctions. This reduces the risk of adverse environmental effects
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.32 © Heathrow Airport Limited 2019
during both construction and operation, including those associated with additional
watercourse crossings and the introduction of elevated structures within views.
There are also programme and cost benefits of retaining a significant proportion of
the existing junction infrastructure.
Option 1 is likely to result in adverse visual effects due to the need for multiple
grade separated carriageways. A number of these additional carriageways would
be constructed to the south of the existing A3113 alignment, reducing separation
between the village of Stanwell Moor and highway infrastructure. This would
increase the risk of adverse environmental effects, including those relating to air
quality and traffic noise. The extent and complexity of the junction layout in this
option would also requires additional watercourse crossings when compared to the
selected option and demolition of further premises to the north west of J14.
Option 2 was discounted relatively early in the evaluation process. Moving the J14
to the south would significantly increase effects on the village of Stanwell Moor,
given the extent to which infrastructure encroaches towards the village. Additional
demolition of properties within the village would be required with retained
properties likely to be subject to severance and greater air quality, traffic noise and
visual effects. This option also increases interaction with the Staines Moor Site of
Special Scientific Interest (SSSI). Beyond environmental and planning issues,
construction complexity was also a key consideration when discounting this option.
Option 3 was not considered to sufficiently reduce the risk of traffic weaving.
Whilst these options were considered favourable from an environmental
perspective, due to minimal works being required, operational considerations were
the primary consideration during evaluation, including those relating to potential
congestion, delay and accident risk.
A4 diversion
Introduction
The provision of the new north-west runway and expansion of the airfield would
directly affect roads other than the M25. As a result of the DCO Project, the
existing alignment of the A4 Bath Road / Colnbrook Bypass would be severed,
between Colnbrook and the M4 Spur. This is specifically due to the location of the
new runway, provision of a northern satellite terminal and supporting apron
infrastructure and the airfield taxiway system.
The importance of re-providing the local road functions is recognised, including
public transport and walking and cycling provision. The options set out below are
there based upon providing connectivity to and from the Airport, to and from local
communities and connectivity for through traffic. The A4 may also need to
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.33 © Heathrow Airport Limited 2019
accommodate increased traffic from the closure of the Northern Perimeter Road.
More detail can be found in Document 3, Chapter 2 of the Updated SDR.
Options
The following main alternative options for the diversion of the A4 (shown in
Graphic 3.12) were considered (described west to east):
1. Diversion of a section of the A4 to the north of the expanded Airport. The
diversion would be routed immediately north of and parallel to the boundary of
the new runway and associated airfield, crossing the M25 and the diverted
Wraysbury River and River Colne, before running parallel to and north of the
diverted Duke of Northumberland’s River. At a point approximately 700m to the
east of the M25, the diversion would deviate from the northern boundary of the
expanded airfield to run immediately adjacent to the Saxon Way Industrial
Estate. It would then follow the existing alignment of Holloway Lane, crossing
the M4 spur and turning south once east of this infrastructure before merging
with the existing A4 Bath Road
2. Diversion of a section of the A4 to the north of the new third runway,
comparable to Option 1 to the west of junction between Holloway Lane and
Harmondsworth Road. However, at this point the alignment would turn south
and includes a section of tunnel under the third runway, in order to merge with
the existing A4 Bath Road alignment to the west of the Emirates Roundabout
3. Diversion of a section of the A4 to the north of the new third runway, similar to
Option 2 described above, but rather than inclusion of a short tunnel under the
runway, the diversion would be routed around the eastern end of the runway. It
would therefore run between the airfield and the western edge of Sipson and
tie into the existing A4 Bath Road west of the Emirates Roundabout. To
facilitate diversion of the A4 around the eastern end of the runway, slight
shifting of the runway to the west would be required, as would the inclusion of a
starter extension. This is an additional runway length, made available for take-
off, prior the normal runway end and commencement of the take-off run
4. Diversion of a section of the A4 to the north of the new third runway, similar to
Option 1, but connecting with the M4 Spur. This option was introduced to
explore whether existing infrastructure (i.e. the M4 spur) could be re-purposed
to reduce the works necessary to re-provide A4 connectivity
5. Diversion of a section of the A4 to the south of the new runway, which broadly
maintains the horizontal alignment of the existing A4 Bath Road/Colnbrook
Bypass. This route would again connect with the existing A4 alignment at a
point approximately 900m east of the existing A4 Colnbrook Bypass/London
Road junction. However, from this point it would be routed immediately south of
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.34 © Heathrow Airport Limited 2019
and parallel to the boundary of the new runway and associated airfield,
crossing the M25 and entering a tunnel underneath the proposed airfield
infrastructure, merging with the existing A4 alignment approximately west of
the Emirates Roundabout
6. Diversion of a section of the A4 to the north of the new third runway, similar to
Option 1, until the point at which it crosses the M4 spur. Beyond this point the
diversion extends further to the east before turning south and tying into the
existing alignment of the A4 Bath Road. A number of sub-options were
considered that would tie into the A4 Bath Road between approximately 1.9km
to 3.4km east of the Emirates Roundabout.
Graphic 3.12: Indicative locations of A4 diversion options
Evaluation summary
Option 1 is the selected route. Given this option does not require construction of a
tunnelled section, delivery complexity and associated programme risk is
significantly reduced when compared to several alternatives. Option 1 would route
the A4 within approximately 160m of properties within Harmondsworth and could
therefore exacerbate effects on views and setting, including at the listed Great
Barn and St Marys Church. However, the routing included in the Preferred
masterplan is considered to balance these considerations against the effects
associated with aligning the route further north. Specifically, increasing separation
with the village further would either result in demolition of the Saxon Way Industrial
Estate, or additional environmental effects. These would include loss and
severance of habitat within the Lower Colne SINC, which provides connectivity
between the Colne and Crane Valleys, and further displacement of flood storage.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.35 © Heathrow Airport Limited 2019
To the east of the M4 Spur, the selected option turns south to reduce
encroachment into the greenbelt and ensure that the existing alignment of the
A408 can be utilised to tie into the A4 Bath Road.
Option 2 is comparable to the selected option west of the Holloway
Lane/Harmondsworth Road junction, however the construction of a tunnelled
section under the runway increases complexity from a delivery perspective and
has significant cost implications, whilst offering limited environmental benefits.
