Ohio Department of Transportation

w w w. t r a n s p o r t a t i o n . o h i o . g o v

John R. Kasich, Governor • Jerry Wray, Director

HAM-75-2.30

HOPPLE INTERCHANGE

RECONSTRUCTION

Friday, January 18, 2013

Page 2: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

2

HOPPLE INTERCHANGE

RECONSTRUCTION

Dennis Stemler, District Construction Engineer

Stefan Spinosa, District Design Engineer

Kelly Wessels, Resident Engineer

Chris Tuminello, Project Engineer

Sharon Smigielski, Public Information Officer

Vince Martini, Kokosing Project Manager

Page 3: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

3

HOPPLE INTERCHANGE

RECONSTRUCTION

Current Status

The project has been sold to Kokosing

Construction Company

Official contract due mid February

All dates are subject to change until

contractor’s construction schedule is

approved

Page 4: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

4

HOPPLE INTERCHANGE

RECONSTRUCTION

Page 5: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

5

HOPPLE INTERCHANGE

RECONSTRUCTION

The project along I-75 will begin near

the Western Hill Viaduct and end near

the I-74 interchange

I-75 will be widened to add an

additional lane in each direction

Page 6: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

6

HOPPLE INTERCHANGE

RECONSTRUCTION

Hopple Street will be reconstructed to

span Central Parkway

The Connector Road will be

constructed to give access from

Hopple Street/Martin Luther King Drive

to Central Parkway

Page 7: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

7

HOPPLE INTERCHANGE

RECONSTRUCTION

HOPPLE INTERCHANGE RECONSTRUCTION

X

Page 8: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

8

Traffic Pattern Changes

Clifton Colony

Drive will be

closed at MLK and

connected to

Central Parkway

in 2013

HOPPLE INTERCHANGE RECONSTRUCTION

X

Page 9: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

9

Traffic Pattern Changes

Northbound I-75

ramp from

eastbound Hopple

Street will be closed

early in the project

The Bates Ramp to

I-74 will be closed

between May 1 -

August 15, Summer

2014

HOPPLE INTERCHANGE RECONSTRUCTION

Page 10: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

10

Traffic Pattern Changes

Southbound I-75

ramp from

westbound Hopple

Street will be

closed in Spring

2014

A left turn to

southbound I-75

will be provided

HOPPLE INTERCHANGE RECONSTRUCTION

Page 11: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

11

Traffic Pattern Changes

I-74 eastbound exit ramp to Central

Parkway will be closed upon the

completion of the new Hopple Interchange

HOPPLE INTERCHANGE RECONSTRUCTION

Page 12: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

12

Traffic Pattern Changes

Central Parkway

near Bates

Avenue will be

reduced to 1 lane

in each direction

for 90 days to

perform MSD

work

HOPPLE INTERCHANGE RECONSTRUCTION

Page 13: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

13

LANE AND RAMP RESTRICTIONS

The contractor has permitted times for

short term lane and ramp closures on I-75

Permitted lane closure times are specified at

http://plcm.dot.oh.us

Disincentives are in place if the contractor

violates the permitted lane closures

I-75: $3,000 per lane for each 15 minutes

I-75 ramps: $1,500 per lane for each 15 minutes

HOPPLE INTERCHANGE RECONSTRUCTION

Page 14: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

14

ODOT CONTACT INFORMATION

ODOT District 8 (800) 831-2142

www.dot.state.oh.us

Sharon Smigielski, Public Information Officer [email protected]

Office: (513) 933-6511

Chris Tuminello, Project Engineer Construction Field Office: (513) 564-6107

Kelly Wessels, Resident Engineer Office: (513) 933-6666

Page 15: HAM-75-2.30 HOPPLE INTERCHANGE RECONSTRUCTION€¦ · Chris Tuminello, Project Engineer Sharon Smigielski, Public Information Officer Vince Martini, Kokosing Project Manager . 3 HOPPLE

15

HOPPLE INTERCHANGE

RECONSTRUCTION

Thank you for attending