Hampshire Streetworks Quarterly Co-ordination
Meeting
Wednesday 9th October 2019
1000 – 1200
Ashburton Hall, EII Court
NEW ROAD AND STREETWORKS ACT 1991 / TRAFFIC MANAGEMENT ACT 2004
Agenda• Upcoming Major Works
• Area West
• Area East
• Area South
• Area North
• Area Central
• Cross Border
• Colas acting on behalf Portsmouth City Council PFI
• Performance Data
• Any Other Business
• Lane Rental
• Permit Scheme Performance
• Resourcing Sites
• TTROs for PROWs
• We're Hiring
• Christmas Restriction
• Next Meeting
Upcoming Major Works
• Area West
• Area East
• Area South
• Area North
• Area Central
• Cross Border
Area West
Holmsley BridgeHCC
• Bridge replacement and new alignment
• Estimated 8 weeks closure of A35 in Autumn 2020, with other TM set-ups after
• Wide diversion route around New Forest
• Works on Traffic Sensitive roads to be restricted
• No SU new apparatus works should be allowed over A35 and C10 (consulatation with Coordinator to be carried out)
Hut Hill Cycle Lane, Chandler’s FordHCC
• 25/10/19 - March 2020
• Construction of cycle lane on Winchester Road between Asda Roundabout and Chilworth Roundabout
• TM: 24hr TTLs
Fernhill Lane, New Milton
• 23/10/19, for approx. 10 days
• TM: Road Closure in both directions
• Sewer Connection
• Collaborative working opportunity
• Works on TS Streets in New Milton will be restricted
Lyndhurst Rd, BrockenhurstHCC
• 4/11/19 – 13/12/19 and 6/1/20 –3/4/20
• Footway works between BalmerLawn Road and Brookley Road
• TM: 2-Way TTLs, off peak between 0930 – 1600
• No weekend working
Romsey Drainage – Middlebridge St HCC
• 15/11/19 – Feb 2020
• Drainage maintenance and improvement works
• TM: 2-Way TTLs, off peak
• From Mainstone Junction to 240m north west along the A27. From Mainstone Junction to 175m north east along the Mainstone
• Diversionary works underway
Romsey Drainage, Duttons RdHCC
• Dates TBC
• Proposed drainage scheme
• Involve 6 week closure between Greatbridge Road and Station Road
• Preference is Summer Holidays 2020
• Highly disruptive as main route into town from North and to rail station
• Politically sensitive
Romsey Drainage, Greatbridge RdHCC
• 3/2/20 for approx. 3 weeks
• Drainage improvement works
• TM: 24hr TTLs, with all day manual control
• Includes weekend closures of Budds Lane
Lepe
• 1/10/19 – 20/1/20
• TM: Road Closure on Lepe Road between Hampton Lane and Exbury Road
• Mains Renewal
• 4/11/19 – 20/1/19
• TM: Road Closue on Road Through Exbury between Summer Lane and Lepe Road
• Mains Renewal
SSEN Upgrade, Crampmoor
• Ongoing SSEN works
• TM: 24hr TTLs on Winchester Road, manual control in peak times
• Next phases TBC, but includes closure of Green Lane (est. Winter 19/20) and Highwood Lane (est. Summer 20)
SSEN Upgrade, Andover
• Proposed network upgrade from Anton Mill Road to substation behind the Hospital
• Full route TBC. A3057 Western Avenue then either Charlton Road or A343 Redon Way - Trial hole investigations underway
• Lane closure on Western Avenue. TM set-up for Charlton Rd or Redon Way TBC
• Completion requested by April 2020, start date TBC but likely November
Footway Works, FordingbridgeHCC
• Resurfacing and civils proposed for February half term 2020
• TM: 24hr closure of Salisbury Rbt at junction of Bridge Street
Eling HillHCC
• 4/11/19 - 8/11/19
• Carriageway works
• TM: 24 closure
• Diversion on TS streets
• 11/11/19 - 15/11/19
• Lexbury Road
• Carriageway works
• TM: Closure, diversion in the estate
TVBC Future Works
Area East
Butts Bridge, Alton278
• Expected end date 14/11/19
• The replacement of the brick arch railwaybridge with a new steel structure
• Replacement of the existing doubleroundabout junction between the A339, ButtsRoad and Winchester Road with a new singlelarge roundabout with widened approaches onthe A339, and improved foot/cycleway links.
