134
HANDBOOK FOR THE POST-EARTHQUAKE SAFETY EVALUATION OF BRIDGES AND ROADS Prepared for the Indiana Department of Transportation, INDOT by Julio A. RAMIREZ, Robert J. FROSCH, Mete A. SOZEN, A. Murat TURK School of Civil Engineering, Purdue University under the JTRP Contract No. 2377 March 2000

handbook for the post-earthquake safety evaluation of bridges and

  • Upload
    lyhanh

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

HANDBOOK FOR THE

POST-EARTHQUAKE SAFETY EVALUATION OF

BRIDGES AND ROADS

Prepared for the Indiana Department of Transportation, INDOT

by

Julio A. RAMIREZ, Robert J. FROSCH, Mete A. SOZEN, A. Murat TURK

School of Civil Engineering, Purdue University under the

JTRP Contract No. 2377

March 2000

ii

iii

DISCLAIMER

While the information presented in this handbook is believed to be correct, authors and the

sponsoring agencies assume no responsibility for its accuracy or for the opinions expressed

herein. The material presented in this publication should not be used or relied upon for any

specific application without competent examination and verification of its accuracy, suitability,

and applicability by qualified professionals. Users of information from this publication assume

all liability arising from such use.

iv

v

PREFACE

In 1999, the Indiana Department of Transportation contracted, through the Joint Transportation

Research Program at the School of Civil Engineering in Purdue University, with Professor’s

Julio A. Ramirez, Robert J. Frosch and Mete A. Sozen to develop a training program for post-

earthquake safety evaluation of highway bridges.

Professor’s Julio A. Ramirez, Robert. J. Frosch, Mete A. Sozen, and Dr. A. Murat Turk, post-

doctoral research associate, prepared this manual and an accompanying training video that was

produced by the Center of Instructional Services of Purdue University. Overall view and

guidance for the project was provided by B. Rinard, W. Dittelberger and J. Thompson of the

Indiana Department of Transportation.

The principal investigators gratefully acknowledge the participation of Prof. Marc Eberhard from

University of Washington, Seattle in the preparation of this material.

Bridge damage examples and pictures were reproduced from; EQIIS Image Database,

Earthquake Engineering Research Center (EERC, University of California at Berkeley), Kandilli

Observatory and Earthquake Research Institute (KOERI, Bogazici University, Istanbul),

National Center for Research on Earthquake Engineering, Taiwan.

vi

vii

TABLE OF CONTENTS

Page

DISCLAIMER ………………………………………………………………………………….iii

PREFACE ……………..………………………………………………………………………....v

TABLE OF CONTENTS ……………………………………………………………………vii

LIST OF FIGURES …………………………………………………………………………..xi

1. INTRODUCTION …………………………………………………………………………….1

1.1. Object and Scope ….……………………………………………………………………… 1

1.2. Level 1 Inspection ……………………………………………………………………………3

1.3. Level 2 Inspection ……………………………………………………………………………3

2. EARTHQUAKE ENGINEERING PRINCIPLES …………………………………………7

2.1. Earthquakes…………………………………………………………………………………...7

2.2. The Structure of the Earth.………………………………………………………………

2.3. Seismic Waves ………………………………………………………………………………9

2.4. Bridge Behavior under Earthquake Excitation ……………………………………………14

3. SEISMICITY OF INDIANA ……………………………………………………………17

3.1. General ……………………………………………………………………………………17

3.2. Earthquake History of Indiana …………………………………………………………….20

4. INDIANA BRIDGE STRUCTURES ………………………………………………………25

5. POSSIBLE TYPES OF BRIDGE AND ROADWAY DAMAGE ……………………….33

5.1. General …………………………………………………………………………………….33

5.2. Classification of Damage …………………………………………………………………..33

5.3. Level 1 Examples of Bridge and Roadway Damage ……………………………………….35

5.4. Level 2 Behavior of Bridges under Earthquake Excitation …………………………………46

viii

ix

6. POST-EARTHQUAKE SAFETY EVALUATION PRACTICE FOR HIGHWAY

BRIDGES ……………………………………………………………………………………...55

6.1. Level 1 Inspection …………………………………………………………………………..55

6.2. Level 2 Inspection ………………………………………………………………………….59

6.3. Suggested Tools for the Evaluation Procedure …………………………………………….63

6.3.1. Suggested tools to perform Level 1 inspection ………………………………………63

6.3.2 Suggested tools to perform a detailed evaluation for Level 2 ……………………….64

6.4. Bridge Closing Procedure …………………………………………………………………66

7. TEMPORARY REPAIRS AND LONG TERM MONITORING TECHNIQUES ……..67

7.1. Temporary Repairs …………………………………………………………………………67

7.1.1. Transition Repair ……………………………………………………………………..68

7.1.2. Shoring ……………………………………………………………………………….69

7.2. Long Term Monitoring ……………………………………………………………………..74

7.2.1. Deflections ………………………………………………………………………….74

7.2.2. Cracks ………………………………………………………………………………..75

7.2.3. Strain …………………………………………………………………………………76

8. EVALUATION EXAMPLES ………………………………………………………………79

8.1. Level 1 Examples …………………………………………………………………………..79

8.1.1. Example 1 ……………………………………………………………………………79

8.1.2. Example 2 ……………………………………………………………………………85

8.1.3. Example 3 ……………………………………………………………………………87

8.2. Level 2 Examples …………………………………………………………………………..90

8.2.1. Example 1 ……………………………………………………………………………90

8.2.2. Example 2 ……………………………………………………………………………94

9. REFERENCES …………………………………………………………………………….101

APPENDIX …………………………………………………………………………………..103

x

xi

LIST OF FIGURES

Page

FIGURE 1.1 Flow-chart of Post-Earthquake Response Assessment …………………………….5

FIGURE 2.1 View of the layers of the Earth (20) ……………………………………………….10

FIGURE 2.2. The thickness of the layers of the Earth (20) …………………………………….10

FIGURE 2.3 The map of the plates on the Earth (21) ………………………………………….11

FIGURE 2.4 The cross section that illustrates the main types of plate boundaries (22) ………..11

FIGURE 2.5 The illustration of the seismic waves (24) ……………………………………….12

FIGURE 2.6 The illustration the main types of faults (23) ……………………………………..13

FIGURE 2.7 A typical near source acceleration record taken after Duzce Earthquake (25) ……13

FIGURE 2.8 The occurrence of the earthquake and traveling of the waves to the bridge site (1) 15

FIGURE 2.9 Typical longitudinal earthquake loading and deflected shape of a bridge (1) ……15

FIGURE 2.10 Typical lateral earthquake loading and deflected shape of a bridge (1) …………16

FIGURE 3.1 The view of the liquefaction mechanism and the map of Southern Indiana regions

where ancient sand blows have been found due to prehistoric earthquakes (28) ………………18

FIGURE 3.2 Approximate Epicenters Powerful Earthquakes since 1811-1812 (3) …………….19

FIGURE 3.3. The Fault Map of State of Indiana (4) ……………………………………………20

FIGURE 3.4 The peak acceleration map with 10% probability of exceedance in 50 years. (5) ..24

FIGURE 3.5. Estimated MM intensity map for 6.5 magnitude earthquake in NMFZ (6) ………24

FIGURE 5.1 View of different structural parts of a typical highway bridge ……………………33

FIGURE 5.2. Damage classification tables for bridges …………………………………………34

FIGURE 5.3 Collapse of roadway due to slope failure after Duzce EQ 1999 (10) ……………..35

FIGURE 5.4 Collapse of roadway due to fault rupture after Izmit EQ 1999 (10) ……………..36

FIGURE 5.5 Failure of a prestressed concrete box beam bridge after Izmit EQ 1999 (10) …….36

FIGURE 5.6. Collapse of deck and piers after Taiwan Earthquake 1999 (15) …………………36

FIGURE 5.7. Failure of a monolithic RC girder bridge after Loma Prieta EQ 1989 (11) ………36

FIGURE 5.8 Collapse of RC girder bridge after Loma Prieta EQ 1989 (11) …………………..36

FIGURE 5.9 Collapse of bridge deck after Northridge 1994 (11) ………………………………36

FIGURE 5.10 Collapse of steel deck bridge after Kobe 1995 Earthquake (12) ……………….37

FIGURE 5.11 Excessive longitudinal movement of the bridge deck (15) ……………………..37

xii

FIGURE 5.12 The excessive transversal movement of bridge after Izmit EQ (10) …………….38

FIGURE 5.13 Excessive longitudinal movement of steel box girder bridge (11) ………………38

FIGURE 5.14 Excessive differential settlement of the backfill (1) …………………………….38

FIGURE 5.15 Lateral movement of prestressed RC box girders (10) …………………………..38

FIGURE 5.16 Longitudinal movement of RC box girders after Duzce EQ 1999 (10) ………….38

FIGURE 5.17 Vertical offset between decks after Northridge EQ 1994 (11) …………………39

FIGURE 5.18 Excessive movement of expansion joints after Taiwan EQ 1999 (15) …………..39

FIGURE 5.19 The expansion of the joints Taiwan EQ 1999 (15) ……………………………..39

FIGURE 5.20 The expansion of the joints after Loma Prieta Earthquake 1989 (11)……………39

FIGURE 5.21 Vertical and horizontal offset on a bridge after Northridge EQ. 1994 (11) ……..39

FIGURE 5.22 Settlement of Bridge (26) ………………………………………………………..40

FIGURE 5.23 Column failure (11) ……………………………………………………………40

FIGURE 5.24 Failure of RC e column (11) …………………………………………………….40

FIGURE 5.25 Failure of the bottom of the RC bridge column (11) ……………………………40

FIGURE 5.26 Failed RC bridge column (11) …………………………………………………..41

FIGURE 5.27 View of damaged RC bridge pier after Kobe Earthquake 1995 (13) ……………41

FIGURE 5.28 Heavy damage in RC bridge piers after Kobe Earthquake 1995 (14) ……………41

FIGURE 5.29 Shear crack in bents after Northridge Earthquake 1994 (11) ……………………41

FIGURE 5.30. Shear key failure of a bridge after Northridge Earthquake 1994 (11) …………..41

FIGURE 5.31 Buckling of steel girders (11) ……………………………………………………42

FIGURE 5.32 Movement of an abutment after Northridge Earthquake 1994 (11) ……………..42

FIGURE 5.33 Separation of abutment (11) ……………………………………………………..42

FIGURE 5.34 Transversal movement of abutment (11) ………………………………………..42

FIGURE 5.35 Pounding damage at abutment (11) ………………………………………………42

FIGURE 5.36 Failure of two anchor bolts for a girder after Northridge EQ 1994 (11) …………43

FIGURE 5.37 Failure of an elastomeric bearing due to longitudinal movement of girder (10)…43

FIGURE 5.38 Failure of elastomeric bearing and cracking of girder beam (10) ……………….43

FIGURE 5.39 View of a failed elastomeric bearing pad after Izmit EQ 1999 (10) ……………..43

FIGURE 5.40 Spalling near location of anchor bolts after Northridge Earthquake 1994 (11) ….43

FIGURE 5.41 Separation of soil at column base of a pier after Northridge EQ 1994 (11) …….44

FIGURE 5.42 Separation of column from the surrounding soil after Northridge EQ1994 (11) ..44

xiii

FIGURE 5.43 Disturbed soil at the base of column after Northridge EQ 1994 (11) ……………44

FIGURE 5.44 Barrier cracking after Northridge Earthquake 1994 (11) ……………………….44

FIGURE 5.45 Minor damage on the deck of a bridge after Northridge EQ 1994 (11) ………….45

FIGURE 5.46 Curb separation after Northridge Earthquake 1994 (11) ………………………..45

FIGURE 5.47 Collapse of asphalt pavement due to washout after Northridge EQ 1994 (11) ….45

FIGURE 5.48 Surface damage to highway pavement after Northridge EQ 1994 (11) ………….45

FIGURE 5.49 Settlement damage on approaches after Northridge EQ 1994 (11) ……………..45

FIGURE 5.50 The cracking of pavement due to pounding and settlement the bridge (15) …….46

FIGURE 5.51 Transversal movement of bridge deck after Taiwan EQ (15) ……………………46

FIGURE 5.52 View of RC bridge deck spalling after Taiwan EQ 1999 (11) …………………..46

FIGURE 5.53 Bearing movement and concrete spalling on the pier (11) ………………………46

FIGURE 5.54 Tilted rocker bearings (9) ………………………………………………………..47

FIGURE 5.55 Shift of bearings after collapse (11) ……………………………………………..47

FIGURE 5.56 Bearing movement (11) ………………………………………………………….47

FIGURE 5.57 Elastomeric bearing movement and spalling of girder concrete (10) ……………47

FIGURE 5.58 Sliding of elastomeric bearing (10) ………………………………………………47

FIGURE 5.59 Yield at pin support (in red color) (11) …………………………………………48

FIGURE 5.60 Buckling of web near lower flange and crack in pedestal (11) …………………..48

FIGURE 5.61 Local buckling of beam web near haunch (11) ………………………………….48

FIGURE 5.62 Damage at the bottom of the RC collector beam (11) ……………………………48

FIGURE 5.63 Buckling in the girder due to pounding (11) ……………………………………49

FIGURE 5.64 Steel box girder movement and collapse of bearings (11) ………………………49

FIGURE 5.65 Heavy damage in RC box girder bridge (15) …………………………………….49

FIGURE 5.66 Yielding at bolted connector beam (11) ………………………………………….49

FIGURE 5.67 Twisted steel braces (11) …………………………………………………………50

FIGURE 5.68 Shear cracks at the RC bridge girder near support (26) ………………………….50

FIGURE 5.69 Abutment slumping after Taiwan EQ 1999 (26) …………………………………50

FIGURE 5.70 Large cracks at abutment wing wall and slope (26) ……………………………50

FIGURE 5.71 Separation of the RC superstructure and the abutment (11) ……………………..50