Option 3 was discounted, primarily based upon the likely air noise effects
associated with shifting the runway to the west, necessary to facilitate diversion of
the A4 around the eastern end of the runway.
Due to risks associated with a new junction to the M4 spur, including reduced
safety and operational efficiency, Option 4 was also discounted. This option would
also compromise resilience, in that it creates a single point of failure in the event of
disruption to the M4 spur.
The provision of a tunneled A4 route through the airfield as with Option 5 would
reduce the risk of adverse environmental effects to the north of the Airport,
including effects on setting and views in Harmondsworth and Sipson. However,
given the significant cost and delivery implications of providing a tunnel greater
than 2km in length within the airfield boundary, along with safety and security
considerations, this option was not progressed for inclusion in the preferred
masterplan.
Option 6 was discounted due to the effects diverting the A4 further to the east of
the M4 spur would have on receptors in Harlington, including potential loss of
properties and likely noise, air quality and visual effects associated with routing
traffic directly through the village.
A3044 diversion
Introduction
3.5.24 North of the Southern Perimeter Road, the existing A3044 alignment runs adjacent
to the current western boundary of the airfield and meets the A4 Colnbrook
Bypass approximately 500m to the east of the M25. The construction of the new
northern runway and extension of the western boundary of the airfield to
accommodate expansion of the Western Terminal Area, would entirely sever the
section of the A3044 between the Southern Perimeter Road and the A4 Colnbrook
Bypass.
3.5.25 As with the A4 diversion, the options for diversion of the A3044 discussed below
are based upon a number of key requirements, including the provision of
connectivity to and from the Airport, to and from local communities and
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.36 © Heathrow Airport Limited 2019
connectivity for through traffic. More detail can be found in Document 3, Chapter 2
of the Updated SDR.
Options
3.5.26 The following main options for the re-provision of the A3044 (shown in Graphic
3.13) were considered (described south to north):
1. Diversion of the A3044 approximately 200m to the west of the existing M25
alignment. This route connects with the M25 Junction 14 roundabout, running
north in parallel to the M25 and diverted Wraysbury River channel, to the point
at which it interfaces with the proposed northern runway. Here, it turns west to
follow the boundary of the expanded airfield, connecting with the existing
alignment of the A4 via a new junction approximately 900m east of the existing
A4 Colnbrook Bypass/London Road junction
2. A route comparable to Option 1 from Junction 14 of the M25 to the point at
which it interfaces with the new northern runway. However, rather than turn
west and follow the expanded Airport boundary, this alternative route continues
on a south-north bearing and includes a tunnelled section underneath the
runway, connecting with the diverted A4 to the north of the Airport and west of
the M25
3. Diversion of the A3044 east of the M25. This route connects with the A3113 at
Junction 14 and runs north in parallel to the M25 to the point at which it
interfaces with the new northern runway. At this point is routed through a
tunnelled section underneath the runway, connecting with the diverted A4 to
the north of the Airport and east of the M25
4. Diversion of the A3044 west of the M25 beyond the western edge of Poyle,
including construction of new highway infrastructure through Poyle and
Colnbrook. Several sub-options were considered, all of which would connect
with Stanwell Road immediately north of Wraysbury Reservoir and continue
north before connecting with the A4 at various points north of Colnbrook
between 0-900m east of the existing A4 Colnbrook Bypass/London Road
junction
5. An option which would utilise the existing route of Horton Road and Stanwell
Road, but upgrade the carriageway to provide sufficient capacity.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.37 © Heathrow Airport Limited 2019
Graphic 3.13: Indicative locations of A3044 diversion options
Evaluation summary
Option 1 is the selected option. The route largely by-passes Poyle and Colnbrook
and is immediately adjacent to the M25 transport corridor. This reduces the risk of
effects on air quality and due to traffic noise, relative to the majority of the
alternatives considered. This route will necessitate demolition of a small number of
properties on the eastern edge of Poyle, though direct impacts are significantly
reduced relative to options further to the west. No designated biodiversity sites will
be crossed by the alignment, however given it is within existing flood zone and
historic landfill boundaries, appropriate environmental measures will be required.
Option 2 is comparable to Option 1 to the south of the new third runway. The
inclusion of a tunnelled section under the runway would provide localised benefits
for properties on the northern boundary of Colnbrook, given the selected option is
located in relatively close proximity to these receptors. However, due to the
significant complexity of constructing an additional tunnel under the runway,
associated costs and conflicts with the preferred M25 alignment, it was
discounted.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.38 © Heathrow Airport Limited 2019
Option 3, as with Option 2, was discounted due to the cost and delivery
implications of providing an additional tunnel under the runway. Diversion of the
A3044 to the east of the M25 would also introduce conflicts with the river
diversions parallel to the M25, presenting a high risk for the quality of the water
environment.
Option 4 would result in the demolition of residential properties within Colnbrook
and Poyle. The evaluation concluded that adverse environmental effects at
retained properties would be likely due to the proximity of the highway, including
air quality, noise and visual effects. The Colnbrook Conservation Area and Listed
assets within would also be affected. Due to the extent of the likely environmental
effects associated with this option, in addition to planning, cost and delivery risks,
it was discounted.
The evaluation of Option 5 concluded that the associated increase in traffic flows
utilising the Horton Road and Stanwell Road corridor would result in adverse noise
and air quality impacts at receptors adjacent to the highway. Upgrading of the
existing carriageway would also be likely to affect the Horton Brook and priority
habitats. This route was also the longest diversion option considered. Due to travel
times and the more remote nature of the route, is was discounted by the
operations and service discipline.
3.6 Displacements and land use
River diversions and flood storage
Introduction
Heathrow is situated within a complex water environment, close to a number of
rivers, lakes and reservoirs. The project would extend the Airport footprint over the
Colne Valley, with the potential to affect the alignment of five rivers and
intersecting areas of floodplain storage within the valley. The ANPS sets a number
of requirements with respect to the water environment, river diversions and flood
risk management, including:
1. That the scheme follows the approach and requirements set out in the National
Planning Policy Framework in respect of flood risk
2. That the scheme takes into account the requirements of the Water Framework
Directive (WFD).
The development of options for River Diversions and Flood Storage was heavily
driven by these requirements with respect to flood risk management and the WFD.