• Provision of a new roundabout junction toserve the Selborne Road site on the A339,providing access to Winchester Road via anew link road.
Budds Ln, BordonHCC
• 29/04/19 - 01/10/19
• Improvement works to footway and carriageway resurfacing
• Drainage works for new school
• TM: Road Closures and TTLs
Butts Bride, AltonBudds Lane
Emsworth Common Rd, HavantHCC
• 23/09/19 – 27/10/19
• TM: 24hr Road Closure
• Drainage Improvement Works
• Diversion through Westbourne
Havant Rd & Warblington Rd, EmsworthSSEN
• 13/06/19 – 18/10/19
• TM: Road Closue on Warblington Road and Multi-way TTLs on Havant Road
• Repair oil filled cable leak
Havant Rd / Selangor Ave, Emsworth278
• 15/07/19 – 30/10/19
• TM: Two-way TTLs, manual control from 0630 – 1830
• New signal junction and pedestrian crossing, with widening of A259
College Rd / Purbrook Way, Waterlooville278
• Approx. 16 week closure proposed from Jan – May 2020
• Next to South Downs College
• Upcoming meeting arranged for these works
Area South
North Whiteley Development 278
• Botley Road, Curbridge
• 16/09/19 – 08/11/19
• TM: Two-way TTLs
• Creation of new Northern Access
• Works up to mid 2020
• Cycleway / footway scheme to be added to Northern Access Junction
Eclipse Busway Phase IIHCC
• Rowner Road, Gosport
• Dates TBC
• TM: TBC
Bull Ln, Waltham ChaseLicence
• 14/10/19 for approx. 3 months
• TM: Road closure of Bull Lane and Little Bull Lane
• New Development at Hunters Green
• Construction of a new sewer
A32 Hoad’s Hill, WickhamS278
• Dates TBC
• Re-surfacing night works
• TM: Road closure
• Approx. 10 nights
Marine Parade West, Lee on the Solent
• Dates TBC
• TM: Multi-way Lights (24hr)
• Gas Mains Upgrade
Redlands Ln, FarehamHCC and SGN
• SGN – Mains Upgrade Project from Upper Saint Michaels Grove to Mill Rd
• Feb 2020 - approx. 6 weeks, involving 4wks of 24/7 road closures severely impacts BRT bus route
• Summer 20 - OPRES resurfacing of Redlands Lane under 2/3 week closure
A27 Southampton RdHCC
• 29/07/19 – 28/10/19
• TM: Lane Closures
• Various minor repair works along the carriageway and footway of the A27 between Segensworth Roundabout and Titchfield Gyratory. Footway closure alongside Titchfield Primary School for replacement of path surface
Quay Street Roundabout278
• Summer 2020
• S278 remedial c/way surfacing works
• Overnight works will be a requirement
Fareham
• 22/07/19 – 31/10/19
• Lay new HV cable
• TM: TTLs and Road Closures
• Roads Affected:• Wallisdean Avenue
• Highfield Avenue
• Fairfield Avenue
• St. Anne’s Grove
• St. Michael’s Grove
Stubbington Bypass, Lee-on-the-SolentHCC
• Reconstruction
• TBC 18/11/19 start
Haslar Development
• Works in progress for approx. 9 months
• Road closure on Clayhall Road between Haslar Road and Anglesey Road for 9 months from the 1st November 2019 to the end of June 2020
• Road closure on the Avenue road between Green Road and Privet Road to run concurrently from July 1st July 2020 for 4 months until the end of October 2020
• Cross connection to make at Privet Road to make at the junction of Oval Gardens – yet to be confirmed
A32 Fareham RdHCC
• A32 Fareham Road junction with Wych Lane
• Widening of A32
• Night works
A27 Delme, FarehamHCC
• 21/10/19 – 22/11/19
• TM: Multi-way signals and night-time Lane closures
• Traffic upgrade signals
Parkway, WhiteleyHCC
• 27/09/19 – 30/11/21
• TM: Lane Closure
• Major junction upgrade works at M27 J9 and Parkway south roundabout in Whiteley
Area North
Hartley Wintney
• 24/06/19 – Dec '19
• Mains Upgrade
• Works left at A30 j/w Hares Lane
• Connection left at Belgrave Mews
Winchester St, Basingstoke
• Dates TBC
• Mains Upgrade Project
• Discussions still ongoing
