161
GROUTING IN ROCK TUNNELLING With Selected Case Studies of Post grouting in Kárahnjúkar Hydroelectric Head Race Tunnel East Iceland. Joseph Oyeniyi Ajayi M.Sc. ritgerð í Umhverfis- og audlindafræði Júní 2007 Umhverfis-og byggingarverkfræðiskor Verkfræðideild Háskóla Íslands

GROUTING IN ROCK TUNNELLING

Embed Size (px)

DESCRIPTION

GROUTING IN ROCK TUNNELLING

Citation preview

Page 1: GROUTING IN ROCK TUNNELLING

GROUTING IN ROCK TUNNELLING

With Selected Case Studies of Post grouting in Kárahnjúkar Hydroelectric Head Race Tunnel

East Iceland.

Joseph Oyeniyi Ajayi

M.Sc. ritgerð í Umhverfis- og audlindafræði

Júní 2007

Umhverfis-og byggingarverkfræðiskor Verkfræðideild Háskóla Íslands

Page 2: GROUTING IN ROCK TUNNELLING

© Joseph Oyeniyi Ajayi, 2007 ISBN: 978-9979-9812-0-6 Printed in Iceland by Háskólaprent, 2007.

Page 3: GROUTING IN ROCK TUNNELLING

3

PREFACE This document is a M.Sc. thesis submitted to the Department of Civil and Environmental

Engineering at the University of Iceland (Háskóli Íslands) for the fulfilment of the award

of Master of Science in a Masters program in Environment and Natural Resources.

The study describes the grouting activities carried out at the Tunnel Boring Machine

(TBMs) fullface and the Drill and Blast sections of the Kárahnjukar Head Race Tunnel

(HRT) all the way from the power intake at the Hálslón reservoir to the power house in the

Fljótsdalur valley (45 km). It sheds more light on the need for grouting (pre-and post

grouting) and highlights the procedures adopted to carry out grouting activities, open-up

some of the problems encountered during excavation such as the possibility of

encountering large quantities of high pressure ground water inflow which may delay or

result in a temporary interruption of production. General water treatment along the stretch

of the tunnel will be described.

The effectiveness of both the traditional cementacious grouting, as well as the chemical

counterparts, as the most acceptable methods of sealing the tunnel against water ingress to

prevent any adverse internal environment, prevent unacceptable impact on the external

surrounding environment as well as maintaining hydrodynamic containment of the tunnel

(NTS.Publication No 14. Ch 9). Necessary equipment and materials needed for the

successful operation will be discussed.

In conclusion, this thesis will generally summarise some of the experiences and lessons

learned during the construction of Kárahnjúkar Hydroelectric Head Race Tunnel.

The study was supervised by Birgir Jónsson associate professor at the Department of Civil

and Environmental Engineering, University of Iceland and Björn A. Hardarson, Senior

Geotechnical Engineer at Geotek Consulting Engineering, at present Resident Engineer at

the 11 km Hedinsfjord Road Tunnel, North Iceland. The External examiner was Emeritus

Professor Julius Solnes, Department of Engineering, University of Iceland, former

Minister for the Environment in the Icelandic government.

Page 4: GROUTING IN ROCK TUNNELLING

4

Aim / Scope of the project. This research describes the grouting activities carried out at the Tunnel Boring Machine

(TBMs) fullface and the Drill and Blast sections of the Head Race Tunnel (HRT) all the

way from the power intake at the Hálslón reservoir to the power house 45 km away in the

Fljótsdalur valley. This research sheds more light on the need for grouting (Pre- and Post-

grouting), and highlights the procedures to carry out grouting activities in the Head Race

Tunnel (HRT). The research will open up some of the challenges encountered during

excavation such as the possibility of encountering large quantities of unexpected high

pressure ground water inflow which directly or indirectly delay production or may even

bring a temporary interruption to the excavation progress.

The significance and the effectiveness of grouting as one of the ground support methods in

tunnelling will be disscussed and the general performance of Tunnel Boring Machine

(TBM) beeing used for the first time in Icelandic basaltic rock will be overview.

Considering the hydrogeological nature of groundwater in Iceland which is very different

in the geologically younger formations – Late Quartenary and Recent in terms of high

permeability, where active and open fissure swarms enhance the permeability as well as

creating a strong anisotropy as compared to the geologically older formations – Tertiary

and Early Quaternary (Sigurðsson and Einarsson 1988)1. Smaller levels of ground water

ingress can cause problems in the tunnel or in the surroundings. Hence, ground water

ingress can be controlled by drainage, proper pre-excavation grouting and post-excavation

grouting 2(Knut F. Garshol 2003).

The research will analyse the effectiveness of both the traditional cementacious grouting

and chemical counterpart, as the most acceptable methods of sealing the tunnel against

underground water inflow to prevent any adverse internal environment, prevent

unacceptable impact on the external environment as well as maintaining hydrodynamic

containment in order to prevent leakage 3(NTS 2004. Publication No 14). Grouting

activities for stabilization as part of the rock support will also be revealed.

1 Freysteinn Sigurdsson and Kristinn Einarsson (1988). Orkustofnun, National Energy Authority, Hydropower Division Reykjavik, Iceland. Groundwater Resources of Iceland- Availability and Demand. Jökull, No. 38, 1988. 2 Knut F. Garshol (2003). Pre-Excavation Grouting in Rock Tunnelling. 3 Norwegian Tunnelling Society, NTS (2004). Ch 9. Grouting. Publication Number 14 pp 43-46.

Page 5: GROUTING IN ROCK TUNNELLING

5

The proper equipment and materials needed for the successful operation will also be

briefly disscussed.

