Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

Embed Size (px)

Citation preview

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    1/87

    School of Engineering, University of 

    E

    A Feasibility S

    Micro-Hy

    Warwick

    S327 Project Report

    tudy on the Implementa

    ro Scheme in Sioma, Za

    0602641

    ion of a

    bia

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    2/87

    School of Engineering, University of Warwick 0602641

    Author’s Self Assessment

    The following project report details the micro-hydropower concept, principles and finally its

    application to the case of Sioma, Zambia. In order to achieve this, both primary and

    secondary data has been collected and analysed. The analysis of this data has led to

    decisions involving the design, and improvements to it, as well as the selection of location. It

    is the author’s intention that the Sioma micro-hydro project will be developed into a pilot

    scheme for developing communities and consequentially will form the basis of future

    engineering contribution. If the ancient techniques of micro-hydro schemes are reworked

    and improved, important improvements within the engineering field are implicit and

    infrastructure development is continuously emphasized.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    3/87

    School of Engineering, University of Warwick 0602641

    Summary

    In light of this project, the application of micro-hydropower appears ideal for rural

    communities, particularly in the developing world. The provision of electricity is a vital step

    in developing infrastructure which, in turn, entails vast improvement to quality of life,

    competitiveness of local businesses and learning opportunities. The first section of the

    project consists of a literature review on the micro-hydro area, which is subsequently used

    for analysis and application to the Sioma site, found in Section III, titled “Feasibility Study”.

    The Sioma Falls were determined to be the most viable location for a potential site, with a

    head of approx. 10 metres. The flow of water in the Zambezi is adequately high year round

    so that the theoretical limit of power production does not limit the proposed project. A

    flow of 0.587 m3/s in the penstock is necessary to develop the 46.1 kW of power that was

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    4/87

    School of Engineering, University of Warwick 0602641

    Table of Contents

    Author’s Self Assessment...........................................................................................................2

    Summary ....................................................................................................................................3

    List of Tables and Illustrations ...................................................................................................6

    Section I - General......................................................................................................................7

    1.1 Introduction.................................................................................................................7

    1.2 Final Project Specification ...........................................................................................8

    1.3 Research Methodology ....................................................................................................9

    Section II - Literature Review...................................................................................................10

    2.1 Hydropower Generation: ...............................................................................................10

    2.2 Micro-Hydro and Rural Development............................................................................12

    2.3 Technical aspects............................................................................................................13

    2.4 Turbines..........................................................................................................................15

    2.5 Coupling..........................................................................................................................19

    2.6 Generators and Control .................................................................................................21

    2 7 Ci il k 23

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    5/87

    School of Engineering, University of Warwick 0602641

    3.3 The potential contribution to the local community.......................................................56

    3.4 Financial viability............................................................................................................593.5 Ownership ......................................................................................................................61

    3.6 Meeting with ZEEC .........................................................................................................63

    Section IV – Conclusions and Recommendations....................................................................64

    4.1 Conclusions.....................................................................................................................64

    4.2 Costing of Project ...........................................................................................................654.3 Recommendations .........................................................................................................66

    Glossary of Definitions .............................................................................................................67

    References/Bibliography..........................................................................................................68

    Appendix A...............................................................................................................................70

    Appendix B ...............................................................................................................................71

    Appendix C ...............................................................................................................................72

    Appendix D...............................................................................................................................73

    Appendix E ...............................................................................................................................74

    Appendix F ...............................................................................................................................75

    Appendix G...............................................................................................................................76

    Appendix H...............................................................................................................................77

    Appendix I ................................................................................................................................81

    Appendix J ................................................................................................................................85

    A di K 86

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    6/87

    School of Engineering, University of Warwick 0602641

    List of Tables and Illustrations

    Figure 1- Worldwide technical hydropower potential versus economically feasible and present

    situation

    Figure 2 – Run of the river micro-hydro scheme typical layout

    Figure 3 – Turbine Classification Chart

    Figure 4 – Turbine Selection Chart

    Figure 5 - Francis Turbine

    Figure 6 - Tube type propeller turbine

    Figure 7 – Pelton Wheel

    Figure 8 – Turgo Turbine

    Figure 9 – Crossflow Turbine

    Figure 10 – Diagram of incorporation of Electronic Load Controller into generating system

    Figure 11 – Dam used to create water reserve for micro-hydro scheme

    Figure 11 – Sioma Falls

    Figure 12 – Intake and weir at Tungu-Kabri project

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    7/87

    School of Engineering, University of Warwick 0602641

    Section I - General

    1.1 Introduction

    Many rural communities in developing countries suffer the same symptoms; a never-ending

    cycle of poverty and lack of basic necessities. For many decades large aid organisations have

    focused on emergency relief without assessing the causes; simply fire fighting incessant

    difficulties. It is the author’s belief that rural infrastructure development is a solution to

    these underpinning problems, and that, with the development of roads, safe water supplies

    and electricity, communities can overcome the barriers to living long, safe and healthy lives.

    Sioma, in South Western Zambia, is such a community. Its population is approximately 1500

    of which about 50% HIV positive. Despite a main power cable passing just a few kilometres

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    8/87

    School of Engineering, University of Warwick 0602641

    1.2 Final Project Specification

    The project specifications at the point of starting in October 2008 included the following

    objectives:

      Research possibility and prove viability of hydroelectric scheme in Sioma, Zambia

      Produce a proposal for such a scheme

      Network with engineering charities for support

      Put plan into action (outside academic boundaries)

    These were realistic objectives that were achieved to different degrees. The project initially

    t t d ith lit t i h l t i f th i h d fi ld

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    9/87

    School of Engineering, University of Warwick 0602641

    Additional completed objectives are:

      Apply for letter of support from local government

      Complete initial technical analysis, calculations and design

    1.3 Research Methodology

    The following project has been approached primarily by literature research. Focusing firstly

    on gaining a wide and comprehensive understanding of the chosen subject area, a literature

    review was completed. The literature review included the reading of a range of textbooks

    along with credible internet sources and journals. Relevant aspects of these sources were

    th d t f l t t hi h th d i th i l t ti f th t

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    10/87

    School of Engineering, University of Warwick 0602641

    Section II - Literature Review

    The literature review is a comprehensive summary of the material covered through the

    project research. It should give a good insight into the development of micro-hydro sites

    in general and provide a sufficient foundation for the following analysis in the feasibility

    study.

