Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
FOREWORD
1 - 1
Tank Instruction Manual
This instruction manual is intended as an aid to
personnel installing Chem Resist Storage
Vessel(s).
This manual is intended as a source of important
information regarding the delivery and installation
of the vessel(s). Following the instructions given
will prolong the life of the vessel(s) and help
prevent hazards.
The location of this manual must be known at all
times by all personnel operating within the
confines of the plant at which the vessel(s) has
been installed.
This manual must be read by any personnel
appointed to work :
• in the vessel(s),
• on the vessel(s),
• on any equipment connected with the vessel(s)
OR
• in the surrounding vicinity of the vessel(s).
during any of the following duties :
1. transport, OR
2. installation.
Apart from the manual and those applicable
obligatory regulations for accident prevention in
the country of use and application location, the
standard technical regulations for safe and
professional operation must be observed.
This manual contains information which must be
observed during installation of the vessel(s) and
therefore must also be read by the Installation
Engineer / Supervisor.
Safety instructions in this manual are identified by
the general hazard symbol :
Non-observance of this safety symbol may lead
to personal injury.
Where damage to the vessel(s) may arise if the
instructions are not followed then the word
is inserted.
Hazards If The Safety Instructions Are Not
Observed
Non-observance of safety instructions may lead to
hazards to personnel as well as the environment
and vessel(s).
Non-observance of safety instructions may lead to
loss of any claims for damages.
Non-observance of safety instructions may lead in
particular to the following hazards,
(a) Failure of the vessel(s) in question,
(b) Personal hazard due to mechanical and / or
chemical influences,
(c) Environmental hazard due to leakage of
hazardous substances.
SAFETY
2 - 1
Tank Instruction Manual
In addition to the safety instructions named below, the safety instructions provided by any associated equipment manufacturer also apply.
General
Apart from the instruction manual and the
applicable obligatory regulations for accident
prevention in the country of use and application
location, the standard technical regulations for
safe and professional operation of the vessel(s)
and any associated equipment must be observed.
Not only the general safety instructions listed in
the chapter “Safety” but also the special safety
instructions added to the other main points must
be observed.
Do not attempt any operation which may be a
safety hazard.
Intended Use
Chem Resist storage vessels are fabricated
according to the latest technology and recognised
safety / design regulations. However improper
handling may lead to hazards for operating
personnel or other third party persons either in the
short term or the long term.
Chem Resist storage vessels should only be used
for the duty as designed by Chem Resist. Any
other duty or use beyond that of the designed duty
is not as intended. Chem Resist is not liable for
damages resulting from this, the user is solely
responsible. Intended use involves observance of
the instruction manual.
If a new duty or use lies outside the limits of use
defined by the vessel design or if the user is in
doubt regarding changes, the change must be
approved by Chem Resist.
Organisational Measures
Always keep the instruction manual in a
recognised location at all times.
Observe the general, legal, national and other
compulsory regulations on accident prevention
and environmental protection in addition to those
described in the instruction manual.
Any individual appointed to undertake work on
the vessel(s) must have read the instruction
manual before starting work, paying particular
attention to the chapter on safety instructions.
If changes are made to the vessel(s) applicable to
safety, then the vessel(s) must be emptied, (if they
still contain process liquids), isolated immediately
and the relevant authority / person must be
informed.
Changes on or additions to the vessel(s) which
could impair safety must not be undertaken unless
permission is received from the supplier.
SAFETY
2 - 2
Tank Instruction Manual
Personnel Selection
No work may be undertaken on any thermoplastic
vessel unless by a skilled plastic fabricator.
Information on Special Types of Hazard
Vessels containing hazardous and / or
environmentally dangerous material, the customer
/ user must inform appointed repair personnel
without being asked.
Environmentally hazardous media are:
• harmful substances
• toxic substances
• corrosive substances
• irritant substances
• combustible substances
• incendiary, highly, easily flammable
combustible substances
• carcinogenic substances
• substances changing hereditary factors
• substances which are dangerous to man in other
ways
If a leakage of hazardous substances occurs, then
the substance must be removed as safely and as
quickly as possible exercising due regard for the
methods stated in the hazard data sheet for that
substance.
Technical Measures
Ensure that following maximum permissible
operating parameters are not exceeded:
1. Pressure
2. Temperature
3. Stored Media Specific Gravity
Associated pipework and / or equipment must not exert excessive load upon the vessel(s) nozzles as this will result in failure and thus stored media leakage.