FIGURE 5.72 Pounding of steel girder to the abutment (11) ……………………………………50

xiv

FIGURE 5.73 Concrete spalling and cracking due to pounding of RC box girder after Izmit EQ

1999 (10) ………………………………………………………………………………………..51

FIGURE 5.74 Compression failure on the top of RC bridge pier after Taiwan EQ 1999 (15) ….51

FIGURE 5.75 Separation of the superstructure and the abutment (11) ………………………….51

FIGURE 5.76 Heavily damaged RC bridge pier (15)……………………………………………51

FIGURE 5.77 Ground crack extending diagonally down slope under bridge (11) ……………..52

FIGURE 5.78 Retaining wall failure after Taiwan EQ 1999 (26) ………………………………52

FIGURE 5.79 Settlement around RC bridge pier (11) …………………………………………..52

FIGURE 5.80 Spalling of concrete at the top of the pile for abutment after excavation (11) …..52

FIGURE 5.81 Sand boils and ground cracks after Kobe EQ 1995 (11) …………………………52

FIGURE 5.82 10 cm gap between ground and RC bridge pier (26)…………………………….52

FIGURE 5.83 Ejected sand and lateral spreading around RC bridge pier (11) …………………53

FIGURE 5.84 Soil failure due to the fault movement through RC bridge piers after Duzce EQ

1999 (10) ………………………………………………………………………………………..53

FIGURE 5.85 Buckled seismic restrainers (11) …………………………………………………53

FIGURE 6.1 Level 1 inspection form …………………………………………………………..58

FIGURE 6.2 Level 1 inspection scheme ………………………………………………………..59

FIGURE 6.3 Level 2 inspection form ………………………………………………………….62

FIGURE 6.4 Road closure sign …………………………………………………………………66

FIGURE 7.1 Different bridge damage cases that steel plates can be used (11) …………………68

FIGURE 7.2 Different bridge damage cases that fill can be used (15,11) ……………………..69

FIGURE 7.3 Temporary shoring of bridge after Taiwan Earthquake 1999 (11) ………………..70

FIGURE 7.4 Another view of temporary shoring after Taiwan Earthquake 1999 (11) …………70

FIGURE 7.5 View of temporary shoring to maintain access after Kobe Earthquake 1995 (27) ..71

FIGURE 7.6 View of temporary shoring to prevent total collapse of bridge (27) ………………71

FIGURE 7.7 View of temporary shoring to prevent total collapse of steel bridge (27) …………71

FIGURE 7.8 View of temporary shoring to prevent total collapse of steel bridge (27) …………72

FIGURE 7.9 View of temporary shoring to support RC bridge (15) ……………………………72

FIGURE 7.10 View of temporary shoring to prevent total collapse of bridge (27) ……………..72

FIGURE 7.11 View of temporary support to prevent total collapse of steel bridge (27) ……….73

FIGURE 7.12 View of temporary support to prevent total collapse of steel girder bridge (15) ...73

xv

FIGURE 7.13 View of temporary support to prevent total collapse of steel girder bridge (11) ..73

FIGURE 7.14 Deflection measurement …………………………………………………………75

FIGURE 7.15. Crack comparator (CTL, Inc.) …………………………………………………..76

FIGURE 7.16. Crack monitor (Avonguard) …………………………………………………….76

FIGURE 7.17. Portable strain indicator (Measurements Group, Inc.) …………………………..77

FIGURE 8.1 View of bridge superstructure after the earthquake (11) ………………………….79

FIGURE 8.2 More damage to the bridge superstructure (11) …………………………………80

FIGURE 8.3 Different views of bridge superstructure (11) ……………………………………81

FIGURE 8.4 The Level 1 form, Bridge Example 1, Steps 1 and 2 ……………………………81

FIGURE 8.5 Damage to one of the bridge piers (11) …………………………………………..82

FIGURE 8.6 The Level 1 Form, Bridge Example 1, Step 3 …………………………………….82

FIGURE 8.7 Damage to the bridge bearings (11) ……………………………………………….83

FIGURE 8.8 The level 1 Form, Bridge Example 1, Step 4 ……………………………………84

FIGURE 8.9 View of substructure and soil of the bridge (11) ………………………………….84

FIGURE 8.10 Completed Level 1 Inspection Form for Example Bridge 1 ……………………..85

FIGURE 8.11 View of the Parkfield Highway Bridge after the earthquake (11) ……………….85

FIGURE 8.12 View of the damaged bridge components (11) ………………………………….86

FIGURE 8.13 Completed Level 1 form for Example Bridge 2 …………………………………87

FIGURE 8.14 Superstructure damage of the third example bridge after earthquake (11) ………88

FIGURE 8.15 Substructure damage of the bridge (11) …………………………………………89

FIGURE 8.16 Completed Level 1 Inspection form for bridge example 3……………………….90

FIGURE 8.17 Different views from the superstructure of the bridge (11)………………………91

FIGURE 8.18 Different views of damage from the damaged bridge (11) ………………………92

FIGURE 8.19 Completed Level 1 form for the example bridge (53-1620D) …………………93

FIGURE 8.20 Completed Level 2 Inspection Form, Bridge Example 1 (53-1620D) …………..94

FIGURE 8.21 Different views of the superstructure of the second example bridge (11) ………95

FIGURE 8.22 Different views of the superstructure of the bridge (11) ………………………..96

FIGURE 8.23 Different views of the superstructure of the bridge (11) ………………………..97

FIGURE 8.24 Different views of the second example bridge (11) ……………………………..98

FIGURE 8.25 Completed Level 2 Inspection Form, Bridge Example 2 ……………………….99

FIGURE 8.26 Completed Level 2 Inspection Form, Bridge Example 2 ………………………100

xvi

FIGURE A.1 Types of Road Closure sign and dimensions …………………………………..108

FIGURE A.2 The pictures of Road Closure sign, bridge signpost and emergency cabinet …..108

FIGURE A.3 The map of primary routes in Vincennes District ………………………………109

1

1. INTRODUCTION

1.1. Object and Scope

It is acknowledged that the most damaging earthquake within the state took place on September

27, 1909 near the Illinois border between Vincennes and Terre Haute. Both nonstructural and

structural damage occurred to the buildings in this area, and it was felt strongly in the southwest

of Indiana including Indianapolis. Other significant earthquakes have been felt in the state with

epicenters occurring in the southwestern corner. Indiana has also experienced damage from

earthquakes originating in neighboring states.

Unfortunately, due to the long recurrence interval of strong earthquakes in Mid-America, a large

inventory of structures has accumulated without explicit consideration of seismic resistance.

Highway bridges are a significant component of this inventory. The seismic vulnerability of

highway bridges constructed within the state, especially in southwestern portion of Indiana,

presents a problem of serious consequences.

The seismic history of the region, and the classification of the Southwestern portion of Indiana as

AASHTO Seismic Performance Zone 2, has resulted in an increased awareness regarding the

need to be prepared against the potential threat presented by earthquakes. As one of the first

steps in the development of seismic policy for the state, the Indiana Department of

Transportation has decided to prepare highway personnel for the post-earthquake safety

evaluation of bridges. Since the highway system is an essential component of the lifelines to a

community following an earthquake disaster, it is important to quickly assess its safety and

functionality, and provide temporary retrofits to quickly restore transportation routes. A post-

earthquake bridge inspection plan with properly trained personnel is a key component of the

disaster response plan to restore quickly the transportation routes in order to permit the access of

relief and reconstruction assistance.

2

The main purpose of this handbook is to provide INDOT personnel of various backgrounds with

a rapid and effective methodology for the post-earthquake safety inspection of bridges and roads

in Indiana. This methodology is intended to promote and maintain the uniformity of the

inspection as much as possible while assessing and rating bridge and road damage. It is likely

that the first personnel to be dispatched or that will reach damaged structures will not be

engineers. Furthermore, depending on the extent of the damage that may occur, it is possible that

there will not be an adequate number of experienced engineers to survey every structure.

This handbook contains the material necessary for a systematic safety evaluation of bridge

structures and roads for a wide range of INDOT personnel. In the handbook, the necessary

material is arranged according to two inspection levels. Level 1 inspection consists of the rapid

visual evaluation of the bridges and roads in the affected area to establish obviously unsafe

structures and roads. The Level 1 section of the handbook is intended for INDOT personnel with

a broad range of backgrounds. Level 2 inspection consists of a more in-depth safety evaluation of

bridges and roads, as well as temporary repair and long-term monitoring techniques. This

segment is designed specifically for INDOT engineers. The Level 2 inspection team will be

expected to make a more detailed structural and geotechnical post-earthquake condition

assessment of the bridge. The inspection team may choose to reduce the speed of incoming

vehicles as they approach the bridge, to restrict access only to emergency vehicles, or to close the

bridge entirely to traffic. The team may also consider, where appropriate, if temporary shoring or

other strengthening and long term monitoring measures are required.

The organization and the management of the post-earthquake inspections are under the

jurisdiction of INDOT, unless declared a State Disaster by the Governor and taken over by

SEMA, and it is outside the scope of this handbook

3

1.2. Level 1 Inspection

The main objective of the Level 1 Inspection section is to prepare INDOT personnel with a wide

range of backgrounds for the visual safety inspection of highway bridges and roads immediately

following an earthquake. The purpose of the Level 1 inspection is to restrict the traffic on unsafe

bridges (Red Tag) and roads, to identify those that are safe (Green Tag), and to indicate those in

need of further evaluation (Yellow Tag). The information gathered also will be used to develop

rough estimates of the extent of the damage. This information will be available to prioritize the

work of Level 2 teams. Level 1 inspection is deemed appropriate for all bridges and roads in the

affected area immediately after the earthquake. The Level 1 inspection consists of aerial view

and/or drive through. Appropriate actions should follow the inspection. Bridges deemed unsafe

must be red tagged and closed to traffic. Roads that cannot be traversed must be identified.

Finally, the geographical extent of the damage should be identified.

The outline of the Level 1 components of the handbook are:

q Brief description of the seismology of Indiana

q Illustration of typical Indiana bridges

q Examples of collapsed bridges and damaged roads

q Preparations necessary for Level 1 inspection

q Teams

q Description of bridge closing procedures

q Suggested equipment and inspection form

q Review/Assignments

1.3. Level 2 Inspection

The top priority of the Level 2 inspection should be the inspection of all the yellow tagged

bridges and roads identified during the Level 1 inspection. In addition to closing unsafe bridges

and identifying routes that cannot be traversed, the Level 2 inspection team will make a more

detailed assessment of the bridges in the affected area. The assessment should include

4

geotechnical and structural aspects. Teams must contain INDOT personnel under the supervision

of an experienced INDOT engineer. The main objective of the material related to the Level 2

inspection in this handbook is to prepare the team members to make a proper structural and

geotechnical assessment of the condition of bridges following an earthquake. These teams can

further refine the conclusions about the Level 1 inspection yellow tagged bridges, restrict their

use for only emergency vehicles, or open the bridge to traffic. At the same time, after completing

the inspection of Yellow tagged bridges, Level 2 teams should inspect the Red tagged bridges in

critical routes to determine if they may be put back into operation with in-house repairs. This

inspection team will also provide recommendations for short-term repair and whether it should

be conducted in house or a consultant is needed. It will also indicate if shoring and monitoring of

the damaged bridges is needed. This inspection will be conducted using ground transportation.

The following is an outline of the items in this handbook pertaining to the Level 2 inspection:

q Examples of damage to typical Indiana bridges

q Preparations necessary for Level 2 bridge assessment

q Teams

q Necessary equipment and inspection form

q Techniques for temporary repair and long-term monitoring techniques

q Review/Assignments

5

FIGURE 1.1 Flow-chart of Post-Earthquake Response Assessment

Earthquake

Level 1 Team

Red Tag Moderately Damaged

but Not Collapsed (Yellow)

Level 2 Team

Red Tag

Limited Entry (Yellow Tag)

Green Tag

Bridge in Service

Post Earthquake Detailed Investigation by Design Engineering Staff / Consultants

Repair or Rebuild

Temporary Repair and Monitoring

Green Tag

Critical Routes, Repair

In-House Possible

6

7

2. EARTHQUAKE ENGINEERING PRINCIPLES

2.1. Earthquakes

An earthquake is the movement of the ground (vibration, distortion, sliding) or Earth's surface

associated with a release of energy in the Earth's crust. This energy is generated by a sudden

movement of segments of the crust, by a volcanic eruption, or by manmade explosions. The

movement of the crust of the earth causes most of powerful earthquakes. The crust may first

bend and then, when the stress exceeds the strength of the rocks, rupture and settle to a new

position. In the process of rupture, vibrations called "seismic waves" are generated. These waves

travel outward from the source of the earthquake along the surface and through the Earth at

varying speeds depending on the material through which they move.