    2.1 Hydropower Generation:

    Close to a quarter of the energy of the sun that reaches the earth’s surface causes water to

    evaporate and hence a proportion of this energy causes vapour to rise against the earth’s

    gravitational pull. This vapour then condenses into rain and snow, which again falls back to

    h h’ f Thi i ll d h l d i h f d l h

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    11/87

    School of Engineering, University of Warwick 0602641

    Figure 1- Worldwide technical hydropower potential versus economically feasible and present situation [4]

    The potential for hydropower expansion is still enormous; the U.S Geological Survey

    estimates that 2/3 of the world’s hydropower resources remain untapped. [5] The main

    advantages of investing into further hydropower development are summarized below:

    N f l b i i i l ll i

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    12/87

    School of Engineering, University of Warwick 0602641

    2.2 Micro-Hydro and Rural Development

    Access to electricity is one of the key recipes for rural development and a necessity for the

    improvement of infrastructure. An estimated 1.5 billion people in developing countries do

    not have access to electricity [6], severely limiting the possibilities of economic growth. An

    increased focus on decentralized energy generation, where the state cannot viably connect

    population centres to the main electricity grid, significantly improves the development

    prospects of struggling communities. Micro-hydro provides a reliable, affordable,

    economically viable, socially acceptable and environmentally sound energy alternative for

    rural development.

    Micro-hydro is the small scale harnessing of energy from falling water, generating typically

    less than 100 KW [7] and powering small communities or factories. It is micro-hydro the

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    13/87

    School of Engineering, University of 

    2.3 Technical aspects

    A brief technical review of 

    technology numerous textbo

    Micro-hydro schemes gener

    scheme where no water stor

    into a canal before being “dr

    Warwick

    ydropower is provided below. Due to t

    ks are available with more detailed technic

    lly follow the layout shown in Figure 2 –

    ge is required. Instead water is deflected f 

    pped” from the forebay tank to the turbine.

    0602641

    e maturity of the

    l analysis.

    a run of the river

    rom a flowing river

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    14/87

    School of Engineering, University of 

    Where PE  = potential energy

    (9.81m/s2) and Hav  = availabl

    (ii) The  power  availa

    product of the ava

    Where P = Power (W), η = eff 

    due to gravity (9.81m/s2), Q =

    Warwick

    (Joules), m = mass of water (kg), g = acceler

    head (m).

    le at a hydropower station will always be

    ilable head and the volume flow rate of the

    iciency of system, ρ = density of water (kg/m

    volumetric flow rate (m3/s) and Hav  = availa

    0602641

    tion due to gravity

    roportional to the

    site:

    3), g = acceleration

    ble head (m)

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    15/87

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    16/87

    School of Engineering, University of Warwick 0602641

    Figure 4 – Turbine Selection Chart [10]

      Reaction Turbines

    Reaction turbines run with a casing completely filled with water, exploiting the oncoming

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    17/87

    School of Engineering, University of 

    The Francis turbine is, in effe

    water is made to enter the tu

    reaction turbines are more c

    and case profiling. This mak

    their superior performance a

      Impulse Turbines

    Impulse turbines are the mor

     jet strikes directly on the tur

    rotational motion (and henc

    energy.

    The most common impulse

    Warwick

    ct, a more complicated version of the prop

    rbine radially and discharge axially. In term

    hallenging to fabricate due to the use of m

    es them less attractive for micro-hydro use

    low-head sites, they are nonetheless increa

    e traditional alternative of turbines, where

    ine blade or bucket surfaces. This pressuri

    e mechanical energy) which can be conve

    turbine is the  Pelton wheel   (figure 7), whi

    0602641

    ller turbine where

    of manufacturing,

    ore intricate blade

    . However, due to

    singly popular. [9]

    pressurized water

    ed jet then caused

    rted into electrical

    ch is fitted with a

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    18/87

    School of Engineering, University of 

    The Turgo turbine (figure 8) i

    strikes the runner at an angle

    not limited by discharge buil

    have a smaller diameter turbi

    Image source: “Small hy

    The Crossflow turbine   (fig

    ff

    Warwick

    s simply a more advanced version of the Pel

    to aid discharge. This ensures that the rota

    up and interference. This also means that

    ne than a Pelton for the same power output

    Figure 8 – Turgo Turbine

    dro power: technology and current status”, Oliver Paish, Elsevier S

    ure 9) is similar to the Pelton and T

    f

    0602641

    ton. The water jet

    ion of the wheel is

    Turgo turbines can

    .

    cience Ltd, 2002

    rgo turbines but

    f

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    19/87

    School of Engineering, University of Warwick 0602641

    2.5 Coupling

    Coupling between the turbine and the generator (or other machinery) is a vital part of any

    micro-hydro system. In the optimal case the turbine and generator are selected to rotate at

    the same speed. If this is achieved, then the need for gearing is eliminated and hence the

    amount of parts that may need maintenance/replacing are minimised. This is the case with

    all large scale hydropower schemes, where careful design of each turbine is necessary.

    However, in many micro-hydro schemes cost may limit this optimisation. So there are two

    main streams of coupling for micro-hydro schemes:

      Direct Coupling

    As stated earlier, this is achievable when the turbine and generator operate at the same

    speed and the set up can be laid out so that their shafts are co-linear. [11] This means that

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    20/87

    School of Engineering, University of Warwick 0602641

    Belts are more elastic than chain drives or gears and so one of their main advantages is that

    they can absorb shock by sudden changes in loads or other factors well. In addition, if one

    component should lock up, slippage of flat belts will prevent damage to the more expensive

    equipment. [11]

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    21/87

    School of Engineering, University of Warwick 0602641

    2.6 Generators and Control

    Generators transform the mechanical energy produced by the water hitting the turbine into

    electrical energy. Early hydroelectric systems made use of Direct Current generation to

    match the requirements of early electrical equipment; however, modern schemes make

    almost exclusive use of three phase alternating current generators. [10] There are two main

    groups of generators:

      Synchronous Generators:

    Excitation with synchronous generators is not grid dependent and so can run in isolated

    locations. The generator operates at a speed directly linked to frequency when not

    connected to the grid, but speed variation is not possible when it is connected to a grid. In

    the case of off-grid use, the voltage controller maintains a predefined constant voltage

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    22/87

    School of Engineering, University of Warwick 0602641

    overloading or over-speeding. Electronic Load Controllers (ELCs) have been developed over

    the past two decades to provide reliable regulation of output power in a micro-hydro

    system. They control the amount of load by automatically varying the amount of power

    dissipated in a resistive load, often known as the dump load. This keeps the load on the

    generator and turbine constant by constantly sensing and controlling the generated

    frequency. [12]

    ELCs contain no moving parts, and are therefore virtually maintenance free. They also

    eliminate the need for expensive hydraulics governors.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    23/87

    School of Engineering, University of Warwick 0602641

    2.7 Civil works

    The main civil works required for a complete micro-hydro scheme are demonstrated by

    Figure 2, shown in the general hydropower discussion. In addition various other

    components may be required, such as spillways, gates etc. However, a designer must be

    very careful when planning a scheme not to include unnecessary components leading to

    excessive and avoidable costs. It must, nonetheless, be ensured that all necessary

    components are included in the design to avoid the malfunctioning of the scheme. Below is

    an overview of the main components and their uses in micro-hydro schemes:

      Dam

    In most large scale hydropower developments dams are thought of as inherent aspects of 

    construction. A dam’s function is to either increase available head (for example when

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    24/87

    School of Engineering, University of Warwick 0602641

    Figure 11 – Dam used to create water reserve for micro-hydro scheme [27]

      Diverting Flow

    In order to ensure adequate flow to the intake for power generation, a weir may be

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    25/87

    School of Engineering, University of Warwick 0602641

      Intake

    The intake is the link between the river and the conduit to the powerhouse. Its role is vital

    in the overall functioning and reliability of the scheme. It is used to control both the quality

    and the quantity of water and must be equipped to deal with extremes in terms of water

    flow.

