GRP Hydrotesting 01.docx

Embed Size (px)

Citation preview

  • 7/28/2019 GRP Hydrotesting 01.docx

    1/12

    ENI MOD

    1. PIPELINES PRECOMMISSIONING

    1.1 PURPOSE

    The purpose of this document is to establish the minimum functional requirements, to

    ensure the correct development of the final hydrostatic tests and their associated activities

    in the scope of this procedure.

    The purpose of the hydrostatic pressure test is to verify the mechanical strength of the pipe

    and piping system components after their construction and ensures they are leak free and

    suitable to content and transport the fluid(s) for which they have been designed.

    1.2 SCOPE

    This procedure covers the activities and requirements required to prepare and perform the

    pressure testing of the newly constructed Pipe lines for ENI MOD in accordance with the

    Project Specifications and Company Approved Standards.

    The newly constructed Pipeline facilities are the following:

    No Mat.Diam. Length

    Qty

    Total

    LengthVolumen

    HT

    Water

    Source

    Remarks

    (Inch) mm (mt) (mt) (mt

    3

    )1 GRP 40 1,016.0 300 2 600 486.44 WI Direct

    2 GRP 28 711.2 19,000 3 57,000 22,643.74 WI Direct

    3 GRP 24 609.6 30,000 2 60,000 17,511.81 WI Through No 2

    4 CS 24 609.6 1,500 1 1,500 437.80 WI Through No 2

    5 CS 20 508.0 2,000 1 2,000 405.37 WI Through No 2

    6 CS 20 508.0 6,500 1 6,500 1,317.44 WI Through No 2

    Water from WI must be filtered (100 m)

    1.3 HYDROSTATIC TEST WATER

    Primary impacts associated with the abstraction of water are potential ground water

    extraction and modification of stream flows. Secondary issues include minimizing erosion at

    intake locations and prevention of fish entrainment into pump suction intakes. Social

  • 7/28/2019 GRP Hydrotesting 01.docx

    2/12

    impacts can also be a concern where water is in short supply and abstraction of water could

    impact water supplies remaining for the community.

    As a common practice no ground water must be abstracted for hydrostatic test use. Water

    is extracted from significant water sources such that ground water tables and river flows are

    not affected. As a guideline, a maximum abstraction rate of approximately 10% of water

    flow in a river or channel could be adopted during water abstraction so as not to have a

    significant impact on environmental systems. Additionally, the maximum water abstraction

    rate will be subject to assessment to confirm that other users of the supply will not be

    adversely affected. Agreement will be required with the water authority and the

    environmental regulator, and the relevant permits obtained.

    1.3.1 Water Source

    The immediate body of water available for the project is located north of the pre-treatment

    plant in the same water intake of the MOD project.

    1.3.2 Pre-fill Water Quality

    Prior to abstraction of hydro-test waters from a source, a water quality analysis will be

    conducted to confirm its quality. Samples will be collected and analyzed by an approved

    independent laboratory. Field exit water analysis will be conducted at discharge locations to

    determine iron Fe levels.

    Specifically for Metallic Pipelines with not protective linings, the key parameters and quality

    standards required for the hydro test water are:

    pH 6.5 to 10.5

    Total Dissolved Solids Less than 30 Kg/m3

    H 2 S Nil

    Suspended Solids 0.005 Kg/m3

    Appearance I Turbidity Clear with no visible

    sediment

  • 7/28/2019 GRP Hydrotesting 01.docx

    3/12

    1.3.3 Water Treatment

    In the past, the generally accepted industry practice was to treat all water entering a

    pipeline to prevent corrosion. Due to environmental concerns, the current accepted industry

    practice is to avoid the use of chemical additives, except under circumstances where the

    test water will remain in the pipeline for a period exceeding one month. This practice is

    based on the fact that once initial corrosion occurs, the corrosion creates a very thin layer of

    rust, and oxygen-induced corrosion will gradually be diminished. The remaining risk to the

    pipeline will be predominantly due to the presence of microbiological organisms (e.g. sulfate

    reducing bacteria (SRB) and acid reducing bacteria (ARB)).

    Should implementation of chemicals for water fitness be required then all test results,

    recommended inhibitor type and dosages shall be sent to the Companys representative for

    approval prior to start of filling operation.

    40, 28 & 24 GRP pipelines have a high resistance to corrosion and the component resins

    are resistance to pH values from 1 to 10; therefore the addition of chemicals, if required, will

    be only considered and evaluated for the hydrotest water to be use in 20 and 24 Carbon

    Steel Pipelines.

    For CS Pipelines the final chemical dosage rates will be determined following a water

    analysis from the proposed sources taken no earlier than 3 month before operations. Any

    water system that contains sulphate has the potential to support the growth of sulphate

    reducing bacteria. The problem is not so much the bacteria themselves but rather the

    production of corrosive hydrogen sulphide and carbon dioxide gases caused by their

    metabolic pathway.