2.2. The Structure of the Earth

The idealized view of the earth, shows it like an egg with three different layers, it is helpful to

the people those who are interested in earthquake effects (Figure 2.1). These main three layers

have very different physical and chemical properties. The earth has a crust (shell), a mantle (egg

white) and a core (the yolk). The outer layer (shell), which averages about 70 kilometers in

thickness, consists of about a dozen large, irregularly shaped plates that slide over, under and

past each other on top of the partly molten inner layer (Figure 2.2). Most earthquakes occur at

the boundary zones where the plates meet. Plate boundaries are spreading zones, transform faults

and subduction zones (Figure 2.3). Along spreading zones or ridges, molten rock rises, pushing

two plates apart and adding new material at their edges. Most spreading zones are found on the

bottom of oceans such as North American and Eurasian plates that are spreading apart along the

Mid-Atlantic ridge. Ridges usually have earthquakes at shallow depths (within 30 kilometers of

the surface). Transform faults are found where plates slide past one another. An excellent

example of a transform-fault plate boundary is the San Andreas Fault, along the coast of

California and northwestern Mexico. Earthquakes at transform faults tend to occur at shallow

8

depths and form fairly straight linear patterns. Finally, subduction zones (trenches) are found

where one plate overrides, or subducts, another, pushing it downward into the mantle where it

melts. An example of a subduction-zone plate boundary is found along the northwest coast of the

United States, western Canada, and southern Alaska and the Aleutian Islands. Subduction zones

are characterized by deep-ocean trenches, shallow to deep earthquakes, and mountain ranges

containing active volcanoes (Figure 2.4).

Earthquakes can also occur within plates, although plate-boundary earthquakes are much more

common. Less than 10 percent of all earthquakes occur within plate interiors. As plates continue

to move and plate boundaries change over geologic time, weakened boundary regions become

part of the interiors of the plates. These zones of weakness within the continents can cause

earthquakes in response to stresses that originate at the edges of the plate or in the deeper crust.

The New Madrid earthquakes of 1811-1812 and the 1886 Charleston earthquake occurred within

the North American plate

Earthquakes are produced by sudden slip and rupture along the faults. A fault can be defined as a

roughly planar fracture in the Earth's crust along which slip, the relative movement of the two

sides has occurred. Faults can be active which means they currently hold the potential for

producing earthquakes or inactive which means they already have slipped once and produced

earthquakes but they are now "frozen" solid. If the tectonic environment of an area changes,

however, inactive faults can sometimes be reactivated.

In terms of size, faults can be anywhere from less than a meter to over a thousand kilometers in

length, with a width of a similar scale. The depth of very large faults is constrained by the

thickness of that portion of the crust and lithosphere in which brittle fracture can occur. In

southern California, this depth is roughly 15 to 25 kilometers. The kind of faults seismologists

study are generally at least a square kilometer in area, and typically more than a 100 km2 in area.

Faults of this size or greater can rupture violently enough to produce significant earthquakes.

There are approximately 200 faults in southern California that are considered major faults. Three

basic types of faults can be identified based on the relative movement. These are normal faults,

reverse faults and strike-slip faults. These fault types are illustrated in Figure 2.6.

9

2.3. Seismic Waves

After rupture of the fault, seismic waves or vibrations are generated. These waves are divided

into two main categories: Body waves (longitudinal P waves and transversal S waves), Surface

waves (Rayleigh Waves and Love waves). The first kind of body wave is the P wave (primary

wave). This is the fastest type of seismic wave. The P wave is able to move through solid rock

and fluids, like water or the liquid layers of the earth. Depending on the stiffness and the

medium, these waves travel at speeds in the range 3-8 km/sec. It pushes and pulls the rock it

moves through just like sound waves push and pull the air. The people only feel the bump and

rattle of these waves. The second type of body wave is the S wave (secondary wave), which is

the second wave people can feel in an earthquake. An S wave is slower than a P wave and can

only move through solid rock. This wave moves rock up and down, or side-to-side. Typically,

the speed of the S-wave is 1-4 km/sec.

The first type of surface wave is called a Love wave; it's the fastest surface wave and moves the

ground from side-to-side. The other kind of surface wave is the Rayleigh wave. A Rayleigh wave

rolls along the ground just like a wave rolls across a lake or an ocean. Because it rolls, it moves

the ground up and down, and side-to-side in the same direction that the wave is moving. Most of

the shaking felt from an earthquake is due to the Rayleigh wave, which can be much larger than

the other waves. Figure 2.5 gives a visual interpretation of these waves.

In a major earthquake, people near the epicenter can feel, and sometimes see, the earth move

strongly. People further away may feel the motion too, although less strongly. The movement

travels away from the epicenter, spreading out in waves and becoming smaller and weaker as

they travel. Seismometers are the main devices to detect and record these motions even when

they are far too small for humans to feel. In addition to seismometers, accelerometers are utilized

to measure the acceleration of the ground. Figure 2.7 shows a typical ground acceleration record

produced by the Duzce Earthquake (time vs. acceleration) plotted in three different directions,

transversal, lateral and vertical.

10

FIGURE 2.1 View of the layers of the Earth (20)

FIGURE 2.2. The thickness of the layers of the Earth (20)

11

FIGURE 2.3 The map of the plates on the Earth (21)

FIGURE 2.4 The cross section that illustrates the main types of plate boundaries (22)

12

FIGURE 2.5 The illustration of the seismic waves (24)

13

FIGURE 2.6 The illustration the main types of faults (23)

FIGURE 2.7 A typical near source acceleration record taken after Duzce Earthquake (25)

14

2.4. Bridge Behavior under Earthquake Excitation

The travel of the seismic waves from source to the bridge site and typical ground acceleration

and displacement diagrams are illustrated in Figure 2.8. The behavior and performance of bridge

structure under earthquake excitation is mainly influenced by proximity of the bridge to the fault

and bridge site conditions. These factors affect the intensity of ground shaking and deformation

of the bridge structure directly. In addition to the external effects, the performance of the bridge

is influenced by structural configuration, materials utilized, connections between different

elements of the bridge structure and fixity of the foundations. The bridge structures can be

assumed to be shaken in longitudinal and transversal directions. Although this simplification

does not reflect the real behavior, it may help to understand the response of the bridges against

earthquakes. Figure 2.9 shows the behavior of a two span monolithic highway bridge under

longitudinal earthquake loading. The illustrated end connections such as roller supports and fixed

support are extensively applied in highway bridge structures. During an earthquake, due to the

shaking, inertial forces are created on the bridge structure depending the nature of the ground

motion and the structural characteristics of the bridge. These inertial forces are represented as

horizontal force on the structure with the corresponding deformation demand. The bridge should

be able to resist these inertial forces and deformation demand in order to keep its structural

integrity. Otherwise, local or entire collapses may occur. In Figure 2.9, pier (mid-column) of the

bridge is resisting the longitudinal movement while the superstructure is taking the longitudinal

deformation demand and dissipating it through the gaps between superstructure and abutments.

Similarly, in the lateral direction the bridge has to resist earthquake force. As it can be seen from

the Figure 2.10, the bridge structure behaves as a simple beam in the lateral direction. Abutments

resist the lateral movement of the superstructure.

The illustrated bridge example shows a typical flexible bridge structure. The major source of this

flexibility is the connection/interface details between the bridge elements. This flexibility brings

the advantage of the construction of economically feasible bridge structures. But at the same

time it increases the seismic vulnerability of the bridge. In the past, a number of bridge collapses

have occurred due to the lack of behavior based design. With the help of the lessons taken form

15

past earthquake damages, bridges are constructed appropriately but a number of bridges

currently under use need modifications for earthquake resistance.

FIGURE 2.8 The occurrence of the earthquake and traveling of the waves to the bridge site (1)

FIGURE 2.9 Typical longitudinal earthquake loading and deflected shape of a bridge (1)

16

FIGURE 2.10 Typical lateral earthquake loading and deflected shape of a bridge (1)

17

3. SEISMICITY OF INDIANA

3.1. General

There has been increasing awareness about seismic hazard in the Midwest region of United

States due to the records of past earthquakes and the evidence of prehistoric earthquake activity.

Since 1875, Indiana has experienced at least 40 earthquakes that reportedly were felt by

residents. Recent studies have shown evidences of the occurrence of at least 6 major earthquakes

with epicenters in Indiana during the last 12,000 years with the help of the surveys of hundreds

of ancient sand blows (See Ref. 28). According to the results of these studies, an earthquake that

had a magnitude of more than 7.5 occurred about 6,000 years ago in the Wabash River Valley

near the Indiana-Illinois border. Numerous prehistoric earthquakes of magnitude 6 to 7 have

occurred in Southern Indiana and Illinois although the last two centuries earthquakes with

epicenters in Indiana have been relatively minor events. Geologic evidence of these earthquakes

is in the form of soil liquefaction that induced intrusions of sand and gravel in river sediments.

These types of formations have been discovered at more than 100 widespread sites in the

Wabash River Valley and along its tributaries (Figure 3.1). These intrusions permit the use of

geologic, archaeological, and engineering techniques to determine when the earthquakes

occurred, as well as their epicenters and approximate magnitudes.

The liquefaction occurs when violent shaking during strong earthquakes causes; loose, clean,

uniformly graded and saturated underground soil layers (sands, gravels and non-plastic silts) to

behave like a fluid under pressure (Figure 3.1). Occasionally, the pressure forces the liquefied

soil to move up through cracks in the overlying soil and flow out over the surface. Sand blow is a

good example of this situation (Figure 5.81). After the sand blow formed, generally it was

covered by layers of silt deposited during floods. When liquefaction occurs, the strength and

bearing capacity of soil decreases. The effects of liquefaction can range from massive landslides

to small slumps or spread of soil. Bridge sites particularly crossing over water can have tendency

to produce liquefaction by considering their general hydrologic and geologic conditions such as

18

the existence of intense fluvial and alluvial deposits. Concurrently, the susceptibility of a soil

layer to liquefaction does not mean that the liquefaction will occur in a given earthquake.

The earthquakes that occurred since 1811-1812 in and near the State can be seen on a Midwest

U.S. map (Figure 3.2). This figures shows that southern portion of State has an important

earthquake potential. In Figure 3.3, the mapped and assumed faults through the State are shown.

Beside the in-state faults, an earthquake that may happen on the New Madrid Fault, which is one

of the important earthquake zones throughout the U.S, may affect the State. Because of the active

portion of the New Madrid Fault Zone is covered by thick alluvial deposit layers, there is no

clear surface evidence that indicates the present fault movement. However, micro-earthquake

records allows the marking out of the active portions of the fault zone.

As an in-state fault zone, Wabash Valley fault zone lies in the southwestern part of the Indiana

(Figure 3.3). Three earthquakes of 4.5 ≤ mb ≤ 5.1 and five of 5.2 ≤ mb ≤ 5.8 have occurred in this

zone. The most important one occurred on November 9, 1968 with a magnitude of 5.5 (mb). A

possible strong earthquake that will occur in New Madrid Seismic zone has a strong damage

potential in most parts of Indiana. The probability for such an earthquake of magnitude 6.0 or

greater is given as significant in the near future, 90% chance by the year 2040. An earthquake

with a magnitude equal to that of the 1811- 1812 quakes could result in great loss of life and

property damage in the billions of dollars. Common belief between scientists is that the region

could be overdue for a large earthquake. Only intense research, preparation and public awareness

may be able to prevent such losses.

FIGURE 3.1 The view of the liquefaction mechanism and the map of Southern Indiana regions where ancient sand blows have been found due to prehistoric earthquakes (28)

19

FIGURE 3.2 Approximate Epicenters Powerful Earthquakes since 1811-1812 (3)

20

FIGURE 3.3. The Fault Map of State of Indiana (4)

3.2. Earthquake History of Indiana

The great New Madrid earthquakes of 1811 and 1812 have strongly affected Indiana, particularly

the southwestern part, but there is little information available from these earlier times other than

personal observations. The New Madrid Seismic Zone lies within the central Mississippi River

Valley, extending from northeast Arkansas, through southeast Missouri, western Tennessee,

western Kentucky to southern Illinois. (Figure 3.2) Between 1811-1812, 4 catastrophic

earthquakes occurred during three month period with estimated magnitudes greater than 7 on

Richer Scale.

21

On the basis of the damaged area (600,000 km2), the area of perceptibility (5 million km2) and

the complex geological and topographical changes ranked these earthquakes of 1811-1812 as the

largest in the United States. The area of strong shaking associated with these shocks is two to

three times larger than that of the 1964 Alaska Earthquake and 10 times larger than that of the

1906 San Francisco Earthquake. The New Madrid seismic zone is named after of the town of

New Madrid, Missouri that was the closest settlement to epicenters of 1811-1812 earthquakes.

At that time, St. Louis and other major cities in US were lightly settled. These series of

earthquakes were felt throughout US and Canada.

The magnitudes of the 1811-1812 New Madrid earthquakes varied considerably. The first and

second earthquakes occurred in Arkansas (December 16, 1811 - two big shocks on the same day-

mb=7.2, Ms= 8.6 and MM=VII-VIII) and the third and fourth in Missouri (January 23, 1812 mb=

7.1, Ms= 8.4 and February 7, 1812 mb=7.3 and Ms=8.7). The first earthquake caused only slight

damage to man-made structures, mainly because of the sparse population in the epicentral area.

The extent of the area that experienced damaging earth motion (MM intensity greater than or

equal to VII) is estimated to be 600,000 km2. However, shaking that was strong enough to alarm

the general population (MM intensity greater than or equal to V) occurred over an area of 2.5

million km2. Although the motion during the first shock was violent at New Madrid, Missouri, it

was not as heavy and destructive as that caused by two aftershocks about 6 hours later. Only one

life was lost in falling buildings at New Madrid, but chimneys tumbled and houses were thrown

down as far distant as Cincinnati, St. Louis and in many locations in Kentucky, Missouri, and

Tennessee. The intensity at the epicenter of this earthquake is thought to be at the MM intensity

X-XI level. The heavy damage imposed on the land by these devastating earthquakes led

Congress to pass in 1815 the first disaster relief act providing the landowners of destroyed

ground with an equal amount of land in unaffected regions.