    In order to prevent debris and sediment carried by the incoming water several objects can

    be incorporated with the intake, such as trashracks, skimmers or a settling basin.

    Water flow control under all conditions is also a necessity. Gates can be used to perform

    this task, along with spillways as backups to release overflow back into the stream. If the

    water flow is not controlled at the intake, the power conduit may overflow at unexpected

    points causing severe erosion and damaging the scheme.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    26/87

    School of Engineering, University of Warwick 0602641

    work will be required at the site. The location along the stream determines the amount of 

    sediment and trash accumulation an intake will see as well as the erosion it will suffer.

    When locating the intake there are four key factors to be considered:

      The streambed

      Bends along the stream

      Natural features of the stream

      Ease of access

    The susceptibility of the streambed to erosion is a key factor when determining the

    elevation of the canal intake. Normally this is done at the time of construction, and hence,

    it is important to bear the nature of the streambed in mind throughout this process. If the

    streambed is particularly susceptible to erosion the intake may eventually reach a point

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    27/87

    School of Engineering, University of Warwick 0602641

    Natural features of the stream can be used to our advantage wherever possible. Features

    such as large boulders have been used in the past to effectively restrict flood flows. Natural

    features can also limit the need for construction, and so, when on site, it is advantageous to

    analyze all potential sites for construction.

    Ease of access is essential in all stages of the scheme. During construction, supplies need to

    be transported easily along the site. During heavy flows it is particularly important to have

    safe and easy access since this is when repairs are most likely to be needed. Trashracks and

    debris must be clearable at all times.

      Power Conduit

    The power conduit’s purpose is to transport water from the intake to the penstock inlet

    with minimum head loss at a minimum cost. In most cases this means that a canal will be

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    28/87

    School of Engineering, University of Warwick 0602641

    Figure 13 – Power conduit in Tungu-Kabri project [28]

      Forebay

    The Forebay tank is the connection between the power conduit and the penstock, serving

    mainly to allow particles to settle down before the water enters the penstock. It can also be

    used as storage for water in the case of increased power consumption at peak times of the

    day, for example. A trashrack is normally installed at the penstock inlet to prevent floating

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    29/87

    School of Engineering, University of Warwick 0602641

    Figure 14 - Penstock at Bamerchara Lake, Bangladesh [29]

      Powerhouse

    The powerhouse is meant to protect the turbine, generator and other electrical and

    mechanical equipment. In the case of micro-hydro, it should be kept to a minimum size in

    order to minimise costs. However, sufficient space must be kept to allow for repairs and

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    30/87

    School of Engineering, University of Warwick 0602641

    2.8 Other micro hydro schemes in Zambia

      NWZDT - Zambezi Rapids Hydro-Electric Scheme [13]

    The Zambezi Rapids Hydro-Electric Scheme was completed in July 2007 after three years of 

    work in the North Western Province of Zambia. This was achieved by NWZDT (North West

    Zambian Development Trust), a charity set up by a group of people connected to the area

    and the Kalene Mission Hospital. The charity’s philosophy is that while many individual

    crises can be solved by food and medicine, real progress comes through the development of 

    infrastructure.

    A sustainable electricity source was seen as a priority to trigger the other aspects of 

    infrastructure, and so the scheme was completed. It is a 700 KW run of the river set up,

    with 99% of work done by local, unskilled labour. It powers a great number of local

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    31/87

    School of Engineering, University of Warwick 0602641

    Zambia and served to demonstrate the viability of small hydro projects in small

    communities. A 2.5 KW generator was installed, generating enough power for lighting the

    community but not much else.

    Currently there is demand to expand the scheme to give 200 KW of power, but there is a

    lack of funding to achieve this. The project cost USD 30,000 in total which was raised by a

    German church organisation (EZE), and a fee of USD 1.05 is charged monthly to all

    households, covering repair and maintenance costs.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    32/87

    School of Engineering, University of Warwick 0602641

    2.9 Local manufacture and labour

    In order to maximize the chances of success when implementing a micro-hydro scheme it is

    extremely important to involve the local community from day one. If this is done the

    community will take pride in   their   project and work to maintain it operational. This

    community involvement means that local manufacture and labour will be used – giving the

    workers an insight and understanding into the functioning of the scheme and hence they

    will be able to maintain the plant without excessive external assistance.

    In addition the use of local manufacture and labour will significantly decrease costs in many

    areas. This does require flexible design of sensitive parts, such as the turbine, to allow for

    inaccuracies during manufacture. Efficient designs can, nonetheless, be achieved – as we

    can see in Las Juntas, Peru, where the L-1 turbine achieved up to 89% efficiency [15].

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    33/87

    School of Engineering, University of Warwick 0602641

    2.10 Cost Reduction

    When planning a micro-hydro scheme it is important to ensure that the idea is financially

    viable. If it is not, it will be difficult to maintain the scheme even after the initial costs are

    covered. This is why income-generating uses of the power must be considered before

    deciding whether the scheme is viable.

    The majority of costs will, however, always be set up costs. The main costs will be the civil

    works involved in site preparation and the cost of electrical and generating equipment.

    However, there are certain innovations available for micro-hydro that can significantly

    reduce these costs. The following list has been compiled from the Practical Action micro-

    hydro website. [16]

      Use of run-of-the-river schemes (eliminates need for water storing dam)

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    34/87

    School of Engineering, University of Warwick 0602641

    2.11 Management/ownership

    Ideally a “village electrification committee” would be put in place. This governing body

    would be responsible for the continuous operation, maintenance and tariff calculation and

    collection. External influence and control would be necessary, at least in the early stages of 

    the scheme, to ensure that all processes are followed correctly and that proper care is taken

    in maintenance.

    This external influence would, however, need to take great care to respect the

    requirements, wishes and customs of the local community. The villagers will always know

    best what they need and in what shape they need it and so it is important to work very

    closely with village leaders and to maintain a good relationship with them. All decisions

    must be made with the best interest of the community in mind.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    35/87

    School of Engineering, University of Warwick 0602641

    Section III - Feasibility Study

    The objective of this section is to analyze the proposed site using and applying the tools

    discussed in the literature review. This will give a complete illustration of how well Sioma

    is suited to the implementation of a micro-hydro scheme and if its realization is viable.