Vessel Periodic Inspection
Chem Resist would recommend that all
thermoplastic storage vessels containing
aggressive / hazardous chemicals are placed
within a periodic inspection regime.
4 - 1
INSTALLATION
Tank Instruction Manual
General
Installation work may only be carried out by
specialist or appointed personnel.
All personnel involved with the installation of
Chem Resist storage vessels must read the
chapter regarding safety carefully.
All personnel involved with the installation of
Chem Resist storage vessels must be made aware
of hazards which arise in connection with these
activities.
Apart from the instruction manual and the
applicable obligatory regulations for accident
prevention in the country of use and application
location, the standard technical regulations for
safe and professional operation must be observed.
Protection of Vessel(s) During Transportation
Small vessels, (up to 6m³), can be packaged by
shrink wrapping onto a pallet to facilitate ease of
handling by fork lift truck.
Larger vessels are not normally packaged but
nozzles can be closed with simple flange blanks.
Keep at least one nozzle open to avoid over pressurisation of the vessel !
No thermoplastic vessel should not be loaded or transported in ambient temperatures below 7° Celsius without prior consultation with Chem Resist
4 - 2
INSTALLATION
Tank Instruction Manual
Loading
Different methods are used to load
thermoplastic vessels dependent upon the
size of the vessel.
Where tanks are lifted using the Lifting
Lugs, slings must be 30 mm wide. Any
wider slings will not fit snuggly into the
lug and may slip out during lifting
Small Vessels
Vessels of volume less than or equal to
6m³ are usually loaded by hand or fork lift
truck.
Lift Correctly Using Pallet
Do Not Lift Directly
These smaller vessels are normally
transported in a vertical position and
should be adequately secured to resist
horizontal and vertical movement.
Only Fibre Ropes or Strapping Should Be Used For This Purpose.
The Use Of Wire Ropes
Or Chains Is
Prohibited !
Medium Vessels
Loading vessels of volume between 6m³
and 20m³ is usually carried out using an
independent or vehicle mounted crane. The
lifting of the vessel will require the use of
a spreader beam, (see Figure 4.1 below).
Figure 4.1
Spreader Beam Lifting Arrangement
Do Not Push Vessel Along
Floor With Forks
4 - 3
INSTALLATION
Tank Instruction Manual
This weight tested horizontal beam has a central
crane attachment and two adjustable vessel lifting
points and therefore prevents damage which can
be caused to vessel covers by central lifting slings.
In cases where a lifting beam is not available a
single wide, (minimum 75mm), webbing strap
with a “choking” action positioned around the
tank cylinder approximately 1/3 rd of the vessels’
height down from the top can be used to lift the
vessel.
Care must be taken to avoid strain on the
connections and the strap must be kept tight
during the lifting operation.
Larger vessels are usually transported in the
horizontal position and extreme care should be
taken during the loading process if the rotation of
the vessel from vertical to horizontal plane uses
the tank base as a fulcrum, (see figure 4.2 below).
Figure 4.2
Loading A Vessel Using Base As Fulcrum
Large Vessels
Vessels of volume greater than 20m³ are normally
loaded using two cranes - in the following
example one crane is vehicle mounted and one
independent.
The independent crane uses the lifting beam
attached to the lifting lugs of the vessel. The
vehicle mounted crane is attached to the vessel
using a sling.
“Top and Tail” Vessel To Restrain Any Swinging Motion
Lift Clear Using Both Cranes
Do Not Drop The Vessel
4 - 4
INSTALLATION
Tank Instruction Manual
These vessels should be supported on felt or
carpet lined vessel support brackets arranged to
prevent deformation of the vessel during transport.
The following aspects should also be considered:-
i) Position of fittings on the vessel,
ii) Stability and shape of structure,
iii) Distribution of load,
iv) Other mechanical loading,
v) The mode of transport.
The vessel(s) shall be adequately secured to resist
horizontal and vertical movement during
transport.
The Use Of Wire Ropes Or Chains Is Prohibited !
Transportation
Once a thermoplastic vessel is correctly loaded
and secured the following guidelines should be
observed.
a) No vessel should be transported in
without prior consultation with Chem
Resist.
b) Shock loading of the vessel(s) due to
high speeds on poor road surfaces
must be avoided as stresses induced
by these actions can cause premature
failure of the vessel.
c) Attention must be paid to particular
requirements of modes of transport,
such as rail, as more stringent
packaging requirements may be
imposed.
d) Attention must be paid to particular
transport requirements of countries of
installation or countries of which the
vessel(s) pass through during
transportation, e.g. allowable vehicle
load widths.