In 1812 (January 23), almost a month later than the previous ground shaking, a third big shock

hit the region. The epicenter of this shock was at New Madrid, Missouri. Finally, the fourth and

largest earthquake of the 1811-1812 series occurred on February 7, 1812. Several destructive

shocks followed the main shock on February 7, the last of which equaled or surpassed the

magnitude of any previous event. The town of New Madrid was destroyed. In the city of St.

22

Louis, many houses were damaged severely and their chimneys were thrown down. The affected

area was characterized by general ground warping, ejections, fissuring, severe landslides, and

caving of stream banks.

In 1876, twin shocks were felt fifteen minutes apart each other over an area of 60,000 mi2. A

shock in 1887 centered near Vincennes was felt over 75,000 mi2 and shock damaged property

and frightened people in church at Evansville.

Another damaging earthquake originating in Indiana occurred on April 29, 1899 and rated

intensity as MM VI-VII on the Modified Mercalli Scale. It was strongest at Jeffersonville and

Shelbyville; at Vincennes, chimneys were thrown down and walls cracked. It was felt over an

area of 40,000 mi2.

The most destructive Indiana earthquake occurred on September 27, 1909 near the Illinois border

between Vincennes and Terre Haute. Some chimneys toppled, several building walls were

cracked, and light connections were severely damaged. It was felt in Indianapolis, Oakland City

and over an area of 30,000 mi2 including the southwestern half of Indiana, all of Illinois and

parts of Iowa, Kentucky, Missouri, Arkansas, and probably in parts of Kansas. In Terre Haute,

two chimneys were toppled and plasters were cracked. At Covington, north of Terre Haute in

Fountain County, a few chimneys were downed and windows were broken. The intensity of the

earthquake was rated as MM VII on the Modified Mercalli Scale.

On March 2, 1937, a shock centering near Anna, Ohio, threw objects from shelves at Fort Wayne

and some plaster fell. Plaster was also cracked at Indianapolis. Six days later, another shock

originating at Anna brought pictures crashing down and cracked plaster in Fort Wayne and was

strongly felt in Lafayette.

On November 7, 1958, an earthquake originating near Mt. Carmel, Illinois, caused plaster to fall

at Fort Branch. Roaring and whistling noises were heard at Central City and the residents of

Evansville thought there had been an explosion or plane crash. It was felt over 33,000 mi2 of

Illinois, Indiana, Missouri, and Kentucky.

23

The earthquakes originating in neighboring states have caused considerable damage in Indiana.

One of the worst occurred on November 9, 1968 and centered near Dale in southern Illinois. The

shock, a magnitude 5.5 (Mb), was felt over 580,000 mi2 and other states including all of Indiana.

Intensity VII was reported from Cynthiana where chimneys were cracked, twisted, and toppled.

Property damage in the area consisted mainly of fallen bricks from chimneys, broken windows,

toppled television aerials, and cracked or fallen plaster. In the epicentral area, near Dale,

Hamilton County, MM intensity VII was characterized by downed chimneys, cracked

foundations, overturned tombstones, and scattered instances of collapsed parapets. Most

buildings that sustained damage to chimneys were 30 to 50 years old. About 10 kilometers west

of Dale, near Tuckers Corners, a concrete and brick cistern collapsed. A large amount of

masonry damage occurred at the City Building at Henderson, Kentucky, 80 kilometers east-

southeast of the epicenter. Moderate damage to chimneys and walls occurred in several towns in

south-central Illinois, southwest Indiana, and northwest Kentucky. The earthquake had been felt

over all or parts of 23 States: from southeast Minnesota to central Alabama and Georgia and

from western North Carolina to central Kansas. People had also felt it in multistory buildings in

Boston, Massachusetts and southern Ontario, Canada.

More recently, Indiana was shaken in 1987 by a quake centered near Olney, Illinois, just west of

Vincennes.

In Figure 3.4, the peak acceleration rates as percent gravity (g) are shown with 10% probability

of exceedance in 50 years (3). Similarly, estimated MM intensity curves of a 6.5 magnitude

earthquake in New Madrid Fault can be seen from Figure 3.5.

24

FIGURE 3.4 The peak acceleration map with 10% probability of exceedance in 50 years. (5)

FIGURE 3.5. Estimated MM intensity map for 6.5 magnitude earthquake in NMFZ (6)

25

4. INDIANA BRIDGE STRUCTURES

In this chapter, typical examples of highway bridges located in the Vincennes district of Indiana,

which is considered to be in the area of seismic risk, are shown (9). They are classified according

to their structural properties (8). In addition, the types of bearings are also illustrated.

ARCHES:

q Unreinforced Concrete Arch

q Reinforced Concrete Arch

q RC Arch Open Spandrel

q Precast Concrete Arch Underfill

26

q Metal Pipe Arch

q Multi-Plate Arch

SLABS:

q Reinforced Concrete Slab Underfill

q Continuous Reinforced Concrete Slab

27

q Precast Concrete Slab Underfill

GIRDERS:

q Reinforced Concrete Girder

q Steel Girder

28

q Steel Box Girder

q Riveted Plate Girder

BEAMS:

q Prestressed Concrete Box Beam-Spread

Boxes

q Prestressed Concrete I-Beam

29

q Continuous Prestressed Concrete I-Beam

q Steel Beam

q Composite Continuous Steel Beam

TRUSSES:

q Steel Pony Truss

q Steel Through Truss

30

q Continuous Steel Tied Arch-Truss

BEARINGS:

q Integral

q Contact

q Rocker Bearing

31

q Elastomeric Bearing

RESTRAINER:

PIPELINES:

32

33

5. POSSIBLE TYPES OF BRIDGE AND ROADWAY DAMAGE

5.1. General

Highway bridges have a structural combination of superstructure, substructure and support

bearings. Superstructure consists of all the structural parts of the bridges that make the horizontal

span like slab, beams, girders or truss members. Substructures consist of structural parts of the

bridges that provide the support to the horizontal span like abutments, piers and columns.

Bearings are placed between the superstructure and substructure. Figure 5.1 shows all the key

components of a typical highway bridge.

FIGURE 5.1 View of different structural parts of a typical highway bridge

5.2. Classification of Damage

The Level 1 Inspection can be summarized as follows:

§ Green Tag - Safe for Traffic

§ Yellow Tag - Require Level 2 Evaluation (or quickly repairable)

§ Red Tag - Unsafe for traffic (must be closed)

More detailed damage classification tables are given in the Figure 5.2 by considering the

different components of highway bridges.

34

FIGURE 5.2. Damage classification tables for bridges

GREEN TAG YELLOW TAG RED TAGTraffic Barriers and Railings

damage does not impede traffic

damage impedes traffic

Movement at Expansion Joints

1) < 1in. offset in vertical or horizontal alignment

1) 1 to 6 in. offset in vertical or horizontal alignment

> 6 in. offset in vertical or horizontal alignment

2) spalling of concrete cover

2) local buckling of steel stringers

Seats at Expansion Joints

< 1 in. reduction in seat length

> 1in. reduction in seat length

unseating

Bearings visible damage

GREEN TAG YELLOW TAG RED TAGColumns, Cross-Beams and Piers

1) vertical cracks in RC beams.

1) diagonal cracks in RC beams, columns and piers.

1) bar buckling in RC beams, columns and piers

2) loss of concrete cover

2) local buckling in steel columns

3) any crack in steel beams or columns

Column/ 1) any cracks.

Beam Joints 2) loss of concrete cover

Footings/ Pile Caps

space between columns and surrounding earth

any other damage (e.g., cracks, spalling, rotation)

2) horizontal cracks in RC columns and piers

GREEN TAG YELLOW TAG RED TAGAbutments spalling at

expansion jointany other damage (e.g., cracks, spalling, rotation)

Approach/ Abutment interface

< 1 in. settlement 1 to 6 in. settlement > 6 in. settlement

Roadway Normal Driving Conditions

Reduced Speed, or Quickly Repairable

Impassible

35

5.3. Level 1 Examples of Bridge and

Roadway Damage

In this section examples of bridge damage are

given. The classification follows the damage

classification tables given in previous section.

The damage examples are organized in the

categories of:

q Bridge Collapse / Bridge Partial

Collapse / Roadway Closed

q Superstructure Damage

q Substructure Damage

q Bearing Damage

q Soil Problems

Collapse / Partial Collapse / Roadway

Closed

FIGURE 5.3 Collapse of roadway due to slope failure after Duzce EQ 1999 (10)

36

FIGURE 5.4 Collapse of roadway due to fault rupture after Izmit EQ 1999 (10)

FIGURE 5.5 Failure of a prestressed concrete

box beam bridge after Izmit EQ 1999 (10)

FIGURE 5.6. Collapse of deck and piers after

Taiwan Earthquake 1999 (15)

FIGURE 5.7. Failure of a monolithic RC girder bridge after Loma Prieta EQ 1989 (11)

FIGURE 5.8 Collapse of RC girder bridge after Loma Prieta EQ 1989 (11)

FIGURE 5.9 Collapse of bridge deck after Northridge 1994 (11)

37

FIGURE 5.10 Collapse of steel deck bridge after Kobe 1995 Earthquake (12)

In the cases shown in the Figure 5.2 to 5.9,

there is no chance to permit traffic flow, it’s

physically impossible. Highway must be

closed immediately and barriers should be

placed and crisis center should be informed.

Walking on or passing under such kind of

collapsed bridge can be dangerous. This

situation is defined as Red Tag.

Superstructure Damage:

Superstructure damage can be classified as

lateral, longitudinal or vertical movement,

pounding, buckling, cracking, and failure. The

examples shown in Figures 5.11-5.22 are red

tagged bridges except for those shown in

Figures 5.17 - 5.21 considered yellow tagged

examples.

FIGURE 5.11 Excessive longitudinal movement of the bridge deck (15)

38

FIGURE 5.12 The excessive transversal movement of bridge after Izmit EQ (10)

FIGURE 5.13 Excessive longitudinal

movement of steel box girder bridge (11)

FIGURE 5.14 Excessive differential

settlement of the backfill (1)

FIGURE 5.15 Lateral movement of

prestressed RC box girders (10)

FIGURE 5.16 Longitudinal movement of RC

box girders after Duzce EQ 1999 (10)

39

FIGURE 5.17 Vertical offset between decks after Northridge EQ 1994 (11)

FIGURE 5.18 Excessive movement of

expansion joints after Taiwan EQ 1999 (15)

FIGURE 5.19 The expansion of the joints

Taiwan EQ 1999 (15)

FIGURE 5.20 The expansion of the joints after Loma Prieta Earthquake 1989 (11)

FIGURE 5.21 Vertical and horizontal offset on a bridge after Northridge EQ. 1994 (11)

40

FIGURE 5.22 Settlement of Bridge (26)

Substructure Damage:

Substructure damage can be classified as local

buckling, shear key damage, settlement,

tilting, sliding, rotation, cracking, and failure.

The following examples are red tagged bridges

except those shown in Figures 5.30 and

Figures 5.33- 5.35.

FIGURE 5.23 Column failure (11)

FIGURE 5.24 Failure of RC e column (11)

FIGURE 5.25 Failure of the bottom

of the RC bridge column (11)

41

FIGURE 5.26 Failed RC bridge column (11)

FIGURE 5.27 View of damaged RC bridge

pier after Kobe Earthquake 1995 (13)

FIGURE 5.28 Heavy damage in RC bridge

piers after Kobe Earthquake 1995 (14)

FIGURE 5.29 Shear crack in bents after

Northridge Earthquake 1994 (11)

FIGURE 5.30. Shear key failure of a bridge after Northridge Earthquake 1994 (11)

42

FIGURE 5.31 Buckling of steel girders (11)

FIGURE 5.32 Movement of an abutment after

Northridge Earthquake 1994 (11)

FIGURE 5.33 Separation of abutment (11)

FIGURE 5.34 Transversal movement of

abutment (11)

FIGURE 5.35 Pounding damage at abutment

(11)

43

Bearing Damage:

Bearing damages consist of failure, movement

of rocker/elastomeric bearings, shearing,

pullout or bearing of bolts for contact type of

bearings. The examples consist of red tagged

bridges except for the case shown in Figure

5.40.

FIGURE 5.36 Failure of two anchor bolts for a girder after Northridge EQ 1994 (11)

FIGURE 5.37 Failure of an elastomeric bearing due to longitudinal movement of

girder (10)

FIGURE 5.38 Failure of elastomeric bearing

and cracking of girder beam (10)

FIGURE 5.39 View of a failed elastomeric

bearing pad after Izmit EQ 1999 (10)

FIGURE 5.40 Spalling near location of anchor bolts after Northridge Earthquake 1994 (11)

44

Soil Problems:

Slope failures, soil liquefaction, soil fissures,

differential settlements can be generalized as

soil problems. The following examples can be

considered as yellow tagged bridges.