It was important that all proposed options were able to effectively convey river
flows, both high flows and low flows, whilst ensuring that there is no increase in
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.39 © Heathrow Airport Limited 2019
flood risk to people or properties. Alongside this, a set of specific criteria were
established to consider the relevant hydro-ecological and hydro-morphological
parameters against which different potential approaches could be judged. More
detail can be found in Document 4, Chapter 1 of the Updated SDR.
Options – river diversions
An initial long list of options was developed to consider the full range of potential
approaches that could facilitate the required river diversions. This long list was
screened against a series of discontinuation rules focused on the headline
feasibility of the options. This process narrowed the options to five approaches,
grouped into two categories:
1. Rivers conveyed mainly under the new runway:
a. All rivers conveyed under the new runway, as close to their original
alignment as possible
b. All rivers conveyed under the new runway, with the exception of diverting the
Duke of Northumberland’s River to the River Crane in a new channel to the
north of the Airport
c. All rivers conveyed under the new runway, but the Colne Brook diverted
around the north-west end of the new runway
2. Rivers mainly diverted to the west of the new runway:
a. Diverting the River Colne and Wraysbury River westwards into the Colne
Brook, with flows then returned to the original Colne and Wraysbury
channels to the south of the Airport. The Duke of Northumberland’s River
and the Longford River would be conveyed under the runway
b. Diverting the River Colne and Wraysbury River westwards around the
runway but kept separate from the additional westwards diversion of the
Colne Brook. The Duke of Northumberland’s River and the Longford River
would be conveyed under the runway.
Evaluation summary
The preferred option is a composite of the two categories presented above,
comprising:
1. Diversion of the Colne Brook to the north and west of the railhead zone and
around the western end of the new runway – this option delivers a better-
functioning river environment and more valuable aquatic habitat compared to
the existing channel, whilst also enabling a larger construction logistics centre
which will aid delivery
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.40 © Heathrow Airport Limited 2019
2. Conveyance of the diverted River Colne and Wraysbury River, and the Duke of
Northumberland’s River and Longford River, under the runway in a Covered
River Corridor. The Covered River Corridor will be optimised to support
ecological connectivity as far as practicable. Further details of the Covered
River Corridor are provided in Appendix 21.3A
3. Continuation of the diverted river channels, south of the runway, around the
western perimeter of the airfield. An open river corridor between the Airport
perimeter and the M25 will provide riparian habitat and capacity for
conveyance of flood flows
4. Alignment of the Duke of Northumberland’s River and the Longford River to the
south of the A3113 and southern parkway, removing the existing inverted
siphon underneath the A3044 and replacing a section of existing trapezoidal
channel and hard bank reinforcement with a more natural watercourse and
softer banks.
All options were evaluated to determine whether the diversion of channels to the
west of the Airport would have the ability to provide ecological connectivity through
the Colne Valley for aquatic species. Evaluation of the proposed dimensions,
gradient and flow rates for the diversion channels of the River Colne, Wraysbury
River, Longford River and Duke of Northumberland’s River concluded that these
options would not provide valuable riverine habitat or ecological connectivity.
Additionally, it was determined that the diversion of flow away from the main
channel of the River Colne could have a detrimental impact on the aquatic
environment for this water body. Substantial diversion of rivers to the west of the
runway would also add significant construction logistics and sequencing
complexity, as well as conflicting with the demands from other uses for the land
parcels that would be required. As such, approaches that maintained existing
watercourses as much as possible, conveying rivers mainly under the runway,
provided the best outcome for the water environment.
Where the Colne Brook is diverted in the north west section, the diversion reduces
the number of river crossings. The alternative of bringing the channel closer to the
Airport boundary increased the number of crossings (under the A4, as well as
access bridges to the logistics area and railhead). The environmental
consequences of additional crossings, such as shadowing and biodiversity effects,
supported the selection of a route further out. Diverting the Colne Brook around
the runway was also seen as preferable from the perspective of cost.
Options – flood storage
The expansion of the Airport will encroach on the existing floodplain of the Colne
Valley, requiring additional flood storage to ensure that the scheme does not
increase flood risk to people and property. The final layout of the DCO Project will
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.41 © Heathrow Airport Limited 2019
affect the volume of compensatory flood storage required, hence the target volume
of floodplain storage to be provided would not be known until later in the Scheme
Design Process; however, this PEIR sets out the compensatory flood storage
areas required based on the work undertaken to date.
The development was therefore guided by an understanding of the scale of
compensatory flood storage required in the Preferred Masterplan, with the focus
on identifying land parcels that could appropriately be utilised to provide flood
storage. As the details of the layout are refined through the scheme development
process the arrangement of compensatory flood storage will continue to be
refined.
The following options for flood storage (as shown in Graphic 3.14) were
considered:
1. New storage within the airfield expansion area
2. New storage to the west of the airfield
3. Catchment-wide storage
4. New upstream storage
5. New storage downstream of the airfield
6. New storage on the River Crane.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.42 © Heathrow Airport Limited 2019
Graphic 3.14: Indicative locations of flood storage site options
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.43 © Heathrow Airport Limited 2019
Evaluation summary
There are two distinct river systems which require compensatory flood storage: the
Colne Brook (to the west of the M25) and the River Colne (to the east of the M25).
There are nine locations that remain in consideration: three that provide
compensation for the western Colne Brook system; and six that provide
compensation for the eastern River Colne system. These are summarised below:
Colne Brook Flood Storage Options (West):
1. Increased conveyance through Colnbrook
2. Colne Brook at Poynings
3. Thorney Mill Road
River Colne Flood Storage Options (East):
1. Existing M25 corridor south of the Covered River Corridor
2. South of Saxon Lake
3. East of Saxon Lake
4. Long Mead
5. Thorney Park Golf Course
6. Huntsmoor Park
The flood storage options would all adopt a similar conceptual design including: a
gated river offtake structure to control the timing of the filling of the flood storage
areas; an inlet weir; an outfall structure to allow for passive draining of the flood
storage area at the end of a flood event; and an appropriate lining solution where
the flood storage area is located on landfill.
Not all sites will be required, and various site combinations continue to be tested to
match the floodplain storage lost on the Colne Brook and River Colne systems,
reflecting the wider development of the scheme.
