GUIDED BORING MACHINE (GBM) TECHNICAL MANUAL Ø 48.00 OD PIPE

Guided Boring Machine (GBM) Technical Manual

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Guided Boring Machine (GBM) Technical Manual

GUIDED BORING MACHINE (GBM) TECHNICAL MANUAL

Ø 48.00OD PIPE

Page 2: Guided Boring Machine (GBM) Technical Manual

2

Notes

Page 3: Guided Boring Machine (GBM) Technical Manual

3

ContentsMethod Of Operation ................................................................................................................................. 4Thrust Frame - Latching - 308A/339A ...................................................................................................... 6 Jacking Frame Dimensions & System Layout 308A .............................................................................................................................. 8 339A .............................................................................................................................. 9 Accessories - Shaft Adapters ................................................................................................. 10 Single Stage - 240A ........................................................................................................................ 12 Jacking Frame Dimensions & System Layout .............................................................. 14 - 15 Accessories Standard Base Frame .................................................................................................. 16 Auger Rig Guidance ................................................................................................... 17 Power Pack P100Q .....................................................................................................................................18 P150Q .................................................................................................................................... 20Thrust Frame - 4800 Series ...................................................................................................................... 22 Jacking Frame Dimensions ................................................................................................... 24 Frame Skid Selection ............................................................................................................ 25 Power Pack P250D .................................................................................................................................... 26Guidance System ..................................................................................................................................... 28Steering Kit .............................................................................................................................................. 30Dual Pilot Tubes & Rack ......................................................................................................................... 32Pilot Tube Accessories TriHawk® Rock Drill ...................................................................................................................... 34 Breakout Tool ................................................................................................................................. 35Upsizing Tooling Auger Boring Adapter 36/530 ........................................................................................................ 37 Integral Bearing Swivel Cutter ....................................................................................................... 38 Reaming Head Assembly ................................................................................................................ 40 Cutter Head Assembly .................................................................................................................... 42 Thrust Casing Assembly ................................................................................................................. 44 Powered Reaming Head Series II ................................................................................................... 46 Eliminator ..................................................................................................................................... 48 Powered Cutter Head PCH 20 - PCH 22.5 - PCH 30.5 ............................................................................................ 50 PCH 36 - PCH 44 .................................................................................................................. 52 Weld-On Reaming Head Single Stage ........................................................................................................................... 54 Two Stage .............................................................................................................................. 55Jetting & Lubrication Pump - 2325D/2325E ........................................................................................... 56Lubrication Pump - 1325G ...................................................................................................................... 58

Page 4: Guided Boring Machine (GBM) Technical Manual

4

Method Of Operation - 240A/308A/339A/4800 SeriesGuided Boring Machine (GBM) equipment is used with pipe outside diameters from 4 to 48 inches. The Guided Boring Method is a trenchless installation method for small diameter pipes with the grade and alignment precision the gravity sewer and water industry demand. The pipe installation involves a three-step process starting with launch and reception shafts strategically located to minimize surface disruption.

For gravity sewer installation, where line and grade accuracy are paramount, the Akkerman Guided Boring Machine provides the precision needed for consistent success. The Akkerman Guided Boring Machine is available in three jacking frame configurations; one is a SINGLE STAGE frame (240A) with 48” stroke cylinders designed for 8 foot by 12-foot trench box operation. The second is the LATCHING FRAME (308A/339A) designed to work in 8 or 9 foot round shaft operations. The latching frame is set up with 10-1/2 stroke cylinders and latching pins to advance the tooling the length of the frame. The 240A, 308A and 339A frames are a robust design capable of providing 100 tons of jacking force and 50 tons of pull back force with 10,000 foot pounds of rotational torque available through the gear box. The third frame is the 4800 Series jacking frame and is designed for a minimum 13-foot round or trench box shaft and installing up to 48” OD pipe. The frame is equipped with 30” or 40” stroke cylinders and a 12-inch latching pin position system to install 1 meter, 2 meter and 8 foot length pipe (optional frame extensions are available to handle 10 foot or 20 foot length pipe). This frame has 265 tons of jacking force and 100 tons of pull back force with 26,000 foot pounds of rotational torque available through the gear box.

Two individual control valves provide smooth independent control of the jacking cylinders and the rotational hydraulic drive motor. For ease of monitoring the machine’s operation, hydraulic gauges are mounted in the operator’s line of sight to observe the jacking and rotational pressures.

The Akkerman Power Pack provides hydraulic power for the jacking frame. The P100Q is equipped with a 4.5-liter diesel engine which drives two load sensing, variable volume, and torque limiting piston pumps. Each system provides 0 to 34 gpm at 5,000 psi operating pressure. The P150Q is also equipped with a 4.5-liter diesel engine driving three load sensing, variable volume, and torque limiting piston pumps. Each system provides the following hydraulic

240A

308A339A

P100Q

P150Q

P250D

flow: two pumps (rotation/cutter bit) 0 to 34 gpm at 5,000 psi, and one pump (jacking) 0 to 26 gpm at 6,000 psi. The P250D is equipped with a 6.8-liter diesel engine driving three load sensing, variable volume, and torque limiting piston pumps. Each system provides the following hydraulic flow: 0 to 60 gpm at 5,000 psi (rotation), 0 to 50 gpm at 5,000 psi (cutter bit), and 0 to 25 gpm at 6,000 psi (jacking).

The power unit is set away from the immediate work area and hydraulic hoses run between the power pack and the jacking frame. The power pack is operated from the launch shaft using a pendant control. The unit has a control pendant so the operator in the launch shaft can control the power pack and monitor vital engine functions. Akkerman Inc. reserves the right to improve its products without notice or obligation.

4800Series

Page 5: Guided Boring Machine (GBM) Technical Manual

5

STEP 1: PRECISE INSTALLATION OF PILOT TUBES

The first step in the Guided Boring Method is the installation of the pilottubes on line and grade.

The pilot tubes are inserted through the ground from the launch shaft to the reception shaft.

On the leading end of the pilot tube is the steering head with an angled tip.

Theodolite/Camera, Sighted DownCenter of Pilot Tubes

In the steering head is a battery powered LED illuminated target that is visible to the operator by means of a theodolite, camera, and monitor.The theodolite is set on line and grade and is positioned to view the target through the bore of the pilot tube with the cross hairs of the theodolite visible on the monitor along with the illuminated target. The operator rotates the steering head as needed to maintain the desired line and grade. This step is complete when the steering head reaches the reception shaft.The pilot tubes are a dual walled tube design. This provides a means to lubricate the pilot shaft as it passes through the ground. This lubrication reduces the force required to thrust and rotate during installation.

GBM_MethodOfOperation

The second step is to follow the pilot tube with a reaming head and or abearing swivel joint to match the diameter of the product pipe. The GBM installs pipe from 4 inch to 48 inch OD.Different types of tooling are available to work in various ground conditions.

The reaming head and auger casings are attached to the pilot tubes and the jackingframe advances the reaming head and casings into the ground.

With the addition of each section of auger and casings in the launch shaft, a section of pilot tube is removed from the reception shaft. The process continues until the auger and casings reach the reception shaft at which point all the pilot tube sections have been removed.

The third step is installation of the product pipe. A pipe adapter is installed on the last section of auger casing to match the product pipe.

As the pipe is thrust into place, the auger casings are removed from the reception shaft. This process continues until the product pipe reaches the reception shaft.

With the installation of the product pipe, the job is complete with minimal impact and disruption to activities in the immediate area.

If a Powered Cutter Head (PCH) or Powered Reaming Head (PRH) is used, it is placed behind the casings and augers and before the final product pipe. The auger spoil flow is reversed toward the reception shaft for removal.

STEP 2: ADVANCING AUGERS ALONG PILOT TUBE PATH

STEP 3: INSTALLATION OF FINAL PRODUCT PIPE

Page 6: Guided Boring Machine (GBM) Technical Manual

6

SPECIFICATIONSDimensions (width x length x height) 308A .........48 x 92 x 62 in. (1219x2337x1575mm) 339A .......52 x 108 x 62 in. (1321x2743x1575mm)Assembly Weight With Shaft Adapters 308A ........................................6,000 lbs. (2,722 kg) 339A ........................................6,600 lbs. (2,994 kg)Latching Positions On Center ...........8 in. (203 mm)Cylinder Stroke ............................. 10.5 in. (267 mm)Operating Pressure (Max.) ... 5,000 psi ( 34,475 kPa)Elevation** .............. 31 to 48 in. (787 to 1,219 mm)Operating Grade (Max.) ......................................10%Pipe OD Diameter (Max) 308A ...........................................28.5” (724 mm) 339A ...........................................31.5” (800 mm)

FEATURES• Assembly consists of the latching frame, drive swivel adapter, alignment adapter and operator platform.• Three speed hydraulic operator controlled motor.• Hydraulic latching mechanism to advance and retract gear box assembly.• Hydraulic pressure gauges for monitoring jacking and rotation system pressures.• Quick coupler connections with lock for easy and secure hydraulic hose installation.• Dual motor travel function for ease of advancing gear box along the frame.• Jacking functions 0 to 26 gpm @ 5,000 psi.• Rotation functions 0 to 34 gpm @ 5,000 psi.• Complete with Powered Cutter Head (PCH) / Powered Reaming Head (PRH) controls.• Independent control for hydraulic make-up tool.• Optional round and square shaft adapters, and frame extensions available to conform to shaft requirements.• Four adjustable legs with leveling screws for ease of frame height adjustment and leveling.