FIGURE 5.41 Separation of soil at column base of a pier after Northridge EQ 1994 (11)

FIGURE 5.42 Separation of column from the surrounding soil after Northridge EQ1994 (11)

FIGURE 5.43 Disturbed soil at the base of

column after Northridge EQ 1994 (11)

Secondary Structure Damage:

FIGURE 5.44 Barrier cracking after Northridge Earthquake 1994 (11)

45

FIGURE 5.45 Minor damage on the deck of a bridge after Northridge EQ 1994 (11)

FIGURE 5.46 Curb separation after Northridge Earthquake 1994 (11)

FIGURE 5.47 Collapse of asphalt pavement due to washout after Northridge EQ 1994 (11)

FIGURE 5.48 Surface damage to highway pavement after Northridge EQ 1994 (11)

FIGURE 5.49 Settlement damage on approaches after Northridge EQ 1994 (11)

46

5.4 Level 2 Behavior of Bridges under

Earthquake Excitation

In this section, bridges that were Yellow

tagged during the Level 1 inspection are

further illustrated to establish whether they

should be Red or Green tag. The damage as

shown can be classified into:

q Roadway/Approach Damage

q Deck Damage

q Bearing Damage

q Superstructure Damage

q Substructure Damage

q Geotechnical Damage

Roadway/Approaches Damage:

FIGURE 5.50 The cracking of pavement due

to pounding and settlement the bridge (15)

Deck Damage:

FIGURE 5.51 Transversal movement of bridge

deck after Taiwan EQ (15)

FIGURE 5.52 View of RC bridge deck

spalling after Taiwan EQ 1999 (11)

Bearing Damage:

FIGURE 5.53 Bearing movement and concrete

spalling on the pier (11)

47

FIGURE 5.54 Tilted rocker bearings (9)

FIGURE 5.55 Shift of bearings after collapse

(11)

FIGURE 5.56 Bearing movement (11)

FIGURE 5.57 Elastomeric bearing movement

and spalling of girder concrete (10)

FIGURE 5.58 Sliding of elastomeric bearing

(10)

48

FIGURE 5.59 Yield at pin support (in red

color) (11)

FIGURE 5.60 Buckling of web near lower flange and crack in pedestal (11)

Superstructure Damage:

FIGURE 5.61 Local buckling of beam web

near haunch (11)

FIGURE 5.62 Damage at the bottom of the RC

collector beam (11)

49

FIGURE 5.63 Buckling in the girder due to

pounding (11)

FIGURE 5.64 Steel box girder movement and

collapse of bearings (11)

FIGURE 5.65 Heavy damage in RC box girder

bridge (15)

FIGURE 5.66 Yielding at bolted connector

beam (11)

50

FIGURE 5.67 Twisted steel braces (11)

FIGURE 5.68 Shear cracks at the RC bridge

girder near support (26)

Substructure Damage:

FIGURE 5.69 Abutment slumping after

Taiwan EQ 1999 (26)

FIGURE 5.70 Large cracks at abutment wing

wall and slope (26)

FIGURE 5.71 Separation of the RC superstructure and the abutment (11)

FIGURE 5.72 Pounding of steel girder to the

abutment (11)

51

FIGURE 5.73 Concrete spalling and cracking due to pounding of RC box girder after Izmit

EQ 1999 (10)

FIGURE 5.74 Compression failure on the top of RC bridge pier after Taiwan EQ 1999 (15)

FIGURE 5.75 Separation of the superstructure and the abutment (11)

FIGURE 5.76 Heavily damaged RC bridge

pier (15)

52

Geotechnical Damage:

FIGURE 5.77 Ground crack extending diagonally down slope under bridge (11)

FIGURE 5.78 Retaining wall failure after

Taiwan EQ 1999 (26)

FIGURE 5.79 Settlement around RC bridge pier (11)

FIGURE 5.80 Spalling of concrete at the top of the pile for abutment after excavation (11)

FIGURE 5.81 Sand boils and ground cracks after Kobe EQ 1995 (11)

FIGURE 5.82 10 cm gap between ground

and RC bridge pier (26)

53

FIGURE 5.83 Ejected sand and lateral spreading around RC bridge pier (11)

FIGURE 5.84 Soil failure due to the fault movement through RC bridge piers after

Duzce EQ 1999 (10)

FIGURE 5.85 Buckled seismic restrainers (11)

54

55

6. POST-EARTHQUAKE SAFETY EVALUATION PRACTICE FOR HIGHWAY

BRIDGES

6.1 Level 1 Inspection

The Rapid Assessment Bridge Inspection Form for the INDOT Level 1 teams is shown in Figure

6.1. This form is for multiple bridges, one bridge per line. Each line should be completed at the

conclusion of the inspection of each bridge site. If a given bridge is in imminent danger of

collapse, the inspection of the bridge shall follow the procedure outlined in this chapter.

Assigned unit personnel (normally two people for each route) should pick up their inspection kit

at their unit and inspect their pre-assigned primary route reporting back the condition of the

roadway and all bridges on that route. Primary routes are the road sections needed for access to

critical areas such as cities, hospitals, power stations, communication centers, schools, industries,

neighboring states. After primary routes are inspected, the supervisor should determine the

secondary routes to be inspected.

The Level 1 Inspection will consist of visual assessment of all bridges on the route. The main

goal for this inspection is to be able to make a quick and accurate conclusion about the post

earthquake situation of the bridges on the assigned route. The only time the inspectors can

interrupt their inspection is when they encounter a life or death situation. It is critical that the

inspection get done, so outside help can be requested and routed via open roads. As indicated by

the result of the inspection, traffic flow on the bridge should be either controlled or restricted or

unrestricted. The results of the inspection will be utilized to develop the inspection schedule of

the Level 2 teams. For each bridge that will be examined, the teams should complete the

information in a given row, after checking all bridge elements. Finally, they should indicate their

decision on the last three columns. If any suspicious situation exists or more detailed information

is collected, team members can use the back page of the forms to make detailed explanations.

Any major bridge and roadway closure should be reported to the Unit/ Subdistrict/ District

immediately. In the previous chapter, common types of damage in bridges similar to those in

Indiana were noted. It is recommended to complete a quick walk around the bridge then follow

56

with a more focused inspection keeping in mind the examples of damage as related to the type

bridge surveyed. A suggested general procedure for the Level 1 inspection can be summarized

as follows:

1. Begin the inspection of the assigned bridges on the previously determined route after

collecting the necessary tools for the inspection (See section 6.3 for information on

suggested equipments)

2. Minor roadway deficiencies should be recorded in the form including pavement damage,

earth embankment failure, road obstructions and failure of the traffic control devices. Unit/

Subdistrict/ District should be informed immediately of any road or bridge damage that

requires the closing of the roadway to traffic.

3. Complete Level 1 Inspection Form. The form is shown in Figure 6.1. It contains columns

and rows. Complete one row per bridge inspected. The suggested step-by-step procedure is

listed below.

4. Upon arrival to the bridge site, review and verify the bridge number.

5. Record the arrival time.

6. Check the traffic flow on the bridge. Although there may be traffic using the bridge that

does not indicate the bridge is safe. Inspect all bridges assuming they may be damaged.

7. Approach bridge with caution and never walk immediately upon arrival directly under or

over the bridge. Do not cross the bridge without first sighting down the curb/rail line and

checking the underside for structural damage.

8. Prepare an inspection routine of the different components. Assign inspection tasks. Begin

by inspecting approaches and continue in the order listed in the inspection form (see Figure

6.2). Upon starting sub-structure inspection each inspector should go down a different side

of the bridge to provide safety by separation and to speed the inspection.

9. Discuss observation with the other members of the team and make the evaluation of the

condition.

10. After completing items 1 through 6 in the form with the comments YES, NO, or DRN

(Detailed Review Needed), the team should come to an agreement regarding the condition

of the bridge and enter in one of the last three columns of the form as appropriate. If a

bridge received at least one YES for the damage types 1 through 5, either a RED tag for

57

closure, or if a more detailed inspection is needed (Level 2) a YELLOW tag should be

entered. In case of no damage, a GREEN tag should be entered.

11. Additional recommendations and observations about the bridge and roadway can be

written in the box provided at the bottom of the form.

12. If the bridge is given a RED tag requiring barricades, the Unit, Subdistrict, and District

should be informed immediately and the disaster closure procedure outlined in Section 6.4

of the handbook should be followed. If the bridge can be traversed, but repairs are needed,

place a YELLOW ribbon, if it undamaged use a GREEN ribbon. Attach ribbons to the

bridge signpost and write time/date/inspector initials.

13. Record time on the form indicating the end of the inspection of the assigned bridges in the

space provided at the top of the form.

58

INDOT RAPID ASSESSMENT BRIDGE INSPECTION REPORT (LEVEL I) Route_______ Direction___________from Intersection___________ Page:____of _____ Date and Local Time: Post Earthquake Condition of the Bridge (Please write “YES, NO or DRN (Detailed Review Needed)” for items 1-6)

1. C

olla

pse

/ Par

tial

Col

laps

e/

Roa

dway

Clo

sed

2. S

uper

stru

ctur

e D

amag

e M

ovem

ent,

Poun

ding

, Buc

klin

g,

Cra

ckin

g, F

ailu

re

3. S

ubst

ruct

ure

Dam

age

Sh

ear K

ey D

amag

e, L

ocal

Buc

klin

g,

Settl

emen

t, T

iltin

g, S

lidin

g, R

otat

ion,

C

rack

ing,

Fai

lure

4. B

eari

ng D

amag

e

Failu

re, M

ovem

ent,

Shea

ring

or

pullo

ut o

f bol

ts

5. S

oil P

robl

ems

Sl

ope

Failu

re, S

oil L

ique

fact

ion,

Fi

ssur

e, D

iffe

rent

ial S

ettle

men

t

6. S

econ

dary

Str

uctu

re D

amag

e W

ing

wal

ls, P

arap

ets,

Pyl

ons

Bridge

Number

YES NO

DRN

YES NO

DRN

YES NO

DRN

YES NO

DRN

YES NO

DRN

YES NO

DRN 7. E

xpla

in O

ther

Pro

blem

s O

bser

ved

(D

amag

e in

Pip

elin

es o

r O

ther

Uti

litie

s et

c.)

RE

D T

AG

YE

LL

OW

TA

G

GR

EE

N T

AG

Roadway Problems Encountered and Comments:

Name of the Inspector(s)

FIGURE 6.1 Level 1 inspection form

59

FIGURE 6.2 Level 1 inspection scheme

6.2. Level 2 Inspection

The bridge inspection form for the INDOT Level 2 teams is shown in Figure 6.3. A separate

form should be completed for each bridge inspected. The bridge classification should be clearly

indicated at the bottom of the form. Team members can use the back of the page to indicate

additional comments. The main goal of the Level 2 inspection is to decide the final situation of

the bridges yellow tagged during the Level 1 inspection. After completing the inspection of

Yellow tagged bridges, teams re-inspect the Red tagged bridges if in-house repairs can be made.

The Level 2 inspection teams consist of two trained and experienced people such as INDOT

Construction and Design Project engineers or Project Supervisors. At no time, the two Level 2

inspectors should not go under the bridge at the same time. Because they have to backup each

other and aftershocks may occur. It is important to note that the condition of damaged structures

60

may worsen due to the additional earthquakes, traffic or simply gravity. When assessing the

bridges, one should assume that additional earthquakes would occur and consider what effect(s)

may have. Sometimes it may be necessary to establish a monitoring plan to detect any changes in

the condition of the damaged structures.

General procedure for the Level 2 inspection can be summarized as follows:

1. Start the inspection of the assigned bridge after collecting the necessary tools for the

inspection.

2. Record the arrival and departure times. Complete the necessary information about the

bridge, route and date/time. Note the difference between inspection day/time and the

day/time of the main shock.

3. Examine the data from Level 1 inspection report for the bridge.

4. Check the traffic flow through the bridge. This may help to reach a conclusion about the

condition of the bridge.

5. Prepare inspection plan for the different bridge components and prepare assignments for

the inspection.

6. Inspect the superstructure and substructure following the sequence given in the Level 2

form.

7. Note the observed damage by checking the necessary boxes. Fill out the form shown in

Figure 6.3. It contains 6 main damage type definitions for the different elements of the

bridge structures and comments and section to make specific recommendations. One form

must be used for each bridge inspected.

8. Discuss the observations with the members of the team and come to an agreement on the

condition.

9. The final rating should be written on the bottom of the form.

10. If the conclusion is that the bridge/road must be closed, or barricades are required, contact

the Unit, Subdistrict and District immediately.

11. Note any additional recommendations and conclusions in the box. The backside of the

form can be used for additional explanations or sketches.

61

12. Place appropriate marked ribbon on the bridge sign to inform later inspectors about its

condition.

Examples of the damage observed during previous earthquakes are summarized in Chapter 5.

During the inspection of the various types of bridge components, care must be taken to make the

correct assessment. All the structural elements, connections, supports, bearing elements and soil

conditions should be checked.

For the concrete elements, flexural and shear cracks should be examined carefully. It should be

considered that spalling of concrete and the exposure of reinforcing bars to open air may

complicate the assessment damage resulting from the earthquake. Observed cracks have to be

marked with paint and crack path and location should be recorded on a sketch with the note of

crack width.

It is important to note that some reinforced concrete elements such as box girders, footings, and

piles cannot be readily inspected. If damage of these elements is suspected, access must be

gained to inspect them. For example, excavating the soil around the footings, checking pile caps

may give better idea for the damage. For the box girder type of elements, opening holes on the

cells and confined space entry may be necessary.

For the steel components, inspection of the damage is often not readily apparent such as in the

concrete elements. All assemblies, plates, anchor bolts, restrainers, connections, hangers, welds

and other details should be carefully inspected. Sheared bolts, buckled or bent members, cracked

welds, shifted girders, anything out of order should be noted. For the composite elements, anchor

bolts to connect the steel parts to the concrete elements should be checked such as in steel

columns connected to abutments and pier caps.

