Upload
nisara-ahamad
View
646
Download
3
Embed Size (px)
Citation preview
GYPSUM PLASTERBOARD PARTITIONS
P R E S E N T E D B YM A H A M A D N I S A R A
A H A M A D
INTRODUCTION
Drywall (Plasterboard, wallboard, gypsum board) is a panel made of gypsum plaster pressed between two thick sheets of paper. It is used to make interior walls and ceilings. Drywall construction became prevalent as a speedier alternative to traditional lath and plaster.
Materials Storage
• Plasterboard, accessories, metal sections and
plasters stored in dry conditions.
• Primers and ready-mixed materials protected from
freezing conditions
Dry wall Partitioning
• Proving a cost effective, multipurpose suitable for all type of building.
Lightweight system solutions Accommodates services within stud cavity 30-180 minute fire resistance to BS Standards Can allow for deflection at the head Achieve high level of sound insulation Satisfies the BS 5234 requirements.
Dry wall Partitioning Installation Details
Gauge and dimension code, e.g. 70 S 50, checked against design specification.
The first two or three digits of a component code refer to the component width, the letters refer to the component type and the last two digits indicate metal thickness or gauge in mm.
70 S 50
“I” and “C” Studs
Axial Difference for Studs Floor Channels Head Channels
For the height up to 4200mm 102 C 50 102 DC 60For height from 4200 to 6800mm 102 DC 60 102 DC 60
Stud Splicing
• Cloaking channel minimum 600mm long. 300mm minimum on each side of stud joint, fixed with
• British Gypsum Wafer Head Jack Point Screws (subject to gauge of metal).
Installation Procedure
• Verify that substrate have achieved “Release to Follow on Works’.
• Installing steel framing except comply with framing spacing indicated
• Installation tolerances as per manufacturer’s recommendations or relevant approved method statement (if applicable).
• Steel studs secured in position and spaced as per IFC drawings.
• Proceed with installation only after unsatisfactory conditions have been corrected.
• Ensure the area is clear of defects/NCR
Gyproc Dry wall Screws
FISHER N6X40Z HAMMERFIX+PLUG SCREW FIXED AT 600MM C/C
Types of Gypsum Plasterboard
Gyproc Wallboard
Gyproc Dura Line
Gyproc Moisture Resistant
Glasroc firecase
Gyproc FireLine
Glasroc multiboard
Gyproc SoundBloc
Gypsum Plasterboard Water-Resistant Gypsum Wallboard: nominal 15mm thick for single layer or nominal 12,5 mm thick for multiple layers. 1200mm wide x minimum 2400mm long, tapered edge, fire and moistureresistant core and finish paper.
Installation Procedure
Framework installation
• Gypframe ‘C’ Studs used to form wall abutments and corners• Gypframe ‘I’ Studs used to form main framework• Gyproc Sealant applied to the perimeter of the framework prior to
boarding• Screws at 300mm centers• No fixings into head channel, maintaining designed deflection• Gypframe GFS1 Fixing Strap used at horizontal joints for double-layer
specifications
Deflection Head
• Boards and studs cut short of soffit.• No fixings into head channel• Gypframe GFS1 Fixing Strap used to maintain 300mm fixing
centres• Dropped soffit formed (always required when deflection is over
15mm)
250 to 600 mm down from Channel Bottom
Gypframe GFS1 Fixing Strap used at horizontal joints
Drawing
SE-BEB-ARSD-D-200MUXX-10002-1
O:\NISSAR\GPB\Drawings
0
1000
2000
3000
4000
5000
6000
700017
38
1283 15
71
2924
6864
4442
5710
865.
423
1129
.82
0 0
3058
.54
3493
1836
872.
5775
153.
1825 15
71
2924 38
05.4
632
949
3874
Total QTYWork DoneTO GO QTY
Work Done
Quantity of GPB
14380
5053.78
9326.22
PTB
Total QTYCompleted QTY To Go QTY
O:\NISSAR\GPB\User Guide
10152
5729
4423
Four Court and Piers
Total QTYCompleted QTY To Go QTY
Repair Work
Used opening repair
This is just to illustrate that the final "patch" will be much larger than the original hole.
Apply the sealant(CP-
606) perimeter of
opening
Apply the sealant around second layer
Make sure about edges
Apply the Screws as per
design requirements
Additional screws (if
required as per site conditions)
Fix last layer
Apply the Screws as per
design requirements
Make sure top surface should even and under the tolerance as mentioned
in Specification
Not Acceptable
Damages due to MEP
Improper opening for MEP box
Improper opening at soffit for MEP
pipes and damages of GPB
Not acceptable due to fire resistance
Not acceptable due to fire resistance
Not acceptable due to fire resistance
Gypsum end frames not fixed to
chamfered concrete column.
Gypsum end frames not fixed
to chamfered concrete column.
Screws still intact to the Deflection Head for
curved frame members
Gypsum end frames not
fixed to chamfered concrete column.
ITP,Spec,ITT and MST
SE-BEB-03QU-ITP-01035
SE-BEB-03AR-MST-0047
SE-BEB-03EG-SPC-0925
SE-000-A-11670
Site Preparation. Act:4.1 (S Point) and Act : 4.2 (W Point )
Installation of GPB and Cancelled Services ( Act : 5.3 (W Point) and Act : 5.6 (H Point)
Joint Treatment and Final Acceptance ( Act : 5.9 (W Point) and Act : 7.1 (W Point)
Inspection Process Release to Follow On Works
ITP: Inspection Test Plan
Reference Documents
O:\NISSAR\GPB\User Guide
O:\NISSAR\GPB\Drawings
O:\NISSAR\GPB\ITP,MST.Spec and ITT
O:\NISSAR\GPB\Repair works
O:\NISSAR\GPB\Site Images
O:\NISSAR\GPB\Presentation
THANK YOU