Chapel Hill, Basingstoke
• 4/11/19 – 2/12/19 (TBC)
• TM: Some Carriageway Incursion
• Mains upgrade
• Likely to cause disruption due to close proximity of train station
• Liaison with NR and B&D BC for specialist material and permission to work on NR land
Newnham Rd, Hook
• 29/07/19 – February 2020
• New Water Main
• TM: Road Closure
• Affected Roads:• Ridge Lane • Crown Lane• Tylney Lane• Newnham Lane
A340 Ringway West, BasingstokeHCC
• 20/05/19 – 30/11/20
• TM: Lane Closure
• Carriageway widening on all approach arms and circulatory carriageway
• Signalisation of roundabout and installation of toucan crossing
Buckskin Flood Alleviation SchemeHCC
• Dates TBC
• TM: Road Closures
• Installation of new drainage infrastructure
Crookham Rd / Glen Rd, Fleet
• November 2019 (TBC)
• Closure of Glen Road, for storage compound at junction with Crookham Road
• TM: Two-way rolling TTLs down Crookham Road, with side road closure
• Manual control in peak hours
• Mains upgrade project
Fernhill Rd / Lane, Hawley
• 24hr closure of Fernhill Lane
• TTLs at junction of Fernhill Road with Woodlands Walk 28/10/19 –8/11/19
• TTLs along Woodlands Walk 30/10/19 – 19/11/19
• TTLs at junction of Fernhill Lane to near Riverside Yard (11/11/19 –26/11/19
Titchners Farm, London Rd, Hook
• 13/1/20 – 31/3/20
• TM: TTLs
• Upgrade to sewer to accommodate new housing development
Area Central
Jewry St, Winchester
• Footway remedials
• Dates 11-22 November
• TM: Some carriageway incursion
• Contact: Duncan Fowler SSE
High St, WinchesterHCC
• Footway resurfacing
• TM: footway closures in place, possible night closures for carriageway repairs
• Currently ongoing due to finish end of November 2019
• HCC Contact – Gary Shotter
Bishopstoke
• Works are now in progress – 40%
of present submitted build phases
completed
• Fibre cabling
• Due to finish March 2020
• TM: Various TM throughout
scheme including TTLs, no road
closures
• Contact: Scott Vander
Hiltingbury Rd VM Chandlers Ford
• Various location around this area -mostly residential areas. Works on Hiltingbury Road, Ashdown Road, Nichol Road etc.
• Due to finish in January 2020.
• TM – Mostly non positive TM but occasional use of TTLs
• Contact: Scott Vander
Stoneham Ln, Housing DevelopmentS278
• New Roundabouts Concorde Club and Lakelands / Old Stoneham Lane Footway construction. New access into the housing site and signalised junction
• The surfacing quality is being investigated
• Minor footway works still remaining
• Due to finish December 2019
• Contact: Abayomi Kasinro
Chestnut AvenueS278
• Follows on from Stoneham Lane project
• Works due to start early 2020
• New signalisation works at junction with Nightingale Avenue
• TM: Under discussion
• Contact: Abayomi Kasinro
Bar End Road, WinchesterS278
• Due to start in March 2020
• Due to be completed end of 2020
• TM will be TTLs and closure for surfacing phase
• New Leisure Centre development
• Blanchard Wells – Chris Hill
Woodhouse Lane, Hedge EndHCC
• Woodhouse Lane to be widened and 3 new highway structure to be installed.
• TM: Road closures and TTLs
• Currently at this time trial holes are being undertaken
• Investigations are ongoing
• HCC contact Chris Campos
Windover Roundabout/ J8
• Carriageway widening of Windover Roundabout and all arms off the roundabout
• TM: Lane closures and proposed full closures
• Due to start March 2020
• HCC contact Mark Webster
Bishopstoke RoadHCC
• Upgrade to existing footway
• Change Pelican crossing to a Toucan crossing
• Starting 16 October
• Due to finish November 2020
• TM: TTLs
• Contact – Steve Swain
Bournemouth Road – New Villiage Hotel
• HCC 278 team – New footway, associated drainage and access.
