Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
GWRS Final Expansion Engineer’s Report‐ Sept 2016
ii
TableofContents
Table of Contents .......................................................................................................................................... ii
Chapter 1 – Introduction ........................................................................................................................... 1
1.1 Background ..................................................................................................................................... 1
1.2 Project Description and Objective .................................................................................................. 1
Chapter 2 – Source Water for the Final Expansion Project ...................................................................... 3
2.1 Source Water ‐ Orange County Sanitation District ......................................................................... 3
Chapter 3 – Groundwater Replenishment System Final Expansion Description .................................... 17
3.1 AWTF Process Expansion .............................................................................................................. 17
3.2 OCSD Improvements ..................................................................................................................... 22
Chapter 4 – GWRS Final Expansion Product Water ................................................................................ 26
4.1 Seawater Barrier (Talbert Barrier) ................................................................................................ 26
4.2 Forebay Recharge Operations ...................................................................................................... 27
4.3 Mid‐Basin Injection ....................................................................................................................... 29
4.4 Water Quality Monitoring ............................................................................................................. 30
Chapter 5 – Financial Analysis ................................................................................................................. 31
5.1 Capital Cost of Project ................................................................................................................... 31
5.2 Annual Operation and Maintenance Costs ................................................................................... 33
5.3 Potential Sources of Financing ...................................................................................................... 33
5.4 Projected Unit Cost of GWRS FE Project Water ............................................................................ 33
Chapter 6 – Project Implementation ...................................................................................................... 38
6.1 CEQA and NEPA Requirements ..................................................................................................... 38
6.2 Institutional Agreements .............................................................................................................. 38
6.3 Regulatory Approvals .................................................................................................................... 38
6.4 Sequencing of Project Activities and Schedule ............................................................................. 38
6.5 Financial Impact to OCWD ............................................................................................................ 39
6.6 Recommendation .......................................................................................................................... 40
Appendix ....................................................................................................................................................... A
GWRS Final Expansion Engineer’s Report‐ Sept 2016
1
Chapter1–IntroductionThe Orange County Water District (OCWD) began operating the Groundwater Replenishment
System (GWRS), located in Fountain Valley, California, in 2008. The 2008 GWRS facility
consisted of a 70 million gallon per day (MGD) advanced water treatment facility (AWTF), a 13
mile GWRS pipeline, and an expansion of OCWD’s Talbert Seawater Barrier Injection Wells. The
original AWTF and pipeline projects were designed and constructed for an ultimate treatment
and conveyance capacity of 130 MGD. The original GWRS design intent was to expand the
GWRS facility in two phases – an initial expansion of an additional 30 MGD of treatment
capacity and a final expansion of another 30 MGD of treatment capacity. The GWRS Initial
Expansion Project was completed in June 2015 and allows the AWTF to produce 100 MGD of
purified water for groundwater injection and recharge. The GWRS Final Expansion project will
include facilities required to upgrade the AWTF to produce 130 MGD of purified water as well
as facilities required to convey the source water for GWRS treatment. This Engineer’s Report
evaluates this final expansion of the GWRS facility.
1.1BackgroundThe OCWD manages the groundwater basin in northern and central Orange County, California
by protecting, monitoring, and recharging the groundwater basin. Northern and central Orange
County cities and water agencies (Producers) pump approximately 75% of their water demand
from the groundwater basin to supply potable water to homes and businesses. The source
water for OCWD’s groundwater recharge currently comes from Santa Ana River base flows and
storm flows, purified recycled water from GWRS, incidental recharge, and imported water from
Metropolitan Water District (MWD).
The 100 MGD AWTF as part of GWRS treats OCSD secondary effluent to drinking water
standards and uses the purified water for both injection and percolation, through injection
wells and recharge basins, as source water to replenish the groundwater basin’s drinking water
supplies. Figure 1 shows the GWRS existing facilities.
1.2ProjectDescriptionandObjectiveThe existing AWTF has the capacity to receive 134 MGD of secondary effluent from the Orange
County Sanitation District (OCSD) wastewater treatment plant and produce 100 MGD of
purified water for recharge. The AWTF treats the secondary effluent with microfiltration,
reverse osmosis and ultraviolet light to produce purified water for groundwater recharge. In
order to increase the capacity of GWRS for the Final Expansion Project, the AWTF will require
additional microfiltration cells, reverse osmosis units, ultraviolet vessels, and associated
equipment in order to produce an additional 30 MGD of purified water. These improvements
are referred to as the AWTF improvements. In addition to the AWTF improvements, for the
GWRS Final Expansion Project, additional source water from OCSD’s wastewater treatment
Figure 1 – Existing OCWD Facilities
GWRS Final Expansion Engineer’s Report‐ Sept 2016
2
plants is required. With the treatment process efficiencies, approximately 40 MGD of secondary
effluent is required from OCSD to produce the additional 30 MGD of purified water through
GWRS. This additional 40 MGD of secondary effluent will be pumped to the GWRS facility from
OCSD’s Treatment Plant No. 2 located in Huntington Beach.
The source water conveyance and AWTF treatment improvements will allow the GWRS facility
to produce the total planned 130 MGD GWRS Final Expansion production capacity. The
additional 30 MGD of purified water will be used as a new source of replenishment water for
the Orange County groundwater basin.
1.2.1SecondaryEffluentReuseStudy,SP‐173The Secondary Effluent Reuse Study, (SP‐173) is a jointly funded study by OCWD and OCSD to
evaluate the feasibility of recycling the majority of OCSD’s secondary effluent for GWRS Final
Expansion Project. CDM Smith and Brown & Caldwell completed the study in July 2016. The SP‐
173 study evaluated numerous alternatives for obtaining the required secondary effluent for
GWRS, to segregating non‐reclaimable flows at OCSD, to conveying the secondary effluent
flows to GWRS, and to maximize the secondary effluent flow to GWRS. The study incorporated
an alternatives analysis approach using ‘Criteria Decision Plus’ to evaluate numerous
alternatives in order to recommend the optimal project implementation plan for the GWRS
Final Expansion. The recommended results from this study are summarized in this Engineer’s
Report.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
3
Chapter2–SourceWaterfortheFinalExpansionProjectThe OCSD operates two wastewater treatment plants that collect all of the wastewater from
north and central Orange County for treatment. The OCWD & OCSD have worked together for
over 40 years with OCSD providing secondary effluent free of charge to OCWD for further
treatment for groundwater replenishment. This section describes the considerations for
receiving an additional 40 MGD of secondary effluent at source water for the GWRS Final
Expansion Project.
2.1SourceWater‐OrangeCountySanitationDistrictThe OCSD owns and operates two treatment plants, Reclamation Plant No. 1 (Plant No. 1) in
Fountain Valley and Treatment Plant No. 2 (Plant No. 2) in Huntington Beach. Currently to
operate the GWRS AWTF to produce 100 MGD of purified water, OCWD receives all its
secondary effluent from OCSD’s Reclamation Plant No. 1. Figure 2 shows the locations of the
GWRS facility, and OCSD’s two treatment plants.
In order for OCWD to reach the final capacity influent water requirement, OCWD will need
effluent water from both of OCSD’s treatment plants.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
4
Figure 2 – GWRS Final Expansion Project Area Map
2.1.1ReclamationPlantNo.1–FountainValleyThe OCSD owns and operates the Reclamation Plant No. 1, which is located in Fountain Valley.
Reclamation Plant No. 1 (Plant No. 1) has a maximum capacity to treat approximately 180 MGD
of raw wastewater to secondary effluent. All the raw wastewater is sent through the OCSD’s
headworks and primary treatment settling basins. The effluent from the primary settling basins
is distributed to three various secondary treatment processes. The three processes are as
follows:
(1) Activated Sludge Plant 1 (AS1): Original activated sludge system optimized for BOD
removal and converted with the addition of anoxic cells to a nitrification and partial
denitrification (NDN) process. The process removes over 90% of tractable organic
GWRS Final Expansion Engineer’s Report‐ Sept 2016
5
material (BOD) and undissolved solids, and has removal of ammonia, partial removal of
nitrate nitrogen, resulting in high quality secondary effluent for GWRS recycling.
(2) Activated Sludge Plant 2 (AS2): Newer activated sludge system designed for nitrogen
removal while providing equivalent removals of trace organics as AS1, producing high
quality secondary effluent for GWRS recycling.
(3) Trickling Filter (TF): Trickling filter system which removes similar amounts of tractable
organic material and suspended material as AS1, however the TF process is less effective
than the AS systems at removing suspended solids, ammonia and organics. The TF
process provides a lesser quality effluent for GWRS recycling, although it does provide
the ammonia necessary to form the necessary combined chlorine (chloramine) residual
upon the addition of sodium hypochlorite for efficient AWTF operations.
2.1.2TreatmentPlantNo.2–HuntingtonBeachThe OCSD also owns and operates the Treatment Plant No. 2 (Plant No. 2), which is located in
Huntington Beach. Plant No. 2 has the capacity to treat 80 MGD of raw wastewater to
secondary effluent. The wastewater comes into Plant No. 2 through the headworks and primary
settling basins. The effluent from the primary settling basins is distributed to one of two
secondary treatment processes. The two treatment processes are as follows:
(1) Oxygen Activated Sludge (OAS): Uses pure oxygen instead of air to provide metabolic O2
for a conventional activated sludge system for BOD removals. The effluent produced is
of lesser quality as compared to the Plant No. 1 AS1 and AS2 facilities NDN process,
featuring greater suspended solids, ammonia, and organics.
