11
HCAs & Pipeline Assessment Intervals Is There a Need for Change? Richard B. Kuprewicz President, Accufacts Inc. For Pipeline Safety Trust New Orleans Conference 11/20 & 11/21/08

HCAs & Pipeline Assessment Intervals Is There a Need for Change?

Embed Size (px)

DESCRIPTION

HCAs & Pipeline Assessment Intervals Is There a Need for Change?. Richard B. Kuprewicz President, Accufacts Inc. For Pipeline Safety Trust New Orleans Conference 11/20 & 11/21/08. Is There A Need For Change?. The Answer is yes! Different yes for many sides/factions in this room - PowerPoint PPT Presentation

Citation preview

Page 1: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

HCAs & Pipeline Assessment Intervals

Is There a Need for Change?

Richard B. Kuprewicz

President, Accufacts Inc.

For Pipeline Safety Trust New Orleans Conference 11/20 & 11/21/08

Page 2: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

Is There A Need For Change?

The Answer is yes!Different yes for many sides/factions in this room

Will briefly present Short regulatory perspectiveSummary on integrity inspectionsWeaknesses in present approachRecommended changes

2

Page 3: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

Current Federal Regulations Liquid Integrity Management (49CFR195.452)

Phased (via Large / Small Operator) Regulation in 5/29/2001 & 2/15/2002

7 year Baseline assessment Large operator 50% by 9/30/2004, all by 3/31/08 Small operator 50% by 8/16/2005, all by 2/17/2009

~ 5 year maximum reassessment interval HCA determined by “could affect”

Captures ~ 43% of liquid transmission pipeline mileage or ~ 73,000 miles

Gas Transmission Integrity Management PSIA of 2002

10 year Baseline Assessment 50% inspected by 12/17/2007, 100% by 12/17/2012

7 year reassessments PHMSA Regulation in 2003 (49CFR192 subpart O)

Maximum Reassessment Interval ranging from 7 to 20 yrs based on stress levels

HCA determined essentially by C-fer empirical correlation sweep Captures about 7% of gas transmission pipeline mileage or ~ 19,000 miles

3

Page 4: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

Anomalies Requiring Immediate Repair

Liquid Transmission Pipelines Metal Loss > 80% nominal wall thickness Remaining strength calc burst pressure at anomaly < MOP Dent on top of pipe with stress concentrator Dent on top of pipe > 6% pipe diameter Anomaly in evaluator’s judgment requires immediate

repair

Gas Transmission Pipelines Remaining strength calc failure pressure at anomaly < 1.1

x MAOP Dent on top of pipe with stress concentrator Anomaly in evaluator’s judgment requires immediate

repair

4

Page 5: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

Liquid - Schedule Repairs 60 – Day Conditions

Top dent > 3% diameter Bottom dent with stress concentrator

180 – Day Conditions Dent > 2% diameter affecting curvature at girth/longitudinal seam Top of pipeline dent > 2% diameter Bottom of pipe dent > 6% diameter Calc showing operating pressure less than MOP at anomaly Metal loss > 50% of nominal wall Predicted metal loss >50% of nominal wall at another pipe

crossing, widespread circumference or could affect girth weld Confirmed crack indication Corrosion of or along a longitudinal seam Gouge or groove > 12.5% of nominal wall thickness

Other Conditions that may need to be scheduled E.g., anomaly in or near a casing, crossing, or near another

pipeline

5

Page 6: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

Gas - Schedule Repairs

1 – Year ConditionsDent on top of pipe > 6% diameterDent > 2% diameter affecting pipe curvature at girth

or at longitudinal welds

Monitored Conditions Not Requiring RepairBottom Dent > 6% of diameterTop Dent > 6% of diameter not exceeding critical

strain levelsDent > 2% diameter affecting curvature at girth or

longitudinal welds but not exceeding critical strain levels

6

Page 7: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

7

From PHMSA web site http://primis.phmsa.dot.gov/iim/index.htm

Page 8: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

8

From PHMSA web site http://primis.phmsa.dot.gov/gasimp/PerformanceMeasures.htm

Page 9: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

Changes Needed In Current IM Approach

U.S. Regs lead the world in area of Integrity Management (IM) Some areas build off technology developed in other countries U.S. approach is “Model One” - first of its kind

U.S. has more transmission mileage than other top fifteen countries combined!

Since inception of IM rule through 2007 - Tens of thousands of repairs have occurred on U.S. pipelines Liquid Pipelines ~ 26,000 repairs in HCAs, another ~ 59,000 outside HCAs Gas Transmission ~ 2,500 repairs in HCAs, non HCA repairs not required to

be reported

Utilize Learning Curve from First Cycle of IM Assessments Be aware history doesn’t define the future Always room for improvement Need public report repairs by anomaly cause Limitations / traps in consensus standards Reward those doing the right thing

9

Page 10: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

On Setting Regulatory Reassessment Intervals

For corrosion Address the different risks of selective vs. general corrosion

Selective corrosion can easily substantially exceed 12 mils/yr Burst calculations models moot if assuming wrong corrosion rate! PHMSA knows the difference between general and selective corrosion

Respect that PHMSA may be prevented from disclosing corrosion rates in certain cases

Other time-dependent anomalies need to be addressed Move to newer stronger pipe (X-70, X-80, X-100, X120)

Delayed third party damage failure much more likely Stress loading (i.e., land movement) complications

Reassessment interval changes must be based on sound science and sound assumptions Are field realities in sync with assumptions in consensus standards? Given uncertainties of present technology, a safety margin is still

required for re-inspection intervals Illusionary more “bad” inspections (whether mileage or frequency) are

not better than fewer good inspections matching the risks!

10

Page 11: HCAs & Pipeline Assessment Intervals Is There a Need for Change?

On Addressing HCAs and Public Confidence

Expand HCAs Increase the pipeline miles prudently inspected/re-inspected

For Liquids Address other sensitive areas beyond current HCAs definitions

of: commercial navigable waterways, populated areas, unusually sensitive area

Capture High Impact and Risk Areas E.g., sensitive parklands / protected areas

For Gas Address the “exotics” where C-fer zone is way too small

More Public Transparency Required PHMSA must report damage database by anomaly type Mandate reporting of all pipe repairs, even beyond HCAs, by

type of damage

11