Upload
ahmad-fauzie-ibrahim-ismail
View
140
Download
0
Embed Size (px)
Citation preview
HAZOP Study MethodologyIEDOSH JB
Semester MAY 2012Prepared by :
Mohd Ismafazil Ismail
1
SCOPE OF THE STUDY
2
BASIC PRINCIPLES
3
HAZOP METHODOLOGY The application of a formal,
systematic and critical examination of the process and engineering intentions of a process design
Potential of hazard – assessed
Malfunction of individual items of equipment and the consequences for the whole system – identified
Involve a team that has experience in the plant or design to be studied
4
HAZOP METHODOLOGY4 overall aims to which any HAZOP should be addressed
Identify all deviations from the way design is expected to work, causes, hazards & operability problems
Decide whether action is required to control the hazard/operability problem
5
HAZOP METHODOLOGY
Identify cases where decision can’t be made immediately, any info/action required
Ensure actions are followed through
6
HAZOP METHODOLOGY
Study may not be resolve all the hazards so firm recommendations for change cannot always be guaranteed to result from deliberation at a HAZOP meeting.
7
HAZOP METHODOLOGY
Draft report – report summarizing the study & giving a list of recommendations together with work sheets.
Final report – giving details of follow-up actions to complete the study.
8
HAZOP Study Procedure6 steps in the development of a HAZOP study :
1) Defining objectives & scope2) Select HAZOP team members3) Preparing for the study4) Undertaking the study5) Recording the results6) Conducting the follow-up
actions.9
1) Defining the objectives and scopeFactors will influence the study Objectives & Scope
o Nature & stage of the projecto Requirement for full documentationo Availability of personnelo Number of P&IDso Timing, duration & budgeto Degree of authority given
10
P & ID
A Piping and Instrumentation Diagram - P&ID, is a schematic illustration of functional relationship of piping, instrumentation and system equipment components.
11
P & ID
P&ID shows all of piping including the physical sequence of branches, reducers, valves, equipment, instrumentation and control interlocks. PID_sample
12
1) Defining the objectives and scopeStudy influence the product
Check a design for hazards/operability
Decide whether & where to build
To buy an equipments Check running instructions Improve the safety of existing
facilities13
1) Defining the objectives and scopeTypes of hazard to be considered
To people working in a plant To plant & equipment To or from product quality To the general public To the environment
14
2) Selecting the HAZOP team members• Detailed technical knowledge of the process.
• Those with knowledge and experience of applying highly structured, systematic HAZOP approach.
15
3) Planning for the study
Session dates and times Documents to be studied in each session
Team members availabilityReporting arrangements Sub session plan Plan for follow up action
16
4) Undertaking the studyA study team to consider part of a process design for a number of deviations & guidewords
7 stages1. Apply a guideword2. Develop a deviation3. Examine possible causes
17
4) Undertaking the study
4. Examine consequences5. Consider
hazards/operability problem
6. Decide upon action7. Make a record of the
discussion & decision18
HAZOP – Hazard and operability
Hazard Identification
Consequence & Qualitative Risk
Recommendation for Mitigation HAZOP Cause
19
HAZOP – Hazard and operability
20
4) Undertaking the study
1st study session – team leader invites the process engineer to outline the design intentions in very broad terms. Required info on flow rates, pressures and temperature within sections.
21
4) Undertaking the study Ensure team member has adequate knowledge of the process and the way section operated.
Guideword applied, discuss causes, consequences and possible actions for each deviation.
22
4) Undertaking the study
2 extreme approaches :
(1)Solution found for each hazard as detected before looking for the next hazard
(2)No search of solution, all issues recorded with recommendations, issues be studied
23
4) Undertaking the study
2 extreme approaches :
Study leader will sum up at the end of discussion before starting with next guideword.Maintain pace, terminate disagreement, resolve outside meeting, no prolonged discussion on solution.
