5
23 rd International Conference on Electricity Distribution Lyon, 15-18 June 2015 Paper 0425 CIRED 2015 1/5 OPPORTUNITIES PRESENTED BY SMART GRIDS TO IMPROVE NETWORK PLANNING, OPTIMISING ELECTRICAL VEHICLE, DER AND LOAD INTEGRATION Ricardo PRATA Pedro MOUSINHO Diogo MOREIRA EDP - Distribuição Portugal EDP - Distribuição Portugal EDP - Distribuição Portugal [email protected] [email protected] [email protected] ABSTRACT Presently at EDP Distribuição, LV networks are planned using probabilistic methods. With InovGrid, the smart grid project developed in Portugal, real data from LV networks is becoming available for planning purposes, enabling new planning methods. Part I of this paper analyses the results obtained with both approaches, probabilistic and chronological, while planning a real LV network. Furthermore, Part II of the paper analyses the impact on the distribution MV networks of three different strategies of electric vehicle (EV) charging Direct Charging, Minimum Cost and Renewable-Following. Finally, we performed a critical analysis of the results obtained, in order to find the strengths and weaknesses of each charging solution, as well as the impact that these have on the medium voltage distribution network. INTRODUCTION The probabilistic method used in EDP Distribuição for LV network planning estimates the contribution of each LV customer to the peak demand, considering its contracted power and a simultaneity factor that allows to estimate power flows with 95 % probability of not exceedance. With smart meter deployment, the grid planner has more detailed information regarding load diagrams of consumption, production and power demand in secondary substations allowing for the development of a chronological method. In the first section of this paper, simulations of a real network are performed with data yielded through smart meters, in order to analyse actual conditions during peak demand and off-peak demand. The connection of new micro-generation units (G) and loads, including electrical vehicles (EV) with different charging strategies, are also considered in the simulations. The results obtained by the chronological method are compared with those obtained by the probabilistic method, concerning the investment needs identified through each methodology, in order to compare them. Regarding the EV, mobility represents a significant portion of world’s economy and is essential to the way we live and organize ourselves. Transport accounts approximately 30% of energy consumption in Portugal and Europe. [1] Power Systems face new challenges associated with the potential massive integration of EV in the future. The increased integration of EV will translate into a new paradigm in terms of energy consumption, with electricity becoming the most used energy source for mobility instead of fossil fuels. Thus arises the need to analyze the impact that a larger EV fleet will have on distribution networks. PARAMETERS In all the simulations was considered that an EV has a constant charging rate of 3kW [2], requiring six hours to fully load. Charging is done at home and it is assumed that it can be done within a 12 hours window, after the vehicle arrival, and it can be done intermittently. Thus it is necessary to find the best charging strategy and analyse the impact in the distribution grid. During the 12 hours window available for charging the EV, the vehicle is connected to the same busbar to which it originally connected. It is assumed that all EVs start the charging period with the same battery state of charge (SOC) and that after 6 hours of charge the SOC reaches 100%. TRADITIONAL VS. FUTURE PLANNING The LV network selected in order to perform the simulations is mostly residential and it is fed by a secondary substation equipped with a distribution transformer of 630kVA. In order to compare both methods, the day analysed with the chronological method corresponded with the day where the 2014 peak load of the transformer was achieved (Figure 1 and Figure 2). Figure 1 - Daily consumption measured in the secondary substation 0.0 0.5 1.0 1.5 2.0 2.5 3.0 01-01-2014 08-01-2014 15-01-2014 22-01-2014 29-01-2014 05-02-2014 12-02-2014 19-02-2014 26-02-2014 05-03-2014 12-03-2014 19-03-2014 26-03-2014 Daily MWh

GUIDELINES FOR THE SUBMISSION OF THE FINAL PAPERcired.net/publications/cired2015/papers/CIRED2015_0425... · 2018. 9. 10. · 23rd International Conference on Electricity Distribution

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: GUIDELINES FOR THE SUBMISSION OF THE FINAL PAPERcired.net/publications/cired2015/papers/CIRED2015_0425... · 2018. 9. 10. · 23rd International Conference on Electricity Distribution