• Works due to commence in Feb/March 2020
• TM will be TTLs
• Contact: Farncombe Construction
Bournemouth RoadLicensed Works
• Due to start in 2020
• New foul and surface water sewer installation
• Coincide with HCC 278 Works
• TM: TTLs and lane closures at times.
• Due to finish summer 2020
• Contractor: Farncombe Construction
Cross Border
A3, A27 Southampton RoadPCC
• 7/10/19 – 1/11/19
• TM: Lane Closure
• Widening and resurfacing of the existing footway/cycleway on the north side of A27 Southampton Road for extents of service road. Scheme also requires changes to lamp column positions, traffic signal heads and street furniture.
• Authority: SCC
• Start: Nov / Dec 2019
• Duration: 12 Months
• Discussion is underway
Portswood Scheme
Southampton City West - Overview
Redbridge Roundabout
• May 2019 – Spring 2020
• An upgrade to the Redbridge roundabout. This will include a dedicated left-turn lane for traffic leaving the M271 to access Southampton docks and city centre.
M27 Romsey Road Bridge, Nursling
• April 2018 – January 2020
• Demolishment and replacement of the bridge
• HCC / SCC have proposed January Dates
• Two-Way TTLs still in place
Smart Motorways
• M27 Junction 4 – 11
• Now – 2021
• Periodic overnight closures
• Narrow lanes – 50mph
• https://highwaysengland.co.uk/projects/m27-junctions-4-to-11-smart-motorway/
Colas acting on behalf Portsmouth City Council PFI
1. Current & Planned Works
2. Cleansing and Grass Cutting Closures
3. Resurfacing, Structures & Signals
4. Special Events
5. Seasonal directional
6. Sample inspection performance Q2
7. Contact details
1. Current & Planned Works
Road Name OwnerStart Date/
DurationEnd Date Comments
King street, (former Southsea
community centre)PMC 29/04/2019 29/10/2021
Road closure / construction of 5 story
building (Ongoing)
Museum Road Wates 24/06/2019 24/11/2020
Removal of coach/parking bays
(Ongoing)
Dundas Lane (Admiral Lord Nelson )
PCC 22/07/2019 22/12/2019
Modify access to school, night works
till 03.09.19 (Ongoing)
Old Star Place Adam Bidhendy 14/05/2018 01/11/2019Premier Inn Build – Advance warning
sent (Ongoing)
King Street PMC 02/10/2019 30/11/2019 Movement of plant
Lonsdale Ave CKH/SGN 07/10/2019 20/10/2019 Gas Mains Replacement
Kings Road and Flint Street A-Plant Lux 14/10/2019 15/10/2019
Manhole replacement (multi-way
signals) Night
Garfield Road, Portsmouth Cappagh Browne 18/10/2019 19/10/2019 Parking suspension only
Landport Street Cappagh Browne 21/10/2019 18/11/2019 Replacing of water main
Road Name OwnerStart Date/ Duration
End Date Comments
Stanhope Road - Commercial Road/Edinburgh Road
City Lifting
27/10/2019
03/11/2019
17/11/2019
28/10/2019
04/11/2019
18/11/2019
Revoke TRO 17, Sat 04:00 till Sunday 05:00
Alec Rose Lane Kier
27/10/2019
03/11/2019
17/11/2019
27/10/2019
03/11/2019
17/11/2019
Road Closure- Crane location in Highway
Elmwood Road Openreach 31/10/2019 02/11/2019 New service , extra night in case
Specks Lane Cobra Traffic Management 31/10/2019 01/11/2019 Telecoms maintenance
Eastern Road Colas Ltd 04/11/2019 06/11/2019 Deflectograph survey works- Night
Western Road Colas Ltd 06/11/2019 08/11/2019 Deflectograph survey works- Night