62

INDOT DETAILED BRIDGE INSPECTION REPORT (LEVEL II) Route: Date and Local Time: Bridge ID: Bridge Location : DAMAGE OBSERVED: 1. ROADWAY/APPROACHES 4. SUPERSTRUCTURE

Reinforced Concrete Slab 1 Flexural Cracks 1 Shear Cracks 1 Connection Failure 1 No Damage 1 N/A

Culverts 1 Flexural Cracks 1 Shear Cracks 1 Local Buckling 1 Connection Failure 1 Metal Pipes Distortion & Deflection 1 No Damage 1 N/A

Tr Steel Truss Members, Floor Beams, Stringers 1 Local Buckling 1 Upper Chord 1 Lower Chord 1 Diagonals 1 Connection Failure 1 No Damage 1 N/A

Concrete Arches 1 Flexural Cracks 1 Shear Cracks 1 Connection Failure 1 Spandrel Wall Cracking/Collapse 1 No Damage 1 N/A

Steel/Concrete Girders, Beams 1 Flexural Cracks 1 Shear Cracks 1 Connection Failure 1 Local Buckling 1 No Damage 1 N/A

1 Not Operational 1 Roadway Settlement 1 Off Bridge Seat 1 Excessive Transversal Movement 1 No Damage 1 Other (explain)

2. DECK 5. SUBSTRUCTURE Abutments 1 Wall Movement/Rotation 1 Pounding Damage 1 Wing wall Movement 1 Wing wall Separation 1 Backfill Settlement 1 Foundation Movement 1 Abutment Pile Damage 1 Cracking on the Walls 1 No Damage 1 N/A

1 Longitudinal Joints Enlarged 1 Expansion Joints Enlarged 1 Wearing Surface Cracking 1 Wearing Surface Spalling 1 Deck Cracking/Spalling 1 Misalignment of Guard Rails, Curbs, Pavement Lines 1 No Damage

Piers 1 Joint Failure 1 Moment Failure 1 Shear Failure 1 Inadequate Splice Failure 1 Flexural Cracks 1 Shear Cracks 1 Local Buckling 1 Foundation Failure 1 No Damage 1 N/A

3. BEARINGS 6. GEOTECHNICAL 1 Failure of Bearings (Integral, Contact, Rocker, Elastomeric) 1 Movement of Bearings 1 Shearing or Pullout of Bolts 1 No Damage

1 Slope Failure 1 Settlement 1 Soil Liquefaction 1 Fault Movement 1 Other 1 No Damage 1 N/A

COMMENTS FOR REPAIR AND RECOMMENDATIONS: 1. BARRICADE NEEDED 2. IMMEDIATE SHORE AND BRACE 3. REPAIR

3a. In-House Repair Possible 3b. Outside Contractor Needed

4. EMERGENCY VEHICLE USE ONLY 5. MONITORING UNDER SERVICE NEEDED 6. OTHER (explain)

Overall Rating For the Bridge: SAFE (Green Tag):_______MORE REVIEW NEEDED (Yellow Tag) ________UNSAFE(Red Tag):__________ Name of the Inspector(s):

FIGURE 6.3 Level 2 inspection form

63

6.3. Suggested tools for the evaluation procedure

6.3.1. Suggested tools to perform Level 1 inspection

q Radio and cellular phone for communications

q Inspection procedures field guide

q Primary and county route maps, state maps

q List of bridges on the routes

q Clipboard, pen, pencil

q Waterproof marker

q Ribbons in three colors: Red ribbon to close, Yellow ribbon to identify open but repairs

or additional inspection needed and Green ribbon to denote undamaged with color

wording on ribbon

q Rope

q Safety vest

q Hardhat

q Flash light

q “Road Closed” signs, flashers and stands. (See section 6.4)

q Shovel

q Barrels

q Cones

q Traffic control paddles

q First aid kit

q Camera and film

q Fire extinguisher

q 100 ft tape

q Hammer

q Extra flashlight batteries

q Binoculars

q Chain saw

64

6.3.2 Suggested tools to perform a detailed evaluation for Level 2

The necessary resources for the Level 2 teams are:

q Level 1 inspection form data

q Bridge inventory book

q Primary and county route maps

q Radio and/or satellite phone for communications

q Water, food, clothes, blankets, tents, shelter and supplies for at least 3 days per person

q Inspection Form for each bridge, field book, sketchpad, paper, pencils, clipboard.

q 100-foot tape, pocket tape, and ruler.

q Testing hammer or geologist hammer

q Inspection mirror and flashlight for inaccessible areas

q Keel marker

q Camera and film

q Binoculars

q Tool belt, boots

q Wire brush, shovel, whisk broom

q Pocket knife

q Safety harness and lanyard

q Scraping toll

q Calipers

q Ladders

q Lead lines

q Hand level

q Thermometer

q Pocket or wrist watch

q Plumb bob

q Safety vest

q Hard hat

q Rope

65

q Axe

q Tape recorder and tape

q Tool box

q Life jacket

q Gloves, PVC coated and leather

q Ear plugs

q Eye wash

q First aid kit

q Cones, traffic safety

q Fire extinguisher

q Sign, flagman’s signal

For detailed inspection, following items may be required for the different type of bridges:

q Crack gage or comparator to measure the width of the cracks

q Piano wire or some other device for measuring the depth of cracks

q Screwdriver

q Pliers

q Wrench

q Magnifying glass

q Periscope, fluorescent tube light

q Hand drill, borer or ship auger

q Straight edge

q Flagging for marking damaged areas

66

6.4. Bridge Closing Procedure

INDOT has a formal procedure for the planned closing of a road or bridge that includes pre-

closure notification to the public (through the media and signs), marking a detour/approach and

signing the actual barricade closure. In a major disaster INDOT has a responsibility to take all

reasonable actions to notify and protect the public as soon as the need for a road closure is

known (see Appendix A, Indot Response Procedure for Major Disasters).

Each unit shall maintain a minimum of one set of “Road Closure” signs (Figure 6.4) with type B

flashers and sign supports for each primary disaster route in their unit. Level 1 inspectors shall

load one road closure setup (2 signs) onto their truck prior to starting their inspection. If there is

a need for closure during inspection, the signs will be put up on each approach and

unit/subdistrict/ district immediately notified so that the approach signing, barricading and a

detour can be placed in a timely manner by follow up personnel. Once this is done, Level 1

inspectors shall continue the inspection on their primary route using the state and county maps to

find a way around the closure. If additional closures are encountered that information is to be

relayed back to the unit/subdistrict for assistance. One inspector may have to remain at the

closure until relieved if no signing or other traffic control is available (try to use local law

enforcement if available

FIGURE 6.4 Road closure sign

67

7. TEMPORARY REPAIRS AND LONG TERM MONITORING TECHNIQUES

7.1. Temporary Repairs

Following an earthquake, many bridges may be damaged. It is important to identify if temporary

repairs can be made in order to provide emergency access or to open a lifeline for the recovery

effort. Temporary repairs may open a structure that would otherwise be closed for these

purposes. These repairs should be consider, as the name implies, only temporary measures and

should not be considered as the final repair or rehabilitation technique.

To identify if a temporary repair is feasible, the first step is to assess the condition of the

structure. Several questions should be considered:

q How widespread is the damage?

q Is this a safety issue?

q What is the cause of damage?

q What are the consequences of the damage?

q Are there similar problems elsewhere?

q Is intervention possible?

In considering these questions, is appropriate to consider the type of damage present. In general

there are two types of damage:

q Local – Damage incurs risks to the users but not to the structure.

q Global – Damage incurs risks to the stability of the structure and the safety of the users.

Local damage may lend itself to repair using quick, temporary measures while global damage

typically does not easily lend itself to quick repair. However, even global damage may be

repaired using temporary measures if this structure is essential to the transportation network.

Once it is determined that a repair may be needed or necessary, it is important to identify the

repair strategy or level of intervention required. The following are typical options to consider:

68

1. No Repair/Monitoring or Instrumentation Required

2. Partial Repair

3. Replace/Redesign Elements

4. Replace Structure

Temporary repair is covered under Options 1 and 2. Option 1 may provide an excellent

alternative to repair when local damage is present or there is doubt as to the performance of the

structure. Monitoring techniques are discussed in the second part of this chapter. Option 2 may

be used to repair local damage. The specific repair technique depends on the actual component

that is damaged. Options 3 and 4 are considered permanent repair procedures and are not

covered by this handbook. These repair techniques will require considerable resources for

design and construction.

Temporary repair procedures will be divided into several categories. The repairs listed provide

general information regarding the procedures that may be applicable for a given structure.

7.1.1. Transition Repair

Roadways and bridges may not provide a smooth riding surface after such an event. Bridge

superstructures may be displaced vertically due to bearing damage or settlement of approaches.

In addition, roadways may also be damaged producing discontinuities in the riding surface. In

these cases, simple solutions often work best. Several temporary repair procedures should be

considered:

Steel Plates: Steel plates that connect the riding surface can be used to bridge gaps and vertical

offsets in both bridges and roadways (See Figure 7.1).

FIGURE 7.1 Different bridge damage cases that steel plates can be used (11)

69

Sand or Stone Fill: Another alternative to provide for a transition in riding surfaces is the use of

sand fill, stone or hot/cold asphalt mixes. These materials can be used in roadways to bridge

gaps as well as vertical offsets. However, in bridges, the most common application is to provide

a transition for vertical offsets (Figure 7.2).

FIGURE 7.2 Different bridge damage cases that fill can be used (15,11)

Jacking: The structure may be lifted with the aid of hydraulic jacks in order to reset or replace

the bearings. This repair should be considered the most intensive and will require considerable

time and resources.

7.1.2. Shoring

The installation of shoring may provide a temporary repair for many structures. There are two

primary cases to consider. First, for some bridges, especially essential ones, it may be desirable

to open the structure to operation even in the case of fairly severe damage. The main method to

achieve this operational level would be to install shoring under the structure to support the loads.

Figures 7.3 to 7.13 illustrate the use of shoring to support the superstructure. In many instances,

shoring may be used to provide superstructure support for a bridge that has incurred substructure

damage.

Shoring may also be used to support a structure that is in danger of collapsing. Shoring can be

used to advantage in these situations in order to maintain access to an underlying roadway

(Figures 7.5).

70

FIGURE 7.3 Temporary shoring of bridge after Taiwan Earthquake 1999 (11)

FIGURE 7.4 Another view of temporary shoring after Taiwan Earthquake 1999 (11)

71

FIGURE 7.5 View of temporary shoring to maintain access after Kobe Earthquake 1995 (27)

FIGURE 7.6 View of temporary shoring to prevent total collapse of bridge (27)

FIGURE 7.7 View of temporary shoring to prevent total collapse of steel bridge (27)

72

FIGURE 7.8 View of temporary shoring to prevent total collapse of steel bridge (27)

FIGURE 7.9 View of temporary shoring to support RC bridge (15)

FIGURE 7.10 View of temporary shoring to prevent total collapse of bridge (27)

73

FIGURE 7.11 View of temporary support to prevent total collapse of steel bridge (27)

FIGURE 7.12 View of temporary support to prevent total collapse of steel girder bridge (15)

FIGURE 7.13 View of temporary support to prevent total collapse of steel girder bridge (11)

74

7.2. Long-Term Monitoring

In many cases, it may be appropriate to monitor the structure rather than conduct a repair.

Monitoring may indicate that the structure is not deteriorating beyond its current state. It may

also be used to support the assumption that the structure is performing adequately and does not

require closure. On the other hand, monitoring may indicate a potential safety problem with the

structure and support the need for bridge closure.

The primary measurements that will be of assistance in providing feedback from the structure

include deflections, crack widths, and strains. Several simple techniques are presented for each

of these measurements. For monitoring a structure following an earthquake, it is important to

consider that the simplest measurement method is often the best method.

7.2.1. Deflections

Deflection measurements may be used to determine if the structure is continuing to function

without a loss of stiffness. Increasing deflections over time would indicate that the bridge is not

adequately performing and is deteriorating. This measurement can provide information

regarding whether the structure should remain operational.

Deflections are often one of the most difficult measurements to obtain from a structure.

However, a very simple technique illustrated below provides a relatively easy deflection

measurement. As shown, a piano wire is stretched across the structure and attached at reference

points. In order to measure deflections in the span, it is common for the reference points to be

located at the supports. A scale is attached at the point of interest, and deflections can be

monitored at this location. This method is inexpensive, does not require significant materials,

and is reliable (Figure 7.14).

75

FIGURE 7.14 Deflection measurement

7.2.2. Cracks

Crack monitoring may be used to determine if damage is continuing to accumulate over time. It

may also be used to provide evidence of unstable crack growth that may be an indication of

unstable structural damage. There are several simple crack monitoring techniques that may be

used:

Plaster Cracks: If it is only required to determine if the cracks are moving, then simply applying

plaster or mortar over the cracks is appropriate. Cracking of the plaster indicates that further

cracking has occurred.

Crack Comparator: Taking measurement with a crack comparator and recording measurements

over time will provide evidence of crack growth (Figure 7.15).

Tape Measure: For some cracks, the widths may be larger than the range provided by the crack

comparator. For these cracks, a tape measure may prove suitable.

Avongard: A mechanical movement indicator available from Avongard can be attached to the

structure. This indicator provides a direct reading of crack displacement and rotation (Figure

7.16).