• Designed To Work In 96”/108”* Minimum ID Or Trenchbox Shafts • • Independent Jacking & Rotation Operation •

Gear Box Rotational Torque***..10,500 ft-lbs (14,238 N·m) Jacking Force ............................ 100 Ton (91 mt) Pull Back Force .......................... 50 Ton (45 mt)Hydraulic Motor ...................................... Three Speed High Speed ................................................ 50 rpm Mid Speed ................................................. 37 rpm Low Speed ................................................ 25 rpm

* 96” ID Dia. Shaft - 308A; 108” ID Dia Shaft - 339A** From shaft floor to drive center*** Output torque in low speed @ 5,000 psi

The GBM 339A latching frame is shown with round shaft adapters.

Thrust Frame - Latching - 308A / 339APart No. FA40032F (308A), FA43500F (339A)

GBM_LatchingFrame308A/339A

Page 7: Guided Boring Machine (GBM) Technical Manual

7 GBM_LatchingFrame339A

High pressure valves for jacking, rotation, frame travel, and PCH/PRH control functions.

The quick couplers connect to the pressure, return, load sense and case drain hydraulic hoses from the

GBM P100Q or P150Q Power Pack.

Drive Swivel Adapter With Fluid ConnectorAnd Alignment Adapter

Dual travel motors for ease of advancing gear box along the frame rails.

Operator platform located 18” above shaft floor provides firm footing to keep the operators

above the water and mud.

Hydraulic pressure gauges for monitoring thrust and rotation system pressures.

Low pressure valves for hydraulic make-up tool, rotation speed and hydraulic latching functions.

Frame extensions are available in 16”, 24”, 40” and 56”.Frame shown with a combination of the

56” and 40” frame extensions.

Page 8: Guided Boring Machine (GBM) Technical Manual

8

Jacking Frame Dimensions - 308AMinimum Shaft Requirements & System Layout

Installing Pilot Tubes

Dimensions are shown in inches

Page 9: Guided Boring Machine (GBM) Technical Manual

9

Installing Auger Casings

Jacking Frame Dimensions - 339AMinimum Shaft Requirements & System Layout

Dimensions are shown in inches

Page 10: Guided Boring Machine (GBM) Technical Manual

10

SPECIFICATIONSFront & Rear Shaft Adapter Dimensions 308A Width ................................ 48 in. (1219 mm) Height ............................... 46 in. (1168 mm) 339A Width ................................ 52 in. (1321 mm) Height ............................... 48 in. (1219 mm)

Frame Opening For Pipe 308A .......................................... 30 in. (762 mm) 339A .......................................... 33 in. (838 mm)

FEATURES• Assembly includes the front and rear round shaft adapters, pilot tube hydraulic make-up tool (not shown),

roller bracket assemblies, pins, and fasteners.• Front and rear adapters can be easily secured to shaft wall with the frame end adjustment screws.• Hydraulic make-up tool allows easy locking and unlocking of pilot tubes in launch shaft.• The 30 inch (308A) and 33 inch (339A) frame opening accommodates larger diameter pipe.• Support rollers used for temporary casing and product pipe.

• Designed To Fit In 96” Minimum ID Shaft • • Connects To Latching Frame For 100 Ton Thrust Capacity •

Latch. Frame Accessories - Shaft Adapters308A: Part No. FA40017F (Round Shaft), Part No. FA40018F (Square Shaft)339A: Part No. FA43501F (Round Shaft), Part No. FA43502F (Square Shaft)

Square ShaftAdapters

Round ShaftAdapters

GBM_LFRoundSquareShaftAdptr RevB

Hydraulic Make-Up Tool Size (WxHxD) ..12 x 16 x 5 in. (305 x 406 x 127mm) Weight .............................................. 120 lbs. (54.5 kg) Cylinder Stroke .................................. 4 in. (102 mm)

Front Shaft Adapter Weight Round 308A ................................. 500 lbs. (227 kg) 339A ................................. 500 lbs. (227 kg) Square 308A ................................ 504 lbs. (229 kg) 339A ................................ 512 lbs. (232 kg)

Rear Shaft Adapter Weight Round 308A ................................ 729 lbs. (331 kg) 339A ................................. 820 lbs. (372 kg) Square 308A ................................ 853 lbs. (387 kg) 339A ................................. 912 lbs. (414 kg)

Page 11: Guided Boring Machine (GBM) Technical Manual

11 GBM_LFRoundSquareShaftAdptr RevB

Common pins secure the round or square shaft adapters to the

frame end assemblies.

The hydraulic make-up tool is used to tighten each section of pilot tubes as they are installed in the launch shaft. In pull

back operation, the make-up tool is used to separate the pilot tubes in the launch shaft.Three roller bracket assemblies support the

line and weight of the temporary casing and product pipe in the launch shaft.

The frame end assemblies are removable for ease of installing frame extentions.

Page 12: Guided Boring Machine (GBM) Technical Manual

12

SPECIFICATIONSDimensions (width x length x height) ........48 x 118 x 55 in. (1219 x 2997 x 1397 mm)Assembly Weight With Base ........................... 5,300 lbs. (2,404 kg) Without Base .......................4,500 lbs. (2,041 kg) Cylinder Stroke .............................. 48 in. (1219 mm)Operating Pressure (Max.) ... 5,000 psi ( 34,475 kPa)Elevation* ................... 27 to 33 in. (686 to 838 mm)Operating Grade (Max.) ..................................... 10%* From shaft floor to drive center

FEATURES• Single stage frame assembly consists of the single stage frame, standard base frame, drive swivel adapter, align-

ment adapter, and pilot tube hydraulic make-up tool.• Three speed hydraulic operator controlled motor.• Two 48” cylinders advance and retract the gear box assembly.• Hydraulic pressure gauges for monitoring jacking and rotation system pressures.• Quick coupler connections with lock for easy and secure hydraulic hose installation.• Jacking functions 0 to 26 gpm @ 5,000 psi.• Rotation functions 0 to 34 gpm @ 5,000 psi.• Designed for trenchbox shafts.• Two stabilizer legs to aid in frame setup.

• Designed To Work In Stand Alone Or Auger Boring Operation • • 48” Stroke Cylinders For Smooth, Continuous Advancement

of Jacking Frame •

Gear Box Rotational Torque**..10,500 ft-lbs (14,238 N·m) Jacking Force ............................ 100 Ton (91 mt) Pull Back Force ........................... 50 Ton (45 mt)Hydraulic Motor ...................................... Three Speed High Speed ................................................ 50 rpm Mid Speed ................................................. 37 rpm Low Speed ................................................ 25 rpm** Output torque in low speed @ 5,000 psi

The GBM 240A Single Stage Frame is shown with standard base frame.

Thrust Frame - Single Stage - 240APart No. FA40027F

GBM_SingleStageFrame, FA40027F

Page 13: Guided Boring Machine (GBM) Technical Manual

13 GBM_SingleStageFrame, FA40027F

Hydraulic pressure gauges for monitoring thrust and rotation system pressures.

The quick couplers connect to the pressure, return, load sense, and case drain hydraulic hoses from the

GBM P100Q or P150Q Power Pack.

Dual 48” Single Stroke Cylinders

Drive Swivel Adapter With Fluid ConnectorAnd Alignment Adapter

High pressure valves for jacking, rotation, & frame travel functions.

Low pressure valves for hydraulc make-up tool, rotation speed, and auxiliary functions.

The hydraulic make-up tool is used to tighten each section of the pilot tubes as they are installed in the launch shaft. In

pull back operation, the make-up tool is used to separate the

pilot tubes in the launch shaft.

Page 14: Guided Boring Machine (GBM) Technical Manual

14

Jacking Frame Dimensions - 240AMinimum Shaft Requirements

Dimensions are shown in inches

Page 15: Guided Boring Machine (GBM) Technical Manual

15

System Layout - 240A

Installing Pilot Tubes

Page 16: Guided Boring Machine (GBM) Technical Manual

16

SPECIFICATIONSDimensions Length ..................................... 92 in. (2,337 mm) Width ...................................... 41 in. (1,042 mm) Height .................... 21 to 27 in. (533 to 686 mm)

FEATURES• Standard base frame includes four leveling assemblies.• Designed for trenchbox shafts.• Standard base for GBM single stage frame.• Hardware secured for ease of installation or removal.

• Single Stage Base Assembly • • For Stand Alone Operation •

Weight ............................................. 790 lbs. (358 kg)

Single Stage Accessories - Std. Base FramePart No. A40101A

GBM_SingleStgStdBaseFrame, A40101A

Page 17: Guided Boring Machine (GBM) Technical Manual

17

FEATURES• Assembly includes auger boring adapter and mounting hardware for the GBM 240A Single Stage Frame.• Increases both the accuracy and profitability of your auger boring machine by using the GBM 240A frame

with your auger boring machine.• Adapter designed for ease of installation or removal from auger rig track. No special tools or welding required.

Adapter is bolted in place to GBM 240A jacking frame.• Once pilot tubes are installed, complete bore as a standard auger boring operation. • Custom adapters are available upon request.

• Increase Productivity Of Your Auger Boring Machine With Line & Grade Accuracy •

• Adapters Position GBM 240A Jacking FrameOn Centerline Of Auger Boring Machine •

Single Stage Accessories - Auger Rig GuidanceAdapter Setup For Auger Rig Sizes: 30”, 36”, 42”, 48”, 60”, and 72”

GBM_SingleStgAugerBoringBase, A41000F

Step 1: Precise Installation Of Pilot Tubes With GBM

Step 2: Installation Of Steel Casing With Auger Boring Machine

The universal adapter is shown for 36” to 72” auger rigs.

Page 18: Guided Boring Machine (GBM) Technical Manual

18

SPECIFICATIONSDimensions Height ...................................... 82 in. (2,083 mm) Width ....................................... 58 in. (1,473 mm) Length ...................................... 96 in. (2,438 mm)Weight* ..................................... 6,220 lbs. (2,821 kg)Fluid Capacities Fuel Tank .................................... 100 gal (378 L) Hydraulic Reservoir ..................... 50 gal (189 L)Power Unit Four Cylinder Diesel Engine ..... 99 HP (74 kW)

* Weight does not include diesel fuel.

• Provides Hydraulic Power To Operate Jacking Frame • • Remote Pendant For In-Shaft Operation Control •

FEATURES• Assembly comes complete with the GBM P100Q Power Pack, remote control pendant, 50 foot hydraulic hose set to connect hoses from the power pack to the GBM 240A/308A/339A jacking frame, & standard tooling for pilot tube installation.• Standard tooling includes: pilot tube breakout tool, pilot tube scraper, pilot tube to reaming head adapter, steering head kit, pilot tube support bars, guidance system, wrench set, and launch shaft breakout tool.• Access doors on both ends for engine ventilation and a walk-through tooling storage area.• Powered by a four cylinder, liquid cooled, charged air cooling with electronic governor, 99 HP tier III diesel engine.• Two load sense, variable volume piston pumps provide smooth efficient operation.• Remote control pendant with 50 feet of cable, controls the engine functions in shaft.• Hydraulic hoses are stored on hose reels for ease of hose routing to jacking frame.• Quick coupler connections with lock for easy and secure hydraulic hoses at jacking frame.• The 25 gpm cooling circuit maintains hydraulic oil at low operating temperatures.• Hydraulic pressure gauges for monitoring jacking and rotation system pressures.• Equipped with E-Stop control for quick access at container.• Sound insulation provides a low decibel noise level (72 dB).

Pumps Variable Piston Jacking .............. 0 to 34 gpm (0 to 129 L/min) Rotation ............ 0 to 34 gpm (0 to 129 L/min) Operating Pressure** ....... 5,000 psi (34,475 kPa) Gear Pump (Cooling) .......... 25 gpm (95 L/min)** MaximumBreakout Tool Breaking Torque ..... 12,000 ft-lbs (16,272 N·m) Power Source ........................................ 110 VACPilot Tube/Reaming Head Adapter ...................4.15” OD x 3” ID Hex Core x 5” OD

Power Pack - P100QPart No. FA42440F

GBM_P100QPowerPack, FA42440F

Page 19: Guided Boring Machine (GBM) Technical Manual

19GBM_P100QPowerPack, F42440F

Hose Reels For Ease Of Hose Management

Suction Line Hydraulic Shutoffs For The

Feed Pump, And Cooling Pump

50 gal (189 L) Hydraulic Reservoir

The hydraulic reservoir includes an oil level and

temperature gauges.

Filtered Hydraulic Return Oil With Indicator

Pilot tube breakout tool is used in the reception shaft to

loosen the pilot tube joints.

Four Cylinder, 99 HP Tier IIIDiesel Engine

Walk-ThroughTooling Storage

Area

The remote pendant contains the engine tachometer, hourmeter, engine oil pressure gauge, water temperature

gauge, electronic engine speed control, and ignition switch.

Page 20: Guided Boring Machine (GBM) Technical Manual

20

SPECIFICATIONSDimensions Height ............................... 82 in. (2,083 mm) Width ................................ 58 in. (1,473 mm) Length .............................. 96 in. (2,438 mm)Weight ............................... 8,500 lbs. (3,855 kg)Fluid Capacities Fuel Tank ............................ 100 gal (378 L) Hydraulic Reservoir .............. 50 gal (189 L)Power Unit Four Cylinder Diesel Engine..154 HP (115 kW)

* Weight does not include diesel fuel.

• Provides Hydraulic Power To Optimize Performance Of Powered Cutter Head With All GBM Jacking Frames • • Three Pump System For Independent Operations •

FEATURES• Assembly comes complete with the GBM P150Q Power Pack, remote control pendant, 50 foot hydraulic hose set to connect hoses from the power pack to all GBM jacking frames, & standard tooling for pilot tube installation.• Standard tooling includes: pilot tube breakout tool, pilot tube scraper, pilot tube to reaming head adapter, steering head kit, pilot tube support bars, guidance system, wrench set, and launch shaft breakout tool• Access doors on both ends for engine ventilation and a walk-through tooling storage area.• Three pump system for independent operation of the jacking, rotation and Powered Cutter Head (PCH) cutterbit.• Powered by a four cylinder, liquid cooled, 154 HP tier III diesel engine.• Three load sense, variable volume piston pumps provide smooth efficient operation.• Remote control pendant with 50 feet of cable controls the engine functions in shaft.• Hydraulic hoses are stored on hose reels for ease of hose routing to jacking frame.• Quick coupler connections with lock for easy and secure hydraulic hoses at jacking frame.• The 25 gpm cooling circuit maintains hydraulic oil at low operating temperatures.• Hydraulic pressure gauges for monitoring jacking, rotation and PCH cutterbit system pressures.• Equipped with E-Stop control at the operational end of container for quick access.

Pumps Variable Piston Jacking ......... 0 to 34 gpm (0 to 129 L/min) Rotation ....... 0 to 34 gpm (0 to 129 L/min) PCH Cutterbit..0 to 34 gpm (0 to 129 L/min) Operating Pressure* ...5,000 psi (34,475 kPa) Gear Pump (Cooling) ..... 25 gpm (95 L/min)* MaximumBreakout Tool Breaking Torque .. 12,000 ft-lbs (16,272 N·m) Power Source ................................. 110 VACPilot Tube/Reaming Head Adapter .............4.15” OD x 3” ID Hex Core x 5” OD

Power Pack - P150QPart No. FA40035F

GBM_P150QPowerPack, FA40035F

Page 21: Guided Boring Machine (GBM) Technical Manual

21 GBM_P150QPowerPack, F40035F

Hose Reels For Ease Of Hose ManagementAnd Walk-Through

Tooling Storage Area

Suction Line Hydraulic Shutoffs For The

Feed Pumps And Cooling Pump

The remote pendant contains the engine tachometer, hourmeter, engine oil pressure gauge, water temperature

gauge, electronic engine speed control, and ignition switch.

50 gal (189 L) Hydraulic Reservoir

The hydraulic reservoir includes an oil level and

temperature gauges.

Filtered Hydraulic Return Oil With Indicator

Pilot tube breakout tool is used in the reception shaft to

loosen the pilot tube joints.

Four Cylinder, 154 HP Tier IIIDiesel Engine

Page 22: Guided Boring Machine (GBM) Technical Manual

22

SPECIFICATIONSDimensions w/14’ Frame(width x length x height) .....77.25 x 167.75 x 67 in. (1,962 x 4,261 x 1,702 mm)Weight w/14’ Frame (approx) .13,000 lbs. (5,897 kg)Latching Position On Center .... 12 in. (305 mm)Cylinder Stroke Standard .......................... 40 in. (1,016 mm) Optional .............................. 30 in. (762 mm)Operating Pressure (Max.) Jacking .....................6,000 psi ( 41,369 kPa) Rotation ....................5,000 psi ( 34,474 kPa)

FEATURES• Assembly consists of the thrust frame, fluid swivel with alignment adapter, make up tool and wrench set.• Two speed jacking (thrust) advancement control (100 ton [fast], 265 ton [slow]).• Three speed hydraulic operated rotation control (23, 34 and 50 rpm).• Dual rotation pressure control (0 to 10,500 ft-lbs, 0 to 26,000 ft-lbs).• Hydraulic pressure gauges for monitoring jacking, auger rotation, and cutter bit system pressures.• Quick coupler connections with lock for easy and secure hydraulic hose installation.• Dual motor travel function for ease of advancing gear box along the frame.• Jacking functions 0 to 26 gpm @ 6,000 psi. • Rotation functions 0 to 40 or 60 gpm @ 5,000 psi.• Independent control for hydraulic make-up tool.• Hydraulic latching mechanism to advance and retract thrust block assembly.• Leveling screws for ease of frame height adjustment and leveling.• Frame skids available; 14’, 10’, 2’ and 12”. Combinations of frames can be used for various sized shafts.• Works with existing GBM tooling (240A/308A/339A/4812A).• Optional Powered Cutter Head (PCH) hydraulic control package available.• Thrust frame is equipped with three lift eyes so it can be repositioned 180° without realigning frame.• Dirt buckets available in 16.5 Cu-Ft and 30 Cu-Ft capacities.

• Designed To Work In 156” Minimum ID Or Trenchbox Shafts • • Independent Jacking & Rotation Operation •

• Capable Of Installing Pipe up to 48” OD •

Elevation* ...... 37.5 to 41 in. (953 to 1,041 mm)Operating Grade (Max.) ...............................10%Rotational Torque (Low/High) .....10,500/26,000 ft-lbs (14,236/35,251 N·m) Jacking Force ....... 100/265 Ton (91/240 mt) Pull Back Force ................. 100 Ton (91 mt)Hydraulic Motor Speed (Rotation) ............................................. 0 - 23/34/50 rpmShaft Installation (minimum) ......... 13 ft (4.0 m)* From shaft floor to drive center

Thrust Frame - 4800 SeriesPart No. FA40037F

GBM_48 Series, FA40037F/FA48500F

Page 23: Guided Boring Machine (GBM) Technical Manual

23 GBM_4800 Series, FA40037F/FA48500F

The quick couplers connect to the pressure, return, load sense, and case drain hydraulic

hoses from the GBM Power Pack, along with the PCH hydraulic hoses.

Drive Swivel Adapter With Fluid ConnectorAnd Alignment Adapter

Low pressure valves for hydraulic make-up tool, auxiliary and latching functions.

High pressure valves for jacking and rotation functions. Hydraulic pressure gauges for monitoring

thrust, rotation and cutter bit system pressures.

Two 40 inch stroke cylinders provide up to 265 ton thrust capacity. Three thrust frame lift points for ease of

repositioning thrust frame.

Page 24: Guided Boring Machine (GBM) Technical Manual

24

Jacking Frame Dimensions - 4800 Series

Dimensions are shown in inches

GBM_4800 Series, FA40037F

Page 25: Guided Boring Machine (GBM) Technical Manual

25

Frame Skid Selection - 4800 Series

GBM_4800 Series, FA40037F

Pipe Length Minimum Shaft Length

Frame Skid Configurations Used 12” 24” 120” 168”

30 “ Pilot Tube 11’ X1 Meter Pipe 11’ X60” Pilot Tube 15’ X2 Meter Pipe 13’ X X8’ Concrete Pipe 15’ X10’ Steel Pipe 18’ X X20’ Steel Pipe 28’ X X X

4800 With 30” Stroke Cylinders

Pipe Length Minimum Shaft Length

Frame Skid Configurations Used 12” 24” 120” 168”

30 “ Pilot Tube 13’ X X1 Meter Pipe 13’ X X60” Pilot Tube 15’ X2 Meter Pipe 15’ X8’ Concrete Pipe 16’ X X10’ Steel Pipe 19’ X X X20’ Steel Pipe 29’ X X X X

4800 With 40” Stroke Cylinders

14’ Frame Skid Shown

Page 26: Guided Boring Machine (GBM) Technical Manual

26

SPECIFICATIONSDimensions Height ............................... 96 in. (2,438 mm) Width ........................... 83.75 in. (2,127 mm) Length ......................... 107.5 in. (2,731 mm)Weight* ........................... 15,500 lbs. (7,031 kg)Fluid Capacities Fuel Tank ......................... 275 gal (1,041 L) Hydraulic Reservoir .............. 80 gal (303 L)Power Unit Six Cylinder Diesel Engine 250 HP (186 kW)

• Provides Hydraulic Power To Operate Jacking Frame • • Remote Pendant For In-Shaft Operation Control •

FEATURES• Assembly comes complete with the GBM P250D Power Pack, remote control pendant, 50 foot hydraulic hose set to connect hoses from the power pack to the GBM 4800 Series jacking frame, & standard tooling for pilot tube installation.• Standard tooling includes: pilot tube breakout tool, pilot tube scraper, pilot tube to reaming head adapter, steering head kit, guidance system, theodolite shaft stand, wrench set, and launch shaft breakout tool.• Access doors on one end for engine access and tooling storage area.• Powered by a six cylinder, liquid cooled, 250 HP tier III diesel engine.• Three load sense, variable volume piston pumps provide smooth efficient operation.• Remote control pendant with 50 feet of cable controls the engine functions in shaft.• Hydraulic hoses are stored on hose reels for ease of hose routing to jacking frame.• Quick coupler connections with lock for easy and secure hydraulic hoses at jacking frame.• The 25 gpm cooling circuit maintains hydraulic oil at low operating temperatures.• Hydraulic pressure gauges for monitoring jacking and rotation (auger drive & PCH cutter bit) systems pressure.• Sound insulation provides a low decibel noise level (75 dB).

Pumps Variable Piston Jacking ......... 0 to 26 gpm (0 to 98 L/min) Rotation: Auger .................0 to 60 gpm (0 to 227 L/min) Rotation: PCH Cutter Bit .................0 to 50 gpm (0 to 189 L/min) Operating Pressure (Maximum) Rotation ....................5,000 psi (34.475 mPa) Jacking ......................6,000 psi (41.368 mPa) Gear Pump (Cooling) ..... 25 gpm (95 L/min)

Power Pack - P250DPart No. FA40038F

GBM_P250DPowerPack, FA40038F

Breakout Tool Breaking Torque ..12,000 ft-lbs (16,272 N·m) Power Source ................................. 110 VACPilot Tube/Reaming Head Adapter .............4.15” OD x 3” ID Hex Core x 5” OD

* Weight does not include diesel fuel.

Page 27: Guided Boring Machine (GBM) Technical Manual

27 GBM_P250DPowerPack, FA40038F

Pilot tube breakout tool is used in the reception shaft to loosen the pilot tube joints.

Tooling StorageArea

Filtered Hydraulic Return Oil With Indicator

80 Gallon (303 L) Hydraulic Reservoir

The hydraulic reservoir includes an oil level and oil

temperature gauges.

Hose Reels For Ease Of Hose Management

Suction Line Hydraulic Shutoffs With Integral

Engine Starting Circuit

The remote pendant contains the engine tachometer, hourmeter, engine oil

pressure gauge, water temperature gauge, electronic engine speed control, and

ignition switch.

Six Cylinder, 250 HP Tier IIIDiesel Engine

Page 28: Guided Boring Machine (GBM) Technical Manual

28

SPECIFICATIONSDimensions (width x length x height) Theodolite Case ....... 12 x 19.5 x 12 in. (305 x 495 x 305 mm) Monitor Case .......... 15 x 24 x 10 in. (381 x 610 x 254 mm) Tablet Case ......... 11.5 x 13 x 6 in. (292 x 330 x 152 mm)

• Provides Line & Grade Accuracy For The GBM • • Designed Accuracy Of 1/4” At 400 Feet •

• Equipped With Remote Focus For Ease Of Operation •

FEATURES• The guidance system consists of a theodolite with remote focus, illuminated target, monitor assembly,

camera, lateral slide assembly, elevator column assembly, counterweight, alignment holder, bore sight laser, and protective cases.

• The theodolite is used to align and maintain line and grade with a designed accuracy of .25 inch up to 400 feet.• The replaceable battery powered, illuminated target is positioned in the steering head.• The video surveillance system consists of a 1.4 mega-pixel camera mounted on the theodolite which

transfers digital video of the illuminated target to the monitor.• The target image is computer enhanced and displayed on the monitor assembly.• The lateral slide and elevator column adjusts the micro calibration of the horizontal line and vertical grade.• In bright light conditions, an adjustable iris is provided to control the amount of light entering the lens

on the theodolite, thus enhancing the target image on the monitor.• The theodolite focus is controlled from the panel on the monitor assembly.• Monitor assembly has a higher image clarity in bright light than the previous tablet assembly.

Theodolite Accuracy ....... 5 sec (1.5 mgon) DINTarget .................................................. Red LEDBore Sight Laser ..........Visible Red Diode Laser Operation ............................ On/Off End Cap Power Supply ......... (3) 392 Button Batteries Construction ........................................ Brass

Guidance SystemPart No. FA47260F

GBM_GuidanceSys, A47260F

Page 29: Guided Boring Machine (GBM) Technical Manual

29

The monitor assembly contains the computer with an outdoor flat screen for viewing the illuminated target in the steering head. The target image can be adjusted with the gain, exposure, zoom, and image centering controls. You can also keep track of the number of pipes that have

been pushed into the drive with the on-screen pipe counter. The monitor assembly case can be used as a sun visor for

reducing the glare on the monitor screen.

GBM_GuidanceSys, A47260F

A retical light is attached to the counterweight for easy viewing of the cross hairs on the monitor. The brightness of this

light can be adjusted with the brightness control on the tablet assembly.

Replaceable Battery Powered Illuminated LED Target

The theodolite contains a dual digital display and key pad

for ease of setting and reading the telescope position. It has a

5 sec DIN accuracy for horizontal and vertical angles.

Bore Sight and Alignment Holderaids in the preliminary theodolite

line setup.

The 1.4 mega-pixel camera has built-in

variable gain, exposure, pan, and zoom to enhance

the viewing image.

Page 30: Guided Boring Machine (GBM) Technical Manual

30

• Multiple Steering Heads For Different Soil Conditions •• Lubrication Fluid Is Ported To The Steering Head •

• Lubrication Fluid Flows Through Steering Head For Cooling •

FEATURES• This kit includes the 30° (4” & 5” diameter), 45° and bullet steering heads, steering head adapter, air and

fluid connection adapter, steering head inner tube, and target holder. The steering head kit is stored in the P100Q, P150Q & P250D Power Pack.

• Lubrication fluid is ported to the steering head opposite the angled face to lubricate the outside of the pilot tube as it is advanced.• Lubrication fluid flows through passage in the steering head adapter to cool the target and steering head.• Check valve located in the assembly prevents ground water from entering the fluid passage in the dual wall pilot tubes.• Smooth body design reduces the jacking force during installation.• The inner tube can be purged of air or fluid by way of a check valve, located at target holder, using a special adapter to pressurize the passage.• Four steering heads are available for very soft/soft, medium density and very hard ground conditions.

SPECIFICATIONSDimensions Steering Head Kit ..48 x 48 in. (1,219 x 1,219 mm)30° SHead ...4 OD x 17.08 in. (102 OD x 434 mm)30° SHead ...5 OD x 17.08 in. (127 OD x 434 mm)45° SHead ...5 OD x 13.25 in. (127 OD x 337 mm)Bullet SHead ....5 OD x 15.87 in. (127 OD x 403 mm)SH Adapter..4.15 OD x 27.25 in. (105 OD x 692 mm)Air/Fluid Adapter ...4.13 OD 5.13 in. (105 OD x 130 mm)

WeightSteering Head Kit ...................... 205 lbs. (93 kg)30° (4”) Steering Head ............... 40 lbs. (18 kg)30° (5”) Steering Head ............ 50 lbs. (22.6 kg)45° Steering Head ................... 39 lbs. (17.7 kg)Bullet ........................................... 44 lbs. (20 kg)Steering Head Adapter ................ 44 lbs. (20 kg)Air/Fluid Connection Adapter . 12.5 lbs. (5.7 kg)

Steering Head KitPart No. FA40245F

GBM_SteeringHeadKit, A40245F

Page 31: Guided Boring Machine (GBM) Technical Manual

31 GBM_SteeringHeadKit, A40245F

30° (5” Dia.) Steering Head For Soft Or Low Blow Count Soil Conditions

“Bullet” Steering Head For Very Hard Or High Blow Count Ground Conditions

The tapered body displaces the soil in all directions as it advances through the ground.

45° Steering Head For Medium Density Ground Conditions

Steering Head Adapter and Housing for targetincludes a three inch hex connection for transfer of torque.

Double Pinned For Ease Of Changing Steering Heads

Area in blue illustrates the fluid path through the dual wall pilot tubes, around the target assembly, and out the porting in the steering head.

Area in red illustrates the air path through the inner tube of the dual wall pilot tube, around the target, and in the fluid cavity.

Area in green illustrates the air and fluid connection adapter. This adapter is installed on the last section of the pilot tube, to purge air through the inner tube for removing moisture from pipe, resulting in

improved target viewing.

Air

Fluid

30° (4” Dia.) Steering Head For Very Soft Or Unstable Soil Conditions

Air And Fluid Connection Adapter

Page 32: Guided Boring Machine (GBM) Technical Manual

32

SPECIFICATIONSLength, Pilot Tube (PT) ............ 30 in. (762 mm)Length, Pilot Tube (PT) ................. 60 in. (1.5 m)Length, PT With Cap & Plug 30” PT. ........................... 34.75 in. (883 mm) 60” PT .................................... 64.75 (1.65 m)Length of Assembly 30” (12 PT) .............................. 30 ft. (9.1 m) 60” (24 PT) ......................... 120 ft. (36.6 m)Tube Diameter (OD) ............... 4.1 in. (104 mm)Inner Tube Diameter (ID) ............. 2 in. (51 mm)Assembly Dimension (W x D x H) 30” 14 x 18 x 44.5 in. (356 x 457 x 1130 mm) 60” 70 x 26 x 40 in. (1778 x 660 x 1016 mm)

FEATURES• One assembly comes complete with twelve (30”) or twenty-four (60”) pilot tubes, caps, plugs, rack and lifting bar/lifting hoops.• Pilot tubes have 2.4 sq. in. of annular area to provide fluid passage.• Double o-ring seal at joints of inner tube.• Inner tube treated to resist corrosion which assures good seal at the mating surface to the o-rings.• Two inch ID to view the illuminated target for steering control.• Three thread start for fast assembly (one and a half turns to lock). Lock joints at 2,000 ft/lbs.• Joints tested to 12,000 ft/lbs. of rotational torque.• Cap and plug included with each pilot tube to protect threads and seals during transport and storage.• Pre-Lubricated threads for easy assembly.

Pilot Tube Weight 30” PT ....................................73 lbs. (33 kg) 60” PT ..................................135 lbs. (61 kg)Assembly Weight 30” PT ............................ 1,050 lbs. (476 kg) 60” PT ..........................3,900 lbs. (1,769 kg) Rotational Torque* .... 12,000 ft/lbs (16,272 N·m)Jacking Force ........................... 100 Ton (91 mt)Joint Lock Force ......... 2,000 ft/lbs (2,712 N·m) * TestedPT - Pilot Tube

• Provides Lubrication At Steering HeadDuring Pilot Tube Installation •

• Allows Visibility Of The Illuminated Target In Steering Head Section •

Dual Pilot Tubes & RackPart No. FA40255F (30”), FA44453F (60”)

GBM_DPilotTube&Rack, FA40255F

Page 33: Guided Boring Machine (GBM) Technical Manual

33

The area in yellow illustrates the fluid path through the dual pilot tubes to the steering head. The fluid flowing out the steering head and along

the side of the pilot tubes, reduces the ground friction on the pilot tubes. This fluid lubrication

reduces jacking force and rotational torque which makes longer drive distances possible. Pilot Tube Cap And Plug

Maintains clean lubrication of the thread joint between pilot tube use. Protects the o-ring

sealing on the inner tube while in storage. The thread joint can be lubricated as the pilot tubes

are removed so they are ready for the next drive.

Pilot tube cap and plug protects the threads during transport and storage.

Dual o-rings at the inner tube seals the connection between the pilot tubes.

The inner tube is treated to resist corrosion assuring a good seal at the

mating surface to the o-rings.

Each pilot tube contains a valve assembly that restricts the fluid from flowing during the installation of the next pilot tube. Fluid can be supplied from the launch shaft or the reception

shaft depending on the job requirements.

To lock and unlock the pilot tubes, two parallel dual slots are located on each end of the pilot tube to work

in conjunction with tooling on the jacking frame.

GBM_DPilotTube&Rack, A40255F

Page 34: Guided Boring Machine (GBM) Technical Manual

34

FEATURES• Assembly includes Akkerman Pilot Tube to TriHawk Adapter to work with TriHawk® drill bits I, III,

IV, V, and VI.• Dual wall pilot tubes provide a means to lubricate the head and remove cuttings from head back to

launch shaft.• Standard Akkerman GBM target positioned in the target housing of the pilot tube to TriHawk adapter.• A bentonite polymer must be added to cool the drill bit and suspend cuttings during transport from the

drilling bit to the launch shaft. The polymer fluid is pumped into the pilot tube annular space, through the pilot tube adapter then out through the TriHawk tooling bit port.

• Boltless modular design of the square-drive spline makes it easy to interchange drill bits.• TriHawk I drill bit is an aggressive cutting tool for boring in soft rock conditions up to 8,000 psi.• TriHawk III drill bit is the cutting tool for soft to medium rock up to 12,000 psi or cobble bores.• TriHawk IV drill bit is designed for glacial till, and heavy, overburden cobble or fractured rock.• TriHawk V drill bit provides unbeatable performance in round rock cobble, flat river stone, hardpan

and loose fill.• TriHawk VI drill bit bores medium to hard rock formations up to 18,000 psi.

• Steerable To Maintain Line & Grade Through Rock • • Drills Pilot Bore Measuring 5.75 In (146 mm) Diameter •

Pilot Tube Accessories - Rock DrillPart No. FA48099F (Pilot Tube To TriHawk® Adapter)

GBM_RockDrill, FA48099F

TriHawk IP0050-164

TriHawk IIIP0050-162

TriHawk IVP0050-161

TriHawk VP0050-160

TriHawk VIP0050-163

Page 35: Guided Boring Machine (GBM) Technical Manual

35

SPECIFICATIONSPump Length ................................. 13 in. (330 mm) Width ............................... 7.75 in. (197 mm) Height ................................... 8 in. (203 mm) Weight (With Oil) ................... 20 lbs. (9 kg) Max Pressure Output ...................... 5,000 psi

FEATURES• Assembly includes hydraulic pump with remote controller, jaw inserts, breakout tool assembly with

hydraulic cylinder and hydraulic plumbing.• Quick disconnects are used to connect remote hydraulic power supply to breakout tool.• Remote power pack comes with valve for extend/retract and neutral positions to control hydraulic

cylinder function of breakout tool.

• Provides Hydraulic Power To Loosen Pilot Tube Joints In Reception Shaft •

• Remote Controller For Ease Of Operation •

Power Unit Power Source .............. 110VAC, Two Stage, 1/4 HP, 60 Hz .............. 230VAC, Two Stage, 1/4 HP, 50 Hz Hydraulics ..............120 Cu-in/Min to 400 psi .........................10 Cu-in/Min to 5,000 psiBreakout Tool Weight ................................. 115 lbs. (52 kg) Breakout Torque Max. @ 5,000 psi...12,000 ft/lbs (16,272 N·m)

Pilot Tube Accessories - Breakout ToolPart No. FA40230F (110VAC 60 Hz), A45440A (230VAC 50 Hz)

GBM_BreakoutTool, A40230F

1. Attach hydraulic hoses

2. Install jaw insert

3. Install opposite jaw insert4. Slide breakout tool over inserts

5. Select extend

6. Extend breakout tool cylinder

Page 36: Guided Boring Machine (GBM) Technical Manual

36

Notes

Page 37: Guided Boring Machine (GBM) Technical Manual

37

SPECIFICATIONSDimensions Height ....................................37.13 in. (943 mm) Width ....................................62.3 in. (1,582 mm) Length .................................57.84 in. (1,469 mm)Weight ..........................approx. 4,800 lbs. (2,177 kg)

Dirt Paddle ..................................................... 2 ScoopDrive Shaft .................................. 5 in. (127 mm) hex

• Designed For Use With GBM 4800 Series Thrust Frame • • 36” OD With Maximum 100,000 Ft-Lb Torque •

• Maximum 530,000 Lb Jacking Force •

FEATURES• Auger boring adapter assembly with integral thrust bearing and planetary gear box.• Eliminates the requirement of an auger boring rig on job site.• Wear strips on frame to reduce friction and wear on rail.• Bi-fold door restricts access to dirt paddles.• Quick mounts allow for swift changeover from pilot tubes.• Lift eyes provide easy handling of assembly.

Drive System Thrust Bearing Gear Ratio ........................ 4.17:1 Output Torque (Max)...43,800 ft-lb/108,400 ft-lb Speed/Output Torque ...8.5 rpm @ 100,000 ft-lb, ....11 rpm @ 75,000 ft-lb, 19 rpm @ 41,000 ft-lb Diameter .................................... 36 in. (914 mm) ODDirt Chute .............................................. Bi-Fold Door

Upsize Tooling - Auger Boring Adapter 36/530Part No. FA48180F

GBM_AugerBoringAdapter, FA48180F

62.32

48.0057.84

ø 37.13

Page 38: Guided Boring Machine (GBM) Technical Manual

38

SPECIFICATIONSSwivel Dimensions (width x length) 11” OD ...... 12.5” OD x 43” (318 x 1,092 mm) 16” OD HD..17.5” OD x 43” (444 x 1,092 mm) Weight (approx.) 11” OD .................................. 700 lbs. (318 kg) 16” OD HD ........................ 1,200 lbs. (544 kg)

FEATURES• The swivel cutter head is the upsizing tool between the pilot tube adapter and the lead thrust casing for

hard ground conditions.• Cutter head allows pilot tubes to remain stationary while the cutting teeth rotate through ground at a full

12.5” (318 mm) OD for the 11” OD head or 17.5” (445 mm) OD for the 16” OD swivel cutter head.• Cutter head equipped with fluid ports at the cutter bit reducing cutting torque through lubrication.• Spoils removed using standard Akkerman augers and casings.• No external swivel necessary.• Internal bearings are serviceable for extended life.

Swivel filled with Mobilgear 600 XP 600 gear oil ONLY. DO NOT USE GREASE!

• Designed For Hard Ground Conditions Leading The Auger/Thrust Casings •

• Keeps Pilot Tubes Stationary While Cutter Bit Rotates •• Sized To Match Product Pipe Diameter •

Thrust Capacity 11” OD Working Continuous Load ................ 35 Ton Maximum Intermittent Load ............. 70 Ton 16” OD HD (heavy duty) Working Continuous Load ................ 50 Ton Maximum Intermittent Load ........... 100 Ton

Upsize Tooling - Integral Bearing Swivel CutterPart No. FA44634F (11” OD), FA44723F (16” OD HD)

GBM_SwivelCutterHd, FA44634F

11” OD Swivel

16” OD Swivel

Page 39: Guided Boring Machine (GBM) Technical Manual

39 GBM_SwivelCutterHd, FA44634F

The swivel cutter head allows the pilot tubes to remain stationary while the cutting teeth rotate through the ground at a full 12.5” (318 mm) OD or 17.5” (445 mm) OD cut (depending on cutter

head). The spoils are removed using the standard Akkerman augers and casings to the launch shaft.

Pilot TubeEnd

Spoils removed to the launch shaft.

Swivel Cutter Head

A fluid connector is equipped on the swivel cutter head permitting lubrication of the

spoils to reduce jacking forces. Cutter head with drag and conical bullet bits.

Swivel cutter head casing and

auger mates to the standard Akkerman 11” (279 mm) OD casings and augers.

For efficient and productive operation of the swivel cutter head, there must be a minimum

jetting supply of 16 gal @2,500 psi.

Page 40: Guided Boring Machine (GBM) Technical Manual

40

SPECIFICATIONSReaming Head Shipping Dimension 11” OD ..... 12.5 x 51.5 in. (318 x 1,308 mm) 12” OD ........ 13 x 51.5 in. (330 x 1,308 mm) 14” OD ........ 15 x 51.5 in. (381 x 1,308 mm) 16” OD ........ 17 x 51.5 in. (432 x 1,308 mm) 16” OD HD .. 17.5 x 55 in. (445 x 1,397 mm)Dirt Bucket Capacity ...........................8, 9.2, 15.7, 16, & 32 ft3

Dirt Bucket Weight Single Stage ...186 or 320 lbs. (84 or 145 kg) Latching ....... 200 to 460 lbs. (91 to 209 kg)

FEATURES• Reaming head assembly is the upsizing tool between the last pilot tube section and the lead thrust auger/casings allowing the spoils to be removed from the pipeline. Recommended for up to 35 blow count ground density.• The reaming head assembly is equipped with a fluid connector which permits lubrication of the lead casing to reduce jacking forces.• Casing thrust adapter installs onto the thrust plate of the GBM for jacking the thrust auger/casing assemblies.• Auger drive adapter is mounted at the gear box/thrust block to rotate the augers while jacking.• Dirt buckets are available in different sizes and capacities for job requirements.

• Upsizing Tool Designed For 100/200* Ton Capacity • • Reaming Head Sized To Match Product Pipe Diameter •

Reaming Head Assembly Weight 11” OD ............................... 295 lbs. (134 kg) 12” OD ............................... 314 lbs. (143 kg) 14” OD ...............................367 lbs. (267 kg) 16” OD .............................. 424 lbs. (192 kg) 16” OD HD ....................... 590 lbs. (268 kg)

* 200 ton capacity for 16” OD HD casing only

Upsize Tooling - Reaming Head AssemblyPart No. FA40304F (11”OD), FA40284F (12”OD), FA40324F (14”OD), FA40344F (16”OD - 2” Hex Auger), FA43804F (16”OD HD - 3” Hex Auger)

GBM_ReamingHead, A42110-13F

Page 41: Guided Boring Machine (GBM) Technical Manual

41 GBM_ReamingHead, A42110-13F

Dirt Buckets Are Available In Various

Capacity Sizes8, 9.2, 15.7, 16, & 32

Cubic Feet

Casing Thrust Adapter Sized Specific For The Diameter Of The Casing

Connecting Reaming Head With 3” Hex Adapter To Pilot Tubes With 5/8” Spiral Pins

Reaming Head Is Equipped With Four Lubrication Ports To Reduce Jacking Force On The Casings

Auger Drive Adapter Connects The Jacking Frame Auger Drive To The

Auger Assembly

Larger Capacity Buckets Are Required

For Larger Diameter Pipe

Page 42: Guided Boring Machine (GBM) Technical Manual

42

FEATURES• Cutter head assembly is the upsizing tool between the pilot tube swivel and the lead thrust auger/casing

allowing the spoils to be removed from the pipeline.• Casing thrust adapter installs onto the thrust plate of the GBM for jacking the thrust auger/casing assembly.• Auger drive adapter is mounted at the gear box to rotate the augers while jacking.• Dirt buckets are available in different sizes and capacities for your job requirements.

• Upsizing Tool Designed For 100 Ton Capacity • • Cutter Head Sized To Match Product Pipe Diameter •

SPECIFICATIONSCutterhead Shipping Dimension 11” OD .............. 12 x 38 in. (305 x 965 mm) 12” OD .............. 13 x 38 in. (330 x 965 mm) 14” OD .............. 15 x 38 in. (381 x 965 mm) 16” OD .............. 17 x 38 in. (432 x 965 mm)Dirt Bucket Capacity ...........................8, 9.2, 15.7, 16, & 32 ft3

Dirt Bucket Weight Single Stage ..186 or 320 lbs. (84 or 145 kg) Latching ....... 200 to 460 lbs. (91 to 209 kg)

Cutter Head Weight 11” OD ............................... 265 lbs. (120 kg) 12” OD ............................... 285 lbs. (129 kg) 14” OD ...............................330 lbs. (150 kg) 16” OD .............................. 376 lbs. (171 kg)

Upsize Tooling - Cutter Head AssemblyPart No. FA40305F (11”OD), FA40285F (12”OD), FA40325F (14”OD), FA40345F (16”OD)

GBM_CutterHead RevC

Page 43: Guided Boring Machine (GBM) Technical Manual

43 GBM_CutterHead RevA, A42121-24F

Dirt Buckets Are Available In Various

Capacity Sizes8, 9.2, 15.7, 16, & 32

Cubic Feet

Casing Thrust Adapter Sized Specific For The Diameter Of The Casing Auger Drive Adapter Connects The 3” Hex In

The Gear Box To The Auger Assembly

Larger Capacity Buckets Are Required

For Larger Diameter Pipe

Open Face Cutter Head Is Used In Harder Ground

Conditions Than The Reaming Head

Takes Less Jacking Force To Advance Through

Ground

Excavator Teeth Are Standard Equipment

(shown)

Optional Teeth Are Available

Page 44: Guided Boring Machine (GBM) Technical Manual

44 GBM_ThrustCasing

SPECIFICATIONSAuger & Casing Weight 11” OD ................................258 lbs. (109 kg) 16” OD ...............................399 lbs. (175 kg) 16” OD HD ........................841 lbs. (175 kg)

FEATURES• The thrust casing assembly includes augers, casings, retaining clips and wire basket.• The standard casings with two inch hex augers are designed to withstand 100 ton jacking force while the 16”OD HD casing with three inch hex augers are designed to withstand 265 ton jacking force with the 4800 Series jacking frame.• Augers constructed of 1/2 inch auger flighting with an 8 inch or 10 inch (16” OD HD) pitch.• Retaining clips lock thrust casings together.• Designed to match the size of product pipe/powered cutter head.

• Withstands 100/265* Ton Jacking Force • • Casings Designed To Match Product Pipe Diameter •

Casing Length 11” & 16” OD .................. 41.85 in. (1.06 m) 16” OD HD ........................ 62.5 in. (1.59 m)

Auger Installed Length 11” & 16” OD ...................... 43.4 in. (1.1 m) 16” OD HD ............................. 60 in. (1.5 m)

* 265 ton capacity for 16” OD HD casing onlyHD - Heavy Duty

Upsize Tooling - Thrust Casing AssemblyAvailable in: 11” OD, 16” OD and 16” OD HD

Page 45: Guided Boring Machine (GBM) Technical Manual

45 GBM_ThrustCasing

Installing Retaining Clips To Lock Casings

1/2” Auger Flighting With 8” Pitch (2” Hex) or 10” (3” Hex)

2 or 3 Inch Hex Connector Bolted To Auger

Wire Basket Carries Augers & Casings.

Retaining Clips To Match Casing Sizes

Page 46: Guided Boring Machine (GBM) Technical Manual

46 GBM_PRH, FA46720F

• Designed To Work in 96” Minimum ID or Trenchbox Shafts • • Auger Drive For Spoil Removal To Reception Shaft •

• Controlled By GBM Operator In Launch Shaft •

SPECIFICATIONSAssembly Length*

Thrust Casing • (from transition casing end to rear of PRH housing) All Models ....................... 68 in. (1,727 mm) • (from auger end to rear of PRH housing) All Models ....................... 72 in. (1,829 mm)

Diameter Powered Reaming Head Body 10.5k Drive ....14 - 20 in. (356 - 508 mm) 20k Drive .......20 - 30 in. (508 - 762 mm) 26k Drive ....30 - 48 in. (762 - 1,219 mm)

Drive System Auger Drive 10.5k (PRH 14 - 20) Max. Torque ..10,500 ft/lbs (14,236 N·m) Hydraulics .............. 34 gpm @ 5,000 psi Max. Speed ................................ 40 rpm

Auger Drive 20k (PRH 20 - 30) Max. Torque .. 20,000 ft/lbs (27,116 N·m) Hydraulics .............. 60 gpm @ 5,000 psi Max. Speed ................................ 38 rpm

Auger Drive 26k (PRH 30 - 48) Max. Torque .. 26,000 ft/lbs (35,251 N·m) Hydraulics .............. 60 gpm @ 5,000 psi Max. Speed ................................ 26 rpm

FEATURES• The Powered Reaming Head (PRH) Series II is an upsizing kit that can be configured from 14” to 48” OD.

For custom sized PRH to match your specific product pipe requirements, contact Akkerman.• Separate jetting lines at overcut ring to lubricate spoils and separate lubrication lines on rear section to

reduce jacking forces on pipe.• Operates with standard jacking frame and P100Q/P150Q/P250D power units.• Spoils are discharged to reception shaft. • Product pipe length does not change tooling.• Product pipe length dependent only on shaft size. • Replaceable teeth.• Uses standard GBM 11” OD or 16”HD OD thrust casings.

Upsize Tooling - Powered Reaming Head Series IIPart No. FA46720F (14” - 16” - 20” OD), FA48030F (20” - 30” OD),

FA47301F (30” - 48” OD)

Page 47: Guided Boring Machine (GBM) Technical Manual

47 GBM_PRH, FA46720F

Jetting Ports (2) On Reaming Head Arms

Lubrication Ports (3) On Rear Section

Auger Chamber Shears Spoils Away From Cutting Ring To

Reduce Jacking Forces

GUIDED BORING METHOD WITH POWERED REAMING HEAD

Step 1: PRECISE INSTALLATION OF PILOT TUBESThe first step is the installation of the pilot tube on line and grade.

Step 2: ADVANCING THRUST CASINGS ALONG PILOT TUBE PATHThe second step is to follow the pilot tube with a reaming head or other upsizing tool and standard 11” OD thrust casings.

Step 3: INSTALLATION OF PRODUCT PIPE WITH POWERED REAMING HEADIn the third step, the powered reaming head follows the thrust casings to increase the bore to match the product pipe diameter.

Page 48: Guided Boring Machine (GBM) Technical Manual

48

SPECIFICATIONS Length ......................................... 49” (1,245 mm)Diameter .................................. 16” (406 mm) ODOvercut ........................................ 17.5” (445 mm)Weight (approx.) .................... 1,500 lbs. (680 kg)

FEATURES• The Eliminator is the lead pilot tool for non-displaceable ground conditions.• Three independent steering control devices to maintain line and grade.• Cutter head equipped with jetting nozzle to increase cutting performance and ease of spoil removal.• Steerable cutter head allows a two step process to install product pipe, eliminating the requirement to

install pilot tubes for the initial bore.• Optically guided with the equipped replaceable battery powered illuminated LED target to maintain line

and grade accuracy, and monitored with the standard Akkerman GBM guidance system.• Hollow center augers required for line of sight to target.• Spoils removed using standard Akkerman 16” casings.• Works with Akkerman GBM jacking frames.• For optimum performance, the Eliminator requires 80 HP of hydraulic input horsepower.

• Designed For Non-Displaceable Soils • • Two Step Process To Install Product Pipe •

Minimum Jacking Force ......................... 20 TonRotational Torque .............. 10,500 - 21,000 ft-lb (14,238 - 28,476 N·m)Hydraulic Operating Pressure For Controllers ..................... Up to 4,000 psi (Up to 27,580 kPa)

Pilot Cutter Tooling - EliminatorPart No. FA46820F (16” OD)

GBM_FlatFaceCutterHd, FA46400F

Hollow Center Auger Installed Length 16” OD HD ........................... 39.37 in. (1 m) 16” OD HD ......................... 60 in. (1.525 m)

Hollow Center Auger Weight (approximate) 39.37 in. (1 m).length ..............152 lb. (69 kg) 60 in. (1.525 m) length .........232 lb. (105 kg)

Page 49: Guided Boring Machine (GBM) Technical Manual

49 GBM_FlatFaceCutterHd, FA46400F

Hollow Center Auger

Cutter head with conical bullet bits.

Replaceable Battery Powered Illuminated LED Target Visible Through Hollow Center Augers

Jetting Nozzle

Independent Steering Controllers

Hydraulic, Jetting & Electrical Connecting Ports

Page 50: Guided Boring Machine (GBM) Technical Manual

50 GBM_PCH, FA42850F

• Designed To Work in 96” Minimum ID or Trenchbox Shafts • • Independent Drives For Rotation & Spoil Removal •

• Controlled By GBM Operator In Launch Shaft •

SPECIFICATIONSAssembly Length ................... 72 in. (1,829 mm) Two sections may be launched separately Diameter Powered Cutter Head Body PCH 20 .......................... 20 in. (508 mm) PCH 22.5 .................... 22.5 in. (572 mm) PCH 30.5 .................... 30.5 in. (775 mm) Overcut ................................ 1.5 in. (38 mm) Weight (approximate) Front Section PCH 20 ...................1,800 lbs. (816.5 kg) PCH 22.5 ...................2,000 lbs. (907 kg) PCH 30.5 ................3,500 lbs. (1,588 kg) Rear Section PCH 20 .........................900 lbs. (408 kg) PCH 22.5 ...................1,000 lbs. (454 kg) PCH 30.5 ...................2,200 lbs. (998 kg)

Drive System Auger Drive Max. Torque ....10,500 ft-lbs (14,238 N·m) Max. Speed ................................. 40 rpm

Cutterface Power PCH 20 ............................32 HP (24 kW) PCH 22.5 ........................ 48 HP (36 kW) PCH 30.5 ...................... 61 HP (45.5 kW)

FEATURES• The PCH 20 is an upsizing tool to match 20” product pipe (15” VCP). Increaser kits available to 22.5” OD.• The PCH 22.5 is an upsizing tool to match 22.5” product pipe (18” VCP). Increaser kits available to 28” OD.• The PCH 30.5 is an upsizing tool to match 30.5” product pipe (24” VCP). Increaser kits available to 36” OD.• Separate lubrication lines on cutter head reduce jacking forces on pipe and lubricate cutter face for ease of spoils removal.• Operates with standard jacking frame and P100Q/P150Q power unit with minimal modifications to jacking frame hydraulics.• Spoils are discharged to reception shaft. • Product pipe length does not change tooling.• Product pipe length dependent only on shaft size. • Uses standard GBM 11” OD thrust casings.

Upsize Tooling - Powered Cutter HeadPart No. FA43100F (Model PCH 20), Part No. FA42850F (Model PCH 22.5), FA47952F (Model PCH 30.5)

Page 51: Guided Boring Machine (GBM) Technical Manual

51 GBM_PCH, FA42850F

Powered Cutter Head In Launch Position

Spoils Discharged In Reception Shaft

Drive Complete With Powered Cutter Head In Reception Shaft

GUIDED BORING METHOD WITH POWERED CUTTER HEAD

Step 1: PRECISE INSTALLATION OF PILOT TUBESThe first step is the installation of the pilot tube on line and grade.

Step 2: ADVANCING THRUST CASINGS ALONG PILOT TUBE PATHThe second step is to follow the pilot tube with a reaming head or other upsizing tool and standard thrust casings.

Step 3: INSTALLATION OF PRODUCT PIPE WITH POWERED CUTTER HEADIn the third step, the powered cutter head follows the thrust casings to increase the bore to match the product pipe diameter.

Page 52: Guided Boring Machine (GBM) Technical Manual

52 GBM_PCH36-44, FA44400F-FA43400F

• Designed To Work in 144” Minimum ID or Trenchbox Shafts • • Independent Drives For Rotation & Spoil Removal •

• Controlled By GBM Operator In Launch Shaft •

SPECIFICATIONSAssembly Length ................... 91 in. (2,311 mm) Two sections may be launched separately

Diameter Powered Cutter Head Body PCH 36 ....................36 in. (914 mm) OD PCH 44 .................44 in. (1,118 mm) OD Overcut ................................ 1.5 in. (38 mm)

Weight (approximate) Front Section PCH 36 ...................4,300 lbs. (1,955 kg) PCH 44 ...................6,500 lbs. (2,955 kg) Rear Section PCH 36 ...................3,000 lbs. (1,364 kg) PCH 44 ...................4,500 lbs. (2,045 kg)

Drive System Auger Drive Max. Torque ..26,000 ft-lbs (35,250 N·m) Max. Speed ................................. 38 rpm

Cutterface Power PCH 36 ........................... 79 HP (59 kW) PCH 44 ........................... 93 HP (69 kW)

FEATURES• The PCH 36 is an upsizing tool to match 36” OD product pipe (30” VCP). Increaser kits available to 44” OD.• The PCH 44 is an upsizing tool to match 44” OD product pipe (36” VCP). Increaser kits available to 48” OD.• Independent ports for pipe lubrication reduces jacking forces on pipe.• Four jetting nozzles to the cutter face increases cutting performance and ease of spoil removal.• Operates with the 4812A/4800 Series jacking frame and P250D power pack.• Spoils are discharged to reception shaft. • PCH equipped with hydraulic dirt wing to • Designed to work with up to two meter pipe. prevent rolling. • Uses 16” OD heavy duty thrust casings.

Upsize Tooling - Powered Cutter HeadPart No. FA44400F (Model PCH 36), Part No. FA43400F (Model PCH 44)

Page 53: Guided Boring Machine (GBM) Technical Manual

53

GUIDED BORING METHOD WITH POWERED CUTTER HEAD

Step 1: PRECISE INSTALLATION OF PILOT TUBESThe first step is the installation of the pilot tube on line and grade.

Step 2: ADVANCING THRUST CASINGS ALONG PILOT TUBE PATHThe second step is to follow the pilot tube with a reaming head, or other upsizing tool and standard thrust casings.

Step 3: INSTALLATION OF PRODUCT PIPE WITH POWERED CUTTER HEADIn the third step, the powered cutter head follows the thrust casings to increase the bore to match the product pipe diameter.

GBM_PCH36-44, FA44400F-FA43400F

Page 54: Guided Boring Machine (GBM) Technical Manual

54

• Upsizing Tool Designed For Auger Boring Machine • • Reaming Head Sized To Match Steel Casing Diameter •

Upsize Tooling - Weld-On Reaming HeadSingle Stage Sizes: 12”, 14”, 16”, 18”, 20”, 22”, 24”, 28”, 30” and 36”

GBM_Weld-OnReamingHead_SingleStage

SPECIFICATIONSAssembly Length 22” & Below .......... Up to 75 in. (1,905 mm) 24” & Above ........ Up to 116 in. (2,946 mm)

Reaming Head Weight (approximate) 12” ..................................... 405 lbs. (184 kg) 14” ..................................... 420 lbs. (191 kg) 16” .....................................440 lbs. (200 kg) 18” ..................................... 452 lbs. (205 kg) 20” ...................................... 465 lbs. (211 kg)

FEATURES• The weld-on reaming head is the upsizing tool between the pilot tube adapter/10’pilot tube section and

the steel casings (customer supplied), allowing the spoils to be removed from the pipeline via auger boring machine.

• Structure designed to withstand jacking forces applied by auger boring machine.• Reaming head contains a 1.5” overcut of the casing OD.• The reaming arms are designed to be flush with the ID of the steel casing so the auger/cutter bit can be

positioned for ease of spoil removal.

22” .....................................476 lbs. (216 kg) 24” ..................................... 490 lbs. (222 kg) 28” ......................................530 lbs. (240 kg) 30” ..................................... 550 lbs. (249 kg) 36” .................................... 1600 lbs. (726 kg)

Page 55: Guided Boring Machine (GBM) Technical Manual

55

• Upsizing Tool Designed For Auger Boring Machine • • Reaming Head Sized To Match Steel Casing Diameter •

Upsize Tooling - Weld-On Reaming HeadTwo Stage Sizes: 24 to 42”, 24 to 48”, 24 to 54”, 24 to 60”, 30 to 54”,

30 to 60”, 30 to 66”, 30 to 72”, & 36” to 72”

GBM_Weld-OnReamingHead_TwoStage

SPECIFICATIONSAssembly Length ........................Varies per head

Reaming Head Weight (approximate) 24 to 42” .......................... 1,488 lbs. (675 kg) 24 to 48” .......................... 1,763 lbs. (800 kg) 24 to 54” ...........................1,858 lbs. (843 kg) 24 to 60” ...........................2,100 lbs. (953 kg)

FEATURES• The two stage weld-on reaming head is the upsizing tool between the single stage weld-on reaming

head and steel casings (customer supplied), allowing the spoils to be removed from the pipeline via auger boring machine.

• Structure designed to withstand jacking forces applied by auger boring machine.• Reaming head contains a 1.5” overcut of the casing OD.• The reaming arms are designed to be flush with the ID of the steel casing so the auger/cutter bit can be

positioned for ease of spoil removal.

30 to 54” .......................... 2,034 lbs. (923 kg) 30 to 60” ...........................2,126 lbs. (964 kg) 30 to 66” ........................2,270 lbs. (1,030 kg) 30 to 72” ...................... 2,414 lbs. (1,095 kg) 36 to 72” ...................... 2,700 lbs. (1,225 kg)

Page 56: Guided Boring Machine (GBM) Technical Manual

56

SPECIFICATIONSDimensions: Height .............................. 64 in. (1,625 mm) Width ........................... 86.75 in. (2,205 mm) Length .............................. 93 in. (2,360 mm) Weight (empty tanks) ... 3,150 lbs. (1,429 kg) (full tanks) ... 8,300 lbs. (3,765 kg)Power Unit: Diesel Engine @ 3,500 rpm ...34 HP (25.5 kW) Electric Motor @ 1,750 rpm ..30 HP (22.5 kW) Drive System: Belt Direct Driven from Engine to Jetting PumpFluid Capacities Fuel Tank ................................ 18 gal. (68 L) Jetting Tank ....................... 325 gal (1,230 L) Lubrication Tank ............... 325 gal (1,230 L) Hydraulic Tank ..................... 25 gal (94.6 L)

• Designed For GBM Jetting & Lubrication Operation • • Independent Pumps For Jetting & Lubrication System •

• Adjustable Pump Pressure & Flow •

Pump Units Jetting Pump (Two): ................... Piston pump Pump Flow Pump 1 ............... 8 gpm (0 - 30 L/min) Pump 1 & 2 ..... 16 gpm (0 - 60 L/min) Speed ..........................................1,725 rpm Max. Pressure Rating .. 2,500 psi (17,237 kPa) Lubrication Pump With Agitator: .................................Progressive cavity pump Pump Flow .....................4 gpm (15 L/min) Speed .............................................550 rpm Max. Pressure Rating ...150 psi (1,034 kPa) Agitator (bidirectional) ................ 1050 rpm

FEATURES• Independent flow control.• Bulkhead connections for pressure and return lines.• In tank agitator keeps mixture from settling in lubrication tank.• Open/close valve at tank outlet.• In-line suction strainer to jetting pump.• The 2325E is designed to be used with a 480 V power supply.

2325D/2325E Jetting & Lubrication PumpPart No. FA45103F (2325D), FA45914F (2325E)

GBM_JettingLubePump, FA45103F

Model 2325D Shown

Page 57: Guided Boring Machine (GBM) Technical Manual

57

Agitator, Lube Pump and Jetting Volume Controls

Separate 325 gallon (1,230 L) tanks for lubricant and jetting. Large opening

for ease of filling.

Fuel 18 gal (68 L) and Hydraulic 25 gal (94.6 L)Tanks

GBM_JettingLubePump, FA45103F

Jetting Piston Pump (2)8 or 16 gpm @ 2,500 psi Maximum

34 HP @ 3,500 rpm Diesel Engine (2325D)

Open/Close valve at tank outlet.

30 HP @ 1,750 rpm Electrical Motor (2325E)

Electrical Controls (2325E)

Page 58: Guided Boring Machine (GBM) Technical Manual

58

SPECIFICATIONSDimensions: Height .............................. 58 in. (1,473 mm) Width ................................ 43 in. (1,092 mm) Length ......................... 88.25 in. (2,242 mm) Weight (empty tanks) ...... 1,000 lbs. (454 kg) (full tanks) ... 3,700 lbs. (1,678 kg)

Power Unit: Gasoline Engine @ 3,600 rpm .. 14 HP (10.4 kW)

Pump Units Jetting Pump Pump Flow ...................7 gpm (26.5 L/min) Speed (Max.) ...............................1,750 rpm Max. Pressure Rating .. 2,000 psi (13,790 kPa)

• Designed For GBM Lubrication Operation & Productive In Other Lubrication Applications •• Compact Footprint For Job Site Positioning •

Drive System .................................. Direct Drive

Agitator .................................................. In-Tank

Fluid Capacities Fuel Tank .............................. 1.9 gal. (7.3 L) Jetting Tank ...................... 325 gal. (1,230 L) Engine Oil ............................... 1.16 qt. (1 L) Jetting Pump ..........................15 oz. (444 ml) Gear Box ............................. 7.4 oz. (219 ml)

FEATURES• Bulkhead connections for pressure and return lines.• In tank agitator keeps mixture from settling in tank.• Open/close valve at tank outlet.• In-line suction strainer to jetting pump.• Sized for container storage during cold weather operation.

1325G Lubrication PumpPart No. FA47850F

GBM_LubePump, FA47850F

Page 59: Guided Boring Machine (GBM) Technical Manual

59

Fluid Bypass Control

A 325 gallon (1,230 L) tank for lubricant solution. Large opening

for ease of filling.

Pressure Gauge2,000 psi Maximum

GBM_LubePump, FA47850F

Jetting Pump7 gpm @ 2,000 psi Maximum

14 HP @ 3,600 rpm Gasoline Engine With Electric Start

Open/Close valve at tank outlet.

Page 60: Guided Boring Machine (GBM) Technical Manual

58256 266th Street Brownsdale, MN 55918 |USA