23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015

Paper 0425

CIRED 2015 1/5

OPPORTUNITIES PRESENTED BY SMART GRIDS TO IMPROVE NETWORK

PLANNING, OPTIMISING ELECTRICAL VEHICLE, DER AND LOAD INTEGRATION

Ricardo PRATA Pedro MOUSINHO Diogo MOREIRA

EDP - Distribuição – Portugal EDP - Distribuição – Portugal EDP - Distribuição – Portugal

[email protected] [email protected] [email protected]

ABSTRACT

Presently at EDP Distribuição, LV networks are planned

using probabilistic methods. With InovGrid, the smart

grid project developed in Portugal, real data from LV

networks is becoming available for planning purposes,

enabling new planning methods. Part I of this paper

analyses the results obtained with both approaches,

probabilistic and chronological, while planning a real LV

network.

Furthermore, Part II of the paper analyses the impact on

the distribution MV networks of three different strategies

of electric vehicle (EV) charging – Direct Charging,

Minimum Cost and Renewable-Following. Finally, we

performed a critical analysis of the results obtained, in

order to find the strengths and weaknesses of each

charging solution, as well as the impact that these have

on the medium voltage distribution network.

INTRODUCTION

The probabilistic method used in EDP Distribuição for LV network planning estimates the contribution of each LV customer to the peak demand, considering its contracted power and a simultaneity factor that allows to estimate power flows with 95 % probability of not exceedance. With smart meter deployment, the grid planner has more detailed information regarding load diagrams of consumption, production and power demand in secondary substations – allowing for the development of a chronological method. In the first section of this paper, simulations of a real network are performed with data yielded through smart meters, in order to analyse actual conditions during peak demand and off-peak demand. The connection of new micro-generation units (G) and loads, including electrical vehicles (EV) with different charging strategies, are also considered in the simulations. The results obtained by the chronological method are compared with those obtained by the probabilistic method, concerning the investment needs identified through each methodology, in order to compare them. Regarding the EV, mobility represents a significant

portion of world’s economy and is essential to the way

we live and organize ourselves. Transport accounts

approximately 30% of energy consumption in Portugal

and Europe. [1]

Power Systems face new challenges associated with the

potential massive integration of EV in the future. The

increased integration of EV will translate into a new

paradigm in terms of energy consumption, with

electricity becoming the most used energy source for

mobility instead of fossil fuels.

Thus arises the need to analyze the impact that a larger

EV fleet will have on distribution networks.

PARAMETERS

In all the simulations was considered that an EV has a

constant charging rate of 3kW [2], requiring six hours to

fully load. Charging is done at home and it is assumed

that it can be done within a 12 hours window, after the

vehicle arrival, and it can be done intermittently. Thus it

is necessary to find the best charging strategy and analyse

the impact in the distribution grid.

During the 12 hours window available for charging the

EV, the vehicle is connected to the same busbar to which

it originally connected. It is assumed that all EVs start the

charging period with the same battery state of charge

(SOC) and that after 6 hours of charge the SOC reaches

100%.

TRADITIONAL VS. FUTURE PLANNING

The LV network selected in order to perform the

simulations is mostly residential and it is fed by a

secondary substation equipped with a distribution

transformer of 630kVA. In order to compare both

methods, the day analysed with the chronological method

corresponded with the day where the 2014 peak load of

the transformer was achieved (Figure 1 and Figure 2).

Figure 1 - Daily consumption measured in the secondary

substation

0.0

0.5

1.0

1.5

2.0

2.5

3.0

01-01-2014

08-01-2014

15-01-2014

22-01-2014

29-01-2014

05-02-2014

12-02-2014

19-02-2014

26-02-2014

05-03-2014

12-03-2014

19-03-2014

26-03-2014

Dai

ly M

Wh

Page 2: GUIDELINES FOR THE SUBMISSION OF THE FINAL PAPERcired.net/publications/cired2015/papers/CIRED2015_0425... · 2018. 9. 10. · 23rd International Conference on Electricity Distribution

23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015

Paper 0425

CIRED 2015 2/5

Figure 2 - Load diagram of the secondary substation on Feb.