(2) Trickling Filter Solids Contact (TFSC): Similar to P1 TF except with an additional biological
treatment step that increases removals of BOD over conventional TF systems and
provides some additional removal of organics and suspended solids, but overall
produces lesser quality than the Plant No. 1 AS1 and AS2 NDN processes, especially for
ammonia.
Approximately 60% of the Plant No. 2 primary treated effluent is sent to the TFSC facility for
secondary treatment. The remaining 40% is sent to the OAS facility for secondary treatment.
The TFSC plant receives peak wastewater flows that come into Plant No.2 and is therefore
operated dynamically to manage the high and low flows.
2.1.3ProjectedSecondaryEffluentFlowsThe proposed source water for the GWRS Final Expansion Project is secondary effluent from
OCSD’s two wastewater treatment facilities. The current combined influent into OCSD’s two
wastewater treatment facilities is approximately 182 MGD. For the final expansion of GWRS,
OCWD will require a total of approximately 174 MGD of secondary effluent to produce 130
GWRS Final Expansion Engineer’s Report‐ Sept 2016
6
MGD of purified water and produce 4 MGD of reclaimed water through OCWD’s Green Acres
Project (GAP) facility. This 174 MGD of recommended secondary effluent assumes that the
AWTF microfiltration (MF) treatment process continues to operate at 90% efficiency, where
10% of the influent water returns to OCSD as Backwash Waste (BWW), and that the Reverse
Osmosis (RO) treatment process operates at an 85% recovery rate, where 15% of the influent
water returns to OCSD as RO concentrate for disposal in OCSD’s ocean outfall. Figure 3 shows
the projected secondary effluent recommended to produce the 130 MGD of GWRS product
water with the associated treatment process wastes.
Figure 3 – Projected Secondary Effluent and Process Waste Flows for the GWRS Final
Expansion Project
Therefore, in order to receive 174 MGD of secondary effluent from OCSD, the flows from
OCSD’s Plant No. 2 will need to be considered.
2.1.3.1OCSDInfluentFlowsIn recent years there has been a steady decline in wastewater influent flows to OCSD. Figure 4
shows the average daily influent flows over the past 20 years.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
7
Figure 4 – OCSD Total Wastewater Inflow for both Plant No. 1 & 2
The 2007‐2009 economic recession, the ongoing drought and the water restriction mandates by
the State of California are possible reasons for the decline in wastewater inflows in these recent
years. Although, OCSD’s treatment facilities have the ability to treat up to 260 MGD on average
during non‐peak flow operations, in the most recent months the average daily influent has
declined to 182 MGD. This 182 MGD average inflow is still more than the 174 MGD required for
GWRS to produce 130 MGD of purified water, however a number of other factors must be
considered to fully evaluate the availability of secondary effluent for GWRS.
2.1.3.1.1TreatmentPlantNo.2FlowsandSARIOCSD Plant No. 2 receives domestic wastewater from the coastal and central Orange County
trunk lines. In addition to the local wastewater, Plant No. 2 also receives water from the Inland
Empire Brine Line. The Inland Empire Brine Line, which is also known as the Santa Ana Regional
Interceptor (SARI) pipeline, accepts desalter brine wastes from utilities and higher strength/sale
waste from industries in the Upper Santa Ana Watershed. This water contains brine,
concentrated waste streams, and effluent from the Stringfellow Hazardous Waste site in
Riverside County and is currently not allowed to be used as source water for recycling through
the AWTF by the Regional Water Quality Control Board permit to operate GWRS. The average
SARI line flows into Plant No. 2 are 31 MGD. Approximately 30% of this flow is the brines,
concentrated waste streams, and Stringfellow flows. The remaining 70% of the flows are local
wastewater collected along the SARI pipeline alignment in Orange County.
175
195
215
235
255
275
295
OCSD Influent Flow, MGD
OCSD Total Influent Flow
GWRS Final Expansion Engineer’s Report‐ Sept 2016
8
Since these SARI flows are currently not allowed to be recycled through GWRS, they will have to
be segregated and treated separately from the other domestic wastewater trunk sewer flows
that flow into Plant No. 2, thereby allowing the remaining Plant No. 2 flows to be recycled. The
improvements required to separately treat the SARI flows are discussed in more detail in
Section 3.2.3 of this report.
Since the SARI line contains approximately 70% of local Orange County wastewater in addition
to the SAWPA area flows, the SP‐173 study evaluated the feasibility of diverting these Orange
County raw wastewater flows out of the SARI line, so that the diverted flows could add
additional secondary effluent for recycling through GWRS.
Per the SP‐173 study, there are three simple diversion projects that will be implemented by
OCSD in the near future. These are referred to as SARI‐1, SARI‐2, and SARI‐3 in the report.
Implementing these three projects will divert an estimated 8 MGD of domestic wastewater out
of the SARI trunkline and into adjacent Plant No. 1 trunklines that can be recycled by GWRS.
Table 1 details the three OCSD diversion projects that are planned to be completed in 2017.
Table 1 – OCSD SARI Diversion Projects
Project ID Description Predicted Domestic WW Diverted Out of SARI
(MGD)
SARI‐1 Yorba Linda Pump Station Diversions into Newhope‐Placentia Trunkline
2.4
SARI‐2 Miller/Miraloma Diversions into Atwood Sub Trunk Sewer
1.9
SARI‐3 Gate Diversions into Atwood East Trunk Sewer
3.7
TOTAL 8
With these diversions, 23 MGD will remain in the SARI Trunkline, approximately half of which is
domestic wastewater and half of which is brine flows. These SARI flows will have to be
segregated and treated separately at OCSD’s Plant No. 2.
2.1.3.1.2TreatmentPlantNo.2FlowsandWasteStreamsDuring normal plant operations, OCSD produces on average 6 MGD of waste streams from their
solids handling processes. These waste streams are made up of centrate/filtrate from
thickening and dewatering processes, DAFT underflow, and OCWD RO Cleaning Wastes. This 6
MGD of waste streams is the average flow for OCSD’s Plant No. 1 & Plant No. 2 combined. It is
preferred to not recycle these flows through GWRS due to possible NDMA precursors in the
GWRS Final Expansion Engineer’s Report‐ Sept 2016
9
polymers used and concentrations of ammonia and organics they contain. Therefore, for these
reasons, the 6 MGD of OCSD waste streams will also be segregated from secondary effluent for
GWRS. These waste streams will be rerouted through the same segregated treatment train that
is designated for the SARI flows discussed in the previous section. Therefore the proposed
segregated flows for separate treatment at OCSD Plant No. 2 include the 23 MGD of SARI
trunkline flows and 6 MGD of waste stream flows for a total of 29 MGD which will not be
recycled through GWRS.
2.1.3.1.3OCWDandOCSDSecondaryEffluentUsesOCWD owns and operates a reclaimed water treatment facility referred to as the Green Acres
Project (GAP) on the GWRS site. OCSD’s secondary effluent is also used for source water for the
GAP treatment system. On average, 4 MGD of OCSD secondary effluent is used to feed the GAP
reclaimed water system. The GAP treatment process consists of a flocculation/mixing tank and
dual‐media filters followed by a chlorine contact basin for disinfection to produce non‐potable
tertiary treated water for reclaimed water endusers. Currently OCWD serves approximately 100
end users (including irrigation for parks, golf courses, schools) with GAP water. Discussions on
the future of this system are on‐going, however for the purpose of this report it will be
assumed that approximately 4 MGD of OCSD secondary effluent will go towards GAP.
In addition to GAP, OCSD uses approximately 2 MGD of secondary effluent internally on
average throughout OCSD’s facilities as dilution water for various treatment processes. This 2
MGD of dilution water will be referred to as Plant Water and is the average plant water usage
for both OCSD’s Plant No. 1 & 2. Since the GAP and OCSD Plant Water have steady demands for
secondary effluent, these flows cannot be used for GWRS.
2.1.3.1.4AdditionalSecondaryEffluentFlowsforGWRSFEAn additional source of treated wastewater used for recycling through GWRS is the backwash
waste water produced from the Microfiltration (MF) Treatment Process at the AWTF. The MF
process requires a 2‐3 minute backwash flush of the MF modules every 22 minutes. This
backwash water is MF filtered water combined with particles that have built up on the outside
of the MF modules. This MF backwash waste water is suitable for recycling and is sent to
OCSD’s Plant No. 1 for treatment, and then returned to GWRS for recycling. The average
backwash waste flows depend on how much water is being treated through the MF cells and
the frequency of backwashes. Based on the current flow predictions for the GWRS Final
Expansion Project, it was assumed that the MF backwash waste returning to GWRS would be
approximately 16 MGD.
Another source of wastewater for OCSD is the treatment of 0.6 MGD of MF cleaning wastes.
After every 21 days of run time for each MF cell, the cell is cleaned through filling the cell with
cleaning solutions (citric acid and sodium hydroxide) and recirculating these cleaning solutions
GWRS Final Expansion Engineer’s Report‐ Sept 2016
10
through the membranes. These cleaning wastes are currently piped to go to OCSD’s waste
streams and are therefore not recycled. However, these cleaning wastes can be safely recycled
through GWRS with minimal piping improvements to allow these flows to comingle with the MF
BWW flows. These flows would then be treated through OCSD’s treatment processes at Plant
No. 1 and counted as additional secondary effluent for GWRS.