M275 NB and SB Colas Ltd 08/11/2019 10/11/2019 Deflectograph survey works- Night
Dorking Crescent DN Associates 12/11/2018 12/06/2020 Temp one way system
2. Cleansing / Grass Cutting Closures Road Name Owner Start Date End Date
Day or Night Works
Comments
J and J
(Southampton Road, M275 / M27)
Colas Ltd 7/10/19 11/10/19 Nights SRW REF ; 83397 22:00 to 05:30
M275 SB and NB
Cleanse +
Southwick Rd
TRO 11/19
Colas Ltd 14/10/2019 18/10/19 NightsNB Full Flyover, NB + SB Lane
closure SRW 83378
Southampton
RoadColas Ltd
20/10/2019
10/11/2019
01/12/2019
15/12/2019
20/10/2019
10/11/2019
01/12/2019
15/12/2019
Day Grass cutting (lane closures)
Holbrook road Colas Ltd 31/10/2019 02/11/2019 Nights Road Closure
Eastern Road
CleanseColas Ltd 02/12/2019 04/12/2019 Nights SRW REF ; 83417 22:00 to 05:30
Western Road Colas Ltd 4/12/19 6/12/19 NightsCleanse (lane closure) SRW Ref
83417
M275 SB and NB
Cleanse +
Southwick Rd
TRO 11/19
Colas Ltd09/12/2019 13/12/2019 Nights
NB Full Flyover, NB + SB Lane
closure SRW 83378
3. Resurfacing, Structures & Signals Road Name Owner Start Date End Date Detail
Twyford Avenue Colas Ltd 09/09/2019 31/07/2020 LCR Carriageway Resurfacing
Stamshaw Road Colas Ltd 09/09/2019 31/07/2020 LCR Carriageway Resurfacing
Havant Road (part) Colas Ltd Mon 14/10/19 Fri 01/11/19 LCR Carriageway Resurfacing
Tangier Road (part) Colas Ltd Mon 28/10/19 Fri 08/11/19 LCR Carriageway Resurfacing
Spur Road Colas Ltd Thu 07/11/19 Tue 19/11/19 LCR Carriageway Resurfacing
Devonshire square (part) Colas Ltd Thu 14/11/19 Fri 22/11/19 LCR Carriageway Resurfacing
Holbrook Road/ Garnier street 2019-1001 Mon 14/10/19 Fri 01/11/19 LCR Electrical – Traffic Signals
Havant Road / Lower Drayton Lane Colas Ltd Mon 04/11/19 Fri 22/11/19 LCR Electrical – Traffic Signals
Allaway Avenue /Woofferton Road Colas Ltd Mon 18/11/19 Fri 06/12/19 LCR Electrical – Traffic Signals
Road Name Owner Start Date End Date Detail
Prince George Street Colas Ltd Tue 07/01/20 Tue 14/01/20 LCR Footway Resurfacing
London Road - Unclassified Colas Ltd Mon 13/01/20 Tue 11/02/20 LCR Footway Resurfacing
Elm Grove Colas Ltd Mon 30/03/20 Wed 06/05/20 LCR Resurfacing 14.1
Programme TTRO Order
Kings Road Colas Ltd Mon 06/04/20 Wed 22/04/20 LCR Resurfacing 14.1
Programme TTRO Order
Victoria Road north Colas Ltd Mon 20/04/20 Fri 29/05/20 LCR Resurfacing 14.1
Programme TTRO Order
Milton road (St Marys Rd RAB -
Velder Avenue)
Colas Ltd Mon 01/06/20 Mon 15/06/20 LCR Resurfacing 14.1
Programme TTRO Order
Havant Road Colas Ltd TBC TBC LCR Resurfacing 14.1
Programme TTRO Order
Hayling Avenue Colas Ltd Mon 01/06/20 Tue 07/07/20 LCR Resurfacing 14.1
Programme TTRO Order
St Marys Road RAB Colas Ltd Wed 10/06/20 Fri 19/06/20 LCR Resurfacing 14.1
Programme TTRO Order
Havant Road / Court Lane Colas Ltd Mon 06/01/20 Fri 24/01/20 LCR Electrical – Traffic Signals
M275 Slip Road / Ferry Port Colas Ltd Mon 03/02/20 Fri 20/03/20 LCR Electrical – Traffic Signals
Holbrook Road/Somers Road North Colas Ltd Sun 23/02/20 Tue 21/04/20 LCR Electrical – Traffic Signals
Stamshaw Road/Angerstein Road Colas Ltd Mon 02/03/20 Fri 20/03/20 LCR Electrical – Traffic Signals
Eastern Road / Copsey path
underpass
Colas Ltd Mon 06/04/20 Wed 13/05/20 LCR Electrical – Traffic Signals