9th 2014

In the following sub-sections, the comparison between

both methods is represented graphically in terms of the

performance of the network related to voltage and current

values obtained in nodes and branches, respectively,

according to the following presented on Figure 3,

Figure 3 – Colour coding used to present voltage and currents

where, Umax is equal to 110% p.u. of nominal voltage, as

stated in EN50160, and Umin is equal to 92% p.u. of

nominal voltage, which corresponds to a voltage drop of

8% p.u. up to the point of common coupling, thus

allowing for a further voltage drop of 2% p.u. up to the

customer’s equipment (10% p.u. of total voltage drop).

Imax is the nominal current of the conductor.

A node or branch coloured in red or blue represents an

unacceptable scenario that must be overcome by means

of new investments in the network or through new

configurations of the network, if possible.

LV network as is

Figure 4 shows the actual state of the network, simulated

according to probabilistic and chronological methods.

Probabilistic (Peak)

Chronological (14h15m)

Chronological (20h45m)

Figure 4 - Actual state of the LV network analysed

Although the three scenarios have nodes coloured in

yellow, the lowest node’s voltage is lower in the

probabilistic approach (92.1% of nominal voltage) than in

the chronological approach (93.5% of nominal voltage).

Connection of new consumers

Figure 5 shows the behaviour of the network after

connecting 2 new consumers of 6.9kVA each (1 in phase

A and 1 in phase C), in 2 of the most unfavourable nodes:

Probabilistic (Peak)

Chronological (14h15m)

Chronological (20h45m)

Figure 5 - Performance of the network after connecting 2 new

consumers

The conclusions yielded through the two approaches are

different: while the probabilistic method shows that the

connection of the 2 consumers requires grid

reinforcements, the chronological method states that the

connection is possible without violating voltage or

current limits.

On this example, the consequence of connecting 2 new

consumers regarding voltage profiles is less severe under

the more rigorous chronological method, which considers

actual load profiles and network unbalance.

Connection of new producers (peak load)

After connecting 2 new consumers as referred in the

previous section, Figure 6 illustrates the behaviour of the

network after connecting 2 new micro generator units of

3.7kVA each (solar), 1 in phase B and 1 in phase C, again

in 2 unfavourable nodes:

0

40

80

120

160

200

0:15

1:15

2:15

3:15

4:15

5:15

6:15

7:15

8:15

9:15

10:15

11:15

12:15

13:15

14:15

15:15

16:15

17:15

18:15

19:15

20:15

21:15

22:15

23:15

kW

Voltage (nodes): Current (branches):

U > Umax

Umax*98% < U < Umax I < Imax*75%

Umin*102% < U < Umax*98% Imax*75% < I < Imax*90%

Umin < U < Umin*102% Imax*90% < I < Imax

U < Umin I > Imax

Page 3: GUIDELINES FOR THE SUBMISSION OF THE FINAL PAPERcired.net/publications/cired2015/papers/CIRED2015_0425... · 2018. 9. 10. · 23rd International Conference on Electricity Distribution

23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015

Paper 0425

CIRED 2015 3/5

Probabilistic (Peak)

Chronological (14h15m)

Chronological (20h45m)

Figure 6 - Performance of the network after connecting 2 new

producers, during peak demand

As in the previous example, probabilistic method would

support the decision for network reinforcements that

might not be necessary. According with the chronological

method, there is an improvement regarding the voltage

profile on the point of common coupling (PCC) of the

generation units, thus sparing the need for further

investments.

Again, in this example the conclusions provided by the

chronological method are more realistic, as it considers

real load and production diagrams and real unbalance

conditions. Furthermore, on residential networks the

chronological method is more effective in analysing

voltage profile variation during the analysis period, given

that solar production and load consumption tend to occur

on different occasions (production will be higher at noon

and peak consumption occurs late afternoon).

Connection of new producers (off-peak load)

The connection of production units must be assessed also

during off-peak demand, due to the potential increase of

voltage values. To illustrate this effect, 9 producers of

3.7kVA each are connected along the furthest branch

from the secondary substation (5 in phase A, 2 in phase B

and 2 in phase C). The off-peak demand is simulated in

the probabilistic approach, considering zero consumption

in the grid, while in the chronological approach considers

the day of 2014 with the smallest consumption (Figure 7).