    The decision to use chemical treatment will depend on the water analysis and the duration

    the water will remain in the CS pipeline. Chemical treatment will be avoided 'wherever

    practicable, and especially for short residence time of the hydrotest water in the pipeline

    (i.e. less than one month), however when treatment should be necessary the use of

    inhibitors and chemicals will be subject to Company approval.

    1.3.4 Water Filtering

    Water taken from the point of project water intake will be filtered to remove all particles 100 mm

    and above.

  • 7/28/2019 GRP Hydrotesting 01.docx

    4/12

    1.4 FIELD HYDROTESTING

    1.4.1 General sequence of Pipelines Pre-Commissioning Activities

    Major activities to consider during the pre-commissioning of the GRP and CS Pipelines are

    as follows:

    a) Cleaning

    b) Gauging (Not Applicable for GRP Pipelines)

    c) Filling

    d) Hydrotesting

    e) Dewatering (Water could remain inside GRP Pipelines ready for operation)

    f) Drying (Not Applicable for GRP Pipelines)

    g) Lay-up (Water could remain inside GRP Pipelines ready for operation)

    Project schedule initiates with the GRP pipelines installation in sequence from water intake

    all the way to WPTP, WFTP and then to Basra Regulator.

    GRP pipelines will be flooded and hydrotested starting from the two portions connecting the

    water intake with the WPTP following with the three 28 GRP pipelines going to the WFTP.

    At this stage the water to fill and hydrotest the next sections will be supplied from the

    previous sections which conduct the water from Water Intake near WPTP.

    Short carbon steel pipelines and remaining two 24 GRP Pipelines will be prepared, flooded

    and hydrotested in their mechanical completion order according with the construction

    program.

    1.4.2 GRP Pipeline

    1.4.2.1 Water Filling, Flushing and Venting.

    Pipeline should be filled from the lowest point (level) and air should be expelled from the

    highest point (level) of the pipeline through air valves. Flow rate of filling should not exceed

    5-10 % of the pipeline nominal design flow rate. If it is not possible to fill the pipeline from

    the lowest point, additional air valves should be installed.

    Just like all other types of pipes, GRP pipelines should also be tested before taking the

    pipeline into operation.

  • 7/28/2019 GRP Hydrotesting 01.docx

    5/12

    Field tests can be performed with water for purpose to detect any leakage points through

    the pipeline.

    If the pipeline is tested as a whole, it is rather difficult to detect exact locations of leakages;

    it is also difficult and costly to fill / un-fill the whole pipeline. Therefore, the maximum

    recommended test lengths is1000m based on the pipeline conditions.

    Below points should be checked before water filling and field hydrotesting:

    a) Make sure that all truss blocks and rigid structures made of concrete has completed

    curing.

    b) Ensure that all testing equipment are functional and in good condition.

    c) Close and seal the ends of the pipeline section subject to testing with end caps.

    d) Ensure that end caps are supported with temporary anchors to resist test pressure.

    For visual inspection of the couplings during hydrotesting, 1/3 of top of the couplings are not

    backfilled.

    Safety precautions should be applied around the pipeline; if possible, tested section of the

    pipeline should be isolated from human access before starting hydrotest. After completion

    of the hydrotest, unfilled top sections of the couplings should immediately be filled with

    approved material.

    1.4.2.2 Pressure Testing.

    Below outlined method can be followed:

    Increase the pressure to 3 5 bar.

    Keep the pipeline under this pressure for 12 hours for stabilization.

    Shut off all air valves after ensuring that all air is expelled from the pipeline.

    After stabilization period, increase the pressure by 1 bar every 10 minutes.

    Perform continuous monitoring of the pipeline section especially the partially

    exposed joints

    Continue to increase the pressure (as explained above) until the applied pressure is

    1.5 times of the nominal operation pressure of the pipeline. (Field hydrotest pressure

    is defined as the 1,5 times of the nominal operation pipeline pressure)

  • 7/28/2019 GRP Hydrotesting 01.docx

    6/12

    Ensure to measure the test pressure referenced to the lowest point of the pipeline

    section.

    1.4.2.3 Allowable leakage

    Allowable leakage will be established as per project specifications and applicable standards

    (e.g. BS 8010: Part 2.5)

    1.4.2.4 Water Discharge

    There are a number of options for disposal of hydrotest water. These include disposal to

    temporary break tanks and/or holding ponds. The purpose of the break tanks is to dissipate

    energy. They will also assist in the reduction of suspended solids while holding ponds allow

    time for Chemicals Degradation. The holding pond will be constructed to enable

    evaporation, infiltration through a soak away or to allow water re-use dependent on site-specific circumstances.