    3.1 Geographical situation

    Zambia Country Profile [17]

      Full name: Republic of Zambia

      Population: 12.2 million (UN, 2008)

      Capital: Lusaka

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    36/87

    School of Engineering, University of Warwick 0602641

    shattering the economy. Copper mining is still the country’s main source of income, despite

    the World Bank’s urges to develop other sources of additional revenue.

    AIDS is blamed for many of the country’s troubles, especially the loss of many of its prime

    engineers and politicians. Malaria still causes large problems for Zambia’s population and a

    large proportion of the population live below the World Bank poverty threshold of 1$ a day.

    Sioma

    Sioma, with an estimated surrounding population of 1500 people, is located in the

    Barotseland region of South Western Zambia. It is situated approximately 315 km from

    Livingstone, accessible by 4x4 through a journey taking 4 to 5 hours. The village is situated

    next to the majestic Zambezi River and is approximately 6 km north of the Sioma Falls by

    road. The planned community woodworking workshop is approximately 4 km south of the

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    37/87

    School of Engineering, University of Warwick 0602641

    A main power cable passes through the region relatively close to Sioma, but the Zambian

    government has no plans to install a sub-station to make the power available to the

    community. The community is too small and does not possess the ability to pay the

    standard fees that would be demanded by the national electricity company. If the

    community is to overcome the difficulties it faces, there is an urgent need for electricity,

    one of the most basic elements of infrastructure and so alternative sources must be

    considered. Due to the village’s proximity to the Zambezi River, micro-hydro provides the

    ideal alternative.

    This proximity does not come without difficulties, however. As I write this, Zambia is

    experiencing the worst floods in 40 years [18], with the Zambezi water levels rising to record

    levels. Not only does this cause severe humanitarian problems, with entire villages being

    flooded, but it also makes the hydro site very difficult to design. If the intake is designed for

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    38/87

    School of Engineering, University of Warwick 0602641

    3.2 Initial Planning and Technical Analysis

    3.2.1 Power Requirements

    The power requirements must be estimated prior to any technical analysis, as it forms the

    basis of what we are designing. The focus of this proposal is the end-user rather than the

    technology; it is their needs we are trying to meet. The following requirements are given as

    estimates rather than facts, as a visit to the community to map out the exact needs has not

    yet been made. In addition, the potential demand does not equal the present consumption.

    The energy demand will be continuously changing, and with economic development,

    consumption will increase.

    Woodworking Workshop:

    -   Band Saw - 5000 W

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    39/87

    School of Engineering, University of Warwick 0602641

    Village

    -   Households (2 light bulbs each x 200 households) - 8000 W

    -   Shared refrigerator (between 10 houses?) - 10000 W

    -   Miscellaneous (TV/Radios/kettles/mobiles etc) - 4000 W

    School 

    -   Lighting - 200 W

    -   Communication (TV/Radios) - 500 W

    -   Total - 45.83 kW

    Our proposed site does not have limitations on a micro-hydro scale with respect to the

    theoretical power output, but is rather limited by economic factors. The population of the

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    40/87

    School of Engineering, University of Warwick 0602641

    17:00. An increase in use of televisions and radios will be seen around 18:00-19:00, which is

    when we see the peak energy use; 35 kW. We can calculate the load factor using the chart

    below:

    10.0%

    20.0%

    30.0%

    40.0%

    50.0%

    60.0%

    70.0%

    80.0%

    90.0%

    100.0%

         %

         T    o     t    a     l     P    o    w

        e    r     U    s    e     d

    Calculating Load Factor 

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    41/87

    School of Engineering, University of Warwick 0602641

    The load factor is a measure of how much the scheme is used, and in that sense, a measure

    of efficiency. A factor of close to 57% is quite high relative to other similar schemes, and

    demonstrates the viability of implementing such a scheme.

    3.2.2 Measurement of Head

    Often this task is assumed to require a surveyor; however, this may not be entirely

    necessarily, and much quicker and more cost effective methods can be employed. Of these

    methods, the level is preferred not only due to its simplicity but also due to its relatively low

    cost. A carpenter’s level is the cheapest option but a Locke hand level can also be used.

    Accuracy will generally be around 5%, but this is dependent on the steepness of the slope.

    [11]

    Using the level method, you begin at point X (in figure 16) which is the proposed location of 

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    42/87

    School of Engineering, University of Warwick 0602641

    Figure 16 – Using a level to measure head [11]

    This method provides a relatively accurate, quick and effective way of measuring the gross

    head of a site. It must be taken into account, however, that the available power from a

    turbine will be proportional to H3/2, and so the measurements will have a severe effect on

    any inaccuracies.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    43/87

    School of Engineering, University of Warwick 0602641

    The figures given above cannot be used accurately, however, to design intake barriers and

    diversion belts as the exact site of the scheme is not yet known. The depth of water and the

    width of the exact portion of the river are not known and so all dimensions derived from

    this information must be taken as estimates.

    3.2.4 Turbine

    Importing existing turbines will often provide a fully functional and effective method of 

    power generation. However, it can be very expensive and will lead to difficulties when a

    part needs replacing or when maintenance is required. This is why we will opt for local

    manufacture, where flexibility of design is important. This design will need a relatively large

    tolerance to deviations due to the method of fabrication, and so will need to function

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    44/87

    School of Engineering, University of Warwick 0602641

    • Easy fabrication so it is possible to make in small, local workshops with basic tools.

    • Use local materials. It was decided that the materials should be easily obtained

    locally in the country of development.

    • Easy operation and low maintenance through lengthy periods of operation.

    Figure 17 – L-1 turbine casing and propeller [15]

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    45/87

    School of Engineering, University of 

    Figure 18 demonstrates that

    would generate 46.1 kW

    requirement will be used in t

    3.2.5 Design o

    Warwick

    the L-1 turbine is adaptable to our parti

    f power from a 10 metre head. This

    e following proposed design.

    intake and canal

    0602641

    ular site, where it

    power generation

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    46/87

    School of Engineering, University of Warwick 0602641

    harsh forces in the wet season. In order to facilitate this deflection it is important to use a

    narrow portion of the river.

    In the event that flows larger than those required by the turbine enter the canal, we will

    make use of two spillways. One will be situated soon after the intake, as demonstrated in

    the sketch, and the other at the site of the forebay tank. The latter will be used during

    times where less power is required of the turbine.