Figure 8 shows the results of the simulations performed.

Figure 7 - Load diagram of the secondary substation on Jun. the

27th 2014

Probabilistic (Off-Peak)

Chronological (14h15m)

Chronological (20h45m)

Figure 8- Performance of the network after connecting 9 new

producers, during off-peak demand

On this example, the probabilistic method returns a

maximum voltage of 111% p.u. during off-peak demand,

leading to the conclusion that the connection would

require grid reinforcements. The use of the chronological

method in the same example returns a maximum voltage

of 109% p.u., which is within the acceptable voltage

values.

The main reason for the differences observed is related

with the off-peak demand conditions considered on the

probabilistic approach, which are more conservative as it

considers zero or near zero consumption on the grid,

while in the chronological approach the off-peak demand

conditions considers the real lowest consumption

observed. The advantage of using real data under off-

peak conditions is even more important in secondary

substations feeding industrial or services loads, where the

period of maximum solar production matches the highest

consumptions and not the off-peak consumptions (Figure

9), allowing for the possibility of connecting more

distributed generation units and minimizing investment

requirements.

Services-type secondary substation

Solar production

Figure 9 - Load diagram of a Services-type secondary

substation

Connection of electrical vehicles

The analysis associated with the connection of EVs is

similar to the analysis of the connection of new

customers, regarding the purpose of comparing

probabilistic and chronological methods, as addressed in

the previous sub-section. The purpose of this section is to

0

20

40

60

80

100

0:15

1:15

2:15

3:15

4:15

5:15

6:15

7:15

8:15

9:15

10:15

11:15

12:15

13:15

14:15

15:15

16:15

17:15

18:15

19:15

20:15

21:15

22:15

23:15

kW

Page 4: GUIDELINES FOR THE SUBMISSION OF THE FINAL PAPERcired.net/publications/cired2015/papers/CIRED2015_0425... · 2018. 9. 10. · 23rd International Conference on Electricity Distribution

23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015

Paper 0425

CIRED 2015 4/5

analyse two different EV charging strategies, and assess

their impact in the grid using the chronological method:

Direct charging - the EV starts to charge when it

arrives at the charging point (normally between

18h and 20h);

Minimum cost - the EV’s charging occurs when

the cost of energy is lower (after midnight).

Figure 10 presents the behaviour of the grid while

feeding the charge of 33 EVs (~1/5 of the number of

consumers) equally divided by the 3 phases. Direct charging (20h45m)

Minimum cost (00h15m)

Figure 10 - Performance of the network after connecting 33

EVs

Real load diagrams usage allows the grid planner to

compare different charging strategies, according to the

load profile of each secondary substation.

Having more information to support the chronological

methodology, the capability of the network to

accommodate the charging of EVs is better assessed, with

less conservative error margins, encouraging this way the

dissemination of EVs.

STRATEGIES FOR ELECTRICAL VEHICLE

CHARGING

The analysis of the EV integration impact on MV

distribution networks will follow the parameters defined

initially, and it is necessary to define the different

charging strategies used for the case study.

Charging strategies

Three different loading strategies are analysed, including

Direct Charging, Minimum Cost and Renewable-

following.

Direct Charging

The Direct Charging model considers that the EV starts

to charge as soon as it arrives at the loading site, and it

finishes after 6 hours. This type of charging does not

impose any restrictions to the owners of EV. This

strategy requires no control or fleet management of EV

charging, since the charging process is to be done

continuously and immediately upon arrival of the EV at

the loading site.

Minimum Cost

The Minimum Cost strategy consists on the minimization

of the energy cost associated with charging the EV,

shifting the load to off-peak hours, when the energy price

is lower. In order to define when the EV charges, it is

necessary to solve an optimization problem. Given that

minimizing the cost of a singular EV is independent of

the others, this can be done individually. Total cost is

obtained by adding the hourly energy cost associated with

the energy consumed. The Minimum Cost strategy

requires the existence of an aggregator element that,

based on market prices, defines when the EV should be

loaded (fleet manager).