Through option development it was recognised that parcels of land should be
multifunctional, combining flood storage, habitat creation, green infrastructure and
community or commercial uses. Flood storage options which are in close proximity
to the Airport were preferred as they are closer to proposed and existing river
alignments. These options also provide opportunities for habitat creation and
green infrastructure enhancements close to the Airport. Flood storage provides
decreasing attenuation benefits the further upstream it is. Sites upstream of the
M40 were discontinued on this basis. Further south (closer to the Airport), the
attenuation benefit of the sites improves, but also encounter potential conflicts with
construction activities and high value land.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.44 © Heathrow Airport Limited 2019
An alternative option of flood storage located in the east involves diverting water
from the Colne Valley catchment into the Crane River catchment. This is highly
unlikely to be required or feasible to use in the context of the retained river flow
conveyance options which divert river flows further to the west, away from the
Crane Valley. As a result, the option to divert flood water to the River Crane is no
longer being considered.
The alternative of catchment wide flood management is complex to implement and
manage due to diverse and diffuse locations and the large size of the catchment.
While there are a number of environmental benefits that could be achieved, this
concept was discontinued as a primary solution for non-environmental reasons.
The provision of additional flood storage downstream, rather than upstream, of the
point at which floodplain is lost is complex as the flood water needs to be
conveyed to the storage without increasing the flood risk in other locations. This
presents a hydraulic challenge as it would be necessary to ensure that flood water
could be safely conveyed through a number of ‘pinch points’ along the river
corridors in order to access the downstream flood storage. The capital investment
required is significant. It could also affect the Staines Moor SSSI, since the
creation of additional flood storage would likely require excavation to create the
required storage volume, leading to potentially adverse habitat impacts. For these
reasons, this alternative option was discontinued.
Drainage and pollution control
Introduction
The DCO Project will result in an increase in the amount of surface water runoff to
be managed. Without the implementation of appropriate measures, this has the
potential to affect the drainage and water quality of the watercourses around the
Airport.
The existing drainage system at Heathrow comprises four catchment areas (north-
western, western, southern and eastern), which operate different treatment
methods and discharge (release) to different locations. Further detail is provided in
Document 4 Chapter 2 of the Updated SDR.
Options
The drainage and pollution control has been considered by breaking down the
options into two processes: capture and attenuate; and treat and release solutions.
The following solutions for capture and attenuate were considered:
1. Underground Airside Storage Tanks
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.45 © Heathrow Airport Limited 2019
2. Tunnel Storage, Landside Pump Station and Attenuation basin
3. Open attenuation basin to the north-west and south-west of the Airport.
The following options were considered for treatment solutions to manage glycol
contamination, based on the range of treatment technologies and approaches to
discharge available and in accordance with the requirements for drainage and
pollution control:
1. Engineered reed beds
2. Combined treatment
3. Discharge to sewer.
The development of options also needed to consider the specific location for the
provision of treatment, focusing on land around the immediate perimeter of the
airfield. Given the potential demands for land around the Airport, consideration
was also given to land parcels further afield. The sites Graphic 3.15 were
considered for treatment locations.
The following options were identified as possible systems to which water could be
released:
1. River Colne
2. Colne Brook
3. River Crane / Frog Ditch
4. Clockhouse Lane Pits
5. Stanwell Ditch
6. Duke of Northumberland River
7. Bath Road Sewer.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.46 © Heathrow Airport Limited 2019
Graphic 3.15: Indicative locations of treatment facility options
Evaluation summary
The preferred airfield drainage and pollution control approach proposes to drain
the Expansion predominantly under gravity conditions to shallow, offsite,
co-located attenuation and treatment areas to the northwest and southwest of the
airfield (Option 3 of Capture and Attenuate).
The selected sites for open attenuation to the southwest and northwest of the
airfield (SW_NEW and NW_NEW), are close enough to the airfield that they are
able to predominantly rely on gravitational flows which is more sustainable and
more resilient. Sites further from the airfield will be more challenging to deliver due
to the length of connecting infrastructure needed. The environmental
consequences of alternative solutions that rely upon a greater use of mechanical
pumping would be only marginally worse (greater energy requirement) but would
not provide robust resilience in the event of failures or exceedance storms, and
require greater capital expenditure. It is this combination of reasons that resulted
in the selection of a predominantly gravitational solution.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.47 © Heathrow Airport Limited 2019
The selected land parcels, although in close proximity to sensitive receptors, avoid
the loss of land for recreation that would result in socio-economic effects and land
parcels that include Sites of Importance to Nature Conservation.
The use of land containing two Scheduled Monuments at Mayfield Farm (land
parcel S-01) was considered to be possible if suitable construction methods were
employed to enable engineered reed beds to be delivered and to preserve the
archaeological remains in situ, however it is likely that this would require an
archaeological evaluation.
The alternative approach to capturing and attenuating using underground storage
tanks (Option 1) would minimise the risk of onsite flooding as it does not rely on
mechanical plant to drain the airfield and it would minimise the effects on local
habitats and communities by locating the majority of infrastructure below ground
and on airfield. However, the construction of the tanks would require significant
earthworks increasing the potential adverse noise and air quality effects on local
sensitive receptors. The approach would also necessitate the need for pumping to
the treatment location, which is less sustainable. Operational concerns, including
the complexity of maintaining the tanks, the resilience of the pumping, and the
greater capital expenditure required, were also reasons why this option was
discounted.
Option 2 for capture and attenuation, requiring the use of tunnel storage, would
also rely heavily upon the use of pumping to pump contaminated water to the
treatment area which is less sustainable. Operational concerns, including the
resilience of pumping, and the greater capital expenditure required, were also
reasons why this option was discounted.
The receiving watercourse was not deemed to be a differentiator between options,
since appropriate discharge limits will need to be agreed and met for all
watercourses. There are also requirements to ensure that all options would be
adequately sized to meet the requirements of the ANPS, including an allowance
for climate change, and that lakes or ponds would not be compromised by the
quantity and quality of discharges. Consequently, the alterative options for
watercourses to release into do not present materially different environmental
consequences.
In the assessment of treatment solutions, engineered reed beds (Option 1) were
selected as the preferred treatment approach, primarily due to non-environmental
reasons, namely that they are proven to be effective, of lower complexity and
lower cost than alternative options. The alternative treatment using a combined
foul water and surface runoff treatment plant (Option 2), would add complexity and
cost of operating a treatment works would reduce Heathrow’s operational
resilience. Option 3, a connection to the Thames Water foul sewer system, will also
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.48 © Heathrow Airport Limited 2019
be required alongside Option 1 to provide operational resilience in the event that
flows cannot be treated on site.