    Determining the cross sectional dimensions of canal:

    Power Required = 46 100 KW

    mQreq

    Q

    QH  P req

    /587.0

    10**81.9*1000*8.046100

    3

     

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    47/87

    School of Engineering, University of Warwick 0602641

    22935.0

    2

    587.0

    m A

     A

    Q A

    In order to maximize efficiency a trapezoidal cross section will be used for the power

    conduit. However, if excavation proves to be difficult a rectangular cross section can also be

    employed.

    To determine the hydraulic radius, r we will use the following equation in order to achieve

    the most efficient canal section.

     Ar 

    2935.0)70cos(2

    )70sin(50.0

    )cos(2

    )sin(50.0

     

     

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    48/87

    School of Engineering, University of Warwick 0602641

    0133.0

    )

    204.0

    2*02.0(

    )(

    2

    3

    2

    2

    3

    2

    S r 

    nvS 

    This slope equates to a drop of 1.33 metres per 100 metres.

    Figure 20 – Cross section of power conduit

    Without exact figures on the river flow at the particular site it is difficult to propose a flood

    0.868 m

    0.204

    mΘ = 70°

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    49/87

    School of Engineering, University of Warwick 0602641

    In order to prevent water borne debris from entering the canal a trashrack will be used.

    This will be removable to allow for maintenance and cleaning. The spacing of the bars will

    be equal to that of a rake in order to facilitate the removal of debris.

    Due to the proposed speed of the water in the canal sediment suspended in the incoming

    water settling should not prove problematic to the flow of the canal. It is only at lower

    velocities that this will settle and disrupt flow. However, a settling basin will be required at

    the forebay to prevent destructive particles getting through to the turbine and causing

    premature erosion.

    As mentioned earlier, the scheme will incorporate two spillways. The overflow spillway will

    be located close to the intake and will be constructed as “broad crested”. This does not

    pass the largest flow per unit of length, but is the simplest to construct.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    50/87

    School of Engineering, University of Warwick 0602641

    In the event of flow entering the forebay and exceeding that passing through the penstock,

    an overflow spillway will be required. This water will then be diverted back to the river on a

    dedicated path – preventing uncontrolled erosion. A trashrack will also be required, to

    remove any floating debris which may have gotten through the intake or entered the canal

    through other means. A drain will also be installed to empty the tank when maintenance is

    required so that settled sediment can be removed. A width and depth of 1.5 m and a length

    of 2 m is appropriate. Figure 21 illustrates a design that would work well at our site.

    Instead of a perforated PVC pipe for filtration, however, a metal trashrack will be used.

    Taps will also be fitted to the side as discussed earlier.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    51/87

    School of Engineering, University of Warwick 0602641

    3.2.7 Penstock

    Typically the Penstock represents 1/3 of total scheme costs. [22] The various alternatives, in

    terms of both size and material, must therefore be considered carefully. We are aiming to

    maximize the power per unit length and determining a realistic slope.

    At this point in the planning process, the specific site is not known so estimates about the

    required pipe length and slope must be made. For this analysis we will use the height and

    length estimates given in the diagram below.

    Forebay

    51 m

    10 m

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    52/87

    School of Engineering, University of Warwick 0602641

    Upon comparison of uPVC and HDPE, it quickly becomes clear that HDPE has numerous

    advantages over uPVC [23]. It is flexible, whereas uPVC is rigid and so requires more joining

    as well as a well as very comprehensive support. HDPE piping can simply be laid on the

    ground, where it will flex to the changing slope adequately. uPVC pipes need trenches to

    provide continual support, as well as covering to protect from UV corrosion. HDPE pipes do

    not suffer from UV corrosion; they have high impact strength as well as high chemical

    resistance. Compared to uPVC pipes they are very easy to install as well as join, and so,

    bearing all the factors considered in mind, HDPE pipes clearly provide a superior alternative.

    Optimal Diameter:

    First it is necessary to determine the optimal diameter of the penstock pipe. This will be a

    compromise between the % head loss and the cost of the pipe, which is generally defined by

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    53/87

    School of Engineering, University of Warwick 0602641

    Although this is less significant in low head penstocks, it is still a factor, and so a pipe with

    minimum wall thickness of 16.2 mm must be selected. [11] Calculations also show that the

    critical shut off time is 0.59 seconds. The penstock will have a gate valve at the bottom

    which must not be closed faster than this, if it is, the penstock will experience the maximum

    pressure of the water. These calculations can be found in Appendix B.

    Thermal Expansion of the Penstock:

    Temperatures in Zambia can vary by as much as 29°C [24] and as a result the HDPE penstock

    will suffer significant thermal expansion. This was calculated to be as much as 0.177 metres

    for 51 metres of piping, as can be seen in Appendix C. The use of HDPE allows for the bends

    in the piping to take up any expansion or contraction between the anchor points. If a more

    rigid material was used, this stress would be transferred to the anchor blocks in the manner

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    54/87

    School of Engineering, University of Warwick 0602641

    previous section. The piping will, however, have to be secured by anchor blocks to ensure

    the stability of the penstock. The piping should be secured by 3 anchor blocks, each block

    made up of 2m3

    of concrete – 1 m3

    per 300mm diameter of piping

    Control Measures:

    Controlling flow into the penstock is an important element to allow for maintenance of the

    turbine, or the piping itself. Control can be achieved through a variety of means, by using

    gate valves or even a simple construction such as that shown in Appendix D.

    This construction is rubber faced, with a steel tube handle. Its face is placed onto the

    penstock intake, where the water pressure maintains it, and blocks further water from

    entering. To avoid fracture through vacuum, a vent pipe can be placed close to the intake

    along the piping – as is also shown in Appendix D.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    55/87

    School of Engineering, University of Warwick 0602641

    AC system will be employed, with a step-down transformer at the end users. In order to

    avoid the use of a step up transformer at the turbine site a high voltage generator will be

    used.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    56/87

    School of Engineering, University of Warwick 0602641

    3.3 The potential contribution to the local community

    Local Clinic 

    The scheme would replace the diesel generator currently in place. The clinic does not

    currently have sufficient funds to purchase diesel to run this and so is using temporary solar

    panels – which are proving themselves to be problematic. A reliable and sustainable

    electricity source such as the hydroelectric scheme would allow for easier operation of 

    medical equipment, treatment, refrigeration, computers, lighting and increased comfort.

    The clinic also suffers from the lack of a permanent doctor. The availability of electricity

    may give the clinic a substantially greater appeal to a doctor and encourage the clinics

    expansion.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    57/87

    School of Engineering, University of Warwick 0602641

    an education nonetheless. This will provide opportunities that were unthinkable earlier,

    and will be an important development in terms of community progression.

    Woodworking Workshop

    The community woodwork training workshop is a ZEEC initiative, started a few years ago.

    The idea is to provide a centre of training for the local community in woodworking skills in

    order to encourage local businesses and develop self-sufficiency. The centre has not yet

    been built, but has a planned site and permission.

    The problem with powering this is that it is situated south of the Sioma Falls, and so

    separate wiring for this site would be required. The distance to it, however, is smaller –

    approximately 4 km. If it proved viable to power this alongside the community it could be

    made commercially viable as furniture produced could be sold at competitive prices, which

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    58/87

    School of Engineering, University of Warwick 0602641

    The availability of electricity would make Sioma an important hub of the surrounding area,

    attracting much more activity.

    Integration with irrigation and water supply projects

    Due to the mechanical movement produced by the moving water, the scheme can be

    integrated with both irrigation and water supply projects to supply the area around the site.

    This is especially achievable due to the surrounding fields of the area. These are not

    currently used for agriculture but have been in the past, as there are remnants of old

    irrigation canals close to the proposed site.

    The socio-economic benefits of the scheme are summarised below:

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    59/87

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    60/87

    School of Engineering, University of Warwick 0602641

    Woodworking Workshop

    The woodworking workshop will be manufacturing furniture to be sold for profit. This

    means that, if successful, there will be funds to pay for the electricity. This tariff will be set a

    level lower than the cost of running a diesel generator but enough to pay for necessary

    maintenance as well as spare parts for the turbine, and will be measured through a metre.

    The income from this beneficiary will be the main source for return on investment.

    In order to determine an appropriate charge, the competition’s price, diesel, must be

    considered. Running a 30 kW generator at ½ power for 8 hours consumes approximately

    54.4 litres per day [25]. At current UK diesel prices this equates to £63 per day [26], which is

    a total of £16,380 in a working year (260 days). The actual price is expected to be higher

    however, as fuel prices in Zambia are higher than in the UK. Clearly, this price does not

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    61/87

    School of Engineering, University of Warwick 0602641

    3.5 Ownership

    The ownership of the scheme is important to clarify if the scheme is to be implemented in

    the future. A proposed model is shown in Figure 25.

    ZEEC

    Registered Charity in

    Zambia

    ZEEC has links to several

    schools, universities and

    organizations in Europe and

    USA, who will raise financial

    support for the initial costs of 

    project

    ZEEC works with local and

    national government, ZESCO,

    NGOs etc.

    ZEEC trustees are people from

    both Zambia as well as W estern

    countries, connected to the area

    and with common goals

    Pro osed Structure of Ownershi and External Relations for Micro-H dro Scheme

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    62/87

    School of Engineering, University of Warwick 0602641

    generated from electricity tariffs. Any profit after maintenance and salary costs will be

    reinvested into new development projects for the region.

    The majority of funding will presumably be raised by ZEEC and so a significant influence on

    the Sioma Power Company’s future decisions is to be expected, possibly by electing ZEEC

    trustees to its board of directors.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    63/87

    School of Engineering, University of Warwick 0602641

    3.6 Meeting with ZEEC

    One meeting with a ZEEC representative, Joachim Meyer, was held in Brussels along with

    numerous e-mail communications. The idea of the micro-hydro scheme was introduced to

    Mr. Meyer via e-mail in mid October, which was received positively. It was agreed to meet

    in March so that the project could be set in motion as quickly as possible.

    Building permission was discussed, and although an application has been sent, nothing has

    yet been heard. Mr. Meyer assured me that rumours are positive and that a positive

    response is almost certain but that such requests take time. The current flooding was next

    on the agenda – and the floods’ impact on design was stressed. Finally a list of questions

    and observations was handed to Lesley Meyer who was planning a trip to Sioma in April, to

    help with the writing of this report.

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    64/87

    School of Engineering, University of Warwick 0602641

    Section IV – Conclusions and Recommendations

    4.1 Conclusions

    In order to break out of the poverty cycle, third world infrastructure development is crucial.

    It is clear from the past analysis that micro-hydropower is one of the most important energy

    sources for achieving this wherever pressurised water is available. It is a relatively

    affordable, clean and completely renewable technology that has proven its effectiveness

    over many decades.

    This report has given an insight into the technology behind micro-hydro schemes and the

    most efficient ways of implementing them. After a comprehensive literature review of the

    subject, the theory was applied to the case of Sioma in Zambia. Based on estimates from

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    65/87

    School of Engineering, University of Warwick 0602641

    4.2 Costing of Project

    Date Person(s)/item(s)  Time

    (hours)  Cost (£) Comment

    30/09/2008 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    17/10/2008 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    12/01/2009 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    04/02/2009 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    18/02/2009 Nigel Sykes & Tom McCluskey 3 150   Staff (Nigel Sykes & Tom McCluskey)

    25/03/2009 Joachim Meyer 2 100   Staff (ZEEC)

    20/04/2009 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    350

    1/10/08-

    21/4/09  Hans Petter Bjornavold 300 4500   Student (30 CATs = 300 hours)

    4900

    09/01/2009 Micro-Hydro Sourcebook 24.94   Consumable (book)

    Total 5274.94

    Figure 26 – Costing of Project

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    66/87

    School of Engineering, University of Warwick 0602641

    4.3 Recommendations

    In the extent that this study goes, the Sioma micro-hydropower scheme has proved itself 

    viable. The project would bring vast benefits to the Sioma community and its surrounding

    area, with a relatively reasonable cost.

    In order to develop the project further, in a minimal amount of time, a trip to the area in

    June 2009 is recommended. This will allow the author to perform key surveying of potential

    sites, as well as to gain a clearer perspective of the true requirements of the community. In

    addition the author will be able to map out the potential of local labour and the possible

    suppliers of parts.

    Following this trip, extensive planning using the detailed measurements made in June will

    have to be performed. The turbine will be sourced, as will the HDPE piping. Arrangements

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    67/87

    School of Engineering, University of Warwick 0602641

    Glossary of Definitions

      Coupling – connecting the rotating turbine to electrical generator/mechanical

    equipment.

      Forebay – water reservoir immediately upstream of penstock

      Generator – an engine that converts mechanical energy into electrical energy

      HDPE – high density polyethylene

      Kinetic Energy – energy due to motion

      Micro-Hydropower – small scale harnessing of energy from falling water

      Sioma – Village with population of approx. 1000-1500 in Barotseland, South Western

    Zambia

      Penstock – piping directing water from forebay to turbine

      Potential Energy – stored energy

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    68/87

    School of Engineering, University of Warwick 0602641

    References/Bibliography

    [1] TAMBURRINI, M., 2004, A Feasibility Study for a Microhydro Installation for the Strangford 

    Lough Wildfowlers & Conservation Association, Thesis (Msc), University of Strathclyde

    [2] Hydropower Fundamentals, http://www.alternative-energy-

    resources.net/hydroelectricity.html, retrieved 20 March 2009

    [3] REN21, Renewables – Global Status Report 2006 Update,

    http://www.ren21.net/globalstatusreport/download/RE_GSR_2006_Update.pdf, retrieved April

    19 2009

    [4] International Energy Agency, Renewable Energy – Status and Prospects, 2003

    [5] USGS, Hydroelectric Power Water Use, http://ga.water.usgs.gov/edu/wuhy.html, retrievedFebruary 10 2009

    [6] UN Economic and Social Council,  Access to Electricity ,

    http://webapps01.un.org/nvp/frontend!polCat.action?id=50, retrieved February 15 2009

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    69/87

    School of Engineering, University of Warwick 0602641

    [16] Micro Hydropower Introduction,

    http://practicalaction.org/practicalanswers/product_info.php?cPath=21_63&products_id=41,

    retrieved 19 April 2009

    [17] Country Profile: Zambia, 2009,

    http://news.bbc.co.uk/1/hi/world/africa/country_profiles/1069294.stm, retrieved February

    2009

    [18] NYAKAIRU, F., Zambia and Namibia face worst floods in 40 years,

    http://www.reuters.com/article/africaCrisis/idUSL0976837, retrieved 26 March 2009

    [19] Zambezi River – Hydrology , http://www.britannica.com/EBchecked/topic/655540/Zambezi-

    River/37114/Hydrology, retrieved March 26 2009

    [20] Buckland, R., Micro Hydro at Las Juntas: Analysis of the scheme to date and the Socio-

    economic, Environmental and Political Effects, 3rd

    Year Project, University of Warwick

    [21] McMULLEN, C., Low Head Micro Hydro in Developing Countries: The L-1 Turbine, April 2004,

    3rd

    Year Project, University of Warwick

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    70/87

    School of Engineering, University of Warwick 0602641

    Appendix A

    Head Loss for different diameter pipes:

    Q net   Q net   Q 2 Lpipe   n d d2 d5,3  hwall

    lossv v2 k

      hturb

    loss

    hfriction

    losshgross

    %

    loss   price/m

    l/s m3/s m m m m/s m m m $

    510 0,51 0,26 51 0,01 0,32 0,10 0,00 5,56 6,35 40,26 0,5 1,03 6,59 10 65,90 N/A*

    510 0,51 0,26 51 0,01 0,37 0,14 0,01 2,58 4,75 22,53 0,5 0,57 3,15 10 31,52 N/A

    510 0,51 0,26 51 0,01 0,42 0,18 0,01 1,32 3,68 13,57 0,5 0,35 1,66 10 16,62 N/A

    510 0,51 0,26 51 0,01 0,5 0,25 0,03 0,52 2,60 6,75 0,5 0,17 0,69 10 6,95 N/A

    510 0,51 0,26 51 0,01 0,55 0,30 0,04 0,32 2,15 4,61 0,5 0,12 0,43 10 4,33 N/A

    510 0 51 0 26 51 0 01 0 6 0 36 0 07 0 20 1 80 3 26 0 5 0 08 0 28 10 2 82 N/A

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    71/87

    School of Engineering, University of Warwick 0602641

    Appendix B

    Wall thickness:

    Minimum wall thickness according to ASME code is:

    mmt 

     Dt 

    2.16

    2.1*5.2

    min

    min

    Water hammer pressures can occur when the critical shut off time is not observed. To find

    this we first find the wave velocity:

     sma

    t  E 

     D K a

    /02.173

    *

    **10001

    1420

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    72/87

    School of Engineering, University of Warwick 0602641

    Appendix C

    Thermal Expansion:

    If an unrestricted HDPE pipe, length “L = 0.51”, changes in temperature, there will be a

    change in its length equal to:

    m L

    T a L L

    177.0

    **

    Where T = change in temperature (°C) = 35-6 = 29

    a = coefficient of linear expansion (°C-1) = 120*10^-6 °C-1

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    73/87

    School of Engineering, University of 

    Appendix D

    Penstock inlet control:

    Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    74/87

    School of Engineering, University of Warwick 0602641

    Appendix E

    Demand Estimate:

    Time Total Power Used Total Power Used Percentage of     Comments

    1 0.5 7 18.8%

    2 0.5 6 16.3%

    3 0.5 6 16.3%

    4 0.5 6 16.3%

    5 0.5 6 16.3%

    6 0.5 8 21.3%

    7 0.5 9 23.8% Increase in lighting in village

    8 15 8 57.5% W.W working day begins

    9 20 8 70.0%10 20 8 70.0%

    11 20 8 70.0%

    12 20 8 70.0%

    13 10 8 45.0%

    14 20 8 70.0%

    15 20 8 70.0%

    h l f f k

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    75/87

    School of Engineering, University of Warwick 0602641

    Appendix F

    Item Cost (£) CommentPlanning   4000 200 hours at 20 pounds per hour

    Management   800

    Overseeing the project during construction (local

    expert)

    Intake

    Concrete 1000

    Labour 20Total 1020

    Spillway

    Total 200

    Canal

    Concrete 5000

    Labour 70

    Total 5070Forebay tank

    Concrete 500

    Labour 50

    Trashrack 200

    Cover 5

    Drain 15

    S h l f E i i U i i f W i k 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    76/87

    School of Engineering, University of Warwick 0602641

    Appendix G

    Project Costs:

    Date Person(s)/item(s)  Time

    (hours)  Cost (£) Comment

    30/09/2008 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    17/10/2008 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    12/01/2009 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    04/02/2009 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    18/02/2009 Nigel Sykes & Tom McCluskey 3 150   Staff (Nigel Sykes & Tom McCluskey)

    25/03/2009 Joachim Meyer 2 100   Staff (ZEEC)

    20/04/2009 Dr. S.C. Li 0.5 25   Staff (Supervisor)

    350

    S h l f E i i U i it f W i k 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    77/87

    School of Engineering, University of Warwick 0602641

    Appendix H

     ZEEC correspondences:

    18/10/2008 from me to Leslie and Joachim Meyer

    Mr. and Mrs. Meyer,

    Hope you're both well and that the new school year is going smoothly. Thanks for the update back in

    September - exciting news about the truck!

    I have some news I thought might interest you! I've been allocated a project based on small scale

    hydro-electric power for isolated communities in developing countries. All similar projects in recent

    years (from this supervisor) have been based on a village in Peru but, since I found continuing the

    pattern a bit dull, I proposed doing my own thing and focusing my project on the implementation of 

    such a scheme in Sioma and coming up with a proposal. My supervisor was happy supporting this so

    it is now officially my third year project, counting for 1/4 of this year. If I manage to come up with a

    decent proposal and the idea proves itself beneficial as well as viable I do plan to pursue the project

    past the academic "boundaries" which hopefully would result in concrete advancements for the

    community of Sioma.

