Upload
celine
View
46
Download
0
Embed Size (px)
DESCRIPTION
Hardware Commissioning. The talk is focussed on the superconducting electrical circuits . While we are aware it is not the only equipment that needs to be commissioned, the HC WG believes it will dominate the scene. - PowerPoint PPT Presentation
Citation preview
Roberto Sabanon behalf of the Hardware Commissioning Working Group
Chamonix XIV 050119
Hardware CommissioningHardware Commissioning
the resourcesthe programme for 2005
The talk is focussed on the superconducting electrical circuits. While we are aware it is not the only equipment that needs to be commissioned, the HC WG believes it will dominate the scene.The commissioning of almost all the other machine subsystems has been studied but an overall commissioning programme has not been prepared yet: it strongly depends on the installation schedule which has lately been very uncertain.
Chamonix XIV 050119 R.Saban/TS
0
12
24
36
48
J an 03 Apr 03 J ul 03 Oct 03 Feb 04 May 04 Aug 04 Dec 04 Mar 05 J un 05 Sep 05 J an 06 Apr 06 J ul 06 Nov 06 Feb 07 May 07 Aug 07
[mon
ths]
why we started getting worried ...why we started getting worried ...
Dec 2003
July 2004Dec 2004
Mar 2003
establish a commissioning programme
define team compositionsdefine team numbersdefine the commissioning times
with a number of boundary conditions
Time allocated for Hardware Commissioning
if the boundary conditions change, we now can predict the impact on the three
Chamonix XIV 050119 R.Saban/TS
Resources for Hardware CommissioningResources for Hardware Commissioning
basic assumptions programme of the tests
sequencesequence of the tests time neededtime needed for each
test inventory of the test test
teamsteams and their compositioncomposition
… This document presents the resources identified for a commissioning scenario restricted by a number of assumptions: in particular, the parallel commissioning of two sectors around an even point -not more and not less- and the staggered commissioning of an additional set of two sectors where the cool down follows the powering tests of the first set.However from the data presented in this document, it is possible to derive the resources needed for a different scenario when some of the restrictions are lifted or relaxed.
Chamonix XIV 050119 R.Saban/TS
Resources for Hardware CommissioningResources for Hardware Commissioning
basic assumptions programme of the tests
sequencesequence of the tests time neededtime needed for each
test inventory of the test test
teamsteams and their compositioncomposition
1. Two sectors at a time around an even point
2. Five-day working weeks3. Two shifts during powering tests4. Two commissioning fronts per
sector5. The magnets are left floating in
temperature after the commissioning
6. The RF system is commissioned just before commissioning with beam
7. The PS and SPS complex run in 2006
Chamonix XIV 050119 R.Saban/TS
basic assumptions programme of the tests
sequencesequence of the tests time neededtime needed for each
test inventory of the test test
teamsteams and their compositioncomposition
1. Tests at warm validation of subsystems,
connectivity, computer networks and filed buses, timing, supervision, etc.
validation of the instrumentation and subsystem functional tests
electrical quality assurance short circuit tests, interlocks
2. Cool down calibration at cold and cryo loop
tuning electrical quality assurance
3. Tests at cold electrical quality assurance quench protection
4. Powering Tests validation of the interlocks validation at low, nominal current
and all circuits in unison
Resources for Hardware CommissioningResources for Hardware Commissioning
Chamonix XIV 050119 R.Saban/TS
The resulting scheduleThe resulting schedule
right of the even point
left of the even point
Chamonix XIV 050119 R.Saban/TS
a closer look ...a closer look ...
warm tests 23 weeks
cool down 8 weeks
powering tests 11-16 weeks
tests at cold
Chamonix XIV 050119 R.Saban/TS
Interlock tests of a powering subsector prior and after connection of the power cables to the DFB leads
Pow
er
Convert
ers
co
nnect
ed
to
Magnets
Pow
er
Convert
ers
co
nnect
ed
to
Magnets
Pow
er
Convert
ers
not
conn
ect
ed
to
Magnets
Pow
er
Convert
ers
not
conn
ect
ed
to
Magnets
300 K
1.9 K
90 K
Test of power converters connected to the DC cables in short circuit, including controls for powering, ramp, monitoring
connexion of power cablesto the current leads
Electrical Quality Assurance
superconducting electrical circuitssuperconducting electrical circuits
Individual System Tests of the Quench Protection and Energy Extraction Systems
Post-Mortem System tests
Commissioning of the electrical circuits one by one or in groups at low, intermediate and nominal currents
Commissioning of all the electrical circuits of the sector powered in unison to nominal current with nominal ramp rates
Individual System Tests of Powering Interlock Control
Powering Tests
Chamonix XIV 050119 R.Saban/TS
circuit count and individual commissioning timescircuit count and individual commissioning times