Utility diversions
Introduction
There is a substation and several major utility services and aviation fuel supply
pipelines that will need to be diverted, relocated or protected as a result of the
DCO Project and some services will need to be expanded to meet the increased
demands of the expanded Airport.
Heathrow has been working closely with the affected statutory undertakers and
asset owners to develop strategies for diverting or relocating assets where
required. This is being looked at in conjunction with any requirements for future
increases in capacity.
The diversion of two utilities, the National Grid Overhead Power Line and the
Scottish and Southern Electricity Network Overhead Line, are two of the most
significant diversions and have been considered in conjunction with the utility
organisations who own and operate those assets. The options for diverting these
two assets and relocating the Longford substation include options above ground
which could have environmental consequences for local receptors. Further detail
is provided in Document 4 Chapter 3 of the Updated SDR.
Options
Five options have been considered for the National Grid Overhead Line Diversion:
1. Re-route the overhead lines above ground further to the west, this would
involve installing new pylons along the M4 corridor and around the Queen
Mother Reservoir (approximately 9 km)
2. Bury the 275kV lines following a similar route to the current pylons
(approximately 2 km). Land use restrictions would be in place over the cable
route. An approximate 30mwide easement would be required along the entire
buried cable route within which no development would be permitted. Terminal
towers and sealing end compounds would be required at each end of the cable
3. Construct a deep bore tunnel between each terminal tower / sealing end
compound and head house to accommodate the relocated 275kV lines
(approximately 2km). There would be fewer land use restrictions with this
option
4. Construct a long deep bored tunnel from North of the M4 to a point near Poyle
(approximately 3.5km)
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.49 © Heathrow Airport Limited 2019
5. Construct a combined tunnel for NG and SSE from North of the M4 to a point
south of Poyle.
Five options have been considered for the Scottish and Southern Electricity
Networks Overhead Line Diversion:
1. Provide an interim diversion along the existing Network Rail railway track. A
permanent solution would be installed in the future
2. Provide an interim diversion adjacent to the M25 carriageway and a permanent
diversion along the new M25 alignment
3. Provide an interim diversion along Lakeside Road. A permanent solution would
be installed in the future
4. Provide a permanent diversion westward around the Airport commission
boundary, through agricultural land and community spaces
5. Option 5: Provide a tunnel below the proposed third runway utilising the
shortest distance possible.
Four options have been considered for the relocation of the Longford Substation
(shown in Graphic 3.16):
1. North of existing Longford substation
2. Adjacent existing Longford substation
3. West of existing Longford substation
4. South of existing Longford substation.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.50 © Heathrow Airport Limited 2019
Graphic 3.16: Indicative locations of substation relocation options
Evaluation summary
National Grid Overhead Line Diversion
A final solution for replacement of the National Grid Overhead Power Lines has
not yet been agreed with National Grid. Options 2, 3 and 4 remain under
consideration. These options, as well as option 5, would all have similar
environmental consequences as a result of the tunnel being underground. The
sealing end compounds would need to avoid sites with sensitive environmental
receptors unless appropriate mitigation can be provided. All options would avoid
ancient woodland. Option 5 is not being pursued due to operational and phasing
reasons.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.51 © Heathrow Airport Limited 2019
Option 1 would have more significant environmental effects, namely visual and
landscape effects. In order to move the overhead lines to a point where they no
longer clashed with the Obstacle Limitation Surfaces (OLS), it would be necessary
to have pylons in a residential area. To avoid that effect, it would be necessary to
route the overhead lines round the Queen Mother Reservoir and add
approximately 6.5km to the network length, potentially harming a greater extent of
land and affecting more receptors. National Grid has, however, confirmed that they
would not pursue this option as it would not be viable or cost effective and
therefore will pursue an underground alternative.
SSE Networks Overhead Line Diversion
For SSE, the preferred option is to temporarily divert the 132kV OHL along the
Lakeside Road in a buried trench to enable M25 works to commence (Option 3).
SSE has approved this option and the design is currently being progressed.
Feasibility work on the final solution is being progressed. The underground
solutions all present relatively few environmental effects, with the exception of
Option 4, which takes a longer route around the airfield, passing through a bat
corridor and landfill and in closer proximity to communities, increasing the risk of
adverse noise and air quality effects during the construction period.
Longford Substation
The replacement Longford substation is proposed as a variation of Option 1. The
preferred site is a vacant area, west of the existing railway and is not a registered
landfill site and therefore avoids the potential pollution constraints. Options 3 and 4
are further from the existing substation and would require more extensive
infrastructure works, causing disruption to neighbouring uses. Environmental
reasons were not the primary reason for discounting Option 2, which would require
the displacement of existing industrial tenants.
Wastewater treatment
Introduction
Heathrow currently discharges wastewater to the local Thames Water trunk sewer
network, which then conveys it to Mogden Wastewater Treatment Works (WWTW)
for treatment. The current network and treatment facilities do not have sufficient
capacity to meet the additional demands of an expanded Airport. New and
upgraded infrastructure must be provided to transfer and treat the wastewater
produced by increased numbers of passengers.
Heathrow is working closely with Thames Water and the Environment Agency to
develop a sustainable solution for the disposal of wastewater which not only
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.52 © Heathrow Airport Limited 2019
considers the requirements of Heathrow and the surrounding communities, but
also the wider environment and population in West London. Further detail is
provided in Document 4 Chapter 4 of the Updated SDR.
Options
Any increase in capacity will involve investment in new treatment and network
infrastructure and the upgrade of existing facilities. Following engagement with
Thames Water and development of other components, four options for providing
the additional wastewater treatment capacity required for the expanded Airport
have been considered:
1. Upgrade the existing treatment facilities at Mogden WWTW in west London
2. Upgrade the existing treatment facilities local to the Airport and divert some or
all flows to this treatment location
3. Construct a new WWTW local to the Airport to treat some, or all the flows from
the expanded Airport and surrounding communities
4. Discharge to local Thames Water sewers (the offset strategy).
The final solution could also involve a combination of these options.