Piano Wire

ScaleReference Point

76

FIGURE 7.15. Crack comparator (CTL, Inc.)

FIGURE 7.16. Crack monitor (Avonguard)

7.2.3.Strain

In some instances, it may be helpful to obtain strain measurements. These measurements may

provide engineers with information regarding the overall structural performance or performance

of specific components that are questionable. The easiest method to obtain strain measurements

is by attaching an electrical resistance strain gage. Hand held bridge balancing boxes (Figure

7.17) are available to permit field monitoring without extensive electronic equipment. This

77

technique would only be applicable for a minimum number of gages at key interest locations. If

detailed information over a long-term period is required, gaging of the entire structure may be

required. However, extensive gaging lends itself to the use of a computer data acquisition

system and complete wiring of the structure.

FIGURE 7.17. Portable strain indicator (Measurements Group, Inc.)

78

79

8. EVALUATION EXAMPLES

8.1 Level 1 Examples

8.1.1 Example 1

In this section of the handbook, the Level 1 Bridge Inspection Form is completed based on a

series of examples of damaged bridges. In the first example, the highway bridge, Santa Clara

River Bridge (Interstate 5, 53-0687, CA) damaged after 1994 Northridge Earthquake, is

evaluated (11). The available photos are arranged in the order of a typical inspection routine as

described in the Level 1 form.

FIGURE 8.1 View of bridge superstructure after the earthquake (11)

80

FIGURE 8.2 More damage to the bridge superstructure (11)

81

FIGURE 8.3 Different views of bridge superstructure (11)

FIGURE 8.4 The Level 1 form, Bridge Example 1, Steps 1 and 2

82

FIGURE 8.5 Damage to one of the bridge piers (11)

FIGURE 8.6 The Level 1 Form, Bridge Example 1, Step 3

83

FIGURE 8.7 Damage to the bridge bearings (11)

84

FIGURE 8.8 The level 1 Form, Bridge Example 1, Step 4

FIGURE 8.9 View of substructure and soil of the bridge (11)

85

FIGURE 8.10 Completed Level 1 Inspection Form for Example Bridge 1

8.1.2 Example 2

The second example is the Parkfield Highway Bridge (Bridge #1309, Parkfield, CA). The bridge

was damaged after Parkfield, California Earthquake, June 27-29, 1966. The available pictures are

arranged in the order of a typical inspection routine as described in the Level 1 form.

FIGURE 8.11 View of the Parkfield Highway Bridge after the earthquake (11)

86

FIGURE 8.12 View of the damaged bridge components (11)

87

FIGURE 8.13 Completed Level 1 form for Example Bridge 2

8.1.3 Example 3

The Interchange Bridge between I-5 and I-210 (California), was damaged after San Fernando

EQ, 1971. The available pictures are arranged in the order of a typical inspection routine as

described in the Level 1 form. At the end, particular row in the Level 1 Inspection Form is

completed according to the damage scenes of the bridge.

88

FIGURE 8.14 Superstructure damage of the third example bridge after earthquake (11)

89

FIGURE 8.15 Substructure damage of the bridge (11)

90

FIGURE 8.16 Completed Level 1 Inspection form for bridge example 3

8.2 Level 2

8.2.1 Example 1

In this section of the handbook, Level 2 Bridge Inspection Form is completed by using a series of

examples of damaged bridge photos. As a first example the highway bridge, I5-14 Interchange,

CA is chosen. The bridge was damaged after the Northridge Earthquake, 1994 (11). (Figures

8.17-8.18). The available pictures are arranged in the order suggested for a typical Level 2

inspection. The bridge is assumed as yellow tagged after inspection by Level 1 Inspection team,

the Level 1 form is shown in Figure 8.19. The completed Level 2 Inspection form is shown

following the example illustrations.

91

FIGURE 8.17 Different views from the superstructure of the bridge (11)

92

FIGURE 8.18 Different views of damage from the damaged bridge (11)

93

FIGURE 8.19 Completed Level 1 form for the example bridge (53-1620D)

94

FIGURE 8.20 Completed Level 2 Inspection Form, Bridge Example 1 (53-1620D)

8.2.2 Example 2

The I5-R216 Interchange Bridge (53-1626,CA) was damaged after the Northridge Earthquake,

1994 (11) (Figures 8.21- 8.24). The completed forms (Level 1 and 2) are shown following the

example photos those are arranged in order of a typical Level 2 inspection (Figures 8.25-26).

95

FIGURE 8.21 Different views of the superstructure of the second example bridge (11)

96

FIGURE 8.22 Different views of the superstructure of the bridge (11)

97

FIGURE 8.23 Different views of the superstructure of the bridge (11)

98

FIGURE 8.24 Different views of the second example bridge (11)

99

FIGURE 8.25 Completed Level 2 Inspection Form, Bridge Example 2

100

FIGURE 8.26 Completed Level 2 Inspection Form, Bridge Example 2

101

9. REFERENCES

1. Seismic Bridge Design Applications, Federal Highway Administration, Report SA-97-018,

1996

2. http://www.eas.slu.edu/Earthquake_Center/newmadrid1975-1995.html

3. Atkinson, W., “The Next New Madrid Earthquake, A Survival Guide”, Southern Illinois

University Press, 1989.

4. http://www.indstate.edu/gga/recent/indiana.gif

5. http://geohazards.cr.usgs.gov/eq/html/ceusmap.shtml

6. http://www.hsv.com/genlintr/newmadrd/

7. http://wwwneic.cr.usgs.gov/neis/states/indiana/indiana_history.html

8. Inventory of Bridges State Highway System of Indiana 1999-2000, Indiana Department of

Transportation

9. Indiana Department of Transportation, Vincennes District Picture Archive

10. http://www.koeri.boun.edu.tr /earthqk/earthqk.html

11. http://www.eerc.berkeley.edu/eqiis.html Northridge Collection, Earthquake Engineering

Research Center, University of California, Berkeley.

12. The Great Kansai Earthquake, Asahi Graph, Vol. 3794, Asahi Shimbun, February 1995.

13. The Earthquake Damage Research Report of Hyougo Ken Nanbu Zisin at 1995, Kajima

Corporation, Vol.1, February 1995.

14. The January 17, 1995 Kobe Earthquake, An EQE Summary Report, EQE International, 1995

15. Investigation Report on Bridge Damage In JiJi Earthquake on September 21, 1999, National

Center for Research on Earthquake Engineering, Taiwan, Roc, November 1999.

16. Vejvoda, M.F., “Strengthening of Existing Structures with Post-Tensioning,” Concrete

International, September 1992.

17. ACI Committee 224, “Causes, Evaluation, and Repair of Crack in Concr

224.1R-89

18. Saiidi, M., “Current Bridge Seismic Retrofit Practice in the United States,” Concrete

International, December 1992

102

19. Student Manual to Accompany Training Video on Post-earthquake Safety Evaluation of

Bridges State of Washington, Wiss Janey Elstner Associates, Inc., WJE No.942730, 1996

20. http://pubs.usgs.gov/gip/earthq3/contents.html

21. http://pubs.usgs.gov/gip/earthq3/contents.html

22. http://pubs.usgs.gov/gip/earthq1/plate.html

23. http://www.geo.mtu.edu/UPSeis/where.html

24. http://clgray.simplenet.com/paper/appendb.html

25. http://www.deprem.gov.tr

26. http://www.structures.ucsd.edu/Taiwaneq/index.html

27. The January 17, 1995 Hyogoken-Nanbu (Kobe) Earthquake, Performance of Structures,

Lifelines, and Fire Protection Systems, National Institute of Standards and Technology,

NIST Special Publication 901 (ICSSC TR18), July 1996.

28. http://adamite.igs.indiana.edu/indgeol/index.htm

103

APPENDIX

INDOT VINCENNES DISTRICT RESPONSE PROCEDURES FOR MAJOR DISASTERS

MAJOR DISASTER: A major disaster is defined as any incident that could cause extended

closure of our highway system. Examples could be localized incidents like fire, winds, tornado,

vehicle accidents and spills or non-localized incidents such as floods, ice storms, blizzards,

nuclear incidents or earthquakes (Intensity > 5.0 Magnitude). All INDOT personnel should

participate in appropriate disaster training and following a perceived disaster (and phones do not

work) report to their designated reporting station or the closest Unit to their home.

DISTRICT RESPONSE: As soon as possible following a major disaster incident, the Vincennes

District will open their District Emergency Operations Center (DEOC). Communications will be

established between affected subdistricts and central office. The Vincennes Emergency

Operations Center will be located in the new District Office building on US 41 just south of

Vincennes. The District presently has a 24-hour switchboard attendant. The DEOC will be

staffed by select department heads and designated staff.

SUBDISTRICT RESPONSE: As soon as possible following a major disaster, each affected

Subdistrict will open their Subdistrict Emergency Operations Center. Communications by phone

and radio will be established with all affected Subdistrict units and the Vincennes District.

Subdistricts should establish procedures to contact those people needed to perform disaster

activities including a system of notification if telephones are not working. The Subdistrict EOC

will be staffed by designated Subdistrict personnel with help from the other departments. If a

Subdistrict is not operational, an adjacent Subdistrict will take over as the Subdistrict EOC.

UNIT RESPONSE: As soon as possible following a major disaster, each affected Unit will open

their facility, establish communications by phone and radio and start Level 1 Inspections of all

Unit Primary Routes (Most units have 2 to 3 Primary Routes). Designated personnel from other

104

departments (such as construction) are to be assigned to the closest unit to assist that unit or

personnel may be sent between units as the need is identified.

UNIT LEVEL 1 INPECTIONS: Each Unit involved in the disaster will be responsible for the

Level 1 Inspection of the Units Primary Routes if the respective disaster warrants. Assigned Unit

personnel (normally two people per route) will pick up an Inspection Kit from their disaster

cabinet and inspect their assigned primary route reporting back the condition of the roadway and

all bridges on that route. Primary routes are road sections needed for access to critical areas such

as cities, hospitals, schools, industries, adjacent States. Once primary routes are inspected the

supervisor will determine if the secondary routes should be inspected. The Level1 Inspection will

be a visual assessment with short stops to inspect all bridges. It is important that Level 1

Inspections should be completed as quickly and accurately as possible so that a quick assessment

of the disaster can be made. Only interrupt your Level 1 Inspection to assist with a life-

threatening situation.

DURING THE LEVEL 1 INSPECTION:

1. Minor roadway deficiencies should be recorded on the Level 1 Inspection Form including

pavement damage, earth embankment failures, road obstructions and failure of traffic control

devices. Any roadway damage requiring the closing of the roadway should be relayed back to

the Unit / Subdsitrict / District office immediately. Each inspection crew will carry a set of

Road Closure Signs to be used in such an event.

2. All bridges are to be inspected using the Level 1 Inspection Form with bridges identified.

Approach all bridges with caution and never walk directly under a bridge following an

earthquake. Do not cross the bridge without first sighting down the curb/rail line and

checking the underside for structural damage. Do not cross the bridge if significant problems

are observed. Close the bridge by placing Road Closed Signs on each approach and place a

Red Ribbon with time, date and your initials on the bridge signpost. Use the provided

State/County Map to find a route around closure. If the bridge is passable but repairs are

needed place a Yellow Ribbon or place a Green Ribbon if no problems are found. Place

ribbons on bridge sign post just under the sign and remember to time/date/initial for possible

follow up inspections. Record all observations and proceed to the next structure. Level 1

105

Inspection Training for unit personnel will be done in house by District personnel using

materials provided by Purdue University.

REQUIRED MATERIALS FOR EACH LEVEL 1 INSPECTION CREW: All noted materials

below must be kept in the units Disaster Signal Box located in the yard of each unit.

1. The Units A, B, C,…. Primary Route Maps with detour county maps and state maps and

inspection procedures (in box).

2. Red Ribbon to close, Yellow Ribbon to identify open but repairs needed and Green Ribbon

to denote undamaged with color wording on ribbon (in box).

3. A tablet with waterproof markers, pen, pencil (in box).

4. Load one set (2 signs) of “Road Closed” signs with B flashers and stands.

5. Load shovel/barrels/cones/traffic control paddles (from unit) in truck.

6. Flashlight, fire extinguisher, hard hats, vests, first aid kit and personal items should go with

each radio equipped Level 1 Inspection truck.

LEVEL 2 INSPECTION TEAM: Each unit reporting roadway or bridge damage requiring

Closure (red) or Damage (Yellow) will report it back to the Unit/Subdistrict/District who will

assign a Level 2 Inspection team to do more in-depth inspection of the damage. The Level 2

Inspection team will be a minimum two-person team made up of at least one trained professional

engineer (CE) or experienced project supervisors (EAS). A list of Level 2 trained personnel

assigned to each Subdistrict/Unit will be kept on file. Level 2 personnel will be formally trained

using materials provided by Purdue University. Unless assigned otherwise each CE & EAS is to

report to the closest unit to their home.

LEVEL 3 INSPECTION TEAM: If additional inspection is needed it will be initiated by CO

using in-house design personnel or consultants.

COMMUNICATIONS: It is likely to be a major problem in any disaster. INDOT will prepare

for the loss of phones and radio towers by setting up a mobile to mobile system by strategically

locating 100 watt radio equipped maintenance vehicles to relay to any part of the district. A letter

identifying 100-watt vehicles and a map where vehicles are to be located shall be kept in each

106

disaster kit at the Subdistrict. Traffic will make operational a boom truck that will have an

antenna capable of working as a temporary tower. All subdistricts will maintain their emergency

power generations and wiring will be done at units to allow the connection of a portable

generator for emergency power. During any such disaster minimize your use of the radio and

phone to only critical information such as road closures.