    As feasible Test water for GRP pipeline will be discharged back into the water In Take. Exit

    water analyses will be conducted prior to any discharge to the environment.

    1.4.3 Carbon Steel Pipeline

    1.4.3.1 Cleaning and Gauging

    Each pipe length has been cleaned and ensured free of obstructions before and during the

    welding of the strings for lowering; additionally all the pipe strings have been kept capped to

    avoid any debris or animal to enter during the construction activities.

    Since CS pipelines in ENI-MOD Project have short lengths, the final cleaning and gauging

    could be performed from their start up to their end, along the entire pipeline. Bi-directional

    scrapers will be launched propelled with compressed air. Scrapers could be provided with

    steel wire brush to increase the removal of mill scale and debris left inside the pipeline.

    Cleaning and Gauging with scrapers propelled by air mainly removes bulk construction

    debris, such as skids, rocks, tools, welding rods, rags etc. Dust and fine sand are not easily

    removed by scrapers run with air irrespective of distances. This will be removed by the

    water flushing during the filling and during the final dewatering.

    Gauging will be performed in a separate run. If major construction related debris, arrive from

    the pipeline in front of the cleaning scraper run at the end of the initial cleaning operation

  • 7/28/2019 GRP Hydrotesting 01.docx

    7/12

    then, the subsequent gauging plate scraper run shall be accompanied with a brush scraper

    to ensure the pipeline section is free of debris,

    Gauging plate diameter shall be according with Project Standards & Specifications. The

    gauging plate will be verified in the presence of Company Representative for scratches or

    bends. If the gauging plate is received in a damaged condition, the gauging scraper shall be

    rerun until the obstruction is found and repaired. Minor scraping or nicks in the gauge plate

    are considered acceptable.

    1.4.3.2 Electronic Caliper Survey

    If required an electronic caliper survey from Company approved Caliper subcontractor.

    Electronic Caliper Survey will be performed prior to the pipeline hydrotesting. Contractor will

    conduct the work in the following sequence:

    Pressurize the pipeline between launcher and receiver to have a backpressure between 45

    to 50 psig (3 to 3.5 barg)

    Run the caliper tool along the pipeline maintaining the correct compressed air injection from

    behind and the back pressure in front in order to keep the speed run at around 3 to 5 km/hr

    avoiding surges.

    Upon the tool arrival the data collected will be down loaded and verification will be made to

    ensure that the pipeline has been completely surveyed. This operation will be done at the

    receiver site. In case are data missing in the run then another run shall be performed.

    Results shall be evaluated and a preliminary written report will be submitted to the Client,

    on-site, within 3 days of the completion of survey. The preliminary report will identify all

    locations having anomalies outside of the acceptance criteria. Contractor shall immediately

    verbally advise Client of all recorded abnormalities. This report will confirm that data has

    been collected and will identify any major features found in the first pass of the data.

    1.4.3.3 Water filling flushing and venting

    A temporary 4 line from the 28 GRP pipelines to the CS Pipelines at WFTP will be

    constructed to supply the water required for the filling and flushing of the CS Pipelines.

    At this stage the required water treatment will be applied to the fill water taken from the

    GRP pipelines.

  • 7/28/2019 GRP Hydrotesting 01.docx

    8/12

    Sequence will be as follows:

    Water filling and flushing will be assisted with minimum one bidirectional scraper launched

    from WFTP with proper air back pressure for scraper run control.

    Pump 100 linear meters of water in front of the filling scraper. This water will provideadditional control, sealant and lubrication to the flushing and filling scraper, while help to

    remove the small particles (sand & dust) left after the cleaning and gauging activity.

    Launch the scraper by pumping the filling water behind. If there is a second filling scraper

    planned to be launched (depends of pipeline length, profile and piping accessories) then

    stop pumping once the first scraper has travelled around 100 Linear Meters and proceed to

    launch the second filling scraper by pumping water until the scraper(s) reaches the pipeline

    section end. Upon all the scrapers are launched the required water treatment shall

    commence.

    A temporary discharge line directed to a Company approved tank/pound will be used to

    control the air back pressure during the water flushing and filling and to receive in control

    manner the filling scraper(s). Initial and final air back pressure must be calculated based on

    the pipeline elevations.

    Once the scraper(s) is received, and therefore the flushing and water filling are completed,

    the raise the pipeline pressure to 10% of the test pressure by the filling pump and allow for

    a minimum of 24 hours for temperature stabilization.

    1.4.3.4 Pressurization and Pressure Test.

    Upon temperature stabilization of the hydro test water the pressure will be raised to the

    strength test pressure in gradually and steady way in steps no greater than one fifth of the

    strength test pressure after 50% of the pressure is reached. In between these steps of

    pressure rising allow for a minimum holding time of 10 minutes.