Main circuits and IT quadrupolesSeparately powered quadrupoles600 A circuits, separation and recombination dipoles80-120 A orbit correctors, IT correctorsTotal
4078
436274828
Num
ber
of
circ
uit
s
Quench
Pro
tect
ion
6078
1310
269
Inte
rlock
test
s
4039
21869
366
Pow
eri
ng t
est
s
120181616
170
22013536585
805
Tota
l
unit is one 15 hour day of one commissioning front
MBMQ, MQXSeparately powered quadrupoles600 A circuits, separation and recombination dipoles80-120 A orbit correctors, IT correctors
11.05.51.70.80.3
Powering Tests
Chamonix XIV 050119 R.Saban/TS
resources deployed for the powering testsresources deployed for the powering tests
Powering Tests
Front 1Front 2 Front 1 Front 2
Left Right
6.6 km
in the field on call2t + 2o 1e+1o cryogenics operation1e+1t cryogenics
instrumentation1x+2e+2t quench protection2x+2t 1x+1t+ ... machine interlocks1x+2t 2e+1t+ ... power converters2e+2t coordination1t 1e controls1o operation
4x+5e+10t+3o 1x+4e+2t+1o
o operatorx experte engineert technician
22 present in the field
Front 1 arc and the matching section on the even side
Front 2 arc, the matching section on the odd side and the inner triplets on both sides
two shifts = 15 hour days
Chamonix XIV 050119 R.Saban/TS
the sequence of tests around an even pointthe sequence of tests around an even point
Powering Tests
Chamonix XIV 050119 R.Saban/TS
power tests of MB circuit power tests of MB circuit 1 of 21 of 2
1. to commission the protection functionalities of the powering interlock controllers and all its connected systems with current through the circuits
2. to verify the compatibility of the switch-on and switch-off processes of the converters with the sensitivity of the protection systems
1. to set up the power converter current loops2. to validate the protection mechanisms under real powering
conditions and with limited energy stored in the circuits3. to validate quench-related procedures, e.g. cryogenic recovery
procedures4. to validate the sensitivity and compatibility during ramps of the
systems susceptible to noise pick-up, couplings, etc5. to perform a last check on the polarities of the circuits by verifying
voltages across current leads during ramp at low current using QPS signals
Powering Tests
HCA:PIC2
HCA:PLI1
33% nominal 66% nominal80% nominal nominalinjectionstandby
HCA:PLI2HCA:PLI3HCA:PLI4
LHC-D-HCP-0003
Chamonix XIV 050119 R.Saban/TS
power tests of MB circuit power tests of MB circuit 2 of 22 of 2
1. to verify the power converters during the ramp2. to calibrate the DCCTs for the main and the Inner Triplet power
converters and to verify the calibration systems3. to validate the protection mechanisms with nominal energy in the
circuits4. to verify the quench current of each circuit5. to validate quench-related procedures, e.g. cryogenic recovery
procedures
1. to verify the tracking of the circuits2. to verify thermal performance of the ventilation and water cooling
systems in underground areas3. to carry-out a 24-h reliability run in order to detect premature
failures due to wrong settings or possible assembly errors
33% nominal 66% nominal80% nominal nominalinjectionminumumstandy-by
HCA:PNO
HCA:PAC
Powering TestsLHC-D-HCP-0003
Chamonix XIV 050119 R.Saban/TS
essential time saversessential time savers
support from the controls group user friendly application suite tool to aid the interpretation of
the test results programmed procedures for
battery tests support from the MTF and
database team optimization of the MTF
configuration for hardware commissioning
exchange of data between the central database and the specialist owned databases
Chamonix XIV 050119 R.Saban/TS
Resources for Hardware CommissioningResources for Hardware Commissioning
basic assumptions programme of the tests
sequencesequence of the tests time neededtime needed for each
test inventory of the test test
teamsteams and their compositioncomposition
… This document presents the resources identified for a commissioning scenario restricted by a number of assumptions: in particular, the parallel commissioning of two sectors around an even point -not more and not less- and the staggered commissioning of an additional set of two sectors where the cool down follows the powering tests of the first set.However from the data presented in this document, it is possible to derive the resources needed for a different scenario when some of the restrictions are lifted or relaxed.
Chamonix XIV 050119 R.Saban/TS
Missing Possible Source
Cryogenic Instrumentation & Process Control
Technical Engineer 8 Staff, NI
Engineer 2 Staff, NI
Database Expert 1 Staff
Quench Protection
Technician 7 Staff, NI
Engineer 5 Staff, NI
Machine Interlocks
Technician 5 Staff, NI
Electrical Engineering (Power Converters)
Technician 3 Staff
Engineer 2 Staff
Commissioning Coordination
Technician 6 Staff
Engineer 4 Staff, NI
Controls
Technician 1 Staff
Engineer 2 Staff, NI, IS
The personnel involved in the individual system tests and the hardware commissioning 142142 of which 4646 are missingare missing.
Additional budget for IS and FSU is 1.335 1.335 MCHFMCHF.
The resulting need for resourcesThe resulting need for resources
with the basic assumption
Chamonix XIV 050119 R.Saban/TS
Report SummaryReport Summary
~20 months 142 people involved 46 missing in some cases experience
is a mustmust engineers and technicians
cryogenics quench protection interlocks coordination & operation controls
possible sources national institutes but also recruitment
staff for supervision is staff for supervision is already criticalalready critical
training of new resources training of new resources for commissioning is for commissioning is criticalcritical
with the basic assumption
Chamonix XIV 050119 R.Saban/TS
Report Summary : ParallelismReport Summary : Parallelism 1 of 31 of 3
powering testscool down
warm tests
powering testscool down
warm tests
powering testscool down
warm tests
powering testscool down
warm tests
28 months
with the basic assumption
Chamonix XIV 050119 R.Saban/TS
15.5 months
powering testscool down
warm tests
powering testscool down
powering testscool down
warm tests
powering testscool down
warm tests
warm testsOverload of Overload of CIWSU, CIWC, CIWSU, CIWC, CIWCS, CIWS, MI-CIWCS, CIWS, MI-PCIST, PCIST, PCIST, PCIST, COCD, HCC, COCD, HCC, ABOPABOP
20 months
powering testscool down
warm tests
powering testscool down
powering testscool down
warm tests
powering testscool down
warm tests
warm tests
Overload of only Overload of only the Operator, HC the Operator, HC Coordination and Coordination and Cryo Operation Cryo Operation TeamsTeams
2.5 months
Report Summary : ParallelismReport Summary : Parallelism 2 of 32 of 3
Chamonix XIV 050119 R.Saban/TS
Report Summary : ParallelismReport Summary : Parallelism 3 of 33 of 3
CIW
SU
CIW
CS
CIW
SM
I-PC
IST
PC
IST
CO
CD
HC
CA
BO
P
20 months for thecommissioning activity
CIW
SU
CIW
CS
CIW
SM
I-PC
IST
PC
IST
CO
CD
HC
CA
BO
P
12 months for thecommissioning activity
142 people (46 missing)
?
• where do we find them?• how long do we have to train them?• who is going to supervise them?
Chamonix XIV 050119 R.Saban/TS
what do we do with the Report ?what do we do with the Report ?
find the additional resourcesresources study alternatives
strategies alternative to personnel strategies alternative to personnel directly under the supervision of directly under the supervision of the Groupsthe Groups
partial commissioning of the partial commissioning of the sectorssectors
review the commissioning review the commissioning proceduresprocedures
Chamonix XIV 050119 R.Saban/TS
programme for 2005: the latest schedule ...programme for 2005: the latest schedule ...
Sylvain Weisz on November 26, 2004 at TCC
a lot is happening before ...
installationcabling
IST
Chamonix XIV 050119 R.Saban/TS
programme for 2005: installation sequence for Sector 78programme for 2005: installation sequence for Sector 78
Point 8
Point 7
1 install QRL subsectors A and B in sector 78 with a return module
2 leak and pressure test the QRL subsectors A and B in sector 78 with the return module
3 cold test the QRL subsectors without any magnet connected to it and warm it up
4 install the Q1Q2Q3D1, Q4D2 and the Q5 machine subsectors and connect them to the QRL subsectors A and B
in parallel, install and interconnect the rest of the QRL in the sector
in parallel, start the interconnection of all the magnets without jumper connection in the DS region L8 and first two arc cells
5 leak and pressure test the QRL and the Q1Q2Q3D1, Q4D2 and the Q5 machine subsectors
6 cold test the QRL and the Q1Q2Q3D1, Q4D2 and the Q5 machine subsectors
7 power test the Q1Q2Q3D1, Q4D2 and the Q5 machine subsectors
in parallel, interconnect all the magnets without jumper connection
8 warm up the QRL and the Q1Q2Q3D1, Q4D2 and the Q5 machine subsectors
9 install and interconnect all the SSSs with jumper
10 leak and pressure test
11 open cryostat interconnect and final closure
Chamonix XIV 050119 R.Saban/TS
programme for 2005: the equipment concernedprogramme for 2005: the equipment concerned
Part of the Matching Section L8 with a Separation Dipole
Inner Triplet L8 with a Separation Dipole
Chamonix XIV 050119 R.Saban/TS
key dateskey dates
QRL subsector A & B cold test LSS L8 short circuit tests LSS L8 subsector cool down
partly in parallel with QRL whole sector test
power tests of LSS subsector partly in parallel with QRL whole
sector test power tests of LSS subsector
must end by
13 June 2005
3 October 2005
31 October 2005
3 March 2006
30 June 2005
Chamonix XIV 050119 R.Saban/TS
the sector test in ... 2006the sector test in ... 2006
Chamonix XIV 050119 R.Saban/TS
... in summary : ... in summary : Effects of the compressed Schedule on the Hardware Commissioning
the situation with the resources for hardware commissioning is worrying it cannot cope with continued reduction of the time available
it is undeniable that additional resources are needed
additional resources must be trained in advance
in some cases, additional resources cannot be integrated because of lack of supervisors
the programme, the scenario, the documentation, the tools and the infrastructure are well in hand
the readiness will be assessed by a review the complete picture will emerge only after a close-to-
final installation schedule becomes available 2005 is certainly a crucial year: with the commissioning
of the first machine subsectors left of Point 8, it could give an indication on how wrong the figures are
Chamonix XIV 050119 R.Saban/TS