Evaluation summary
The preferred option is to discharge to the existing sewer network (Option 4),
which avoids the requirement for land-take from around the Airport for a new
treatment facility, avoiding environmentally sensitive sites or the use of sites which
may displace other uses to more sensitive sites. By using the existing network, this
option is also a resource efficient solution (low energy and material use). Pumping
will, however, be required due to the scale of the Airport and its topography, which
make gravitational methods unfeasible. Other non-environmental reasons for
selection include the lower capital expenditure and operational and maintenance
costs. The preferred option relies upon a reduction in existing foul water flows
resulting from the displacement of residential and commercial buildings by the
airport expansion, however, should the results not support this option then it would
be necessary to progress with an alternative solution.
The alternative options which utilise a new or enhanced WWTW (Options 2 and 3)
would, however, provide other environmental benefits, namely the ability to use
the treated water for non-potable uses within the Airport, reducing water
consumption. This option has not been selected as the preferred option, however,
as the environmental benefits are considered to be outweighed by the need to
acquire additional land for the provision of a new facility and/or the expansion of
the existing, as well as the expenditure and operational issues associated with
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.53 © Heathrow Airport Limited 2019
running a treatment facility. Alternatively, the treated water from the WWTW could
be discharged into local watercourses which would also provide benefits to the
flows of local watercourses, for example the River Crane which is known to have a
low flow issues. These alternative solutions are being kept under review.
Home office immigration removals centre
Introduction
The expansion of Heathrow will result in the displacement of a number of existing
land uses, including the Harmondsworth and Colnbrook Home Office Immigration
Removal Centres (IRC).
A specific site selection process has commenced to investigate potentially suitable
locations for the replacement IRC, which has included engagement with the Home
Office. Further detail is provided in Document 4 Chapter 5 of the Updated SDR.
Options
The following locations for the IRC (shown in Graphic 3.17) were considered:
1. Site E1: Mayfield Farm
2. Site B1: Land east of M4 Spur
3. Site A4: Land at Holloway Lane
4. Site F1: Land to the south west of existing Airport boundary
5. Site D1: Airport Business Park.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.54 © Heathrow Airport Limited 2019
Graphic 3.17: Indicative locations of IRC replacement options
Evaluation summary
All of the sites considered for the relocation of the IRC are constrained by
environmental designations and sensitive receptors. Airport Business Park (Option
5) was selected as the are there is considered to be greater opportunities to
mitigate potential effects and the site benefits from significantly greater support
from the Local Planning Authority than other sites.
The selected site is within the Green Belt and is constrained by two areas of Sites
of Importance for Nature Conservation and a graveyard that runs through the
middle of the site. Screening from adjacent uses would be required. The specific
location of the buildings will need to respond to these constraints and be located
sufficiently far south to minimise noise impacts on the facility as far as practicable.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.55 © Heathrow Airport Limited 2019
The most preferred alternative, Option 1, also has a number of environmental
constraints. It is located within the Green Belt and an Archaeological Priority Zone
and is constrained by two areas of Scheduled Monument located at the eastern
and north-western corners of the site. However, it has good access to public
transport, is in close proximity to Airport gate, is available for early construction
and is further away from residential uses. The Local Planning Authority does not,
however, support the use of the site for the replacement IRC due to the potential
conflict with the aspirations of the draft Local Plan.
The other alternative sites considered are all within the Green Belt. Option 4 is
partially located within the Public Safety Zone and is in close proximity to Stanwell
Moor, a sensitive visual receptor. Options 2 and 3 are located to the north of the
airport further from public transport interchanges. Option 2 is partially covered by a
Site of Importance for Nature Conservation and the land is proposed for alternative
uses.
Airport supporting development
Introduction
Airport supporting development (ASD) is a term which is used to describe a range
of development that is related to the Airport’s operation, such as hotels, offices,
and warehousing. Those ASD facilities that represent the largest land take and are
likely to have the most significant environmental effects (car parking, cargo, MRO)
are set out separately in this chapter having been through the Scheme
Development Process separately.
In developing the preferred masterplan for land required beyond the expanded
operational Airport boundary the approach has been to consider three inter-related
land use components, namely:
1. Scale of land uses - what is the type and scale of ASD that may be generated
as a result of the Airport expansion and of this what should be brought forward
by Heathrow and what should be left for the market to deliver.
2. Location of land uses - what land parcels or sites may be appropriate to be
utilised to accommodate the identified scale of land use demand.
3. Zoning of land uses - what design and development principles should be set for
areas around the Airport to inform land use distribution principles and
subsequently the evolution of development zones.
Further detail is provided in Document 4 Chapter 7 of the Updated SDR.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.56 © Heathrow Airport Limited 2019
Options
To facilitate the preferred masterplan development and determine the scale of
provision allowed for ASD, the Stage 2 and 3 process resulted in two alternative
land use scenarios:
1. Option 1: ‘Lean’ or low land use scenario – a strategy that minimises the scale
of ASD included in the DCO and leaves a larger quantum to be delivered by
the market, guided by the Heathrow Strategic Planning Group (HSPG) land
use policies in future local plans
2. Option 2: ‘Striving to Meet Demand’ or high land use scenario – inclusion of a
land use quantum and / or development sites that increases the quantum of
ASD delivered in the application for consent for development, leaving a lower
quantum to be delivered by the market. This would increase Heathrow’s control
over delivery and offers potential commercial benefits but might increase
planning risks on some additional quantum sites.
Graphic 3.18 shows the range of sites considered for ASD that met the initial
requirements and so were considered in the early stages of the process. Note that,
at this stage, all site boundaries were approximate and were based on the best
information available at the time. These would be subject to further work and
possible amendment.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.57 © Heathrow Airport Limited 2019
Graphic 3.18: Indicative locations of ASD opportunity sites
Evaluation summary
Option 1, the ‘Lean’ land use strategy, has been selected as the preferred
strategy. This approach limits the number of sites that are required for
development when compared with the Option 2 and consequently reduces the
pressure on the use of sensitive sites, including those with formal environmental
designations and in close proximity to sensitive receptors.
The long list of sites proposed includes highly sustainable locations in close
proximity to sustainable transport routes. There are positive environmental
consequences associated with their use in comparison to alternative sites that are
not so well connected.
The proposed approach to ASD has been to locate hotels and offices along the
public transport spine and in areas with good connectivity to them such as Hatton
Cross or the Parkways to promote sustainable modes of transport.