MAJOR DISASTER PROCEDURES FOR UNITS:

The first person to arrive at the Unit should gain access and then:

1. Turn off the incoming gas if the Unit building has been damaged or if gas is smelled

(earthquake/tornado). Do not turn on lights prior to checking for leaking gas. The gas valve

with wrench is located _______________________________________________________.

Also, if electricity is damaged, you may want to disconnect the breaker or shut off water if a

leak is discovered. Units should label all critical gas and water valves. If no key is available

access may have to be gained by cutting/breaking locks.

2. Establish communications with the Subdistrict by telephone and radio and start the Unit

Communications Log, always have someone assigned to monitor communications. If a phone

connection is made with the Sub you may want to leave it open and not hang up to maintain

an open line. Each unit shall id vehicles with 100-watt radios and assigns them to relay

locations such as the unit and strategic hilltops if towers are down.

3. Unlock all doors, locate vehicle keys and start emergency generator, if available and as

needed. Extra vehicle keys may need to be stored in the Units Disaster Signal Box if your

unit building is likely to be affected (older brick buildings). A complete set of backup

vehicle/facility keys should be kept at the Subdistrict.

4. As additional personnel report to the Unit, they should immediately start the Units Primary

Route Level 1 Inspections unless directed otherwise by the Subdistrict. You should assign

two maintenance workers to each primary route. All materials for the inspection should be

available in the Disaster Signal Cabinets or unit.

A. Sign the route assignment sheet and pick up the primary “A” route kit. Later workers will

pick up routes B or C until all routes are being inspected.

107

B. Each Inspection Kit will include a primary route map with detour state and county maps

and inspection procedure, Red Yellow and Green Ribbon, tablet, waterproof marker, pen

and pencil.

C. Load your radio-equipped truck with 2 road-closed signs, B flashers and stands, shovel,

barrels, cones and traffic control paddles.

D. Vehicle should already contain flashlight, fire extinguisher, hard hats, vests, first aid kit

and personal items such as food, water and clothing.

E. Driver should read instructions and begin the Primary Route Level 1 Inspection.

F. When the Primary Route Inspection is completed and you have returned to the Unit, sign in

on the route assignment sheet and report to your supervisor.

G. If all routes have been assigned for inspection additional personnel who arrive should

prepare equipment for possible use.

DISASTER ROAD/BRIDGE CLOSURE PROCEDURE

INDOT has a formal procedure for the planned closing of a road or bridge that includes pre-

closure notification to the public (through the media & signs), marking a detour/approach and

signing the actual barricade closure. In a major disaster, this procedure will be impossible to

follow but INDOT has a responsibility to take all reasonable actions to notify and protect the

public as soon as the need for a road closure is known. To that end each unit shall maintain a

minimum of one set of “Road closure” signs with type B flashers and sign supports for each

primary disaster route in their unit. The Level 1 inspectors shall load one Road Closure setup (2

signs) onto their truck prior to starting their inspection. If the need for a closure is encountered

during the inspection, the signs will be put on each approach and the Unit/Subdistrict will be

immediately notified by radio so that the approach signing, barricading and a detour can be

placed in a timely manner by follow up personnel. Once the sign is placed the Level 1 inspectors

shall continue the inspection on their primary route using the state and county maps to find a way

around the closure. If additional closures are encountered that information is to be relayed back

to the Unit/Subdistrict for assistance. One inspector may have to remain at the closure until

relieved if no signing or other traffic control is available (try to use local law enforcement if

available). The Sub is complete State Form 1866 to notify other agencies of the emergency

108

closure. Remember that the Level 1 inspection must be done as quickly and accurately as

possible so a determination of the extent of damage can be made and repairs started.

FIGURE A.1 Types of Road Closure sign and dimensions

FIGURE A.2 The pictures of Road Closure sign, bridge signpost and emergency cabinet

109

FIGURE A.3 The map of primary routes in Vincennes District

110

111

EARTHQUAKE PREPAREDNESS

BEFORE

Develop a family earthquake plan. Prepare yourself, your family and your home by completing the activities on this checklist. • Decide how and where your family will reunite if separated. • Choose an out-of-state friend or relative that separated family members can call after the quake to report their whereabouts and condition. • Know the safe spots in each room: under sturdy tables, desks, against inside walls. • Know the danger spots: windows, mirrors, hanging objects, fireplaces, bookcases, tall and unsecured furniture. • Conduct practice drills. Physically place yourself in safe locations. • Learn first aid and CPR (cardiopulmonary resuscitation) from your local Red Cross chapter or other community organizations. • Keep a list of emergency phone numbers. • Learn how to shut off gas, water and electricity in the case the lines are damaged. (Safety note: Do not attempt to relight gas pilot) • Secure water heater and appliances that could move enough to rupture lines. • Secure heavy furniture, hanging plants, heavy pictures or mirrors. • Keep flammable or hazardous liquids in cabinets or on lower shelves. Put latches on cabinet doors to keep them closed during shaking. • Maintain emergency food, water and other supplies, including a flashlight, a portable battery-operated radio, extra batteries, medicines, first aid kit and clothing (for 3 day long).

DURING If indoors, stay there, take cover under a table, desk, or other sturdy furniture: • Face away from windows and glass doors. • Doorways without doors are OK also. • Lay, kneel, or sit near a structurally sound interior wall or corner away from windows, brick fireplaces, glass walls. • Protect your head and body from falling or flying objects. • Remain until shaking stops. Think out your plan of action first, and then move. • Know exit routes if in commercial building. Take cover, don’t move till shaking stops. If outside, get into an open area away from trees, buildings, walls and power lines: • Lie down or crouch low to maintain balance. • Get to best available shelter if there not open area available. If driving, stop safely as soon as possible. Stay inside until the shaking stops: • Do not stop under overpasses or bridges. • Stay below window level in your car. • Turn off engine. • Turn on radio. Fellow emergency instructions. • Stay in vehicle if downed power lines have fallen across it. You are insulated by the tires. Wait for help. You might be able to back away from lines. • If you have to leave your vehicle, move to open area quickly.

AFTER Check for injuries. Apply first aid. Do not move seriously injured individuals unless they are in immediate danger. Do not use the telephone immediately unless there is a serious injury or fire. • Check utilities (water, gas, electric). If there is damage turn utility off at the source. • Check for other hazards and control them (fire, chemical spill, toxic fumes and precarious collapse). • Check building for cracks and damage, including roof, chimneys, and foundation. • Check food and water supplies. • Emergency water can be obtained from water heaters, melted ice cubes, canned vegetables, and toilet tanks. • Never use matches, lighters or candles inside. • Turn on radio and listen for emergency broadcasts/announcements, news reports, and instructions. Cooperate with public safety officials. • Do not use your vehicle unless there is an emergency. Keep the streets clear for emergency vehicles. • If buildings are suspect, set up your shelter area away from damage. • Work together with your neighbors for a quicker recovery. Stay calm and lend a hand to others. • Be prepared for after shocks. • Plan for evacuation in case events make this necessary. Leave written messages for other family members or searchers. • Use gloves, wear heavy shoes, have adequate and appropriate clothing available. • Contact to your work site and report

112

113

INDOT RAPID ASSESSMENT BRIDGE INSPECTION REPORT (LEVEL I) Route_______ Direction___________from Intersection___________ Page:____of _____ Date and Local Time: Post Earthquake Condition of the Bridge (Please write “YES, NO or DRN (Detailed Review Needed)” for items 1-6)

1. C

olla

pse

/ Par

tial

Col

laps

e/

Roa

dway

Clo

sed

2. S

uper

stru

ctur

e D

amag

e M

ovem

ent,

Poun

ding

, Buc

klin

g,

Cra

ckin

g, F

ailu

re

3. S

ubst

ruct

ure

Dam

age

Sh

ear K

ey D

amag

e, L

ocal

Buc

klin

g,

Settl

emen

t, T

iltin

g, S

lidin

g, R

otat

ion,

C

rack

ing,

Fai

lure

4. B

eari

ng D

amag

e

Failu

re, M

ovem

ent,

Shea

ring

or

pullo

ut o

f bol

ts

5. S

oil P

robl

ems

Sl

ope

Failu

re, S

oil L

ique

fact

ion,

Fi

ssur

e, D

iffe

rent

ial S

ettle

men

t

6. S

econ

dary

Str

uctu

re D

amag

e W

ing

wal

ls, P

arap

ets,

Pyl

ons

Bridge

Number

YES NO

DRN

YES NO

DRN

YES NO

DRN

YES NO

DRN

YES NO

DRN

YES NO

DRN 7. E

xpla

in O

ther

Pro

blem

s O

bser

ved

(D

amag

e in

Pip

elin

es o

r O

ther

Uti

litie

s et

c.)

RE

D T

AG

YE

LL

OW

TA

G

GR

EE

N T

AG

Roadway Problems Encountered and Comments:

Name of the Inspector(s)

114

115

INDOT DETAILED BRIDGE INSPECTION REPORT (LEVEL II) Route: Date and Local Time: Bridge ID: Bridge Location : DAMAGE OBSERVED: 1. ROADWAY/APPROACHES 4. SUPERSTRUCTURE

Reinforced Concrete Slab 1 Flexural Cracks 1 Shear Cracks 1 Connection Failure 1 No Damage 1 N/A

Culverts 1 Flexural Cracks 1 Shear Cracks 1 Local Buckling 1 Connection Failure 1 Metal Pipes Distortion & Deflection 1 No Damage 1 N/A

Tr Steel Truss Members, Floor Beams, Stringers 1 Local Buckling 1 Upper Chord 1 Lower Chord 1 Diagonals 1 Connection Failure 1 No Damage 1 N/A

Concrete Arches 1 Flexural Cracks 1 Shear Cracks 1 Connection Failure 1 Spandrel Wall Cracking/Collapse 1 No Damage 1 N/A

Steel/Concrete Girders, Beams 1 Flexural Cracks 1 Shear Cracks 1 Connection Failure 1 Local Buckling 1 No Damage 1 N/A

1 Not Operational 1 Roadway Settlement 1 Off Bridge Seat 1 Excessive Transversal Movement 1 No Damage 1 Other (explain)

2. DECK 5. SUBSTRUCTURE Abutments 1 Wall Movement/Rotation 1 Pounding Damage 1 Wing wall Movement 1 Wing wall Separation 1 Backfill Settlement 1 Foundation Movement 1 Abutment Pile Damage 1 Cracking on the Walls 1 No Damage 1 N/A

1 Longitudinal Joints Enlarged 1 Expansion Joints Enlarged 1 Wearing Surface Cracking 1 Wearing Surface Spalling 1 Deck Cracking/Spalling 1 Misalignment of Guard Rails, Curbs, Pavement Lines 1 No Damage

Piers 1 Joint Failure 1 Moment Failure 1 Shear Failure 1 Inadequate Splice Failure 1 Flexural Cracks 1 Shear Cracks 1 Local Buckling 1 Foundation Failure 1 No Damage 1 N/A

3. BEARINGS 6. GEOTECHNICAL 1 Failure of Bearings (Integral, Contact, Rocker, Elastomeric) 1 Movement of Bearings 1 Shearing or Pullout of Bolts 1 No Damage

1 Slope Failure 1 Settlement 1 Soil Liquefaction 1 Fault Movement 1 Other 1 No Damage 1 N/A

COMMENTS FOR REPAIR AND RECOMMENDATIONS: 1. BARRICADE NEEDED 2. IMMEDIATE SHORE AND BRACE 3. REPAIR

3a. In-House Repair Possible 3b. Outside Contractor Needed

4. EMERGENCY VEHICLE USE ONLY 5. MONITORING UNDER SERVICE NEEDED 6. OTHER (explain)

Overall Rating For the Bridge: SAFE (Green Tag):_______MORE REVIEW NEEDED (Yellow Tag) ________UNSAFE(Red Tag):__________ Name of the Inspector(s):

116

117

QUESTIONNAIRE FOR THE WORKSHOP OF POST-EARTHQUAKE SAFETY EVALUATION OF BRIDGES AND ROADS IN THE STATE OF INDIANA We appreciate your effort in completing all items on this evaluation form. Your comments and constructive criticisms will be carefully studied and will be used to improve the workshop material for future presentations to the other INDOT personnel. Please mark the box that you feel best indicates the quality and effectiveness of the item being evaluated.

THE RATING ABOUT

WORKSHOP CONTENT, MATERIAL, PRESENTATION.

NO

T

APP

LIC

AB

LE

VE

RY

PO

OR

PO

OR

AV

ER

AG

E

GO

OD

y G o

1. Were the objectives of the workshop clearly defined and accomplished?

Comments: 2. Do you believe that subjects were covered adequately in

the allocated time?

Comments: 3. Did the presentations have the right combination of theory

and practice?

Comments: 4. Was the use of the handbook in the classroom effective?

Comments: 5. Will the workshop material serve as a useful reference for

you in the future?

Comments: 6. What is your opinion about the workshop examples and

exercises?

Comments: 7. Were the instructors able to convey the objectives of the

workshop properly?

Comments: 8. Were the participants of the workshop given adequate

opportunity to ask questions and get the satisfactory answers?

Comments: 9. Was the instruction well organized?

Comments: 10. What is your overall assessment about this workshop?

Comments: 11. Do you feel yourself ready to go out and inspect the

bridges?

Comments: