Upload
stevefinnie
View
1.461
Download
2
Tags:
Embed Size (px)
DESCRIPTION
A Holistic Approach to Road Construction and Environmental Impact, and the Role of Ecologically Based Techniques in Planning and Design
Citation preview
CONFIDENTIAL PRIVATE INFORMATION
International Forum on Life-Cycle Maintenance and Management
Technologies for Smart Highway System
2
Highway Challenges
A Holistic Approach to Road Construction and Environmental Impact, and the Role of Ecologically Based Techniques in Planning and Design
Authors: Steven B Finnie and Harold T M Insley
• Steven B Finnie
Associate Director, Pavement, Trackbed and Materials Consultancy
URS Scott Wilson Ltd, Nottingham, United Kingdom
• Harold T M Insley
Associate Director, Head of Environmental Services
URS Scott Wilson, Hong Kong
CONFIDENTIAL PRIVATE INFORMATION
Contents of Presentation
• Halsema Highway Case Study
• Typical Slope Problems
• Design of Remedial Works
• Environmental Aspects
• Examples of other Mountain Road Projects
• Typical Design Features
3
Highway Challenges
Theme of paper: Mountain Highways in Developing
Countries
Halsema Highway History
4
Highway Challenges
• Road at 2,000m elevation and above
• Typical rainfall 2,400mm per year
• Partially paved mountain road damaged by earthquake and typhoons in1990s
• Richter 7.8 magnitude quake in July 1990 seriously damaged road, and Hyatt Hotel in Baguio collapsed killing 80 people
• Damage to road not immediately repaired
• Significant typhoons caused major erosion damage
• Consultants appointed in 1996 for feasibility study to rehabilitate highway
• World Bank funded
CONFIDENTIAL PRIVATE INFORMATION
Major Arterial Highway serving Region
5
Highway Challenges
• Halsema Highway runs from Baguio City to Bontoc to Banaue (rice terraces)
• Baguio City regional capital
• Major vegetable growing area
• Vegetables trucked down to outskirts of Baguio in small trucks
• Transferred to 10 wheeler trucks or bigger for transport to Manila (capital city)
• Construction on first section from La Trinidad to Mount Data started in 2000
Feasibility Study, Rehabilitation Design and Construction Supervision
6
Highway Challenges
• 180 km long Halsema Highway links Philippines summer capital of Baguio with famous “ Banaue rice terraces” World Heritage Site considered to be more than 2,000 years old
• Road crosses some of most difficult topography in South East Asia – main ridge of Central Cordillera runs approximately north-south
• Central Cordillera: steep, knife-edged and underlain by highly fractured, faulted and weathered materials
• Scott Wilson carried out feasibility study, design and construction supervision of geotechnical works
• Scope of services included geotechnical, geological, bio-engineering, hydrological, environmental, ecological and social impact aspects
CONFIDENTIAL PRIVATE INFORMATION
Halsema Highway, Philippines
7
Highway Challenges
• Rural highway in high rainfall, seismically active mountainous
area
• Carried out feasibility study for rehabilitation including geotechnical, hydrological,
environmental and social impact investigations
• Although Halsema Highway is a major road, it is classed as a “low-cost” road for purposes of this
rehabilitation, which restricted scope of investigations (i.e. limited ground investigation) and scope of rehabilitation work
Halsema Highway, Philippines
8
Highway Challenges
• Landscape very fragile, and highly
susceptible to erosion caused by intense storm runoff and destabilising earthquakes
• Programme of aerial photography
carried out
• Followed by field mapping, engineering geological inspection and the sinking of boreholes
• Initial Environmental Assessment carried out
• Innovative bio-engineering designs
needed to stabilise slopes
CONFIDENTIAL PRIVATE INFORMATION
One of “Most Dangerous Roads in World”
9
Highway Challenges
Typical Slope Problems
10
Highway Challenges
• Failure of slopes on to road (rock falls, debris slides etc)
• Failure of slopes below road
Leading to loss of road edge
(including wall foundation failure)
• Failure of entire road formation
• Debris flows & slope erosion
Technical Assistance for Risk Assessment and Management D2
282800 in 1997
CONFIDENTIAL PRIVATE INFORMATION
Large Landslide below Highway
11
Highway Challenges
Unstable Slopes above Highway
12
Highway Challenges
CONFIDENTIAL PRIVATE INFORMATION
“Temporary” Structures to Maintain Access
13
Highway Challenges
• After earthquake and typhoons in 1990s access along highway provided with mixture of “temporary measures”including Bailey Bridges, and temporary diversions
• Photo of crossing of “saddle” where roadway failed on both sides of highway
Design of Remedial Measures
14
Highway Challenges
Integrated Approach Required
•Geotechnical engineering measures
•Drainage engineering measures and erosion control
•Slope protection and bio-engineering measures
•Environmental protection
CONFIDENTIAL PRIVATE INFORMATION
Typical Rehabilitation
15
Highway Challenges
Halsema Highway
Typical Major Rehabilitation
16
Highway Challenges
Halsema Highway
CONFIDENTIAL PRIVATE INFORMATION
Integration of Bio-Engineering with Geotechnical Design
17
Highway Challenges
Failures and Erosion below Road Bench
18
Highway Challenges
Pre-Construction
CONFIDENTIAL PRIVATE INFORMATION
Rehabilitation below Road Bench
19
Highway Challenges
Works Substantially Complete
Masonry Wall to Support Road Bench
20
Highway Challenges
CONFIDENTIAL PRIVATE INFORMATION
Drainage and Stream Protection Measures
21
Highway Challenges
Above Road Retaining Structure
22
Highway Challenges
Completion of shotcrete &
construction of above-road
retaining structures
CONFIDENTIAL PRIVATE INFORMATION
Environmental Aspects
23
Highway Challenges
• Environmental Impacts related to Heritage Sites and National Park
• Construction Impacts
• Traffic Related Impacts
• Social Impacts
Environmental Impacts – Heritage Sites and National Park
24
Highway Challenges
• Photo shows rice terraces near Banaue
• Heritage site
• Road also passes through National Park
• World Bank required impacts on Heritage Site and National Park minimised as far as practical
CONFIDENTIAL PRIVATE INFORMATION
Construction Impacts
25
Highway Challenges
• Noise (generated by construction plant)
• Dust
• Disposal of excavated material
• Excavation of borrow areas
• Water quality impacts, and erosion
• Social impacts from clearance, etc.
• Impact of construction on traffic using road
Traffic Related Impacts
26
Highway Challenges
• Improved road surface, previously unpaved, now concrete pavement, results in increased vehicle speeds
• Increased speeds result in greater potential for accidents involving excessive speeds
• Accidents as a result of “blind” corners, pedestrians on roads, boulders from slopes above causing obstacle on road, fog banks
• Mountain road creates opportunity for major accidents with vehicles crashing off road, and causing many fatalities (especially buses)
• Limited budget for road side barrier but small up stand wall included
• Road humps to reduce speed
• Increased axle loads
CONFIDENTIAL PRIVATE INFORMATION
Social Impact Assessment
27
Highway Challenges
• Clearance of encroachments into road reserve
• Some acquisition of agricultural land for minor alignment improvements
• Socio-Economic Surveys carried out
• Resettlement Action Plan prepared
• Community engagement
Examples of Other Mountain Road Projects
28
Highway Challenges
• Nepal: Prithvi Highway
• Nepal: Third Road Improvement Project
• Tajikistan: Shagon-Zigar Road
• Bhutan: Road Network Study
• Ethiopia: Koombolcha – Mekane Salem – GundewienRoad
CONFIDENTIAL PRIVATE INFORMATION
Prithvi Highway, Nepal
29
Highway Challenges
Flood Damage Assessment, Study Report, Design of
Remedial Works and Supervision
• Geotechnical examination, inventory of flood damage