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.58 © Heathrow Airport Limited 2019
The key alternative options would be to concentrate hotels within the Central
Terminal Area (CTA) and Western Landside Terminal Zone (WLTZ). This option
would reduce the need to occupy sensitive sites outside of the existing Airport
boundary, however phasing and physical constraints do not allow appropriate sites
to be readily available.
Industrial type uses were preferred in locations to the south of the Airport, in an
arch between Poyle Industrial Estate and Feltham Trading Estate, in close
proximity or adjacent to on and off airport cargo functions to create efficiencies by
clustering uses of similar nature. Alternative sites to the north and north east of the
airport are not preferred as these locations are more sensitive for trip generating
uses and are not favoured within the Surface Access Strategy.
Landscape Design and Green Infrastructure
Introduction
The landscape design and green infrastructure elements of the Preferred
Masterplan can be defined as a proposed network of new and enhanced hard and
soft landscape that mitigates the impact of the DCO Project on the natural and
historic environment, including landscape and visual amenity, and which forms an
integral part to health and quality of life of local communities.
Landscape design forms part of the Updated SDR (Document 4, Chapter 9), but
the evaluation of this component has followed a different path to the others. The
design response (quantum and distribution of Landscape Measures) has been
directly shaped by the requirements set out in the ANPS and this has not
fundamentally changed during the subsequent evolution of the Preferred
Masterplan but has been refined by, and has influenced the development of, other
components.
Refinements to the proposals should not result in materially different
environmental consequences on the basis that the purpose of the strategy
remains constant: to provide necessary mitigation for lost Public Open Space and
for effects on legally protected and notable species and biodiversity more
generally.
The constrained nature of the landscape surrounding the airport and the fact that
mitigation for effects on public open space or biodiversity designations must
typically be provided as close as practicable to the site of impact, also reduces
potential optionality.
The approach to landscape and green infrastructure design is also being informed
by historic environment principles which are detailed further within the Preferred
Masterplan document. Design refinement leading up to submission of the ES will
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.59 © Heathrow Airport Limited 2019
therefore be informed by the Heritage Design Strategy, which aims to provide a
positive contribution to the historic environment, which might benefit the
sustainable use of heritage assets. This is anticipated to include, for example, the
promotion of positive opportunities to sustain heritage assets through
diversification in use and the provision of pedestrian and cycling access that better
connects heritage assets to Public Open Space and other green spaces.
Earthworks
Introduction
Earthworks generally respond to and enable the construction of other components
(e.g. the runway, roads etc.) rather than comprising a component their own right.
As such, component level option evaluation was undertaken only for certain
aspects of the earthworks strategy, namely the identification of viable sources of
earthworks material to use in the DCO Project.
At a strategic level, the use of fill materials sourced from external projects (e.g.
Western Rail Link to Heathrow, HS2 etc.) was considered. However, due to
programme uncertainties, the required volume of materials and the likely effects of
haulage, borrow pits were identified as the preferred option.
Options have been considered for on-site and off-site borrow pits, which could
provide fill materials (e.g. sand and gravel) and prevent the need to acquire and
transport large volumes of material via the public highway. These sites must be
capable of transitioning from being a source of fill, to becoming new landfill once
excavation is complete. To avoid excessive haulage, options within 6-7km of
Heathrow, accessible via dedicated haul routes off the public highway, were
considered.
Options
The following sites for establishing borrow pits / landfill (shown in Graphic 3.19)
were considered:
1. Land within the order limits boundary to the immediate south of
Harmondsworth
2. Land to the immediate west of Sipson, partially within the order limits boundary
3. Land to the south of the M4 and west of the A312
4. Land to the east of Junction 13 of the M25, immediately adjacent the Staines-
Windsor rail line
5. Land to the south of Datchet, immediately west of the Staines-Windsor line
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.60 © Heathrow Airport Limited 2019
6. Land to the south of Brands Hill and Colnbrook, east of The Queen Mother
Reservoir
7. Land in-between Langley and Richings Park
8. Land south west of Iver, extending to the Great Western Main Line
9. Old Slade Lake (landfill only).
Graphic 3.19: Indicative locations of borrow pit site options
Evaluation summary
The selected option is a combination of Option 1 and Option 9, with an additional
land parcel to the west of Sipson kept under review (Option 2). Use of Old Slade
Lake would facilitate disposal of waste generated west of the M25, without the
need to cross the motorway. It would however result in adverse effects on surface
water. Option 1 has potential to adversely affect adjacent receptors in
Harmondsworth, due to the associated risk of noise, air quality and odour and
visual impacts. However, given proximity to the development boundary, it would
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.61 © Heathrow Airport Limited 2019
avoid the need to establish significant haul roads, falls within the proposed airport
boundary and is favourable from a cost perspective.
Option 3 was discounted due to the associated impacts on public open space at
Cranford Park and historic assets to the north. Borrow pits in this locality would
also rely on establishing a haul route close to residential receptors, including those
in Harlington, Sipson and Harmondsworth. The haul route would also need to
cross the M4 spur which would increase construction complexity, and costs.
Option 4 would result in the loss of habitat within the Staines Moor Site of Special
Scientific Importance (SSSI) and was subsequently discontinued. It would also rely
on haul routes crossing local roads near Stanwell Moor.
Given the location of Option 5 to the west of The Queen Mother Reservoir, it would
result in long haulage distances compared to the select option and demand routing
of construction traffic through residential areas, including Brands Hill and
Colnbrook. Associated haul routes would also need to cross the Windsor-Staines
rail line, increasing construction complexity and costs. This option was therefore
discontinued.
Option 6, as with Option 5, would route large volumes of construction traffic
through the Brands Hill and Colnbrook area and was similarly discontinued due to
the potential effects of establishing borrow pits in this area on local air quality.
Options 7 and 8 would result in adverse effects for a range of receptors, including
loss of agricultural land and habitat north of the M4. The associated haul routes
would also be required to cross the M4 and in the case of Option 8, the GWML
and Grand Union Canal. Option 7 would also potentially extinguishment the sports
and recreation facilities north of the M4. These options were therefore less
favoured than the selected option.
Construction Support Sites
Introduction
The DCO Project will require multiple Construction Support Sites (CSS) located on
or near to the periphery of the development boundary.