    S h l f E i i U i it f W i k 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    78/87

    School of Engineering, University of Warwick 0602641

    Best regards,

    Joachim

    22/10/2008 from me to Joachim Meyer

    As I see it now, the scheme would produce enough electricity for all of Sioma as well as the

    community training workshop. Of course this is very ambitious and would prove to be quite

    expensive. Projects of similar scale have cost approximately $50,000 (US) but have proven very

    effective in increasing not only quality of life but also attracting new businesses and revamping the

    local economy.

    An interesting project just being finished is the North West Zambia Development Trust

    (www.nwzdt.org) - it gives an idea of what can be achieved. It is on a much bigger scale though, with

    an output of approx 700KW whereas I am aiming for approx 30KW for Sioma.

    I will be working on a more complete plan throughout the rest of the week, aiming to have it done

    by the end of the weekend. I can then send it to you and, if you approve, we can pass it on to Joe

    and the local authorities. If we get their backing, I imagine it will be easier to apply to various

    charities for support. I do have a copy of the request for the establishment of the training workshop,

    I assume it is the one I have attached?

    Also, do you have an idea of the machinery that would be needed for the training workshop? It

    would be useful in order to calculate the required power output for the turbine.

    School of Engineering University of Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    79/87

    School of Engineering, University of Warwick 0602641

    28/10/2008 from me to Joachim Meyer

    Hi,

    I have attached a brief letter/plan for the local government asking for a letter of support. Will we be

    able to use this (or something like it)? If you have any suggestions please let me know.

    Thanks,

    Hans

    2008/10/28 from Joachim Meyer to me

    Good morning hans,

    I have had a long conversation with Joe this morning. He would be delighted to assist in any way.

    The Western Province has recently suffered lengthy power cuts because development of economic

    activity and power supply are not balanced.

    I am sending your proposal to Joe who will in a week's time have a meeting with the minister of 

    energy for the Western Province and he is sure that you proposal will be supported and a letter send

    to you.

    This will work,

    Joachim

    School of Engineering University of Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    80/87

    School of Engineering, University of Warwick 0602641

    10/11/2008 from Joachim Meyer to me

    Hello,

    Not much feedback at this stage. But what we have sound promising.

    Joe has met with the Director of Zesco responsible for the Western Province. You proposal outline is

    therefore sitting on the desk of the top man running the Zambian Electricity Supply Company in the

    area.

    We await their reaction. I think it would be good to have their support particularly when it comes to

    maintain the facility later.

    Joachim

    23/1/2009 from Joachim Meyer to me

    Hello Hans Petter,

    Below a response from Joe the project looks like it will be signed off by the LOZI parliament KUTA.

    All the best,

    Joachim Meyer

    22/1/2009 from Joe to Joachim Meyer

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    81/87

    School of Engineering University of Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    82/87

    School of Engineering, University of Warwick 0602641

    14/11/2008 from me to Vanessa Scott

    Dear Vanessa,

    Thanks for your very quick reply! I'm glad to hear you approve of the project, I am currently waiting

    for a letter of support from Zesco (Zambian Electricity Supply Company) in the Western Province,

    which should hopefully help in terms of funding applications and other practicalities.

    As far as other information goes, I'm in close contact with Mr and Mrs Meyer so they've been able to

    help a lot. If there is anything else though I will make sure to contact you.

    Hopefully I'll be heading to Sioma during my easter break, but I can't confirm that yet due to certain

    practical issues. If not, I'll be aiming for a trip in July or August. Of course, this all depends on the

    outcome of my research and the acquisition of funding.

    I'll keep you updated on any news,

    Kind regards, Hans

    1/1/2009 Vanessa Scott to me

    > Dear Hans,

    > Please see the email below from Sister Catherine. I hope this information

    > helps?

    School of Engineering University of Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    83/87

    School of Engineering, University of Warwick 0602641

    6/1/09 me to Vanessa Scott and Richard White

    Dear Vanessa and Richard,

    Thank you very much for your help, I can only apologise for such a late reply. If you have some more

    general statistics on the clinic, this would be very helpful (as in how many people are treated there a

    year, the max. Amount of patients at one time, the amount of staff etc.), simply so I can provide a

    more detailed picture of the requirements for my report.

    As for updates, I have a progress report due for the project on Friday, so I will pass this on to you

    over the weekend.

    Kind regards,

    Hans

    18/3/2009 Vanessa Scott to me

    Dear Hans,

    I wanted to check in with you regarding your project for Sioma and also let you know that our

    program will be sending two groups of students to Sioma this summer. One in May/June, and

    another group in August.

    Please let me know if you need me to have them collect any information or data on your behalf!

    School of Engineering University of Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    84/87

    School of Engineering, University of Warwick 0602641

    24/3/2009 Vanessa Scott to me

    Dear Hans,

    Please tell Joachim hello for me! He was in Sioma with me in August of 2007.

    Let me know if you have any assignments for the students going down there in May/June or in

    August, I'm happy to give them any sort of project!

    Cheers,

    Vanessa

    27/3/2009 me to Vanessa Scott

    Hello again!

    I met with Joachim and Lesley yesterday afternoon and had a long chat with them regarding the

    project and Sioma in general. They are both very motivated to work with me on the project, which is

    great. Mrs. M is actually off to Sioma tomorrow evening with a group of 22 students from the

    European School and so I gave her a list of questions and issues that I asked her to make notes on. If 

    there is anything else I need notes on I will make sure to let you know, but it is difficult to give

    instructions on possible site locations etc over e-mail and not in person.

    However, it looks like I might be able to go travel down there in early June with Joachim (as long as

    my provisional exam timetable doesn't change), which would be fantastic and would really help the

    School of Engineering University of Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    85/87

    School of Engineering, University of Warwick 0602641

    Appendix J

    Sioma Falls from the air:

    School of Engineering, University of Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    86/87

    School of Engineering, University of Warwick 0602641

    Appendix K

    Satellite image of Sioma Falls area:

    School of Engineering, University of Warwick 0602641

  • 8/9/2019 Hans Petter Bjornavold_Implementation of a Microhydro Power Scheme_2009_REPORT

    87/87

    Appendix L

    Gannt Chart of Project Work:

    We ek* 1 2 3 4 5 6 7 8 9 10 Christmas Bre ak 11 12 13 14 15 16 17 18 19 20 Easter Bre ak 2 1 22

    Literature Review

    Initiate Contact with ZEEC

    Produce Plan for ZEEC/Zambia

    Initiate Contact with Zambia / Apllication for backing of local government

    Initiate Contact with NWZDT

    Research possible sponsors for trip/project as a whole

    Meeting with ZEEC in Brussels / Discussion in further detail

     Apply to Lord Rootes Memorial Fund + other potential sponsors

    Organise notes - finalise structure

    Writing of report

    Finish draft report

    Review s uggestions/changes

    Finalisation of report

    Preparation of oral report

    * Note: Academic weeks. Start date: 29.09.2008 End date: 01.05.2009