Another source of additional secondary effluent for the GWRS Final Expansion Project is the
Extraction Wells for the North Basin Clean‐up Project. OCWD will begin construction in
December 2016 on the Extraction Well No. 1 (EW‐1) Project. The extraction well will be
installed within the City of Placentia and the discharges from this extraction well will be routed
into an OCSD sewer trunkline which feeds Plant No. 1. The project is scheduled to be complete
in 2017 and it is estimated to discharge approximately 1.4 MGD to Plant No. 1 for treatment
and eventual recycling through GWRS.
In addition to the process waste streams mentioned above, there are potential urban runoff
flows within Orange County that currently flow into storm drains/channels that could be
diverted to OCSD for treatment. The OCSD Board of Directors adopted a resolution in 2000 to
allow 10 MGD of urban runoff to be treated at OCSD free of charge to any parties interested.
This incentive helps cities and agencies with urban runoff water quality issues develop new
projects that would divert the urban runoff into OCSD’s sewer trunklines for treatment. The
cities/agencies responsible for the runoff would fund and manage these projects. Recently, the
OCWD Board of Directors approved helping fund the Santa Ana Delhi Channel Diversion Project
with City of Costa Mesa, Newport Beach, Santa Ana, and County of Orange which will divert
approximately 1.4 MGD of urban runoff to OCSD Plant No. 1. This project is currently in design
and is scheduled to be complete in 2017.
Table 2 below shows the predicted flows to GWRS considering the segregated SARI, segregated
waste stream flows, OCSD Plant Water Flows, GAP flows, and MF backwash waste (BWW) flows
and new listed influent flows.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
11
Table 2 – Predicted Available OCSD Secondary Effluent for GWRS
Water Type Average Flows (MGD)
OCSD Wastewater Influent 182
Segregated SARI Trunkline Flows ‐31
Segregated OCSD Waste Stream Flows ‐6
GAP Flows ‐4
OCSD Plant Water Flows ‐2
MF Backwash Waste Flows 16
OCSD SARI Diversion Projects 8
MF Cleaning Waste Flows 0.6
EW‐1 Flows 1.4
Urban Runoff Delhi Channel Flows 1.4
TOTAL 166.4
The predicted secondary effluent of 166 MGD is 7 MGD less than the optimal 174 MGD of
secondary effluent to produce 130 MGD of purified water through GWRS and 4 MGD of
reclaimed water through GAP. However, the total 166 MGD reflected in Table 2 is an average
predicted daily flow to OCSD. In OCSD’s current inflow are peak and low flows throughout the
day that can range between 20‐30 MGD in each direction. Therefore during peak flows, the
production of 130 MGD of purified water with the GWRS Final Expansion can still be met.
Also, with an average secondary effluent inflow of 166 MGD to the GWRS facility, OCWD will
still be able to maintain a reliable annual yearly production average of 25,000 acre‐feet per year
(AFY). The annual water production target is currently based on a 92% on‐line factor, however
the GWRS facility has been operating at a more consistent 97% on‐line factor in recent years.
With these considerations, the average 166 MGD of secondary effluent available for GWRS will
still allow the annual production of 25,000 AFY to be met with an on‐line factor of 90%. This
annual average production target will be compared with the annual costs for the GWRS Final
Expansion project in the financial section of this report. It is with these considerations that
OCWD recommends the GWRS Final Expansion Project despite lower than optimal average
influent wastewater flows.
However, if wastewater inflows for OCSD continue to decrease, there are additional outside
sources of wastewater flows that can produce new influent for OCSD and provide water for
GWRS. These potential projects are summarized in the section below.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
12
2.1.3.1.5PotentialFutureSecondaryEffluentFlowsforGWRSFEThe SP‐173 Study analyzed all projects that would be required to divert the entire domestic
wastewater flows out of the SARI trunkline. However, the majority of these additional diversion
projects included the requirement for new sewer lift stations within Orange County, which add
significant operational and maintenance costs for these diversions. These diversions will not be
further considered at this time. However there are four more diversion projects that would not
require sewer lift stations and could be implemented if proven cost effective.
The four additional potential domestic wastewater diversion projects are referred to as SARI‐4,
SARI‐5.1, SARI‐5.3, and SARI‐5.7 in SP‐173. Summarized descriptions of these projects are
included in Table 3 below.
Table 3 – Potential OCWD Diversion Projects
Project ID Description Predicted Domestic WW Diverted Out of SARI
(MGD)
SAR‐4 Two New MHs & 200‐feet of 15‐inch Pipe Diversions into Taft Branch & Olive Sub
Trunkline
1.5
SARI‐5.1 2,800‐feet of Pipe Diversions from Orange to Atwood West
2.9
SARI‐5.3 11,000‐feet of Pipe Diversion from Anaheim to Olive Trunkline
1.6
SARI‐5.7 300‐feet of Pipe from Brea to Atwood West 1.4
TOTAL 7.4
OCSD’s Treatment Plant No. 2 receives the SARI line flows in addition to domestic wastewater
from trunk lines of OCSD’s sewer system. As mentioned in Section 2.1.2, the continuous flow
out of the advanced secondary treatment train at Treatment Plant No. 2 is approximately 55
MGD. The flow from this process could be pumped back to OCWD’s AWPF to make up the total
of 173 MGD of secondary effluent required for the source water for the final expansion.
There are additional urban runoff projects that may add more influent to OCSD’s Plant No. 1.
The Peters Canyon Wash Groundwater Disposal and Reuse Pipeline Project is designed to
capture groundwater dewatering or seepage related discharges from four locations in the lower
Peters Canyon Wash. The anticipated diversion flow to OCSD will could be approximately 1.8
MGD. Another potential urban runoff project is the Santa Ana‐Santa Fe Channel Diversion
Project. The City of Santa Ana is interested in diverting approximately 1 MGD of their Santa
GWRS Final Expansion Engineer’s Report‐ Sept 2016
13
Ana‐Santa Fe Channel and Lane Channel urban runoff flows to OCSD. If needed, OCWD would
pursue the schedule for implementing these projects.
The North Basin Groundwater Remediation Project is also recommending the installation of 4
more extraction wells. The four additional extraction well discharges could all be diverted into
an OCSD trunk sewer main for treatment at OCSD’s Plant No. 1. The flows from EW‐2 through
EW‐5 are projected to total 2.8 MGD on average. These discharges would be treated through
OCSD’s Plant No. 1 free of charge with the GWRS Final Expansion Project.
OCWD is also exploring the option of treating the GWRS RO concentrate flows and/or
recovering more water via the RO process. It is predicted that the RO concentrate discharge
flows will be approximately 23 MGD for the GWRS Final Expansion. These concentrate flows are
sent to the OCSD ocean outfall. There are pilot systems that OCWD will be evaluating that
would convey these concentrate flows through an additional specialized RO membrane stage
with approximately 50% recovery and therefore producing approximately 11 MGD of additional
GWRS product water. The cost to pilot such a system is included in the budget for the GWRS
Final Expansion Project in order to determine if such a system would be a cost effective tool to
boost water production.
2.1.3.2OCSDDiurnalFlowsRaw wastewater flows coming into Plant No. 1 and Plant No. 2 vary depending on the time of
day. Night time flows into OCSD can be as low as a total of 100 MGD into both plants.
Wastewater flows begin to lesson around midnight and gradually decrease until approximately
6am when wastewater influent flows begin to rise again. By 10am OCSD is typically back to
their peak influent flows.
In order to provide 133 MGD of secondary effluent continuously, for the GWRS Initial
Expansion, OCWD constructed Secondary Effluent Flow Equalization (SEFE) tanks to capture
peak flows from Plant No. 1. These peak flows are stored in the two 7.5 MG SEFE tanks and
pumped back to OCWD at night to supplement night‐time low flows of secondary effluent. With
this system, OCWD is able to capture the majority of the flows into OCSD’s Plant No.1 for
treatment at the Advanced Water Purification Facility.
In 2015, two 7.5 million gallon Secondary Effluent Flow Equalization steel tanks (SEFE) were
constructed on the AWTF site. These tanks store the secondary effluent peak flows from OCSD’s
Plant No. 1 during the day and at night this stored water is drained to supplement the low flows
from OCSD’s Plant No. 1.
For the GWRS Final Expansion Project, the feasibility of capturing the peak secondary effluent
flows and supplementing the low flows from OCSD’s Plant No. 2 is being studied. This separate
project may have the potential to enhance the overall water production through GWRS Final
GWRS Final Expansion Engineer’s Report‐ Sept 2016
14
Expansion. A final report analyzing the feasibility of this water production enhancement project
for OCSD’s Plant No. 2 will be completed in November of 2016 for further evaluation.
2.1.4ProjectedSecondaryEffluentWaterQualityThe AWTF of GWRS currently receives on average 25% secondary effluent from OCSD’s Plant
No. 1 Trickling Filter (TF) process. The remaining 75% of secondary effluent is from OCSD’s Plant
No. 1 Activated Sludge (AS) processes.