The equations that describe the optimization function are:

𝑀𝑖𝑛 𝑍 = ∑ ∑ 𝐶𝑘 × 𝐸𝑉𝑖,𝑘

24

𝑖=14

24

𝑘=1

Subject to:

∑ 𝐸𝑉𝑖,𝑘 = 6 ∀𝑖

24

𝑘=1

𝐸𝑉𝑖,𝑘 ≤ 𝐷𝑖,𝑘 ∀𝑖, 𝑘

𝑖 − 𝑎𝑟𝑟𝑖𝑣𝑎𝑙 𝑡𝑖𝑚𝑒 𝑜𝑓 𝑡ℎ𝑒 𝐸𝑉

𝑘 − 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 ℎ𝑜𝑢𝑟

𝐸𝑉𝑖,𝑘 − 𝐵𝑖𝑛𝑎𝑟𝑦 𝑣𝑎𝑟𝑖𝑎𝑏𝑙𝑒, 𝑖𝑛𝑑𝑖𝑐𝑎𝑡𝑖𝑛𝑔 𝑡ℎ𝑒 𝑠𝑡𝑎𝑡𝑒 𝑜𝑓 𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔

𝐶𝑘 − 𝐸𝑛𝑒𝑟𝑔𝑦 𝑐𝑜𝑠𝑡

𝐷𝑖,𝑘 − 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑡𝑜 𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔

Renewable following

The Renewable following model aims charge the

batteries when there is higher renewable production on

the network, in order to benefit from the advantages of

distributed generation for loading the EV, trying to match

demand with offer. Contrary to the other strategies, it

isn’t the owner of EV who defines when it is loaded, but

an entity responsible for EV fleet management. In

Renewable Following strategy, EVs are not independent

of each other to charge, so the user will only have control

in defining the overall time period during which she/he

will require the vehicle to be fully charged.

The equations that describe the optimization function are:

𝑀𝑖𝑛 𝑋 = ∑ 𝑍𝑘

24

𝑘=1

− ∑ ∑ (𝛼 × 𝐸𝑉𝑖,𝑘 × 𝑁𝑘 − 𝑅𝑘)

24

𝑖=14

24

𝑘=1

Subject to:

∑ 𝐸𝑉𝑖,𝑘 = 6 ∀𝑖

24

𝑘=1

𝐸𝑉𝑖,𝑘 ≤ 𝐷𝑖,𝑘 ∀𝑖, 𝑘

𝑍𝑘 ≤ 0 ∀𝑘

𝑍𝑘 ≥ ∑ (𝛼 × 𝐸𝑉𝑖,𝑘 × 𝑁𝑘 − 𝑅𝑘) ∀𝑘

24

𝑖=14

𝑖 − 𝑎𝑟𝑟𝑖𝑣𝑎𝑙 𝑡𝑖𝑚𝑒 𝑜𝑓 𝑡ℎ𝑒 𝐸𝑉

Page 5: GUIDELINES FOR THE SUBMISSION OF THE FINAL PAPERcired.net/publications/cired2015/papers/CIRED2015_0425... · 2018. 9. 10. · 23rd International Conference on Electricity Distribution

23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015

Paper 0425

CIRED 2015 5/5

𝑘 − 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 ℎ𝑜𝑢𝑟

𝐸𝑉𝑖,𝑘 − 𝐵𝑖𝑛𝑎𝑟𝑦 𝑣𝑎𝑟𝑖𝑎𝑏𝑙𝑒, 𝑖𝑛𝑑𝑖𝑐𝑎𝑡𝑖𝑛𝑔 𝑡ℎ𝑒 𝑠𝑡𝑎𝑡𝑒 𝑜𝑓 𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔

𝑍𝑘 − 𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑏𝑒𝑡𝑤𝑒𝑒𝑛 𝐸𝑉 𝑙𝑜𝑎𝑑 𝑎𝑛𝑑 𝑟𝑒𝑛𝑒𝑤𝑎𝑏𝑙𝑒 𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑖𝑜𝑛

