MARCH 31 2019
HAZEL SITE PROGRESS PHOTOS
PROJECT MAIN ENTRY – SECURITY ROOM
CLUB HOUSE- FRONT ELEVATION
EXTERNAL – CLUB HOUSE
CLUB HOUSE-GYM,MULTI PURPOSE HALL
CLUB HOUSE- INDOOR GAMES
CLUB HOUSE - ACTIVITIES
HOUSEWARMING FUNCTION DANCE CLASS
TABLE TENNISDRAWING CLASS
CLUB HOUSE - ACTIVITIES
HOUSEWARMING FUNCTION TABLE TENNIS
TABLE TENNISCAROM BOARD
ROAD FROM MAIN ENTRY TO ‘B’ BLOCK
BLOCK ‘B’ NORTH SIDE ROAD
BLOCK ‘B’ SOUTH SIDE ROAD
TRANSFORMER
EXTERNAL WORKS – ROAD WORKS/DRAIN WORKS/FIRE HYDRANT
BLOCK E SOUTH SIDE BLOCK F SOUTH SIDE
EXTERNAL WORKS – ROAD WORKS/DRAIN WORKS/FIRE HYDRANT
IN BETWEEN BLOCK D&F BLOCK F EAST SIDE
Block C North Side Swimming pool
WORKS IN PROGRESS:-
compound wall cum storm water drain Completed in Block E ,block F south side and
block A & C north side . Block F north east corner balance 20rmt in progress
Service work Completed in Block E & Block F south& east
side and in-between block D&F. progress in block C north side
Road work Completed in block E& Block F south side ,
85% completed in between block D& F. block F east side 50% ready for rcc road and balance in progress for pcc
Fire fighting work completed block E and block F south side and
progress in block A & C north side .
Swimming pool Structure completed .RR to be submitted the
final service drawing to commence the waterproofing and tiling work.
BLOCK F NORTH EAST CORNER WORKS IN PROGRESS:
OSR LANDSCAPE WORKS