The AS process at OCSD’s Plant No. 1 (i.e. advanced secondary process) includes Nitrification‐
Denitrification (NDN) and it greatly reduces the concentration of ammonia in the secondary
effluent from OCSD. The NDN treatment process converts ammonia first into nitrite, then into
nitrate, and then a denitrifying bacteria converts some of the nitrate into nitrogen gas. The low
ammonia concentrations in the majority of the secondary effluent for GWRS allow the
microfiltration treatment process efficiencies to remain high.
The TF process at OCSD’s Plant No. 1 consists of a fixed bed of media over which a microbial
layer covers the outside of media. The primary effluent flows downward over the media for
treatment. This form of treatment does not remove ammonia. Currently OCWD is receiving
approximately 25% of OCSD’s secondary effluent from the trickling filter treatment process.
Since GWRS has been in operation, the more secondary effluent GWRS receives from the
trickling filter system, i.e. the more ammonia in the feed water, the quicker the microfiltration
membranes can foul, and require more frequent cleanings.
The ammonia in the feed water does also provide a benefit for GWRS. OCWD uses sodium
hypochlorite upstream of the microfiltration process to reduce biofouling of the microfiltration
and RO membranes. The small ammonia concentration from the TF process binds with the
hypochlorite to produce chloramines (combined chlorine), which act as a biocide to limit
fouling, but prevents the formation of free chlorine that can damage the membranes.
With the GWRS Final Expansion Project, secondary effluent from OCSD Plant No. 2 will be
required. In addition, the entire Plant no. 2 Oxygen Activated Sludge treatment train will be
isolated for SARI trunkflows and not available for GWRS source water. Therefore, the makeup
of the secondary effluent for the GWRS Final Expansion Project will be different with respect to
water quality. Table 4 below shows the predicted amount of secondary effluent from each
treatment process at OCSD that will be available for GWRS.
Table 4 estimates combined inflow of 182 MGD plus 3.4 MGD of new wastewater influent from
MF cleaning wastes, OCWD extraction wells, and Delhi Channel urban runoff flows.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
15
Table 4 – Predicted OCSD Secondary Effluent Flows for GWRS
Water Treatment Process/Source Predicted OCSD/GWRS Flows (MGD)
Percent
Plant No. 1 ‐ Activated Sludge (AS1) Treatment 37 22%
Plant No. 1 ‐ Activated Sludge (AS2) Treatment 37 22%
Plant No. 1 ‐ Trickling Filter Treatment (TF) 20 12%
Plant No. 2 ‐ Oxygen Activated Sludge (OAS) ‐ SARI(1) 29 0%
Plant No. 2 ‐ Trickling Filter Solids Contact (TFSC) 60 35%
Recycled GWRS Flow ‐ MF Backwash Waste Flows 16 9%
TOTAL 170
(1) These flows will be treated separately and not recycled through GWRS
Table 4 shows that about 50% of the GWRS Final Expansion secondary effluent will come from
OCSD’s trickling filter treatment systems from both Plant No. 1 and 2. This will increase the
ammonia concentration in the feed water for GWRS.
In addition to the increase in ammonia, there are increases predicted in BOD, TOC, and TSS – all
of which also have the potential to foul the MF and RO membranes more quickly. There will
also be an 80% predicted increase in GWRS feedwater TDS (from the saltier effluent from Plant
No. 2 related to the infiltration of seawater into coastal sewer lines) which will increase feed
pressure for the RO process. Alkalinity, boron and chloride concentrations are also predicted to
increase. The higher concentrations of these constituents in the secondary effluent for GWRS
Final Expansion will have to be evaluated in more detail.
OCSD and OCWD are currently beginning a pilot study which will directly evaluate the effects of
this new TFSC source water from OCSD’s Plant No. 2 on the microfiltration membranes. OCWD
has set up a pilot MF unit at OCSD’s Plant No. 2 which will receive OCSD’s Plant No. 2 effluent.
The MF pilot unit will be evaluated for fouling and cleaning frequency. Pilot testing on 100%
trickling filter flows, including SARI flows, represents a worst case scenario for fouling potential
and actual fouling will likely be less. The unit will be run for approximately 6‐months and the
data from the study will be available for analysis prior to the design of this project to evaluate
whether additional water quality improvements should be recommended for optimal GWRS
operation.
2.1.4.1WaterQualityofSARIflowsThe current GWRS permit from the Regional Board (Order No. R8‐2004‐0002) has specified a
requirement for OCWD’s source water for GWRS. Specifically this order states: “Only secondary
treated wastewater from the OCSD Reclamation Plant No. 1 that does not include wastewater
flows from the Santa Ana River Inceptor (SARI) line shall be used as influent source water for
GWRS Final Expansion Engineer’s Report‐ Sept 2016
16
advanced tertiary treatment at the interim WF21 and GWRS”. The California Department of
Public Health also noted that SARI flows should not be utilized as source water for GWRS given
concerns related to unknown or potential risks from discharges to the SARI line. In order to
consider allowing OCWD to use the SARI line as source water for the final expansion, OCWD has
been asked to provide the following information:
1) Water quality characterization of the quantity and quality of discharges from the SARI.
2) A source control evaluation comparing the discharges of OCSD’s Plant 1 (GWRS Source
Water) and that of the SARI flows.
OCWD has conducted a separate water study to assist with the implementation of the GWRS
Final Expansion, which evaluated the water quality of the SARI trunkline, characterized the
number, type and flow of the individual IEBL/SARI dischargers in the SAWPA area, and reviewed
the SAWPA pre‐treatment (source control) program for IEBL/SARI. This study has concluded
that the SAWPA area IEBL/SARI brine flows have TDS concentrations in excess of 5,000 mg/L as
they enter Orange County. Recycling TDS water will add significant costs to operation GWRS.
The brine flows into the SARI line are expected to increase and become more concentrated
with increase in the use of groundwater and reclamation RO brine recovery processes. It has
also been noted that some irregular discharges from dump stations that flow into the SARI
trunkline are not adequately monitored for source water for water recycling. The SAWPA pre‐
treatment program for the IEBL has also been revamped in recent years due to serious
deficiencies uncovered by an OCSD audit. Additional SAWPA source control changes would be
recommended in addition to address potential risks associated with SARI recycling. It is for
these reasons that OCWD is currently not recommending to pursue actions that would allow
the SARI flows to be recycled through GWRS. In turn, this requires OCWD and OCSD to
recommend improvements that will treat the SARI flows separately and not allow these flows
to be conveyed to GWRS. These improvements are described in the next chapter.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
17
Chapter3–GroundwaterReplenishmentSystemFinalExpansionDescriptionThe current GWR System is made up of an advanced water treatment facility, a pipeline,
injection wells and recharge basins. The original advanced water treatment facility (AWTF)
incorporated the final expansion water production capacity of 130 MGD into the design of the
process equipment spacing, pipeline sizes, number of pumps, and conveyance pipeline sizes.
These improvements are detailed as part of the AWTF Improvement Project section. In addition
to the added treatment capacity, a new pump station and pipeline at OCSD’s Plant No. 2 will
need to be constructed to convey additional source water to GWRS for treatment. With the
exclusion of Inland Empire Brine Line flows for treatment at GWRS, a headworks bypass facility
will also need to be constructed at OCSD Plant No. 2. These Plant No. 2 improvements
recommended for the GWRS Final Expansion Project are detailed as part of the OCSD
Improvements Section in this chapter.
3.1AWTFProcessExpansionThe following sections describe the proposed improvements to the Advanced Water Treatment
Facility in order to treat and produce 130 MGD of purified water.
3.1.1ScreeningFacilityThe Screening Facility currently has all that screens that are needed for the final expansion.
However current operations have shown that the screening facility storage tank may be
undersized or pipe elevations into the tank are too high. In order to make sure OCWD receives
the maximum flows, OCWD fills the screening facility tank in order to gravity flow the secondary
effluent into the 96‐inch Microfiltration Feed (MFF) pipe. There is a narrow water elevation that
allows water to flow into the MFF pipe before reaching too high of an elevation to overflow the
water to the ocean outfall (or SEJB 7). Therefore, when the screening facility storage reservoir
water elevation reaches the overflow elevation – secondary effluent is lost to the ocean. As
part of the final expansion, OCWD would like this scenario evaluated to ensure that all the
secondary effluent available is able to be captured and treated through the Advanced Water
Purification Facility.
3.1.2MicrofiltrationTo expand the microfiltration system to its final ultimate capacity, 12 additional microfiltration
cells will need to be added to the existing system. Train E will need to be expanded with 4
additional treatment cells. In addition, a new Train F will need to be constructed south of Train
E and on the west side of the microfiltration process area. Train F will be made up of 8 new
cells. The construction of the twelve new cells would occur by increasing the size of the
microfiltration building and basement, which houses most of the actual MF equipment. The MF
basement includes all piping, valves, pumps, instruments, and control panels. Figure 5 shows
GWRS Final Expansion Engineer’s Report‐ Sept 2016
18
the additional MF cells being added and the expanded building footprint.
Figure 5 – GWRS Final Expansion of Microfiltration Process
During the backwash process, in addition to water running through the membranes the
opposite direction to remove particulates that have accumulated on the membranes, the
membranes are agitated with a high volume of air blown over them. The high volume of air is
provided by the air blowers in the microfiltration basement. As part of the final expansion
project, one additional air blower will need to be installed (along with all the piping, valves,
appurtenances) that go along with feeding air to the new microfiltration cells.