• Recommendations for and prioritisation of reinstatement and further erosion protection
works
• Remedial, reinstatement, and protection measures
• Design/supervision/ contract
management services for damage repair, contract management and supervision
Third Road Improvement Project, Nepal
30
Highway Challenges
• Improvement and rehabilitation
of 350km of rural access road to
bitumen standard in mountainous
and flat terrain
• Economic screening study
• Typical design details, and
design checks
• Procurement and construction
supervision
Improvement and Rehabilitation of Rural
Roads
CONFIDENTIAL PRIVATE INFORMATION
Shagon-Zigar Road, Tajikistan
31
Highway Challenges
• Situated along border with Afghanistan,
alignment through foothills of Pamirs and
bordered by Pyanj River to east
• Alignment traverses extremely rugged,
mountainous terrain
• Challenges to engineering team included
rockfall from natural slopes, extreme
topography and weather conditions and
sensitive ground conditions disturbed by
pre-contract blasting and seismic activity
Feasibility, Design, Supervision
Road Network Study, Bhutan
32
Highway Challenges
• Survey and analysis of typical slope
stability problems
• Slope maintenance manual
• Economic evaluation of proposed
improvements
• Environmental Impact Assessment
of proposed improvements
• Road improvement strategies
Technical Assistance Project to Prepare Prioritised Road
Improvement Programme
CONFIDENTIAL PRIVATE INFORMATION
Kombolcha – Mekane Salem – Gundewien Road, Ethiopia
33
Highway Challenges
• Construction of 136 km new gravel road,
with dense base macadam on steep
gradients, and simultaneous construction
of 2 new bridges over River Nile and
tributary, Difarsa River
• Geotechnical services included detailed
aerial photograph interpretation, field
engineering geological and
geomorphological mapping, reference
condition mapping, landscape evolution
modelling, ground investigation and
outline design of slope works.
Remote Sensing, Engineering Geological Mapping, Ground
Investigation, Design Review (including redesign) and
Construction Supervision
Typical Design Features
34
Highway Challenges
• Bio-engineering
• Gabion Wall
• Combined Masonry and Gabion Wall
• Reinforced Earth Wall
• Reinforced Concrete Grid Wall
• Surface Reinforcement
• Buttress Wall
CONFIDENTIAL PRIVATE INFORMATION
Bio-Engineering Slope Protection
35
Highway Challenges
Bio-engineering is the use of vegetation, either alone or in conjunction with civil
engineering structures, to reduce slope instability and erosion on slopes.
4 main groups of techniques are available:
� Grass line planting
� Brush layering etc
� Shrub, tree and bamboo
planting
� Composite techniques
Bio-engineering
36
Highway Challenges
• Low construction cost
• Low maintenance cost
• Visually preferable
• Contributes to local economy
• Species selection is key:
• Hardy
• High rainfall and drought resistant
• Extensive use of grasses
• Bamboo and Shrub species with strong root network
• Pine trees
• Pilot trials
• Indigenous and imported species
• Local expertise utilised
CONFIDENTIAL PRIVATE INFORMATION
Gabion Wall
37
Highway Challenges
Above Road: Gabion Wall in Nepal
Below Road: Gabion Wall in Ethiopia
Combined Masonry and Gabion Wall
38
Highway Challenges
Pre-Construction
Construction Substantially Complete
CONFIDENTIAL PRIVATE INFORMATION
Reinforced Earth Wall
39
Highway Challenges
Under construction
(Ethiopia)
Reinforced Earth Wall
40
Highway Challenges
Completed wall (Ethiopia)
CONFIDENTIAL PRIVATE INFORMATION
Reinforced Concrete Grid Wall
41
Highway Challenges
Reinforced Concrete Grid Wall comprising Reinforced Concrete Members with Mortared Masonry Panels on Halsema Highway
Surface Reinforcement
42
Highway Challenges
“Plastering” a thin concrete layer over decomposed rock slope in Laos
CONFIDENTIAL PRIVATE INFORMATION
Buttress Wall
43
Highway Challenges
Buttress wall under construction in Sri Lanka