Fratton Road/Bridge Centre Colas Ltd Mon 20/04/20 Mon 11/05/20 LCR Electrical – Traffic Signals
St Marys Road/Shakespeare Road Colas Ltd Mon 11/05/20 Mon 01/06/20 LCR Electrical – Traffic Signals
Rudmore RAB - 4 subways Colas Ltd Mon 11/05/20 Fri 10/07/20 LCR Electrical – Traffic Signals
Winter Road/Devonshire Avenue Colas Ltd Mon 01/06/20 Fri 26/06/20 LCR Electrical – Traffic Signals
Eastney Road/Bransbury
Road/Devonshire Avenue
Colas Ltd Mon 29/06/20 Fri 17/07/20 LCR Electrical – Traffic Signals
3. Resurfacing, Structures & Signals 2020
4. Special EventsName Date Location
Walk for freedom Sat 19/10/19 - Sat 19/10/19 Portsmouth Guildhall Square
Great South Run Sat 19/10/19- Sun 20/10/19 Clarence esplanade – Pier Road – Pembroke
Road - High Street – St Georges Road – B2154
– Main Road – Victoria Road – Gloucester Road
– Cross Street - Queen Street – Anglesea Road
- A2030 – A288 – Kings terrace – Clarence
parade – Eastern Parade – Eastney Esplanade
King George Fireworks Wed 06/11/19- Wed 06/11/19 King George Playing Field
Remembrance Sunday service Sun 10/11/19- Sun 10/11/19 N/A
Commercial Road Christmas lights switch on Thu 21/11/19- Thu 21/11/19 Commercial Rd and Cascades shopping centre
Cosham Christmas lights switch on Thu 28/11/190 Thu 28/11/19 High Street
Victorian Christmas festival Fri 29/11/190 Sun 01/12/19 Portsmouth Historic Dockyard
Festival of Lights Thu 05/12/190 Thu 05/12/19 Fratton Road
Lake of Lights Sun 15/12/190 Sun 15/12/19 Canoe Lake
5. Seasonal directional
All highlighted routes starting on 7th December through to 5th January will have restrictions / directions imposed.
Ideally works to be completed before or postponed to after the dates detailed above.
7. Contact details Noticing, FPNs, S74, S81’s etcColas LtdWalton RoadFarlingtonPortsmouthHantsPO6 1TAGeneral Tel 02392 310 900
Network Coordinator (primary contact)
Noticing Admin & licensing
Network Utility Inspector
TM auditor / TSCO
Parking [email protected]
TTRO / TRN applications
Performance
Any Other Business
Lane Rental
• HCC planning to introduce a scheme in 2021
• Early engagement with DfT
• We'll be keeping everyone updated as things progress
Street Manager
• HCC testing in sandbox from Nov
• We will be using Confirm through the API
• Potential lag in permit processing – please don't send 'clusters of permits' as the lag may cause permits to be loaded out of sequence
Permit Scheme Performance
• Some headline figures so far (data for SU works only, at the moment)
• 70% of works are completed in one phase
• 175 instances of collab working
• ¼ of all works have improved info for residents / motorists
• ¼ of all works done outside of peak times / extended working hours
Resourcing Sites
• Critical sites need to be resourced appropriately
• Failure to do so will draw criticisms and complaints
• Continued failure to resource sites, may result in permits being revoked
TTROs for PROWs
• https://www.hants.gov.uk/landplanningandenvironment/rightsofway/temporaryclosures
Area Co-
Ordinator East
Christmas Restrictions In
Hampshire
9/12/19 – 10/1/20
Some A & B Class and Traffic Sensitive Roads
Next Meeting
15/01/20
0930 arrival
1000 – 1200
Ashburton Hall, Podium Level, Winchester