One additional backwash waste pump will also be required to send water from the backwash
process to OCSD to be recycled as part of the final expansion. This waste is sent directly to
OCSD’s secondary treatment process.
3.1.3ReverseOsmosisWith exception of the equipment and piping, the Reverse Osmosis building is built out to full
capacity. Therefore for the final expansion, only two new trains will need to be installed. The
trains are made up of 3 units producing 5 MGD each, with 150 pressure vessels per unit. The
GWRS Final Expansion Engineer’s Report‐ Sept 2016
19
building also has room to house all the process equipment, piping, and electric cables for
operating the trains. The treatment train equipment includes pressure vessels, RO membranes,
RO feed pumps, and associated piping for each train. Figure 6 shows the location of the
additional RO equipment units that are being added as part of the GWRS Final Expansion
project.
Figure 6 – GWRS Final Expansion of Reverse Osmosis Process
One additional RO Flush Feed Pump will need to be installed as part of the Final Expansion
Project. This pump is a 50 hp horizontal end suction centrifugal pump which pumps RO
permeate at 1000 gpm at a rated head of 120 feet. This pump provides RO permeate water to
the RO membranes for flushing when a train is taken off‐line or for water when a train needs to
be cleaned.
3.1.4UltravioletDisinfectionThe advanced oxidation system currently part of the GWRS facility consists of hydrogen
peroxide being injected upstream of the Trojan Ultraviolet (UV) processes. The system currently
being used is the Trojan PHOX. In order to reach the final expansion capacity, three new trains
GWRS Final Expansion Engineer’s Report‐ Sept 2016
20
of the Trojan UV PHOX system will need to be installed. The piping leading up to the main
influent and effluent headers is already installed. In addition to three new trains, there will be
the three new electrical panels and PCS controllers. Figure 7 shows the layout of the existing
and proposed UV trains.
Figure 7 – GWRS Final Expansion of the UV System
In addition to the new trains, the UV canopy area is in need of a bridge crane system to allow
the UV units to be disassembled and moved out of the area for service or future installation.
3.1.5DecarbonationandLimeAs part of the GWRS Final Expansion Project, one additional decarbonation tower and
associated blower will need to be installed. The piping influent piping has already been
constructed. In order to connect the decarbonation tower to the existing influent piping, an
approximately 10‐foot 24‐inch diameter spool piece and valve will have to be installed. The
effluent will drain into the Decarbonated Water Tank directly underneath the towers. Figure 8
shows the location of the proposed decarbonator tower.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
21
Figure 8 – GWRS Final Expansion of the Decarbonation System
The lime system is currently built out to incorporate final capacity flow rates and therefore no
additional work is required in this area.
3.1.6PumpStationsFor the Final Expansion Project, there will be one additional vertical diffusion vane pump
required to be installed in the existing Product Water Pump Station building. The pump shall be
rated at 20,140 gpm for 315 feet of head with a rated horsepower of 2,250 to match the four
existing pumps in the building. The 30‐inch discharge pipe and valve for the pump will be
connected to an existing 30‐inch pipe piece with a blind flange which connects to the common
discharge header for all the product water pumps.
For the Final Expansion two new Backwash Supply (BWS) pumps need to be installed. These
pumps are provided by Siemens and have existing 20‐inch discharge piping in the RO Transfer
Pump Station Building assembled and ready to be connected to the new pumps.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
22
3.1.7ChemicalFor the Final Expansion Project, at least one additional 32,000 gallon steel sulfuric acid tank and
dosing pump will need to be installed. Currently there is room for two new sulfuric acid tanks
and pumps, however with developments in the use of new Threshold Inhibitors in the
treatment process, the sulfuric acid usage for the AWPF has decreased significantly. Therefore,
if the current operation of the AWTP is maintained, then only one sulfuric acid tank and pump
will be required to meet the production requirements for the GWRS Final Expansion Project.
During the design phase of the GWRS Final Expansion Project, the predicted sulfuric acid
chemical usage will be calculated taking into account the different source water quality.
3.1.8ElectricalEach process component that is being expanded as part of the final expansion project (as
mentioned in the above sections of this report), also has corresponding electrical work and
equipment (cables, panels, conduit) that needs to be installed.
3.2OCSDImprovementsAs mentioned in previous sections, OCWD requires 173 MGD of secondary effluent from OCSD
to produce 130 MGD of purified water for the GWRS Final Expansion Project. In order to convey
this volume of water to OCWD a few improvements on OCSD property will be required. An
effluent pump station, conveyance pipeline, and a separate headworks facility for SARI flows
will have to be constructed at OCSD’s Plant No. 2.
3.2.1OCSDP2EffluentPumpStationA secondary effluent pump station at OCSD’s Plant No. 2 is being proposed to send between 50
‐ 85 MGD of secondary effluent from Plant No. 2 to the GWRS facility. This pump station will be
referred to as the OCSD P2 Effluent Pump Station. Figure 9 shows the location of this pump
station.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
23
Figure 9 – OCSD P2 Effluent Pump Station Location Map
The preliminary pump station layout is estimated to be approximately 47‐feet by 100‐feet with
a three duty and one standby pump configuration. The four (4) pumps will be 500 hp vertical
turbine pumps. The P2 Effluent Pump Station will take secondary effluent from the 120‐inch TF‐
SE pipeline and boost this flow into a new conveyance pipeline to GWRS.
3.2.2OCSDPipelineRehabilitationOCSD owns an existing unused 66‐inch gravity reinforced concrete pipeline (RCP) that connects
Plant No. 2 to Plant No. 1. This pipeline was constructed prior to 1965 and is no longer in
service. The pipeline alignment is 3.6 miles from Plant No. 2 to Plant No. 1. OCSD has surveyed
the interior of this pipeline and determined that the pipeline is no longer usable with exposed
rebar and deteriorating manholes. For the conveyance of secondary effluent from Plant No. 2
to the GWRS facility, OCSD will allow OCWD to use the 66‐inch existing pipeline and
construction easement. In order to convert this aging gravity RCP into a pressure pipeline to
convey the effluent pump station discharge, it is being proposed to slip‐line the existing
pipeline with a smaller diameter High‐Density Polyethylene (HDPE) pipe. The slip‐line repair
entails excavation of access pits along the pipeline alignment to expose and enter into the
existing pipeline. The new smaller diameter HDPE pipe will be pulled through the existing
pipeline between the access pits. The new pipeline will be connected on the south to the
GWRS Final Expansion Engineer’s Report‐ Sept 2016
24
Effluent Pump Station at OCSD’s Plant No. 2 and to the north to the existing 90‐inch OCSD
South East Junction Box No. 6 (SEJB6) influent pipeline. Figure 10 shows the pipeline alignment.
Figure 10 – P2 Secondary Effluent Conveyance Pipeline Alignment
3.2.3OCSDP2HeadworksSegregation/Modification In order to separate the SARI (brine) flows from comingling with domestic wastewater flows
into OCSD’s Plant No. 2, a separate headworks facility and bypass pipeline must be constructed.
The SARI brine flows will have a dedicated flowmeter vault and screening and grit basins. After
conveyance through the separate headworks, the SARI brine flows till be routed to the A‐side
clarifiers of OCSD’s Oxygen Activated Sludge treatment facility. The P2 OAS treatment facility
will be entirely dedicated to the treatment of the SARI trunkline brine flows. Figure 11 shows
the site plan for OCSD’s Plant No. 2 headworks segregation project.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
25
Figure 11 – OCSD P2 Headworks Modification Project
GWRS Final Expansion Engineer’s Report‐ Sept 2016
26
Chapter4–GWRSFinalExpansionProductWaterThe 130 MGD purified water produced from the GWRS Final Expansion Project will be
recharged into the groundwater basin through a combination of existing and new facilities. The
two main sources for the GWRS product water are 1) the Talbert Seawater Barrier Injection
wells and 2) the GWRS Pipeline to recharge basins in the Anaheim area (i.e. the forebay area of
the groundwater basin).
4.1SeawaterBarrier(TalbertBarrier)OCWD owns and maintains the Talbert Seawater Barrier Injection Wells (Talbert Barrier).The
Talbert Barrier was constructed to minimize early evidence of seawater intrusion into the
groundwater basin. Currently, the Talbert Barrier contains 36 injection well sites, 32 of which
are joined by a common pipeline which run along Ellis Avenue in the City of Fountain Valley and
four along the Santa Ana River between Yorktown Ave. and Adams Ave. in Huntington Beach.
Figure 12 shows the locations of the injection well sites.
The annual Talbert Barrier capacity ranges from approximately 15 MGD to 36 MGD, with the
lower flow rates occurring in the winter season and higher flow rates in the summer. The
Talbert Barrier capacity is dependent on basin conditions, such as the degree of overdraft and
seasonal water level fluctuations. However, over the past 8 years of operation, the average
injection capacity for the Talbert Barrier has been 25 MGD (28,000 acre‐feet per year).
GWRS Final Expansion Engineer’s Report‐ Sept 2016
27
Figure 12 – Talbert Barrier Injection Wells
For the GWRS Final Expansion Project, to be more conservative in planning for necessary
recharge capacities, the average Talbert Barrier demand will be decreased 10% to 22 MGD.