24
5) Recording the results Record the results (may
need a secretary) Follow-up of actions noted
› final report contain resolution of all recommended actions
› must appoint someone as leader to check progress of action
25
5) Recording the results
› team may meet again if answers to questions do not simply lead to an action
› team may meet again if significant design changes in interim report
26
6) Conducting follow up Prioritize the recommendation, giving
highest priority to the class which could be most sensitive to the company
Determine the type of recommendations : Rejected recommendations Procedural Small projects Additional study
27
HAZOP - Procedure
HAZOP keeps all team members focused on the same topic and enables them to work as a team
NODE: Concentrate on one location in the processPARAMETER: Consider each process
variable individually (F, T, L, P, composition, operator action, corrosion, etc.) 28
HAZOP - Procedure
GUIDE WORD: Pose a series of standard questions about deviations from normal conditions. We assume that we know a safe “normal” operation.
29
HAZOP - Procedure
NODE: Pipe after pump and splitter
PARAMETER*: Flow rate
GUIDE WORD*: Less (less than normal value)• DEVIATION: less flow than normal
• CAUSE: of deviation, can be more than one
• CONSEQUENCE: of the deviation/cause
• ACTION: initial idea for correction/ prevention/mitigation
A group members focus on the same issue simultaneously
30
NodeEach P&ID is divided into smaller sections called nodes.
A node will typically contain a major piece of equipment plus associated piping and instrumentation.
Depending on the experience of the study leader, the portion of a process included in a single study node can vary.
31
HAZOP - Hazard and operability
Identify nodes ?
32
HAZOP Process Parameter
Flow Composition pHPressure Addition SequenceTemperature Separation SignalMixing Time Start/stopStirring Phase OperateTransfer Speed MaintainLevel Particle size ServicesViscosity Measure Communication Reaction Control
33
HAZOP Guidewords with explanation
Guidewords Meanings Comments
No, Not or None The complete negation of the design intentions
No part of the intentions is achieved and nothing else happens
More of Quantitative increases of any relevant parameters
These refer to quantities + relevant physical properties such as flow rates and temperatures a well as activities like “HEAT” and “REACTION”
Less of Quantitative decreases
34
HAZOP Guidewords with explanation
Guidewords Meanings Comments
As well as A qualitative increase
All the design and operating intentions are achieved together with some additional activity
Part of A qualitative decrease
Only some of the intentions are achieved, some are not
Reverse The logical opposite of the intention
This is mostly applicable to activities for example, reverse flow or chemical reaction. It can also be applied to substances e.g. “POISON” instead of “ANTIDOTE” or “D” instead of “L” optical isomers
Other than Complete substitution
No part of the original intention is achieved. Something quite different happens.
35
HAZOP Guidewords with explanation
The first 3 guidewords (none, more of and less of ) – straightforward
Example : water system
Remaining 4 guidewords are tricky :
Qualitative deviations like “as well as” and “part of” allow all or part of the design intention to be retained.
36
HAZOP Guidewords with explanation
Ex : As well as substance A could mean
a) Some material is transferred as well as substance A
b) Substance A is transferred elsewhere as well as to the vessel being considered
c) Other activity takes place concurrently with the transfer of substance A. Ex : decomposition or a change of phase of the material.
37
HAZOP Guidewords with explanation
Ex : Part of transfer of substance A
a) Component of substance A missing
b) Substance A is transferred to other parallel vessel
Ex : Reverse transfer
c) Opposite of design intentions38
HAZOP Guidewords with explanation
Ex : Other than transfer of substance A
a) A different substance is transferred
b) Substance A is transferred elsewhere
c) Activity halted due to solidification
39
HAZOP Guidewords and Causes – Continuous operation
Guidewords Causes
No Flow Wrong routing – blockage – incorrect slip plate – incorrectly fitted check valve – burst pipe – large leak – equipment failure (CV, isolation valve, pump, vessel, etc) – incorrect pressure differential, etc
Reverse Flow Defective check valve – incorrect pressure differential – two way flow – emergency venting – incorrect operation, etc.
More flow Increased pumping capacity – increased suction pressure – reduced delivery head – greater fluid density – control faults – running two pumps, etc.
Less Flow Line restrictions, filter blockage – defective pumps – fouling of vessels, valves, etc.
More Level Outlet isolated or blocked – inflow greater than outflow – control failure – faulty gauge, etc
40
HAZOP Guidewords and Causes – Continuous operation
Guidewords Causes
Less Level Inlet flow stops – leak – outflow greater than inflow – control failure – draining of vessel, etc
More Pressure Surge problems – connection to high pressure systems – gas breakthrough (inadequate venting), thermal overpressure, defective relief valves, etc
Less Pressure Restricted pump/compressor suction line – undetected leakage – vessel drainage – gas dissolving in liquid, etc
Less Flow Line restrictions, filter blockage – defective pumps – fouling of vessels, valves, etc.
More Temperature
Failed exchanger tubes – fire situations – cooling water failure – defective control – heater control failure – reaction control failures, etc
41
HAZOP Guidewords and Causes – Continuous operation
Guidewords Causes
Less Temperature
Loss of heating – failed heat exchanger – reducing pressure, etc
More Viscosity Incorrect material or composition – incorrect temperature – high solid concentration, etc.
Less Viscosity Incorrect material or composition – incorrect temperature – solvent flushing, etc.
Composition Change
Leaking isolation valves – incorrect specification – inadequate quality control – process control upset, etc
Contamination Leaking exchanger tubes – incorrect operation of system – wrong additives – grade change, etc.
Relief Relief valve discharge location – inlet and outlet piping, etc
42
HAZOP Guidewords and Causes – Continuous operation
Guidewords Causes
Instrumentation Control philosophy – response time – alarm & trip setting, auto/manual facility & human error, etc.
Sampling Sampling procedure and operator safety – time for analysis result – calibration of automatic samplers – loss of sample flow, etc
Corrosion/ Erosion Cathodic protection arrangements – internal/external corrosion – stress corrosion cracking, etc
Service Failure Failure of instrument air/ steam/ nitrogen/ cooling water/ hydraulic/ power – computers, etc
Abnormal Operation
Purging – flushing – clearing blockages – emergency shutdown, etc.
43
HAZOP Guidewords and Causes – Continuous operation
Guidewords Causes
Maintenance Isolation philosophy – drainage – rescue plan – training – pressure testing, etc.
Ignition Grounding arrangements – flame arrestors – static electricity – hot surfaces – hoses, etc.
Spare Equipment Installed/non-installed spare equipment – availability of spares – modified specifications, etc
Safety Toxic properties of process materials – fire & gas detection system – contingency plan – emergency response plan, etc
Human Factors Layout - accessibility
HAZOP case studies at section 8.244
Guide word -Parameter
45
Guide word -Parameter
Loss of containment (Part of)
– Piping failures from corrosion induced leaks or mechanical impact– Failures of flanges and fittings– Leaks from valve stems or pump seals– Heat exchanger tube rupture or shell failure– Pressure vessel failure– Releases from small bore fittings, instrument bridles, drains and vents– Materials of construction, corrosion
46
Guide word -Parameter
Utilities failures (Part of)– Instrument Air or Nitrogen– Power– Cooling water or Steam failure– Fuel Gas or Fuel Oil failures
Environment impact– Lightning, Wind or Flood– Earthquake– Noise
47
Guide word -Parameter
Testing– Equipment such as alarms, trips PRV settings– Product or intermediate sampling and analysis
Maintenance (Other than)– Access and means of isolation– Draining, Purging and drying– Cooling or warming of equipment– Availability of spares/replacement items– Special activities (for example Hot Tapping)
48
Guide word -Parameter
Electrical– Area classification– Isolation and earthing
Instrumentation– Suitability/reliability/sufficiency of sensors and transmitters– Location, failure modes and effect on any voting logic– Alarms, hierarchy and ability of operator to respond
49
Guide word -Parameter
Personnel protection
– Basic equipment, boots, hard hats, gloves goggles– Escape masks, breathing apparatus (Toxics or confined entry)– Permit to work and requirements (escape routes, ladders, ropes etc)– Protective instruments (oxygen analysers, flammable /toxic gas detectors)
50
Guide word -Parameter
Plant protection– Fire and smoke detection– Flammable or toxic gas detection– Firewater systems, monitors, deluges and sprays– Passive fire protection– Chemicals storage and handling– Fences and measures against intruders, saboteurs– Housekeeping
51
Deviation table
Deviation Column Tank/Vessel LineHeat
Exchanger Pump
High Flow X
Low/no Flow X
High Level X X
Low Level X X
High Pressure
X X X
Low Pressure X X X
High Temp. X X X
Low Temp. X X X
High Concen. X X X
Low Concen. X X X
Reverse Flow X
Tube Leak X
Tube Rupture X
Leak X X X X X
Rupture X X X X X52
Guide word –Parameter Exercise
53
Preliminary HAZOP ExampleRefer to reactor system shown.
The reaction is exothermic. A cooling system is provided to remove the excess energy of reaction. In the event of cooling function is lost, the temperature of reactor would increase. This would lead to an increase in reaction rate leading to additional energy release.
The result could be a runaway reaction with pressures exceeding the bursting pressure of the reactor. The temperature within the reactor is measured and is used to control the cooling water flow rate by a valve.
Perform HAZOP Study
TC
Cooling Coils
MonomerFeed
Cooling Water to Sewer
Cooling Water In
Thermocouple
54
Preliminary HAZOP on Reactor - Example
Guide Word Deviation Causes Consequences Action
NO No cooling Temperature increase in reactor
REVERSE Reverse cooling flow
Failure of water source resulting in backward flow
MORE More cooling flow
Instruct operators on procedures
AS WELL AS Reactor product in coils
Check maintenance procedures and schedules
OTHER THAN Another material besides cooling water
Water source contaminated
55
Case Study – Shell & Tube Heat Exchanger
• Using relevant guide works, perform HAZOP study on shell & tube heat exchanger
Processfluid
Cooling water
56
Case Study – Shell & Tube Heat Exchanger
Guide Word Deviation Causes Consequences Action
Less Less flow of cooling water
Temperature of process fluid remains constant
More More cooling flow
More of More pressure on tube side
Install high pressure alarm
Contamination Contamination of process fluid line
Proper maintainance and operator alert
Corrosion Corrosion of tube
57
Case Study – Shell & Tube Heat Exchanger
Guide Word Deviation Causes Consequences Action
NONE No cooling water flow
Process fluid temperature is not lowered accordingly
MORE More cooling water flow
LESS Less cooling water
Installation of flow meter
REVERSE Reverse process fluid flow
Install check valve (whether it is crucial have to check?)
CONTAMINATION
Process fluid contamination
58
Espresso Machine - Exercise
(B) Water tank
(H) Electrical Heating
(L) Connecting pipe
(K) Coffee reservoir
(T) Cup
59
Espresso Machine1. Filling
Fill 100 ml water into the water tank and close the lid.
2. Feed coffeeFeed the coffee reservoir with 10 g of coffee and screw it onto the discharge line.
3. HeatingHeat to boiling by switching on.
4. DischargePress hot water through the coffee into the cup.
60
Operating Procedure HAZOP
A procedure HAZOP is an examination of an existing or planned operation (work) procedure to identify hazards and causes for operational problems, quality problems, and delays.
• Can be applied to all sequences of operations
61
Operating Procedure HAZOP
• Focus on both human errors and failures of technical systems
• Best suited for detailed assessments, but can also be used for coarse preliminary assessments
• Flexible approach with respect to use of guide-words
62
Operating Procedure HAZOP
• Breakdown of operation (work) procedure to suitable steps
• Define intention of each step
• Establish boundary conditions
63
Operating Procedure HAZOP
else asconventional Process HAZOP
• Apply guide-words to intention and boundary conditions for each step.
64
Operating Procedure HAZOP• Team should identify the
intent of the procedure• Understand the state of the
equipment at the beginning and end of the procedure
• Know objective of the procedure and overall in detail
65
Operating Procedure HAZOP
• Study will be carried out in a ‘step by step’ manner
• Review the step as requiring an action at a time in a sequence
• Review the wording of the instructions as a flow of information
66
Operating Procedure HAZOP• The procedure is a set of instructions
whose aim is to direct an operator to make changes to the state of a system in a safe manner.
(a) Commissioning(b) Start – up(c) Normal shutdown(d) Emergency shutdown(e) Preparation for maintenance(f ) Sampling/tapping/draining(g) Inspection/monitoring/checking
67
Procedure HAZOP Guidewords and Issues
Guideword
ACTI ON TI ME SEQUENCE I NFORMATI ON
None x x
Reverse (wrong) x x
More x x x
Less x x x
Part of x
As well as x
Other than x x
Parameter
68
Procedure HAZOP Guidewords and Issues
Guidewords Causes
Purpose Is the step needed? – is the intent of this step clear? – can this step be miss applied?
No Action Step is missed or omitted – action impossible – equipment not ready (Locked out/ not in service)
More Action Operator does more than intended (opening valve too far) other actions occur affecting this operation
Less Action Operator does less than intended (added less catalyst than required) – not enough time to complete the step
Wrong Action Operator open the wrong valve – starts the wrong pump – reads the wrong instrument
Part of Action Operator only completes part of a composite action (misses out middle part or final part)
69
Procedure HAZOP Guidewords and Issues
Guidewords Causes
Extra Action Operator assumes he is required to do something in addition to what is specified – poor communication - other procedure interfering
Other Action Operator misunderstands instruction and does something completely different
More Time Operator takes longer than necessary over action – start next action later than expected
Less Time Operator carries out action too quickly (stop the flow before required level is reached)
Out of Sequence
Operator misses out a step – carries out a step before it should occur or after it should occur
More Information
Procedure includes information that is unnecessary and could lead to confusion – contains information that contradicts other information
70
Procedure HAZOP Guidewords and Issues
Guidewords Causes
Less Information Necessary information is missing from the procedure – information about the starting condition – information which allows operator to check progress or to troubleshoot problem
No Information No feedback from the process (transmitter failure) – not specify standard operating conditions (temperature, pressure, flow)
Wrong Information
Out of date – contradiction (oral vs written, other procedures within this procedure)
Clarity Step confusing – poor procedure from layout
Unattended Safeguards – adequate information feed-back (alarms, signals)
Operation Remote – starting equipment – emergency response (time, personnel, equipment)
71
Procedure HAZOP Guidewords and Issues
Guidewords Causes
Training Adequate training – is certification required and provided for this step – procedure control
Abnormal Emergencies – recovery from abnormal situations
Conditions Failure – severe or unusual weather
Maintenance Work permit required – equipment conditions - recalibrations
Safety Personal protection – OSHA compliance – industrial hygiene – environmental considerations – fire, explosion or chemical release potential
72
Procedure HAZOP exercise
Please perform Procedure HAZOP using the guidewords
Guide Word Deviation Causes Consequences Action
73
HAZOP
HAZOPNodes
ParametersGuide words
Consequence
Deviation
All of these terms! This stupid table!I hate HAZOPS. Why don’t we just
learn the engineering?
ATTITUDE CHECK
74
HAZOP
I suppose that I should have done that
HAZOP Study!
75
HAZOP log sheet
HAZOP log sheet
76
Log sheet Node/Section
A node is a specific location in the process in which (the deviations of) the design/process intent are evaluated.
Examples might be: separators, heat exchangers, scrubbers, pumps, compressors, and interconnecting pipes with equipment.
77
Log sheet Design Intent
The design intent is a description of how the process is expected to behave at the node; this is qualitatively described as an activity (e.g., feed, reaction, sedimentation) and/or quantitatively in the process parameters, like temperature, flow rate, pressure, composition, etc.
78
Log sheet Deviation
A deviation is a way in which the process conditions may depart from their design/ process intent.
Parameter
The relevant parameter for the condition(s) of the process (e.g. pressure, temperature, composition).
79
Log sheet Guideword
A short word to create the imagination of a deviation of the design/process intent. The most commonly used set of guide-words is: no, more, less, as well as, part of, other than, and reverse. In addition, guidewords like too early, too late, instead of, are used; the latter mainly for batch-like processes.
80
Log sheet GuidewordThe guidewords are applied, in turn, to all the parameters, in order to identify unexpected and yet credible deviations from the design/process intent.
Guide-word + Parameter = Deviation
81
Log sheet Cause
The reason(s) why the deviation could occur. Several causes may be identified for one deviation. It is often recommended to start with the causes that may result in the worst possible consequence.
82
Log sheet Consequence
The results of the deviation, in case it occurs. Consequences may both comprise process hazards and operability problems like plant shut-down or reduced quality of the product.Several consequences may follow from one cause and, in turn, one consequence can have several causes
83
Log sheet Safeguard
Facilities that help to reduce the occurrence frequency of the deviation or to mitigate its consequences. There are, in principle, five types of safeguards that:
1. Identify the deviation (e.g., detectors and alarms, and human operator detection)
2. Compensate for the deviation (e.g., an automatic control system that reduces the feed to a vessel in case of overfilling it. These are usually an integrated part of the process control)
84
Log sheet
3. Prevent the deviation from occurring (e.g., an inert gas blanket in storages of flammable substances)
4. Prevent further escalation of the deviation (e.g., by (total) trip of the activity. These facilities are often interlocked with several unitsin the process, often controlled by computers)
5. Relieve the process from the hazardous deviation (e.g., pressure safety valves (PSV) and vent systems) 85
HAZOP Study
HAZOP study are applied during :
• Normal operation
• Foreseeable changes in operation, e.g. upgrading, reduced output, plant start-up and shut-down
• Suitability of plant materials, equipment and instrumentation
86
HAZOP Study
• Provision for failure of plant services, e. g . steam, electricity, cooling water
• Provision for maintenance.
87
Strength of HAZOP• HAZOP is a systematic, reasonably
comprehensive and flexible.• It is suitable mainly for team use
whereby it is possible to incorporate the general experience available.
• It gives good identification of cause and excellent identification of critical deviations.
88
Strength of HAZOP
• The use of keywords is effective and the whole group is able to participate.
• HAZOP is an excellent well-proven method for studying large plant in a specific manner.
• HAZOP identifies virtually all significant deviations on the plant, all major accidents should be identified but not necessarily their causes.
89
Weakness of HAZOP• HAZOP is very time consuming and can
be laborious with a tendency for boredom for analysts.
• It tends to be hardware-oriented and process-oriented, although the technique should be amenable to human error application.
• It tends to generate many failure events with insignificance consequences and generate many failure events which have the same consequences. 90
Weakness of HAZOP• It stifles brainstorming although this is
not required at the late stage of design when it is normally applied.
• HAZOP does not identify all causes of deviations and therefore omits many scenarios.
• It takes little account of the probabilities of events or consequences, although quantitative assessment are sometime added. The group generally let their collective experiences decide whether deviations are meaningful.
91
Weakness of HAZOP
• HAZOP is poor where multiple-combination events can have severe effects.
• It tends to assume defects or deterioration of materials of construction will not arise.
• When identifying consequences, HAZOP tends to encourage listing these as resulting in action by emergency control measures without considering that such action might fail. It tends to ignore the contribution which can be made by operator interventions
92
Mechanistic procedure• At the beginning of a study, leader should
choose small, simple section of equipment & piping to review.
• If pre-planning done, always be on the basis of simple sections until leader confident with the team capabilities
• Leader should ensure consensus before moving to next point.
• Moving rapidly to next cause can inhibit another not so quick team member
93
Mechanistic procedure• It is helpful to list all causes of a
particular g/word before moving to consequences.
• Leader should check causes is real & not just restatement of deviation.
• It similarly applies to consequences
• When scenario identified where expected a serious consequences, team should decide which risks are acceptable & vice versa.
• Often helpful to have a relatively philosophical discussion as preferences
94
Mechanistic procedure• When insufficient information is available,
record an action to review the section at specific date.
• Major redesign, record the design parameters & note further review is required.
• Assign ‘checking’ issues to a team members
• If P&ID is out of date, study stop until get new updated version
• Handicapped by lack of info, stop discussion & assign ‘checking’ duty
95
Process Hazard Assessment - best practice
Concept Stage Risk Assessment
Conceptional Design
Basic Risk Assessment
Process Flow Sheet Development
Detailed Risk Assessment
Piping & instrumentation Diagram Development
Construction Design Verification
Pre-commissioning Assessment
Hand Over
PRAstep 1
PRAstep 2
Mechanical Completion
96
Process Hazard Assessment - best practice
97
Hand OverPre-operations Inspection
Post Start-up Assessment
Start of Operation
Risk Assessment Revalidation
Change
Normal OperationPRAstep 3
Concept Stage Risk Assessment Definition
Concept Stage Risk Assessmentis an early systematic investigation on safety, health, environment issues relevant to the project
This assessment defines: Scope of project Process description Material hazards Involvement of external authorities Organization and human factors Additional assessments
98
Concept Stage Risk Assessment Method
Application of inherent SHE to -Eliminate the use of hazardous materials
-Minimize production of waste-Process conditions (pressure, temperature, etc.)
Review previous incidents on similar processes or plants
Collect information on hazards of chemicals involved
99
Concept Stage Risk Assessment Method
Review Environmental and Occupational Health Statements
Consider Interaction of the project with site activities
Review application of local legislation
100
Basic Risk AssessmentDefinition
Basic Risk Assessment is an systematic approach to :
Define the main hazards of a project
Assess probability and severity
Define the basis of safe operation regarding- Toxics- Fire and explosions- Exothermic reactions
Specify the need for corrective actions
101
Basic Risk AssessmentMethod
Use of a guide tool to:
Identification of main hazards like - Explosion- Fire- Toxic release (loss of containment)- Uncontrolled exothermic reaction
Identification of consequences and related probabilities
Identify the need for additional protective systems
102
Detailed Risk Assessment Definition
Detailed Risk Assessment is an systematic approach to:
Identify hazards that arise from deviation from design intend
Assess probability and severity of such deviations
Specify the need for additional safeguards
103
Detailed Risk Assessment Method
Structured use of guidewords to assess possible deviations and their consequences:
a. A firm reviewed Piping and Instrument Diagram (P&ID)b. Lay-out sketch c. Process descriptiond. Process control procedure e. Material characteristics (MSDS)f. Area electrical classification drawings (zoned areas)g. Interlocking diagram and SIL classificationh. Outline operating, commissioning, maintenance and test
proceduresi. Operating instructionsj. Relief systems philosophy
104
Detailed Risk Assessment Method
Structured use of guidewords to assess possible deviations and their consequences:k. Actions/recommendations from basic risk
assessment l. Specification of vessels and pipe work requiring
periodic inspectionm.Provision of a list of critical machine systemsn. In addition, for batch processes a full sequence
description is requiredo. Plant tour (to confirm that the above mentioned
documents are in line with the existing equipment)
105
Construction/design Verification Definition
Construction/design verification is a pre commissioning check that hardware has been built as intended.
106
Construction/design Verification Method
Use of a check list for: Installation check
Check that the hardware is as the design intended and that the software requirements are completed
Implementation checkCheck that what was called for in earlier hazard studies and engineering change orders has been implemented
107
Construction/design Verification Method
Use of a check list for:
Modification CheckCheck that modifications made during construction/commissioning have been formally reviewed and documented
108
Pre-commissioning Assessment Definition
Pre-commissioning Assessment is an systematic site inspection to ensure that the plant is a safe place to work and meets company and legislative requirements before hand over to operation.
109
Pre-commissioning Assessment Method
Key aspects include an assessment of:
Arrangements for the protection of employee health, covering the facilities provided and the arrangements for workplace monitoring
Arrangements, including emergency systems, for employee safety
Equipment and systems provided to protect the environment and for monitoring environmental performance
110
Post Start-up Assessment Definition
Post start-up Assessment is a formularized review meeting 3-6 month after start-up. Purpose of this assessment meeting is to review the initial running period and to provide feedback to engineering of the plant’s performance.
111
Post Start-up Assessment Method
Use check list to ensure that: Previous risk assessments have been
completed and documented Early operation has been reviewed and
confirmed that it is consistent with the design intent with regard to safety, health and environmental issues, and that assumptions defined in earlier assessments are borne out in actual operation
112
Post Start-up Assessment Method Operating and maintenance difficulties
have been reported and documented, and ensure feedback to the design engineering organization responsible for the project
Modifications during start-up have been reviewed, approved and documented
Performance of trip and alarm system has been reviewed
113
Risk Assessment Revalidation Definition
Risk Assessment Revalidation is a formularized review of the process safety
Upon any change (process, equipment, raw materials, …)
Following an incident
Operational learning
Change in legal or Henkel requirements
After 5 years
114
Risk Assessment Revalidation Method
Use of a standardized proceeding to ensure that: Opportunities for hazard reduction or elimination
and risk reduction are considered Process risk control measures are sufficient for
the continued operation of the plant Process risks for which the control measures are
no longer sufficient and which require action are identified
Legal and Henkel requirements are met
115
THANK YOU
116