A copy of these guidelines should be given to the driver of the particular transporting vehicle.
4 - 5
INSTALLATION
Tank Instruction Manual
Offloading
On arrival at the installation site it is
recommended that a representative of the client
carry out a short inspection of the vessel(s) prior
to offloading to ascertain any damage or
movement of the vessel(s) during transportation.
Any damage or signs of movement should be
reported to Chem Resist immediately.
The unloading sequence is the reverse of the
loading sequence and therefore all guidelines
observed in the loading of the vessel(s) also apply
in the offloading of the vessel(s).
Intermediate Storage
Vessel(s) should be stored in a vertical position, on flat level ground and secured to prevent wind damage.
Installation
Care should be taken to ensure all rainwater which has entered the vessel(s) during storage is completely drained prior to lifting the vessel(s).
The vessel(s) should be sited on a continuous flat surface, e.g. concrete plinth.
If the installation surface is rough or uneven, e.g. broken stone, then siting of the vessel(s) cannot take place.
4 - 6
INSTALLATION
Tank Instruction Manual
There should be no other material placed between the vessel(s) base and the installation surface, e.g. sand, as the gradual loss of this layer will cause uneven stressing of the tank base.
Pipe Work
Allowance must be made for expansion of the vessel(s) and connected pipes to reduce the stress build up in the pipe work.
Ensure that pipe work and vessel connections are aligned properly to avoid unnecessary strain on the connections.
All valves and pipe work running to and from the vessel(s) should be correctly supported.
Important Notes
DO USE THE PROPER
EQUIPMENT WHEN OFFLOADING
DO NOT ROLL VESSELS OFF THE
TRANSPORT VEHICLES
DO NOT LIFT VESSELS BY THEIR
FITTINGS
DO PROVIDE A SOLID FLAT
BASE TO SIT THE VESSELS UPON
All Bulk Storage Vessels Should Be
Bunded
If the vessel is fitted with a side manway, all bolts must be tightened to 95 Nm in case they came loose during transport.
A full hydrostatic test with water must be carried out after installation and all bolts should be re-tightened within 24 – 48h following the first fill.
.
5 - 7
BUND INSTALLATION
PROCEDURE Tank Instruction Manual
General
All bulk storage vessels should have a safety bund
in case of any leaks from the vessel. The two best
known methods to create a bund around the
storage vessel(s) are:
1. Protective Coated Concrete Bund
2. Thermoplastic Integral Bund
Concrete bunds are best used for large numbers of
vessels where the bund can be placed around all of
the vessels.
Thermoplastic integral bunds are ideal for small
numbers of vessels where the cost of a concrete
bund would be prohibitive.
Bund capacities MUST be 110% of the maximum
contents of the vessel. Of course where two or
more vessels are linked in a “balanced” fashion,
the bund volume will be 110% of the combined
maximum contents.
Chem Resist supplies a number of thermoplastic
integral bunds. Sizes are linked to the Chem
Resist range of thermoplastic storage vessels of
which they are designed to accompany.
The following are important points which should
be adhered to in order for the bund to be installed
safely and correctly.
Installation
The bund must be installed prior to storage vessel
installation.
The bund should be sited on a continuous flat surface, e.g. concrete plinth.
If the installation surface is rough or uneven, e.g. broken stone, then siting of the bund cannot take place.
There should be no other material placed between the bund base and the installation surface, e.g. sand, as gradual loss of this layer will cause uneven stressing of the bund base, (compounded by the weight of the vessel).
5 - 8
BUND INSTALLATION
PROCEDURE Tank Instruction Manual
When installing the vessel into the bund, the
Emergency Valve, (in between the vessel and
bund), must be removed.
Failure to remove the Emergency Valve may cause damage to the valve and / or fitting.
After the tank has been installed into the bund,
ensuring that the outlets are aligned properly, the
Emergency Valve can be fitted. Correct fitting of
the Emergency Valve is shown below.
Water Testing
The vessel and bund connection must be water
tested after installation in the bund by the
following method:
(a) Isolating the bund outlet valve, (optional),
(b) Opening the Emergency Valve,
(c) Filling the vessel to the maximum fill level,
(prior to overflow).
Failure to perform this Water Test may result in unnecessary and dangerous Chemical Spillages.
Bund Emptying
If the bund is situated external to any buildings,
then regular monitoring for fluid build up within
the bund must be performed.
This is due to the possible ingress of rainwater
into the bund, especially if the bund is not fitted
with the optional rain skirt.
If the bund is fitted with an optional rain skirt,
then, due to the skirt obscuring the view of the
bund internals, a high level liquid alarm must be
fitted.
Caution MUST be used when emptying the bund contents. As the purpose of the bund is for chemical retention should the vessel skin fail, the bund could contain leaked or condensed chemical and could therefore be dangerous. Correct Personal Protective Equipment MUST be considered when emptying bund.
TEST BUND CONTENTS PRIOR TO DISCHARGE !!
Before tightening flange bolts ensure that the
joining faces are flush and positioned closely to
Bund
Outlet
Valve Emergency
Valve
Bund
Outlet
Valve
Emergency
Valve
Tank Instruction Manual
8 - 1
Bolt Tightening Torque
the gasket. Pulling pipes towards a flange will
create tensile stress which may cause failure in the
long term.
The length of the bolts should be such that the bolt
protrudes past the nut by two or three turns.
A washer should be placed under the bolt head
and the nut
Bolts should be covered with Copper grease or
Molybdenum Sulphide to ensure that they can be
removed after years of service.
Ensure that the bolts are tightened evenly, check
that the distance between the backing rings is the
same at each bolt.
The gasket material must be chemically
compatible with material stored or pumped.
We recommend using gasket materials with a
Shore A hardness of 70. Harder materials are
commonly used in steel piping and require
considerably higher tightening torque to ensure a
proper seals. The use of such gasket materials in
thermoplastic flanges is not recommended as this
may lead to deformation of the flange.
Nominal Diameter
Number of Bolts x Thread Diameter
Recommended Bolt Tightening Torque
Flat Gasket, 40 °C Profile Gasket, 16
bar max. O-ring, 16 bar
max.
15 4 x M12 10 Nm @ 10 bar 10 Nm 10 Nm
20 4 x M12 10 Nm @ 10 bar 10 Nm 10 Nm
25 4 x M12 15 Nm @ 10 bar 10 Nm 10 Nm
32 4 x M16 20 Nm @ 10 bar 15 Nm 15 Nm
40 4 x M16 25 Nm @ 10 bar 15 Nm 15 Nm
50 4 x M16 35 Nm @ 10 bar 20 Nm 20 Nm
65 4 x M16 50 Nm @ 10 bar 25 Nm 25 Nm
80 8 x M16 30 Nm @ 10 bar 15 Nm 15 Nm
100 8 x M16 35 Nm @ 10 bar 20 Nm 20 Nm
125 8 x M16 45 Nm @ 10 bar 25 Nm 25 Nm
150 8 x M20 60 Nm @ 10 bar 35 Nm 30 Nm
200 8 x M20 70 Nm @ 6 bar 45 Nm 35 Nm
250 12 x M20 65 Nm @ 6 bar 35 Nm 30 Nm
300 12 x M20 90 Nm @ 6 bar 50 Nm 40 Nm
350 16 x M20 90 Nm @ 6bar 40 Nm N/A
400 14 x M24 100 Nm @ 6bar 60 Nm N/A
Tank Instruction Manual
8 - 2
Bolt Tightening Torque
600 mm Tank Side Manway
28 x M12 90 Nm N/A N/A
900 mm Tank Side Manway
30 x M24 90 Nm N/A N/A
Bolt-on item without backing ring, for example
top manways and scrubber inspection ports
require considerably less torque. They should be
tightened comfortably with a spanner (hand tight).
Over tightening will deform the cover and cause
leakage.
Tank Instruction Manual
9 - 1
Tank Anchoring
All Chem Resist Vessel must be anchored using
the anchor and spacer plates provided. The
anchors should be evenly spaced around the tank
The anchor bolt PCD should be selected so that
the anchor and spacer plates have 5 mm gap
between respectively the tank weld and the tank
base, please see drawing below.
The gaps allow for the thermal expansion of the
tank without ‘hitting’ the plates which would
cause stress points.
Bolts should be hand tight, secure, without
compressing the tank base.
Bolt holes should be at least 5 diameters away
from an unsupported edge, for example the edge
of a plinth.
Bolts must be anchored with suitable plugs or
chemical anchors.
For further information on positioning the bolts
and the required depth of holes consult the
technical manual provided by the bolt or plug
manufacturer or stockist.
If it is not possible to anchor the tank, for example
during temporary storage, the tank should be filled
with water to at least 1 m fill height. This is to
prevent deforming the base during pressure uplift
of the barrel.