𝑁𝑘 − 𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐸𝑉 𝑙𝑜𝑎𝑑𝑖𝑛𝑔

𝐷𝑖,𝑘 − 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑡𝑜 𝑐ℎ𝑎𝑟𝑔𝑖𝑛𝑔

𝑅𝑘 − 𝑅𝑒𝑛𝑒𝑤𝑎𝑏𝑙𝑒 𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒

𝛼 − 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 𝑟𝑎𝑡𝑒 (3𝑘𝑊)

An example of the charging load profile for 1,200 EVs

obtained with a give renewable production diagram is

presented on Figure 11

Figure 11 - Load profile for Renewable Following

Charging availability

The profile used is based on the data of the number of EV

arrivals per day, obtained from a study on mobility held

in the North [3] region of Portugal. The original data

regarding the expected number of EVs on 2030 can be

considered optimistic, (863,000 EV in Portugal), given

the trend meanwhile verified. According to [4], it is only

expected a large EV integration of EV after 2030, in

Portugal. In order to adapt these studies to the values

used on this case study, that data was normalized to

values between 0 and 100%, corresponding to 100% of

the total number of EV present in the network under

study.

It is assumed that EV arrivals at the charging points occur

between 14:00h and 00:00h.

Case study description

On this case study was analysed a radial MV distribution

network, with 69 buses, having distributed renewable

production of wind and photovoltaic type associated with.

Wind generation is represented by three wind farms,

while the PV is present on the buses with energy

consumption. The amount EV is a parameter in the

network, as well as the profiles of renewable production,

in order to cover more possibilities.

Results

The results to consider are the daily losses, minimum

voltage values throughout the day, the total number of

limits violated and the maximum load line flow. In

addition to these, are still analysed the energy costs

associated with charging the EV as well as the amount of

renewable energy used. The hybrid strategy is a mix one,

on which half of consumers use the Direct Charging

strategy and the other half the Minimum Cost strategy.

The results of the simulation for all strategies are shown

in Table I:

Results/Strategies Direct Cost Renewable Hybrid

Losses (MWh) 2.4 2.031 1.946 2.084

Min. Voltage (p.u.) 0.9 0.957 0.959 0.958

Limits violated

(N.º) 15 0 0 0

Capacity usage (%) 52.3 42.3 39.6 45.7

Energy Cost (€) 1380 1221 1229 1301

Renewable

Energy Used (%) 34.4 32.7 34.8 34.7

Table 1 – Results for 1200 EV

CONCLUSIONS

Chronological information from InovGrid allows to

assess more precisely the actual conditions verified

during peak demand and low load demand. In all the

examples presented, the benefit of having more

information regarding real load diagrams led to different

conclusions concerning the possibility of connecting new

loads and new generation units without requiring further

investments on grid reinforcements. From the results

obtained, it can be concluded that a methodology that

considers actual load and generation profiles can boost

the increase of distributed generation and electrical

vehicles connected to the grid.

Analysing the results of each strategy, it is concluded that

the production Renewable Following strategy is the one

with less negative impacts on the networks, including

losses, minimum voltage, line flow, and total limits

violated per day. Thus, a greater integration of EV in

networks is favoured by the strategy, without causing

constraints in the functioning of networks and leading to

lower losses. This solution is not only the best in energy

costs, losing to the Minimum Cost strategy, which has the

lowest cost for all cases, but leads to worst results in the

other parameters studied.

REFERENCES

[1] J. Amador, “Produção e consumo de energia em Portugal:

Factos estilizados,” Boletim Económico, 2010.

[2] J. F. N. Soares, “Impact of the deployment of electric

vehicles in grid operation and expansion,” dissertação para

obtenção do Grau de Doutorado em Engenharia Electrotécnica e

de Computadores pela FEUP, 2011. [3] I. N. de Estatística, “Inquérito à mobilidade da população

residente,” Inquérito à Mobilidade da População Residente

2000, Direcção Geral de Transportes Terrestres.

[4] I. PORTO, “Carro elétrico: Massificação só em 2030,”

http://www2.inescporto.pt/noticias-eventos/notas-de-

imprensa/carroeletrico-massificacao-so-em-2030/, acedido em

Abril de 2013.