During wet winter months, if the Talbert Barrier demands are temporarily below 22 MGD, the
AWTF can be operated at a lower production during those wet months if needed.
4.2ForebayRechargeOperationsOCWD operates several recharge facilities in north Orange County with the purpose of
percolating water via gravity into the ground. The majority of these recharge basins percolate
Santa Ana River water that is diverted into them. However, there are currently four recharge
basins that are dedicated for GWRS product water. These basins are Kraemer, Miller, Miraloma,
and La Palma Basins. Figure 1 shows the existing GWRS pipeline and their connection to the
GWRS recharge basins.
These basins are filled with GWRS product water as needed. Overtime, as the water percolates
into the ground, their fill rates decrease slowly until they require a cleaning. For cleaning
operations, the basins are fully drained, dried, and then scraped with heavy equipment to
GWRS Final Expansion Engineer’s Report‐ Sept 2016
28
remove the clogging layer. Including these operational and maintenance activities, average
recharge rates for these basins have been established and are summarized in Table 5 below.
Table 5 – Average Percolation Rates of Recharge Basins in Anaheim
Recharge Basin Average Percolation
Rate (MGD)
Kraemer Basin 45
Miller Basin 20
Miraloma Basin 26
La Palma Basin* 45
TOTAL 136 *The percolation rate for La Palma is estimated and not based on a yearly average. The La Palma basin is currently
being constructed and estimated to be completed in November 2016.
OCWD began using Kraemer and Miller Basins in 1988 and 1963, respectively. Kraemer Basin is
owned by OCWD. Miller Basin is owned by OC Flood Control District. During storm events, peak
storm flows overflow into Miller Basin and when this occurs percolation into the groundwater
basin stops. Miraloma Basin is located in Anaheim on E. Miraloma Ave. between N. Kraemer
Blvd. and N. Miller Street. Miraloma Basin is owned and operated solely by OCWD and began
operation in 2013. Miraloma Basin has received all of its influent water solely from the GWRS
AWTF from the GWRS Pipeline. With this fully advanced treated influent water, Miraloma Basin
has been able to percolate up to 50 cubic feet per second (CFS) or 32 MGD. However the
average percolation rate, including down time for cleanings, since its operation has been 26
MGD.
Geotechnical reports indicate that La Palma Basin should have a percolation rate similar to
Miraloma Basin because of their similar sand material. La Palma Basin is going to be slightly
larger than Miraloma Basin and therefore a percolation rate of 70 CFS or 45 MGD is predicted.
4.2.1PipelineCapacityConstruction for the GWRS Pipeline was completed in 2008. The pipeline conveys water from
the Advanced Water Purification Facility along the Santa Ana River for 13 miles to the
Kraemer/Miller, Miraloma and La Palma Recharge Basins in Anaheim. The GWRS pipeline is
concrete mortar lined and coated steel pipeline telescoping in diameter from 78‐inch, 72‐inch,
66‐inch and 60‐inch. During design of the pipeline, it was anticipated that there would be a
significant volume of water recharged in the mid‐basin area. With this assumption, the pipeline
GWRS Final Expansion Engineer’s Report‐ Sept 2016
29
and product water pump capacity to the recharge basins in Anaheim is limited to 85 MGD,
which is the maximum flow that can currently be pumped to the recharge basins.
4.2.2BurrisBoosterPumpStationThe current Product Water Pump Station located within the AWTF in Fountain Valley in
combination with the existing GWRS pipeline currently has a maximum capacity to convey 85
MGD to the recharge basins in Anaheim. Through a preliminary evaluation, using a hydraulic
model, incorporating a Booster Pump Station at Burris Basin would allow a total of 100 MGD of
product water to be pumped to the recharge basins in Anaheim. The existing Product Water
Pumps would operate in order to convey a minimum of 100 MGD to Burris Basin. The proposed
Burris Booster Pump Station would boost the remaining 100 MGD through the existing 60‐inch
GWRS pipeline to the recharge basins in Anaheim. The velocities in the existing 60‐inch pipeline
under the pumping scenario described above would be approximately 7.8 ft/sec which is within
a reasonable operating range. The proposed Burris Booster Pump Station configuration would
be five 600‐hp pumps total (4‐duty and 1‐standby) where each pump shall have a capacity to
pump 17,400 gpm to approximately 100‐feet of total dynamic head to the recharge basins. The
footprint of this pump station will be approximately 20‐feet by 40‐feet and will be located on
southern end of Burris Basin. In addition to the Burris Booster Pump Station, there is an existing
outlet on the GWRS pipeline that can be used to recharge GWRS product water into Burris
Basin. As needed, during wet winters, up to 7 MGD can be discharged into Burris through this
outlet. This Burris Booster Pump Station and Outlet Project will be evaluated under a separate
Engineer’s Report, however construction of this facility is required to recharge the GWRS Final
Expansion Product Water.
4.3Mid‐BasinInjectionIn addition to sending GWRS product water to the Seawater Barrier Injection Wells and the
recharge basins in Anaheim, the intention during the design of GWRS was to also send GWRS
product water to injection wells located in the mid‐area of the OC groundwater basin.
Historically, this mid‐area of the groundwater basin (mid‐basin) has had the lowest
groundwater levels comparatively throughout the basin. Therefore, in 2015, OCWD put into
operation the first Mid‐Basin Demonstration Injection Well. The Mid Basin Demonstration
Injection Well capacity was originally estimated to be 2,080 gallons per minute (gpm) or
approximately 3 MGD. However, to date the Mid Basin Demonstration Injection Well has been
operating at an average flow of 1,050 gpm or 1.5 MGD. OCWD is attributing this under
performance to potential issues that occurred during construction of the well. However, with
increased backwashing frequencies, OCWD staff have been able to raise the injection capacity
of this well. OCWD is proceeding forward with the construction for an additional 4 injection
wells in the mid basin area. These 4 wells are referred to as the Centennial Park Injection Wells
GWRS Final Expansion Engineer’s Report‐ Sept 2016
30
Project. To more appropriately reflect the performance of the demonstration mid‐basin
injection well – the capacity of these injection wells is predicted to be 6.5 MGD.
With all of the above mentioned facilities, the total 130 MGD of product water from the GWRS
Final Expansion will be able to be recharged. Table 6 below lists the facilities proposed to
recharge product water from GWRS Final Expansion Project. Since the Talbert Barrier Injection
wells have variable demands that depend on the season, the proposed recharge facilities will
also have variable demands corresponding with the Talbert Barrier. Table 6 lists the proposed
recharge facilities and the range in demand for each.
Table 6 – Summary of Average GWRS Recharge Basin Capacities
Recharge Facility
Capacity Range (MGD)
Talbert Seawater Barrier Injection Wells 15 ‐ 35
Mid‐Basin Injection Wells 8 ‐ 0
Burris Basin Outlet 7‐ 0
Burris Booster Pump Station to Recharge Basins 100 ‐ 95
Total 130
4.4WaterQualityMonitoringPer our permit from RWQCB, we are required to monitor for the following 400+ constituents on
either a quarterly or yearly basis. We are also required to prove that our facility is running
effectively. We do this by monitoring for the following indicators either daily or 24 hours a day,
7 days a week. Those indicators are TOC, pH, Turbidity, and EC. We don’t anticipate that using
the additional source water for the GWRS Final Expansion Project will require any additional
water quality monitoring beyond the current program.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
31
Chapter5–FinancialAnalysisThe GWRS Final Expansion Projects costs will be estimated in this section. In addition to the
estimated capital cost, the operation and maintenance costs, unit costs, and comparison costs
to imported water will be evaluated for the GWRS Final Expansion Project.
5.1CapitalCostofProjectThe capital improvement projects required to enable the GWRS facility to produce 130 MGD of
product water include the Advanced Water Treatment Facility Improvements, the OCSD P2
Effluent Pump Station, the OCSD Pipeline Rehabilitation Project, and the OCSD Headworks
Segregation Project. The costs for these projects are represented in Table 7 below. The OCSD
Headworks Segregation Project will be managed by OCSD and costs reimbursed by OCWD. The
estimated capital costs for the three projects at OCSD’s Plant No. 2 (Effluent Pump Station,
Pipeline Rehabilitation, Headworks Segregation Projects) were incorporated from the
OCSD/OCWD joint study and include 35% contingency which is appropriate for the pre‐design
phase. The estimated capital cost for the AWTF Improvements was based on the bid results
from the GWRS Initial Expansion Project and therefore has a lower contingency due to having
recent accurate construction costs. The more detailed breakdown of the capital and
operational and maintenance costs for all these projects are included in the appendix of this
report.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
32
Table 7 – GWRS Final Expansion Estimated Capital Costs
Description Cost
GWRS Final Expansion Projects
Advanced Water Treatment Facility Improvements
Pre‐Design $500,000
Design $12,000,000
Construction Services $10,000,000
Administration $6,000,000
Construction $94,000,000
Contingency $7,500,000
Total AWTF Project Cost $130,000,000
OCSD P2 Effluent Pump Station
Pre‐Design $50,000
Design $1,250,000
Construction Services $1,000,000
Administration $1,000,000
Construction $10,850,000
Contingency $3,550,000
Total Pump Station Project Cost $17,700,000
OCSD Pipeline Rehabilitation Project
Pre‐Design $250,000
Design $1,750,000
Construction Services $2,000,000
Administration $2,500,000
Construction $22,400,000
Contingency $8,100,000
Total Pipeline Project Cost $37,000,000
OCSD P2 Headworks Segregation Project
Pre‐Design $500,000
Design $3,000,000
Construction Services $3,400,000
Administration $3,000,000
Construction $31,300,000
Contingency $3,500,000
Total Headworks Project Cost $44,700,000
TOTAL GWRS FINAL EXPANSION CAPITAL COST $229,400,000
GWRS Final Expansion Engineer’s Report‐ Sept 2016
33
In addition to the projects required to produce the 130 MGD of GWRS Final Expansion Project
water, there are projects that are required to be constructed to recharge the GWRS Final
Expansion Project water into the ground. These projects required for recharge include the Mid‐
Basin Demonstration Injection Well, Centennial Park Injection Wells, and Burris Booster Pump
Station Projects. The total project costs for these recharge projects are included in separate
Engineer’s Reports for each project.
