Has Large-Scale Solar got its Sums right? EPC Perspective Vikas Bansal Head of International Business Development

Has Large-Scale Solar got its Sums right?...Project Development Longer Development Cycle means more Cost Insurance Africa/SE Asia/Argentina has High Cost of Insurance ( MIGA,CAR) OPEX

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Has Large-Scale Solar got its Sums right?...Project Development Longer Development Cycle means more Cost Insurance Africa/SE Asia/Argentina has High Cost of Insurance ( MIGA,CAR) OPEX

Has Large-Scale Solar got its Sums right?

EPC Perspective

Vikas Bansal

Head of International Business Development

Page 2: Has Large-Scale Solar got its Sums right?...Project Development Longer Development Cycle means more Cost Insurance Africa/SE Asia/Argentina has High Cost of Insurance ( MIGA,CAR) OPEX

DRIVERS: LEVELIZED COST OF ELECTRICITY

Other CAPEX

Project Development Longer Development Cycle means more Cost

Insurance Africa/SE Asia/Argentina has High Cost of Insurance ( MIGA,CAR)

OPEX Remote locations have higher cost of SLAs

due to low installation base

Generation Higher Module Efficiency

1500 V Technology

Bi Facial Modules

Automated Cleaning Technologies

EPC CAPEX PV Module: Recent increase in Prices

Tracker: Higher Steel Cost in 2017

Local Cost (Civil, Installation): Low in Middle East,

India, Mexico, could be 2X in Africa , Argentina or Bangladesh

Transportations: Extremely high in Africa

Construction Period Interest During Construction

Africa/SE Asia/Australia have longer construction Period

Borrowing Rate Higher for Africa, Parts of Asia

DFIs are usually more expensive

2017 VS 2016 2018 VS 2017

Levelized Cost of Electricity

Page 3: Has Large-Scale Solar got its Sums right?...Project Development Longer Development Cycle means more Cost Insurance Africa/SE Asia/Argentina has High Cost of Insurance ( MIGA,CAR) OPEX

TARIFF TREND, EXPECTATION GAP: IPP, LENDER AND EPC

TARIFF (USD/MW-Hr)

0

10

20

30

40

50

60

70

80

90

2015 2016 2017

IPP/DEVELOPER

• Aggressive assumptions on business

model: Technology, Construction

Timelines, Design Life, Capex (Module

Price), Opex and Contingencies

• Abundant Capital: Deployment

Pressure

• Medium term perspective: More Capex

Driven

LENDER

• Zero risk on Technology and

Construction: Transfer all risk to EPC

• Long term perspective (Loan

Tenure): Life Time Cost Driver

Balancing Act: EPC

• Immense Pressure to justify Business Model

assumptions of IPP

• Meet Lenders expectations to keep Life Time

cost low

• Difficult to maintain balance between profits

and liabilities

Page 4: Has Large-Scale Solar got its Sums right?...Project Development Longer Development Cycle means more Cost Insurance Africa/SE Asia/Argentina has High Cost of Insurance ( MIGA,CAR) OPEX