Heathrow has sought to keep construction activities within those areas identified
for permanent development as much as reasonably practicable. However,
construction activities need to be kept away from the active airfield and space is
tightly constrained in the main works areas themselves. There is subsequently a
requirement for temporary use of land during construction outside the permanent
boundary. Key requirements for CSS are set out below:
1. Provide sufficient land and space for necessary construction support functions
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.62 © Heathrow Airport Limited 2019
2. Located in close proximity to the main works sites
3. Provide access to the existing road and rail network (specifically the Rail
Freight area) and existing services and utilities infrastructure
4. Controlled access to the Airport boundary which will not impact existing airport
operations
5. Seek to avoid negative impacts on local communities and the environment
where reasonably practicable.
Rail Freight
In developing our construction proposals, the option of transporting materials and
delivering goods by water via the River Thames and / or the Grand Union Canal
has been considered. This is suggested as a possible mitigation measure by
ANPS paragraph 5.40. However, due to lack of water connectivity to the site and
the distance between the site and the nearest river / canal, this option is not
considered feasible.
The construction strategy is therefore based upon use of rail to transport materials
and goods to the construction site and in doing so this reduces potential vehicle
trips on the road network.
Options
The below sites were considered for the provision of a railhead facility to support
construction of the DCO Project:
1. Provision of a new railhead facility to the north-west of the third runway, parallel
to the northern boundary of the airfield, accessed by the existing spur
connecting with the Colnbrook railhead with the Great Western Main Line
(RF1)
2. Provision of a new railhead facility immediately east of and parallel to the M25,
approximately 1km south of Junction 14, accessed via a new spur off the
Staines-Windsor Line (RF2).
Evaluation summary
The selected option is to construct a new railhead facility to the north-west of the
third runway. This proposed site benefits from the existing connection to the
GWML, minimising the need for construction of additional rail infrastructure. The
site is located in close proximity to the Airport boundary and therefore facilitates
efficient transfer of materials from rail to within the main works area. Construction
of a railhead in this location will result in interaction with biodiversity receptors and
therefore appropriate mitigation will be required. Given the presence of historic
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.63 © Heathrow Airport Limited 2019
and authorised landfill in this locality appropriate management measures will be
implemented.
The site east of the M25 would locate the railhead facility itself immediately
adjacent to the Staines Moor Site of Scientific Interest, however the access spur
would result in the loss of habitat within this designation. As with the selected
option, this site would also result in interaction with historic and authorised landfill.
The southern part of the site extends into Flood Zone 2.
Other construction support sites
Beyond rail freight, other construction support site uses include load consolidation,
pre-fabrication and pre-assembly of structural elements, temporary parking for
staff and construction vehicles and contractor compounds, providing office space
and laydown areas. Further detail on the different activities which will be
conducted within CSS is provided in Document 4 Chapter 11 of the Updated SDR.
At the PEIR stage, these different uses have not been assigned to specific sites.
Instead, site options have been considered at a higher level based on their
suitability for one or preferably more of the activities set out above and within the
Updated SDR.
Options
The following options for provision of CSS (shown in Graphic 3.20) were
considered:
1. Land to the north and south of the existing A4 Bath Road and west of the M25
a. CS1 – between Brands Hill and Colnbook and south of the A4
b. CS2 – directly north of Poyle and south of the A4
c. CS13 – directly east of Brands Hill and north of the A4
2. Land north of the A4 Bath Road between the existing airport boundary and the
new third runway
a. CS4 – west of Polar Park
b. CS5 – east of Polar Park
c. CS6 – immediately west of Sipson Community Centre
d. CS7 – immediately west of Sipson
3. Land adjacent to the eastern boundary of the airport
a. CS8 – adjacent the existing Terminal 2 and 3 Long stay car park
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.64 © Heathrow Airport Limited 2019
b. CS9 – opposite the existing car park west of Hatton Cross station
4. Land south of the southern perimeter road/Horton Road
a. CS10 – north of Stanwell
b. CS11 – east of Stanwell Moor
c. CS12 – south of Poyle Industrial Estate
5. Land to the north of the proposed third runway
a. CS14 – north of Harmondsworth immediately south of the M4
b. CS15 – north east of Harmondsworth immediately south of the M4
c. CS16 – north west of Sipson
d. CS18 – north west of Sipson (between CS16 and CS16)
Graphic 3.20: Indicative locations of construction support site options
Evaluation summary
The evaluation of Options was primarily led by the delivery discipline, given the
criticality of CSS to the construction of the DCO Project. Given the complexity of
the construction programme, multiple CSS will be required to facilitate the wide
range of activities necessary to deliver the DCO Project. As such it was concluded
Heathrow Expansion PRELIMINARY ENVIRONMENTAL INFORMATION REPORT: Chapter 3: DCO Project alternatives
3.65 © Heathrow Airport Limited 2019
that the majority of the CSS considered are likely to be required, to ensure the
DCO Project can be delivered as efficiently and effectively as possible. The scale
and scope of works required prevents a single site being established to support all
construction activities. Instead, the requirement is for an even distribution of sites
around the periphery of the airport, to provide convenient access to multiple work
sites.
Of the land parcels north of A4 Bath Road (Option 2), CS6 was discounted on
environmental and community grounds. This site constitutes the Sipson
Recreational Ground. In addition to displacing this community facility, the risk of
adverse effects during construction would be increased given the site boundary is
adjacent to receptors within the village. This includes the effects of noise and
visual impacts, for example.
Whilst a combination of all options has been selected, the size of sites has been
reduced to manage risk of adverse environmental effects on adjacent receptors.
For example, this includes the land parcels under Option 1, where a buffer has
been included between the site boundary and receptors to the south within
Colnbrook. This approach has been adopted to increase separation between
construction activities and receptors and provide additional opportunities for
appropriate environmental measures. These include the use of noise barriers and
landscape screening as appropriate, to reduce potential noise and visual effects.
The risk of adverse air quality effects associated with construction traffic
movements and workforce travel was identified during the evaluation. The
construction strategy will be further refined between the PEIR and ES to identify
the most appropriate activities to be undertaken at each CSS. This will include
consideration of the measures contained within the Construction Traffic
Management Plan and Construction Workforce Management Plans to manage the
risk of adverse effects on transport users and local air quality during construction.