5.2AnnualOperationandMaintenanceCostsIn addition to the normal operational costs, the final expansion project should see an increase
in the electricity usage due to a number of reasons. The pump pressure to push saltier water
through the reverse osmosis membranes will be increased and will therefore increase the
electricity usage accordingly. Also, in addition to operating the treatment facility – a new pump
station facility will be added to the equation. The OCSD pump station will most likely be
operated by OCSD and the operational costs paid by OCWD. For the purposes of this report the
cost of operating the new pump station is based on the costs of operating the SEFE pump
station. For the unit cost calculations, it is estimated that electricity usage will increase by 10%
per acre‐foot from current operations.
In addition to an increase in electricity costs, there is also a predicted increase in chemical
usage for more frequent cleaning requirements. With approximately 50% of the secondary
effluent for GWRS coming from trickling filter processes at OCSD, this increases the organics,
suspended solids, and ammonia concentrations in the secondary effluent. The higher organic,
suspended solids and ammonia concentrations in the influent for GWRS will affect the fouling
rate of the MF process, which could lead to reduced recovery due to increased cleaning
requirements. For the unit cost calculations, it is estimated that the chemical usage costs will
increase by 8% per acre‐foot from current operations.
5.3PotentialSourcesofFinancingOne potential source of financing this project is the Sate Revolving Fund (SRF) Loan Program.
Currently the state has a program of 30‐year loans at a 1.7% interest rate. This is being offered
on a first‐come, first‐serve basis and staff will be applying for this program for the GWRS Final
Expansion Project. However, to be more conservative, the unit cost for the GWRS Final
Expansion project was calculated for two scenarios, 1) with the SRF Loan Program at 1.7%
interest for 30 years, and 2) with typical bonds issued by OCWD at 5% interest for 30 years.
5.4ProjectedUnitCostofGWRSFEProjectWaterThe unit cost of the GWRS Final Expansion water includes the capital costs along with the
operation and maintenance (O&M) costs divided by the amount of extra water produced. Table
8 summarizes the calculated unit cost for the GWRSFE Project. For the calculation of this
GWRS Final Expansion Engineer’s Report‐ Sept 2016
34
number for the GWRS Final Expansion Project, a couple of assumptions were made. They are
the following:
1) It is anticipated that the Total Dissolved Solids (TDS) concentration of the secondary
effluent for the final expansion is going to increase by approximately 20%. This would
correlate with an 10% total electricity cost increase to compensate for the additional
electricity required to ramp up the RO feed pumps for the higher salinity water.
Likewise the increase in ammonia concentrations in the secondary effluent will most
likely increase the amount of chemical cleanings required to prevent fouling of the MF
membranes. This correlates with a 8% total chemical usage cost increase for GWRS Final
Expansion.
2) OCSD will continue to provide secondary effluent for GWRS free of charge as per the
original agreement and assist OCWD in efforts to treat free of charge additional
secondary effluent for recycling through GWRS.
3) An increase of 1 additional I&E technician and 1 additional maintenance full time
employee.
4) The GWRS Final Expansion Project is based on a maximum capacity to produce 130 MGD
of purified water. However, there are variable influent flow rates, plant facility planned
outages for maintenance, power service agreement outages, and construction outages
that must be factored into the amount of water that can be reliably produced within
one year. For this project, it is assumed that with a 92% plant on‐line factor, 25,000 AFY
can be reliably produced by GWRS Final Expansion. This is the production value used to
calculate the unit cost for this project.
5) The annual payment of the capital costs are calculated using both a 30‐year loan at a
1.7% interest rate if SRF Loan Program for GWRSFE is approved and a 30‐year loan at a
5% interest if the SRF Loan is not received.
6) There will be no MWD LRP subsidy available.
7) The R&R Debt service is the amount OCWD will budget for Repairs and Refurbishment
(R&R) of the treatment facility. This R&R value is the predicted annual cost of
replacement or refurbishment of equipment installed as part of this project. For this
analysis, the R&R value is half of the construction cost divided by the life of the
project/equipment. For this project, thirty years was assumed for the life of the
equipment.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
35
Table 8 – GWRS Final Expansion Project Unit Cost
Item Costat1.7% Costat5%AnnualPaymentonCapitalCost $9,725,000 $14,780,000
O&MCosts $8,925,000 $8,925,000
R&RCosts $1,980,000 $1,980,000
TotalAnnualProjectCosts $20,630,000 $25,685,000
WaterProduced(AFY) 25000 25,000
UnitCost($/AF) $825 $1,027
Based on the assumptions listed above, the unit cost for the GWRS Final Expansion Project is
between $825/AF to $1,027/AF. OCWD policy established in April 2009 calls for comparing the
cost of new local water supply projects against the MWD treated full service rate. To be more
conservative, the higher unit cost of $1,027/AF for the GWRS Final Expansion Project based on
a 30‐year loan at 5% interest will be used to compare to MWD imported water rates.
On January 1, 2017, the cost of treated full service MWD water will increase from $942/AF to
$979/AF. There is a ‘readiness to serve’ charge that adds approximately an additional $65/AF
to the total cost of MWD water. This will bring the total treated full service MWD imported
water costs to $1,044/AF.
The GWRSFE local water supply project is groundwater replenishment water with a unit cost of
$1,027/AF. Since this product water is pumped into the ground – to accurately compare the
GWRSFE unit cost with the MWD treated full service rate – an estimated variable cost to pump
water out of the ground must be added to the GWRSFE Project costs. This variable cost to
pump the water out of the ground is received from a survey of Producers within the OCWD
service area and is currently estimated to be $97/AF. Figure 13 below shows the comparison of
the GWRSFE unit costs to the MWD treated full service water with all the applicable
adjustments.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
36
Figure 13 – Comparison of GWRSFE Unit Costs to MWD Treated Full Service Unit Costs
With this comparison, the estimated GWRSFE unit cost is slightly more than the MWD Treated
Full Service Unit Cost. MWD Treated Full Service Unit Costs are predicted to increase by 4.5%
annually for the foreseeable future. The GWRSFE unit costs will increase on average with
inflation for only the operation, maintenance and electricity costs. The GWRSFE annual debt
service cost will be fixed. Therefore, although the GWRSFE Project unit costs are currently more
than MWD imported water rates, in the near future with the predicted increases in MWD
treated water rates, the GWRSFE Project unit costs should be less than imported rates. Figure
14 compares the predicted increases in GWRSFE Project unit costs versus MWD imported water
costs for the next 15 years.
$0
$100
$200
$300
$400
$500
$600
$700
$800
$900
$1,000
$1,100
$1,200
GWRS FE Project Cost MWD Treated Cost
Cost of Water ($/A
F)
TOTAL ‐ $1,044/AF
MWD Treated ‐ $979/AFGWRS FE Cost ‐ $1,027/AF
Pumping Cost ‐ $97/AF
TOTAL ‐ $1,124/AF
Readiness to Serve ‐ $65/AF
GWRS Final Expansion Engineer’s Report‐ Sept 2016
37
Figure 14 – Projected Increases to GWRSFE Unit Costs and MWD Treated Unit Costs
Figure 14 is compares the base unit rates for both the MWD treated full service water and the
GWRSFE Project unit costs without the readiness to serve and pumping costs included. Also,
two different inflation rates (1% and 2%) are compared for the GWRS FE Project unit costs
based on the future potential Consumer Price Index (CPI).
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
$2,0002016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
Unit Cost ($/A
F)
MWD Treated Full ServiceWater
GWRS FE w/ CPI ‐ 1%
GWRS FE w/ CPI ‐ 2%
GWRS Final Expansion Engineer’s Report‐ Sept 2016
38
Chapter6–ProjectImplementationTo complete the GWRS Final Expansion Projects, CEQA will need to be completed, an
agreement between OCSD & OCWD will need to be completed, and any necessary regulatory
compliance issues addressed.
6.1CEQAandNEPARequirementsThe CEQA process for the GWRS Final Expansion Project will involve issuing an addendum to the
original Groundwater Replenishment System EIR. This addendum will address all the processes
that are being expanded as well as the new facilities at OCSD’s Plant no. 2. If this project is
financed by the State Revolving Fund Loan Program, the NEPA process will also need to be
completed.