    During the hydrostatic pressure testing the pressure and pipe/water temperature must be

    continuously monitored and recorded with the approved testing equipment as per project

    specifications.

    Two Hours of Strength test will be followed by the pipeline depressurization to 95% of the

    strength test pressure and then, the 24 hours of tightness test will continue. Appropriate,

    safety devices, procedures and monitoring to maintain the strength test pressure in between

  • 7/28/2019 GRP Hydrotesting 01.docx

    9/12

    the safe limits must be implemented and volumes of water removed or injected must be

    recorded. During tightness test the addition or removal of water is not allowed.

    Pressure test shall demonstrate to Client satisfaction that there are no leaks in the pipeline.

    Should the final tightness test pressure be lower than the initial pressure, Subcontractormust determine if this pressure variation is resulting from temperature change in the

    pipeline section during the test period. Pressure changes shall be calculated and supported

    by the formulas previously approved by Company.

    Upon approval of the tightness test, the pressure will be reduced to a minimum of 30-50

    psig at the highest pipeline elevation.

    1.4.3.5 Pipeline Dewatering and Hydrotest water disposal.

    Upon successful completion of pressure testing, the Section will be depressurized, the

    temporary test headers and blinds removed, and reinstatement with final tie-ins performed.

    Any disposal of hydrostatic test water shall be done to the designated disposal / evaporation

    pond or tank through temporary discharge line. Displacement of the water from the pipeline

    section will be performed using dewatering pigs driven by compressed air.

    As possible the use of water inhibition or chemical additives will be avoided to reduce the

    environment impact to just sediment and suspended debris. Water will be discharged into

    sedimentation pools or temporary holding tanks, before discharge into the environment. If

    the addition of chemicals and additives to the test water then they will be selected as much

    as possible to be environment friendly and the holding time in the discharge ponds must be

    longer to reduce the chemicals reaction. Subcontractor will ensure compliance with current

    environmental regulations and permits obtained for the project, which are in force in the

    relevant areas of hydrotest water discharge.

    1.4.3.6 Pipeline Drying and Lay-up

    Drying of the pipeline will be carried out immediately following dewatering. Various

    techniques can be used, including:

    - Chemical swabbing;

    - Vacuum drying.

    - Air drying; and

    - Nitrogen Drying

  • 7/28/2019 GRP Hydrotesting 01.docx

    10/12

    The dryness level and drying technique followed by the required Lay-up will be addressed in

    detail during the development of the specific procedures for the Project in compliant with the

    Specifications and Codes approved by Company.

  • 7/28/2019 GRP Hydrotesting 01.docx

    11/12

    ANNEX 1 - SCHEMATIC OF THE PIPELINES

  • 7/28/2019 GRP Hydrotesting 01.docx

    12/12

    ANNEX 2 - SPECIFIC EQUIPMENT

    Description Minimun Specifications (desirable) Qty Units

    Pick-up 4x4 / double cabin 2 Each

    BoomTruck 6x6 - 5 Tons 2 Each

    Water Tanker 12 M3 2 EachStorage Tank 12 M3 2 Each

    Compressor 16,000 Lts/min 12 Bar 3 Each

    Compressor 8,000 Lts/Min 7 Bar 1 Each

    Torquing Wrench 700 Bar 2 Each

    Torquing hydraulic Air Driven

    Pump 700 Bar 2 Each

    Water Pump 150 M3/Hr 20 Bar 2 Each

    Selfcleaning Filter 200 M3/Hr X 100 m Mesh 10 Bar 2 Each

    Pressure Pump 100 Lts/Min 30-40 Bar 2 Each

    Mobile Test CabinW/ Instrumentation (gauges, Recorder P-T,

    etc) 2 Set

    Dead Weight Tester 50 Bar 2 Each

    Generator 25 Watts 3 Phases 380/240 v 2 Each

    Lighting Tower/Gen 10 wats 4 Lights 3 Each

    Scrapers (Pigs)

    Bi-Di 4 Rubber Discs/ SteelBody 20" 5 Each

    Bi-Di 4 Rubber Discs/ SteelBody 24" 3 Each

    Bi-Di Soft Rubber Type 24" 7 Each

    Bi-Di Soft Rubber Type 28" 10 Each

    Foam Mediun Density 20" 4 Each

    Foam Light Density 20" 8 Each

    Foam Mediun Density 24" 4 Each

    Foam Light Density 24" 6 Each

    Foam Mediun Density 28" 4 Each

    Foam Light Density 28" 6 Each

    Gauge Plate 20" 3 Each

    Gauge Plate 24" 2 Each

    Spare 4 Discs Sealant (Set) 20" 2 Set

    Spare 4 Discs Sealant (Set) 24" 2 Set

    Pig Locator + Receiver 6 Set

    Hand Tools Spanner all Sizes 4 Set