6.2InstitutionalAgreementsOCWD and OCSD are currently working on an amendment to a joint agreement between the
two agencies which defines each agencies responsibilities for the GWRS Final Expansion Project.
In general it defines the project costs, land leases, and operational responsibilities for each
agency as part of all the joint OCWD and OCSD GWRS Projects.
6.3RegulatoryApprovalsGWRS is currently permitted by the Regional Water Quality Control Board (RWQCB) and
Division of Drinking Water (DDW). The RWQCB/DDW permit contains input and regulations
from California Department of Public Health (CDPH) as well. The DDW was formerly a part of
CDPH as a department/branch of the State Water Resources Control Board (SWRCB). The
current RWQCB/DDW permit will need to be amended to allow for the GWRS FE or a new
permit will need to be developed; the latter may be required, given the changes in
RWQCB/DDW regulations since the original GWRS permit was adopted in 2004.
6.4SequencingofProjectActivitiesandScheduleThe four improvement projects that make up the GWRS Final Expansion Project, will need to be
closely coordinated with OCSD. The three projects proposed on OCSD’s Plant No. 2 will have to
tie‐in with OCSD’s utilities and therefore incorporate many OCSD standards in addition to
OCWD’s standards. Additional design coordination time between the two agencies are factored
into the proposed schedule. The schedule for the GWRS FE projects are attached in the
appendix of this report. The final completion date for these projects may depend on the
availability of the rehabilitated primary clarifiers on OCSD’s Plant No. 2. These clarifiers are
required for the segregated SARI flows. OCSD is planning on rehabilitating these clarifiers
through their P2‐92 capital improvement project. The P2‐92 Project is currently in design.
Therefore, design‐construction‐operation schedules for the GWRS Final Expansion Projects and
GWRS Final Expansion Engineer’s Report‐ Sept 2016
39
the OCSD P2‐92 Projects will have to be closely coordinated in an effort to begin operating
these proposed facilities without delays.
6.5FinancialImpacttoOCWDIncorporating the GWRS Final Expansion Project will allow OCWD to increase the amount of
AWTF water used for groundwater replenishment to manage the groundwater basin. Figure 15
compares the yearly typical water supplies with and without the GWRS Final Expansion Project
available for recharge. As shown in Figure 15, the OCWD service territory could reduce the
amount of imported water purchased with the additional GWRS Final Expansion product water.
The financial benefit to the OCWD service territory of purchasing less imported water would
begin approximately after year 2018 as previously shown in Figure 14. After 2018, the GWRSFE
unit costs should continue to be less than the predicted increase in MWD treated water rates.
Figure 15 – Average Yearly Recharge Water Sources with and without the GWRSFE Project
With the GWRS Final Expansion project implemented, the OCWD service territory would
purchase 25,000 AFY less MWD treated imported water. With the predicted average increase in
‐
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
450,000
500,000
Typical Supplies Typical Supplies withGWRS FE
Average
Yearly Recharge
(AFY)
Treated MWD
MWD Untreated/Carson IRP
Misc
Natural Incidental
SAR Storm
SAR Base Flow
GWRS
GWRS Final Expansion Engineer’s Report‐ Sept 2016
40
the cost of MWD imported water of 4.5% each year, the OCWD service territory would gain a
financial benefit from implementing the GWRSFE Project after year 2018.
6.6RecommendationIt is recommended to establish the GWRS Final Expansion Project detailed within this report as
a feasible and viable project for the Orange County Water District.
GWRS Final Expansion Engineer’s Report‐ Sept 2016
A
Appendix
AWTF Expansion Project
Description Cost
Pre‐Design
CEQA 500,000$
Design & Consulting Services
Design of Construction Documents 12,000,000$
Construction Management 8,000,000$
Construction Inspection Services & Administration Costs 2,000,000$
Construction
Mobilization 6,000,000$
Microfiltration Equipment (Evoqua) 21,000,000$
Microfiltration West Building Expansion (Incl. piping, electrical) 16,000,000$
Reverse Osmosis Membranes, Vessels, Pumps, Piping, Apprt. 12,500,000$
UV Equipment (Trojan) 7,000,000$
Sulfuric Acid Tank & Pumps 500,000$
Electrical Equipment 9,000,000$
Process Control Integration (KDC) 5,500,000$
GWRS Pump Additions 2,500,000$
Construction Escalation/General Requirements/Bonds/Insurance 14,000,000$
Total Construction Cost 94,000,000$
Engineering, Legal and Administration
Administration Labor 1,700,000$
RO Recovery Pilot Study 300,000$
Public Outreach 500,000$
Legal Services 1,200,000$
Survey Consultants 800,000$
Outside Consultants 1,500,000$
Contingency 7,500,000$
Total AWTF Expansion Project Capital Costs 130,000,000$
Annual Costs for AWTF Expansion Project Cost
Electricity $4,200,000
Chemicals $1,800,000
Labor (2 laborers @ $150,000/yr) $300,000
Plant Maintenance $1,000,000
Total Annual O&M $7,300,000
Total Annual R&R $1,500,000
A1
OCSD Effluent Pump Station Project
Description Cost
Pre‐Design
CEQA 50,000$
Design & Consulting Services
Design of Construction Documents 1,250,000$
Construction Management 600,000$
Construction Inspection Services & Administration Costs 400,000$
Construction
Mobilization 3,000,000$
Pump Station 7,700,000$
Connection Pipelines 150,000$
Total Construction Cost 10,850,000$
Engineering, Legal and Administration
Administration Labor 200,000$
Survey Consultants 600,000$
Outside Consultants 200,000$
Contingency 3,550,000$
Total Pump Station Project Capital Costs 17,700,000$
Annual Costs for PS Project Cost
Electricity $1,000,000
Chemicals $0
Labor $275,000
Plant Maintenance $200,000
Total Annual O&M $1,475,000
Total Annual R&R $180,000
A2
OCSD Pipeline Rehabilitation Project
Description Cost
Pre‐Design
CEQA 250,000$
Design & Consulting Services
Design of Construction Documents 1,750,000$
Construction Management 1,000,000$
Construction Inspection Services & Administration Costs 1,000,000$
Construction
Mobilization 3,000,000$
Slip‐line Pipeline 14,600,000$
Connection Pipelines 4,800,000$
Total Construction Cost 22,400,000$
Engineering, Legal and Administration
Administration Labor 200,000$
Public Outreach 200,000$
Legal Services 400,000$
Survey Consultants 500,000$
Outside Consultants 1,200,000$
Contingency 8,100,000$
Total Pipeline Project Capital Costs 37,000,000$
Annual Costs for Pipeline Project Cost
Electricity $0
Chemicals $0
Labor $0
Plant Maintenance $150,000
Total Annual O&M $150,000
Total Annual R&R $300,000
A3
OCSD Headworks Modification Project
Description Cost
Pre‐Design
CEQA 500,000$
Design & Consulting Services
Design of Construction Documents 3,000,000$
Construction Management 2,000,000$
Construction Inspection Services & Administration Costs 1,400,000$
Construction
Mobilization 2,000,000$
Flowmeter & Vault for SARI 6,000,000$
Headworks Modifications 8,800,000$
New Plant Water PS 7,000,000$
New Sidestream PS 500,000$
Junction Box for A‐side clarifiers 2,000,000$
Pipelines 5,000,000$
Total Construction Cost 31,300,000$
Engineering, Legal and Administration
Administration Labor 800,000$
Public Outreach 200,000$
Legal Services 300,000$
Survey Consultants 500,000$
Outside Consultants 1,200,000$
Contingency 3,500,000$
Total Headworks Project Capital Costs 44,700,000$
Annual Costs for Headworks Project Cost
Electricity $0
Chemicals $0
Labor $0
Plant Maintenance $0
Total Annual O&M $0
Total Annual R&R NA
A4
GWRS Final Expansion Schedule
Jan‐Apr May‐Aug Sep‐Dec Jan‐Apr May‐Aug Sep‐Dec Jan‐Apr May‐Aug Sep‐Dec Jan‐Apr May‐Aug Sep‐Dec Jan‐Apr May‐Aug Sep‐Dec Jan‐Apr May‐Aug Sep‐Dec Jan‐Apr May‐Aug Sep‐Dec Jan‐Apr May‐Aug Sep‐Dec
OCWD Advanced Water Treatment Facility Expansion
OCSD Plant No. 2 Effluent Pump Station
OCSD Pipeline Rehabilitation
OCSD Plant No. 2 Headworks Modification
OCSD P2‐98 Primary Treatment System Rehabilitation Project*
*This is a Captial Improvement Project for OCSD to rehabilitate the primary clarifiers intended for the segregated SARI flows as part of OCSD P2 Headworks Modification Project. Therefore the construction phase for this project will need to be coordinated with GWRS FE construction schedule to
ensure adequate primary clarifier capacity is available upon completion of the GWRS Final Expansion Projects.
CONSTRUCTIONBID
BID
BID
CONSTRUCTION
BID CONSTRUCTION
CEQA RFP DESIGN CONSTRUCTION
RFP DESIGN
CEQA RFP DESIGN
CEQA RFP DESIGN
2021 2022 2023
CEQA RFP DESIGN CONSTRUCTION
2020
BID
PROJECT2016 2017 2018 2019
A5