The Practical application techniques of pressure grouting ahead of the full Tunnel Boring

machine (TBM) and Drill and blast sections of the tunnel as well as already excavated

sections supported by theory are in focus.

In conclusion, it will generally summarise some of the experiences and lessons learned on

the construction of Kárahnjúkar Hydroelectric Head Race Tunnel .

Page 6: GROUTING IN ROCK TUNNELLING

6

Acknowledgement. Special thanks to my supervisors Birgir Jónsson, associate professor and Björn Hardarson,

Senior geotechnical engineer at Geotek Consulting Engineering. I am highly grateful for

their great assistance and guidance. My sincere appreciation to all the staff and students of

the Geology and Geography Department, Environment and Natural Resources

Management Department and Civil and Environmental Engineering Department for all the

assistance they rendered during the whole study period. My appreciation to Hnit

Consulting Enginering for supporting the printing of this thesis.

My in-depth thanks to my wife and family for all the support and love from the beginning

of my life.

All honour and glory to God for a successful completion of the study.

Page 7: GROUTING IN ROCK TUNNELLING

7

Table of Contents 1 Introduction. ..............................................................................................................13 2 Historical Background and Description of the Project Area. ....................................17 3 Environmental Impacts Assessment..........................................................................24 4 Rock Distribution and Geology of the Project Area. ................................................28 5 Hydrogeology/Groundwater Condition in Iceland. ...................................................31 6 The Tertiary-Early to Middle Quaternary Bedrock...................................................33

6.1 Sedimentary Aquifers. .......................................................................................34 6.2 Late Quaternary and Recent Bedrock................................................................35 6.3 Pyroclastics, lavafields and fissure swarms.......................................................35 6.4 Great springs and springs areas. ........................................................................37

7 Land Use Planning. ...................................................................................................39 8 Design and Construction. ..........................................................................................40

8.1 Design and Construction of the project. ............................................................40 8.2 Excavation Methods. .........................................................................................41

8.2.1 Excavation Class/Rock Support. ...............................................................41 8.3 Bore Classes. .....................................................................................................42

9 Monitoring Instrumentation.......................................................................................46 9.1 Deformation monitoring. ...................................................................................46 9.2 Groundwater Control.........................................................................................46 9.3 Vibration monitoring. ........................................................................................47

10 Grouting into the rock. ..............................................................................................48 10.1 Reasons for grouting in tunnelling. ...................................................................48 10.2 Comments on Pre-grouting and Post-grouting. .................................................48 10.3 Reasons behind increase in the use of pressure grouting. .................................53 10.4 Design of grouting in rock tunnels. ...................................................................54 10.5 Practical basis for injection works in tunneling.................................................55 10.6 Influence of tunneling to the surrounding and the conditions inside the tunnel56 10.7 Condition inside the tunnel................................................................................57 10.8 Issuing Of Site Instruction.................................................................................57

11 Boreholes in Rock. ....................................................................................................59 11.1 Top hammer percussive drilling. .......................................................................59 11.2 Down the hole drilling.......................................................................................60 11.3 Low speed rotary drilling. .................................................................................61 11.4 High speed rotary drilling. (Core drilling). .......................................................61

12 Typical solution example for drill and blast excavation............................................64 12.1 Probing ahead of the face. .................................................................................64 12.2 Drilling of injection holes..................................................................................67 12.3 Cleaning of holes/ Flushing of boreholes for injection. ....................................67 12.4 Placement of packer...........................................................................................68 12.5 Water Testing/Water Pressure Testing. (WPT).................................................68 12.6 Choice of injection materials.............................................................................70 12.7 Injection pressure and procedure.......................................................................70 12.8 Injection records and quality control during injection.......................................72 12.9 Settling of grout, time until next blast. ..............................................................72

Page 8: GROUTING IN ROCK TUNNELLING

8

12.10 Drilling of control holes. ...................................................................................73 13 Typical solution example for Tunnel Boring Machine (TBM). ................................74

13.1 Probing a head of the face. ................................................................................74 13.2 Drilling of injection holes..................................................................................74 13.3 Cleaning of holes/ Flushing of boreholes for injection. ....................................75 13.4 Placement of packer...........................................................................................75 13.5 Water Pressure Testing......................................................................................75 13.6 Choice of injection materials.............................................................................75 13.7 Injection pressure and Procedure.......................................................................76 13.8 Injection records and quality control during injection.......................................77 13.9 Setting of grout/ Hardening time. ......................................................................77 13.10 Drilling of control holes. ...................................................................................77

14 Packers.......................................................................................................................79 14.1 Mechanical Packers (expanders). ......................................................................79 14.2 Disposable packers. (Single application). .........................................................80 14.3 Hydraulic packers. .............................................................................................81 14.4 Standpipes techniques. ......................................................................................83 14.5 Tube-a-manchet. ................................................................................................84 14.6 Types used on the Project..................................................................................84

15 Cement-Based Grouts................................................................................................85 15.1 Basic properties of cement grout. ......................................................................85 15.2 Cement particle size, fineness. ..........................................................................85 15.3 Bentonite etc. .....................................................................................................87 15.4 Rheological behaviour of cement grout.............................................................87 15.5 Pressure stability of cement grout and use of high injection pressure...............88 15.6 Grout setting characteristics and durability of cement injection in rock...........95 15.7 Additives and admixtures for cement injection.................................................96 15.8 Equipments for Cement injection. .....................................................................97

15.8.1 Mixing equipment. (Mixer). ......................................................................97 15.8.2 Agitator......................................................................................................98 15.8.3 Grout Pumps..............................................................................................99 15.8.4 Complete systems. ...................................................................................101 15.8.5 Automated mixing and grouting plants ...................................................102 15.8.6 Recording of grouting data. .....................................................................103 15.8.7 HIR ..........................................................................................................103 15.8.8 HFR .........................................................................................................103

16 Chemical Grouts. .....................................................................................................104 16.1 General. ...........................................................................................................104 16.2 Overview of Polyurethane grouts. ...................................................................105 16.3 Adopted Products on Kárahnjúkar Head Race Tunnel....................................111 16.4 Silicate grouts. .................................................................................................114 16.5 Acrylic grouts. .................................................................................................115 16.6 Epoxy resins. ...................................................................................................116 16.7 Bitumen Asphalt. .............................................................................................116

17 High Pressure Ground Water Condition..................................................................121 17.1 Basic Problem..................................................................................................121

Page 9: GROUTING IN ROCK TUNNELLING

9

17.2 Practical procedure in high risk areas..............................................................121 17.2.1 Pumping System. .....................................................................................121 17.2.2 Probe drilling /coring...............................................................................122 17.2.3 Injection. ..................................................................................................122 17.2.4 Special cases. ...........................................................................................122

18 Experiences /Summaries of Case Studies................................................................124 18.1 Case study 1. Chainage 135 – 1+ 146. Power Intake. .....................................124

18.1.1 General remarks and recommendation. ...................................................131 18.2 Case study 2. Chainage 19 + 645- 19 + 595. Adit 2 ( TBM Stuck 6-months) 132 18.3 Case study 3. Chainage 1 + 468, 5. Adit 4. (Dry-dyke) ..................................145 18.4 Case study 4. Chainage 002 + 255. Adit 3. ~150- 200 l/sec. ..........................148 18.5 Adit 2. Jökulsa Valve Chamber. Curtain Grouting – Plug 2.2. .......................151

19 Discussions and summaries of lessons learned, results and conclusion..................155 20 References. ..............................................................................................................157

Page 10: GROUTING IN ROCK TUNNELLING

10

List of figures and tables. Figure1. Pictures showing the dam area and the vertical Penstock of the project.

Figure 2. Kárahnjúkar Pressure shafts compared to the highest building of the World.

Figure 3. Map Showing reservoirs, tunnels, dams and roads. Description of the Project

Area.

Figure 4.The Project alignment. Showing Description of the Kárahnjukar Head Race

Tunnel (HRT) including Power House, (VIJV- Database 2006).

Figure 5. Map showing the project area, reservoirs, HRT, power house, roads,

transmission lines and the neighbouring communities.

Figure 6. Summary of the Major Environmental Impacts of the project.

Sources. Landsvirkjun website.

Figure 7. Diagram Showing Geology-Longitudinal section.

Figure 8. Map showing the demarcation of Iceland based on the bedrock classifications.

Figure 9. Map of Iceland showing great springs from the Late Quaternary and Recent

Zone, most of them in connection with fissure swarms or lava fields.

Figure 10. Showing differnt Bore Classess, rock types and percentage of face surface.

Source: VIJV Database 2002.

Figure 11. Map showing excavation details of part of head race tunnel, (Power-intake) and

Adit 4 junction. Source, VIJV Database 2004.

Figure 12. Map showing the profile of the Head race tunnel, directions of the three tunnel

boring machines (TBMs) and Jumbo Drilling Machines. (Source. Landsvirkjun Database

2006).

Figure 13a. Multi-boom drilling jumbo in operation for blasting and grouting holes

Figure 13b. Sandvik Tamrock Axera T12 and Atlas copco Rocket Boomer WL3 C drilling

jumbos. At right, a rod changer system for the drilling jumbo (Garshol, 1999).

Figure 14. Pre-grouting drilling system on a Robbins TBM (Garshol, 1999).

Figure 15a. Showing disposable packers (With a distance of 100-150mm between the

rubber sleeves). Source BASF Construction Chemicals.

Figure 15b. Showing inflatable packers, (Source Bimbar).

Figure 15c. Showing Inflatable Packers, (Source Hany AG Equipment).

Figure 16. Dispersing effect of an admixture using Micro-cement.

Page 11: GROUTING IN ROCK TUNNELLING

11

Figure 17. Rehological behaviour of Newton and Bingham fluids.

Figure 18. (A1). Curves showing consumption drops and pressure remains constant after

peak.

Figure 18. (A2).Curves showing pressure increases and consumption remain constant after

Peak.

Figure 18 (B1). Curves showing. pressure and consumption remains constant after Peak.

Figure 18 (B2). Curves showing pressure and consumption rise to some value and then fall

rapidly.

Figure 18 (C1). After a rise in pressure to a certain value, the pressure remains more or

less constant, while the rate of consumption goes on rising.

Figure 18. (C2). After reaching a certain value, the pressure quickly drops while the rate of

consumption remains constant.

Figure 19. Mixer. (Photo Hany AG Equipment).

Figure 20. Agitator (Photo Hany AG Equipment).

Figure 21. Grout Pump. (Maximum Pressure 100 bar).

Figure 22. Grout Pump. (Maximum Pressure 200 bar). (Photo Hany AG Equipment).

Figure 23. Complete grout pump. ( Photo Hany AG Equipment).

Figure 24. Automated mixing and grouting plants. (Photo Hany AG Equipment).

Figure 25. Showing Recording Systems. (Photo Hany AG Equipment).

Figure 26a. Showing typical reactive polyurethane prepolymers.

Figure 26b. Water reactive prepolymers.

Figure 27.Core showing Infilling of rock cavities with Polyurethane.

Figure 28. Showing Power intake, tunnel concrete lining outline and grout plan.

Figure 29. Diagram showing Contact, Consolidation and Curtain grouting in the

dismantling chamber (Ch 1 + 135 -1+ 146).

Figure 30. Diagram showing the Chronological advancement of the TBM 2 through fault

#1, #2 and #3.

Figure 31. Diagram showing the length of the Extraordinary Geological Section(EGO)

Figure 32. Diagram showing grouting activities and backfilling of void as part of the rock

support and finishing works.

Figure 33. Geological Mapping showing the geological over break (Dyke).

Page 12: GROUTING IN ROCK TUNNELLING

12

Figure 34. Drawing showing grouting/Treatment of dry dyke at Ch 1+ 468. 50

Figure 35. Geological Mapping showing the geological over break (Fault).

Figure 36. Diagram showing the drilling and grouting activities/treatment of faults at

Ch 002 +255.

Figure 37a. Sketches Showing Ring A (15m). Curtain Grouting ( 1,3,5,7,9,11,13,15,17,19,21,23).

Figure 37b. Sketches Showing Ring B (15m). Curtain Grouting ( 2,4,6,8,10,12,14,16,18,20,22,24). Figure 37c. Sketches Showing Ring C (15m). Curtain Grouting ( 1,3,5,7,9,11,13,15,17,19,21,23). Figure37d. Sketches Showing RingD (5m). Curtain Grouting ( 2,4,6,8,10,12,14,16,18,20,22,24). Figure 37e. Curtain drilling and grouting of plug 2.2.

List of Tables. Table 1. Showing the key figures of the project.

Table 2.Ranking of Major Grout Properties.

Table 3. Ranking of Chemical Grouts by Application. (EM 1110-1-3500. 31 Jan 1995).

Table 4. Summary Timeline of chronological advancement of the TBM 2 through fault #1,

#2 and #3.

Page 13: GROUTING IN ROCK TUNNELLING

13

1 Introduction.

The Kárahnjúkar Hydro-Electric Project is located in eastern Iceland between the Jökulsa

á Dal and Jökulsa í Fljótsdal rivers. The rivers have their origin from the Vatnajökull

glacier and run towards the northeast. In the Hálsón reservoir the water of the Jökulsá á

Dal will be stored and then conveyed by the headrace tunnel to the pressure shaft and then

to the underground power house in the Fljótsdalur valley about 40 km south of the town of

Egilsstaðir. In the Jökulsá diversion, the discharge of some tributaries to the Jökulsá í

Fljótsdal will be stored in Kelduá reservoir and then conveyed from there by a tunnel to

Ufsarlón pond to be located in the Jökulsá í Fljótsdal river course. The Jökulsá tunnel

conveys water from the Ufsarlón pond to the Jökulsá junction with the headrace tunnel.

Power from the project is transmitted by two 400 kV transmission lines to the port of

Reyðarfjörður where Alcoa a multinational company from the United States of America

has almost completed the construction of a 340 thousand tonnes per year aluminium

smelter. These two interrelated projects are built as a result of the long term governmental

policy to develop Icelandic renewable energy mainly for export revenue and employment

opportunities in the power intensive industries. In the light of this, a 40 year contract to

provide power for the plant was concluded with US Multinational Alcoa in March

2003.4(J. Roby 2006)

Landsvirkjun the owner of this project, founded on 1 July 1965 is an independent legal

entity formerly owned by the Icelandic Government, the City of Reykjavik and in 1983,

the Municipality of Akureyri became a third owner but solely owned by the Icelandic

Government as from 1 January 2007 through taken over the shares of Reykjavik and

Akureyri. Since then, the company is a state-owned partnership.5( http:www.lv.is/EN)

The company with a current installed electricity generation of over 1,200 MW, is the

largest power producers in Iceland. Landsvirkjun has until 2006 owned and operated the

main National Grid which is now owned by a seperate company named Landsnet.

Landsvirkjun generates about 87 % of the country,s electricity.

4 Joe Roby. February (2006). Tunnel Bussiness Magazine. Nothern Exposures. Supplying Iceland,s New hydropower Plant. Tunnelling Overcome Extreme Weather and Geological Conditions. 5 Landsvirkjun Website. http: www.lv.is/EN.

Page 14: GROUTING IN ROCK TUNNELLING

14

The Project area extends from the power house and about 40 km south and southwest, and

onward to the glaciers protruding north from the north-eastern part of the Vatnajökull Ice

cap.

Picture showing the dam area, (Reservoir).

Page 15: GROUTING IN ROCK TUNNELLING

15

Figure1. Pictures showing the dam area and the vertical penstock of the project.

Page 16: GROUTING IN ROCK TUNNELLING

16

Figure 2. Kárahnjúkar Pressure shafts compared to some of the highest buildings of the

World.

Page 17: GROUTING IN ROCK TUNNELLING

17

2 Historical Background and Description of the Project Area.

The establishment of large-scale industry has been on the agenda in East Iceland for the

past three decades and in all this period, the attention has been on the industry site in

Reyðarfjörður. Below are the summary of some disscussions that has came up since the

last three decades:6(http// www.kárahnjúkar.is)

• 1975-1976: Norsk Hydro the Norwegian company examined possibilities of

building an aluminium plant in Reyðarfjörður. The power was scheduled to come

from the 200 MW Fljótsdalur hydroelectric power plant.

• 1980-1985: Rio Tinto Zink the Australian company had plans to build a silicon

metal plant in Reyðarfjörður. The power was also planned to come from the

Fljótsdalur hydroelectric power plant. This project was later abandoned while on

its way.

• 1989-1990: Reydarfjörður was again in mind as a site for large-scale industry

when the multinational firm Atlantal, owned by Hoogovens, Alumax and

Gränges, was searching for a site for an aluminium plant. The final choice was

Keilisnes in South of Iceland and the power was still to come from Fljótsdalur

hydroelectric power plant. Construction was just about to start when the project

was suspended in 1991.

• 1998: Norsk Hydro took up discussions again about an aluminium plant and a

hydroelectric Power plant in East Iceland. Memorandum of understanding was

signed in June 1999, for a 120.000 tonnes smelter and a power plant in

Fljótsdalur with reservoir at Eyjabakkar, known as the Noral Project. In 2000

investors came to the opinion that the smelter needed to be bigger in order to be

profitable then, in May a new memorandum of understanding was signed for the

Noral Project whereby the aluminium plant was now planned to have a

production capacity of about 240.000 tonnes per annum in its first stage and a

second stage with a capacity of about 120.000 tonnes was planned for later. A

project company, Reyðarál, jointly owned by Norsk Hydro and Icelandic

6 Kárahnjúkar – Large Scale Industry in East Iceland. (2002). Landsvirkjun website http//www.Kárahnjúkar.is.

Page 18: GROUTING IN ROCK TUNNELLING

18

investors was to develop the plans for the smelter and Landsvirkjun would

supply the power for both stages with a hydroelectric power plant at Kárahnjúkar

and a diversion in Fljótsdalur Valley.

• In March 2002: It was revealed that Norsk Hydro could not meet deadlines set

for September 1st in the decision process, due to Hydro´s massive investment in

the German aluminium company VAW. However, they still maintained their

interest in the project at a later stage. In the light of this, the Icelandic

Government established a commission to deeply look into other company´s

interest in the project and shortly afterwards talks started with Alcoa, the worlds

biggest aluminium producer.

• April 19th 2002, a joint action plan ( JAP) was signed with Alcoa to explore the

possibility of constructing a state-of-the-art aluminium production plant in

Eastern Iceland. The joint action plan was extended on May 23rd until July 18th,

2002 by which the parties must have made up their mind to sign a formal

Memorandum of Understanding and proceed with the project. In the project,

Alcoa would own and operate a 340,000 metric ton per year aluminium plant

with power from a 500+ MW hydroelectric power station in Eastern Iceland to be

constructed and operated by Landsvirkjun, the National Power Company of

Iceland.

• July 19th 2002 a Memorandum of Understanding (MOU) was signed in

Reykjavik between the Government of Iceland, Landsvirkjun, Iceland´s National

Power Company and Alcoa formalizing their co-operation on a 295,000 metric

ton per-year, low emission aluminium smelter to be built in eastern Iceland. In

the contents of the new Memorandum of Understanding, Landsvirkjun will begin

development of a 630 MW hydropower facilities in eastern Iceland and Alcoa

will embark and carry out environmental and engineering feasibility studies of

the smelter in Reyðarfjordur. The MOU also involved a harbour facility at

Mjóeyri coupled with appropriate infrastructures improvements In eastern

Iceland.

• The Management of Alcoa decided to present the Plant Project to its Board of

Directors for full approval in January 2003 as Landsvirkjun also aimed at

Page 19: GROUTING IN ROCK TUNNELLING

19

submitting the Power Contract, and the Harbour Fund was aiming at submitting

the Harbour agreement, to their respective Boards of Directors for final approval

before the end of December 2002. It was jointly agreed that in the event that

Alcoa, the Government and Landsvirkjun were unable to ultimately agree upon

the basic premises for binding definitive agreements on implementation of the

Plant Project before the end of march 2003, this MOU will terminate, unless the

concerned bodies jointly agreed to extend the term of the MOU or alternatively

replace it by a further Memorandum.

The Kárahnjúkar Hydropower project is located in the highlands of remote northeastern

Iceland. While the project has been discussed for nearly 40 years, it only became a reality

in the last five years. In 2001, a thorough Environmental Impact Assessment (EIA) on the

project was completed. The Iceland Ministry for the Environment gave a final positive

ruling and in 2002, followed by approval from a sizable majority of the Althing, Iceland

Parliament. Later that year, the Ministry for industry issued all of the necessary permits for

the project and preparatory work was able to begin, including road construction. Local

Municipalities issued the necessary construction permits in February 2003 and in March

2004, a 40 year contract to provide power for the new aluminum smelter was concluded

with Alcoa.

The project area is lying generally at an elevation slightly exceeding 600 m above sea

level. It is charactrised by the high plateau which gradually built up and formed over a

time period of some 10 Million years. Into this, valleys have been eroded by various rivers

and the glaciers during numerous glaciation periods resulting in mountains of different

prominence which rise above the plateau.

Kárahnjúkar power plant will have an installed power of 690 MW and the annual

generating capacity will be about 4,600 GWh. To meet this standard, the Jökulsá á Dal

river is dammed by three dams at Fremri Kárahnjúkar. The largest of the dam

Kárahnjúkastífla, is located at the Southern (upper) end of the Hafrahvammar canyon and

is about 730m (2,400 ft) long and 193m (633 ft) high containing 8.5 million cu m of rock.

The structure is concrete-faced rock fill dam (CFRD) type and when completed will be the

Page 20: GROUTING IN ROCK TUNNELLING

20

highest of its kind in Europe, among the highest and fourth largest of its type in the World.

(Peter Reina 2006, Joe. Roby 2006).7

Completing the trio are other smaller saddle dams which will be built at Kárahnjúkar,

these are Desjarárstifla dam to the east, and Sauðárdalsstífla dam to the west. Both dams

will be rock fill dams with an earthen core, and together the three will combine the main

57 km2 Hálsón storage reservoir. The three dams will retain the Hálslón reservoir with

about 2.1 × 109 usable storage. When the reservoir is full, its water level will reach a

height of 625 m above sea level, and its shores will reach the edge of Brúarjökull glacier.

It is estimated that the Hálsón reservoir will be filled by late summer in most years.

Surplus water will then be diverted through a spillway chute at the western end of the

Kárahnjúkastífla dam down to the edge of the Hafrahvammar canyon.

On the east side of the mountain Snæfell, the Jökulsá í Fljótsdal river is dammed about 2

km downstream of the Eyjabakkafoss waterfall on the north side of the Eyjarbakkar

wetlands. The intake pond this creates has been named Ufsarlón, and water from three

tributary rivers on the eastern side of the Jökulsá is also diverted into it.

Two steel-lined vertical pressure shafts lead the water from the intake to the underground

powerhouse. Each shaft is 420 m high, and the total head is 599 m. The power house has

six Francis turbines each with a rated output of 115 MW. When water exits the power

house, a tailrace tunnel and canal take it to the course of the Jökulsá í Fljótsdal river.(see

table 1).

The total length of the whole tunnel system is over 70 km, and they vary in depth from

100 to 200 m. Around 40 km of the head race tunnel and parts of the access adit tunnels

has been full faced bored using the three Tunnel Boring Machine (TBMs).

7Peter Reina. (June 2006). Energy: Harsh Climate, Difficult Geology Temper Peace of Work. Joe Roby. ( February 2006). Tunnel Bussiness Magazine. Nothern Exposures. Supplying Iceland,s New Hydropower Plant. Tunnelling Overcome Extreme Weather and Geological Conditions. Focus on Iceland (2005). Extreme tunnelling – Kárahnjúkar. Tunnels and Tunnelling International October 2005. Pg 16 -20. Peter Reina (June 2006). Energy: Iceland Digs Deep To Develop Power in the Wilderness.

Page 21: GROUTING IN ROCK TUNNELLING

21

Figure 3. Map showing the project area, reservoirs, HRT, power house, roads,

transmission lines and the neighbouring communities.

Page 22: GROUTING IN ROCK TUNNELLING

22

Figure 4. Map Showing reservoirs, tunnels, dams and roads. Description of the Project

Area.

Page 23: GROUTING IN ROCK TUNNELLING

23

Figure 5.The Project alignment. Showing Description of the Kárahnjukar Head Race

Tunnel (HRT) including Power House, (VIJV- Database 2006).

LAY

OU

T PL

AN O

F KA

RA

HN

JUKA

R U

ND

ER

GR

OU

ND

EX

CA

VATI

ON

S

AD

IT 2

JU

NC

TIO

N A

REA

AD

IT 1

JU

NC

TIO

N A

REA

Page 24: GROUTING IN ROCK TUNNELLING

24

3 Environmental Impacts Assessment.

In accordance with the Icelandic law No. 106/2000, all hydro power project greater than

10MW or with reservoir greater than 3 km2 are to be subjected to Environmental Impact

Assessment. Landsvirkjun, as the developer promoting the project was required to carry

out such evaluation.

The impact area of the project includes highlands by the glacier Vatnajökull as well as

land along the rivers through the valleys of Jökuldalur and Fljotsdalur out to the coast of

Héraðsflói. This expanse of land lies within the following two communities:

• Fljótsdalshreppur

• Fljótsdalshérað.

Hydroelectric power plants always involve changes in the environment when rivers are

dammed and their flow diverted through power-generating stations, their courses below

the dams are altered and land above the dams remains flooded. In addition, channels, new

roads as well as various other visible structures are introduced.

The area affected by Kárahnjúkar Power Plant, particularly through dams, reservoirs and

roads, is in all ramifications very unique and certain parts of it are considered to have high

conservation value.

The impact area of the development stretches from the Brúarjökull glacier down to the sea

at Héraðsfloi. On the one hand, there is a sparsely vegetated highland area with broad open

spaces, glacial rivers and land use limited primarily to sheep grazing and hiking. On the

other hand, there is a lowland area with the main utilisation being agricultural (Sheep,

cattle and forestry farming), along with denser centres of human settlement at Egilsstaðir

and Fellabær. As in many marginal areas, centuries of grazing, especially by sheep, but

later also reindeer, have had impact on highland vegetation.

The Kárahnjúkar hydropower project will leave a lasting impression on its impact area,

drastic changes will occur in the natural terrain and land use in areas where vegetation and

Page 25: GROUTING IN ROCK TUNNELLING

25

fauna are sensitive. Some of the main aspects of nature which will be affected or become

extinct due to the establishment of the plant are as follows:8

• Changes in the landscape occur with the formation of Hálslón reservoir, covering an area of approximately 57 km2 .

• About 32 km2 of established vegetation is submerged by Hálslón and an additional 8 km2 disappear under other structures and storage reservoirs. Valuable habitats of vegetations and small animals are lost under Hálslón.

• Structures impinge upon undisturbed open spaces in the highlands, reducing them by 925 km2 .

• Worth considering changes will occur in the flow of two large glacial rivers due to diversion. Volume increase in Lagarfljót is expected, but average flow in Jökulsá á Dal decreases significantly.

• Important Calving and grazing grounds of reindeer stock are lost and migration routes are disturbed.

• Increased blowing of dust and sand from the Hálslón shores has potential of harming vegetation on Vesturöræfi as the Kringilsárrani reserve is reduced by a quarter.

• Important geological features are inundated and scientific investigation of them becomes difficult.

• Changes will occur in the alluvial flats of Jökulsa á Dal: deposits of sediment will become somewhat vegetated and the river will be restricted to a narrower channel.(Beneficial).

• Many waterfalls, mainly in the catchment of Jökulsá í Fljótdal, will be reduced or become completely extinct.

• Sediment in Lagarfljót will increase, the river becomes darker in colour and conditions for aquatic life deteriorate.

• Some hayfields along Jökulsá í Fljótsdal and Lagarfljót will be dampened (waterlogged) by a raised groundwater table.

• The coastline of Héraðsflói will recede, but natural impact on that area is minimised.

According to Landsvirkjun,s Environmental Policy and Objectives, aimed to minimize

disturbance of the environment during construction and to achieve exemplary project

finish at the end of construction. It has been actively aimed at to show consideration for

the environment. The layout of the project has been the result of co-operation between the

8 Landsvirkjun. (May 2001). Kárahnjúkar Hydroelectric Project. Environmental Impact Assessment. Summary of Environmental Assessment Report.

Page 26: GROUTING IN ROCK TUNNELLING

26

designers and the EIA scientists as well as the conclusion of the Icelandic Government in

its ruling on the environmental impact of the project.

The structures have been designed to appear neatly in their surroundings and to cause

minimum impact to the environment. The entire construction areas, including borrow

areas, disposal areas and temporary camp and working areas, has been planned in light of

the policy9. Main environmental aspects that has been subjected to a significant impact on

the environment and compelled to be adhered to by the concerned parties with the project

are the followings:

• Borrow areas and disposal areas.

• Waste

• Hazardous substances and use of chemicals

• Dangerous substances.

• Noise and vibrations.

• Transportations

• Soil and water

• Flora and fauna. (Ecosystem).

• Air pollution

• Landscape unit

• Cultural heritage

• Education and competence.(Information).

9 Landsvirkjun (Nov 2002). Kárahnjúkar Project – Landsvirkjun’s Environmental Policy and Objectives.

Page 27: GROUTING IN ROCK TUNNELLING

27

Figure 6. Summary of the Major Environmental Impacts of the project.

Sources. Landsvirkjun website.

Page 28: GROUTING IN ROCK TUNNELLING

28

4 Rock Distribution and Geology of the Project Area.

Geologically, Iceland is a young country, built up during the later part of the Cenozoic era,

i.e. Miocene, Pliocene and Quaternary. It is almost entirely composed of lava flows and

eruptive móberg (hyaloclastites/volcanic breccias) while in between are widespread, thin

sedimentary beds. Older geological formations are characterized by igneous intrusions.

The geological formations of Iceland are divided into four main groups according to

stratigraphical age which differ considerably from one another. Oldest is the Tertiary

Basalt Formation formed in the late Tertiary period. Next in sequence of age is the Grey

Basalt Formation which was formed in the very late Pliocene and early to middle

Pleistocene and thirdly the Móberg Formation which was formed in the very late

Pleistocene. These three formations form the bedrock of the country of which the fourth

and youngest formation rests, which is made up of unconsolidated or poorly hardened

beds such as till and glaciofluvial deposits, marine and fluvial sediments and soil, as well

as volcanic tephra and lava flows. This youngest formation was formed at the end of the

Pleistocene and in the Holocene.10(Einarsson 1991)

The bedrock in the project area was formed over the past 6.5 million years, consisting

mainly of thick sequences of basalt flows with intercalated sediments and móberg

formations of various kinds and due to this, mixed conditions arises. This has made

excavation more difficult because of the variation in the strength and elasticity of the

encountered materials at the virgin face.

The basalt is classified into the following three petrographic types namely, tholeite basalt,

olivine basalt and porphyritic basalt. The accumulation rate of lava and the average period

between eruptions in the Fljótsdalur-Jökuldalur area have been determined to be about 500

m (1600 ft) per million years and 20,000 to 30,000 years respectively.11(J. Roby 2006).

Sediments in the area occur as intercalations between lava flows, as well as thick

accumulations filling depressions and old valleys.

10 Þorleifur Einarsson (1991). Geology of Iceland Rocks and Landscape. 11 Joe Roby. ( February 2006). Tunnel Bussiness Magazine. Nothern Exposures. Supplying Iceland,s New Hydropower Plant. Tunnelling Overcome Extreme Weather and Geological Conditions.

Page 29: GROUTING IN ROCK TUNNELLING

29

Móberg formations occur in the upstream part of the project as buried bodies of pillow

lava, pillow breccia, tuff breccia and tuffs.

The nature of the sediments varies with their locations within the lava-pile, in the lowest

part of the pile, most sediments are fine grained and tuffaceous. In the upper part of the

pile, the sediment intercalations indicate cold climate with deposition of conglomerates

and tillites. The thick sediments are of fluvio-glacial origin, mainly consisting of

conglomerates and sandstones. Heavy underground water inflows were encountered

during the tunnel excavation phase with peaks up to 350 l/sec.

Peter Pitts (2006), Tomasz Najder (2006). Personal discussions on site, Joe Roby (2006).12

12 Peter Pitts. Senior Geothecnical Engineer. VIJV- Viseningar Enginering Joint Venture. Kárahnjúkar Hydroelectric Project Supervision Team. Tomasz Najder. Senior Grouting Engineer. VIJV- Viseningar Enginering Joint Venture. Kárahnjúkar Hydroelectric Project Supervision Team.

Page 30: GROUTING IN ROCK TUNNELLING

30

Geology – Longitudinal section

Figure 7. Diagram Showing Geology-Longitudinal section.

Page 31: GROUTING IN ROCK TUNNELLING

31

5 Hydrogeology/Groundwater Condition in Iceland.

The precipitation is very high in Iceland, exceeding 3,000 mm/year in mountainous parts

of southern Iceland, although it may be less than 600 mm/year over wide stretches in the

northern part of the country. 13(Sigfúsdóttir, 1995 & Tómasson, 1982).

The hydrogeological nature of groundwater in Iceland is very different in the geologically

younger formations – Late Quaternary and Recent, as compared to the geologically older

formations – Tertiary and Early Quaternary. In the former ones the bedrock is highly

permeable, while active and open fissure swarms enhance the permeability as well as

creating a strong anisotropy 14(Sigurðsson & Einarsson 1988). These characteristics result

in a concentration of the groundwater flow appearing in springs or groups of springs with

an unusually high discharge and a high seasonal stability. In the older formations, Tertiary

and early to middle Quaternary the bedrock usually has a low permeability, wide open

fissure swarms are absent and the groundwater is restricted to recent sediments of a

limited extension and characterized by strong seasonal fluctuation in the discharge of the

springs. The real conditions are much more diversified beyond this simplified general

classification, but the deviations are varying and are in each case restricted to limited areas 15(Hjartarson et al., 1980). Gíslason and Eugster, 1987, observed a degree of regularity in

the chemical composition of the groundwater. The main factors are the marine component

in the precipitation, the silica increase and cations in the groundwater through reactions

with the rocks as well as the mixing with geothermal water from high-temperature areas.

Local deviations can be traced to organic compounds from peat-bogs in the lowlands and

to recent snowmelt in summer in the highlands. Due to the low population density ~3

13 Paper presented at the Nordic Hydrological Conference, Förde, 28 -30 June 1982. Orkustofnun, mimieographed report No. OS -82059/VOD -10, Reykjavík. 14 Freysteinn Sigurðsson and Kristinn Einarsson (1988). Orkustofnun, National Energy Authority, Hydropower Division Reykjavik, Iceland. Groundwater Resources of Iceland- Availabilty and Demand. Jökul, No. 38, 1988. 35-54. 15Hjartason Á., Andersen L.J ., Kelsrup N and Rasmussen J. 1980: Explanatory Notes for the International Hydrogeological Map of Europe, Sheet B 2 Island. 55 pp. Gíslason S.R. and Eugster H.P. 1987: Meteoric water –basalt interaction. 11 A field study in N.E. Iceland. Geochimica et Cosmochimica Acta, 51, No. 10, p. 2841 -2855. 15b Freysteinn Sigurðsson and Kristinn Einarsson (1988). Orkustofnun, National Energy Authority, Hydropower Division Reykjavik, Iceland. Groundwater Resources of Iceland- Availabilty and Demand. Jökul, No. 38, 1988. 35-54.

Page 32: GROUTING IN ROCK TUNNELLING

32

inhabitants/km2, and high precipitation ~ 2000 mm/year, freshwater has been considered

an easily available and inexpensive commodity. Nevertheless, some prime factors have

influenced this development such as the population growth and higher standard of living.

The groundwater in Iceland is generally low in chemical contents and free from pollution. b(Sigurðsson & Einarsson 1988).

Page 33: GROUTING IN ROCK TUNNELLING

33

6 The Tertiary-Early to Middle Quaternary Bedrock.

The bedrock of the Tertiary-Early to Middle Quaternary formations is predominantly built

up of stratified basaltic lava flows, with a number of central volcanoes dispersed in the

strata. The strata are usually slightly tilted in accordance with the tectonic history of

Iceland, but in some areas the tilting even exceeds ten degrees 16(Sæmundsson, 1980). The

past volcanic activity occurred in distinct, elongated volcanic systems, accompanied by

swarms of open fissures compared to the presently active zones. The fissures are now in

most cases tightly closed, but in some regions they have been rejuvenated during later

tectonic events. Some regions are characterized by new fissure zones been formed in the

course of the later tectonic development, though of different intensity as those connected

with the Mid Atlantic rift volcanism. These “young” fissure swarms represent zones of

strongly increased permeability as well as anisotropic elements in the structure of the

bedrock.

The thickness of the lava flows in the basalt sequences is variable, intercalations are

usually much thinner than the lava flows, consisting of ash layers, windblown sand and

sometimes of remnants of soils. The columnar parts of the lava flows have an effective

porosity only in the narrow fissures between the joints, and they may be nearly closed

through alteration, tightening and deformation due to the overburden. The scoriaceous

parts, especially at the contact of lava flows, have a higher effective porosity and

permeability, but they are much thinner than the columnar part. The glassy and vesicular

scoriae are more prone to alteration than the massive columns. The originally higher

permeability in the scoriaceous parts can thus be more strongly reduced than the

permeability in the massive parts. 17(Sigurðsson & Einarsson.1988).

The intercalative layers have originally had a rather high effective porosity, but their

lithological nature makes them highly susceptible to geothermal alteration, which can

reduce their permeability, until it eventually becomes negligible. In principle, the same

applies to sedimentary layers more abundant in the stratigraphically higher parts of the

16 Sæmundsson K. 1980: Outline of the Geology of Iceland. Jökull, 29, p. 7 – 28. 17 Freysteinn Sigurðsson and Kristinn Einarsson (1988). Orkustofnun, National Energy Authority, Hydropower Division Reykjavik, Iceland. Groundwater Resources of Iceland- Availabilty and Demand. Jökul, No. 38, 1988.

Page 34: GROUTING IN ROCK TUNNELLING

34

sequences in particular in the Early to Middle Quaternary. In the younger formations the

rocks have not been buried as deeply as in the older ones, so the degree of alterations is

much less reduced. Parts of the older (Tertiary) formations have never been buried deep

enough to be subject to any recognized alterations and tightening.

The stratigraphical, lithological and tectonic structure of the central volcanoes is much

diversified, showing inhomogeneities and anisotropies. In these complex systems some

small-scale aquifers with higher permeability may occur, seldom of great extension and

often very irregular. Eventually, only small springs, if any, are to be found under these

hydrogeological conditions. Rejuvenated (Secondarily created fissures swarms are

regionally of importance due to the greater part they play in the geothermal hydrology of

the country).

6.1 Sedimentary Aquifers. During the last glaciation Iceland was to a large extent covered by glaciers, which carried

most of the loose sediments on the surface out to the sea. The present sedimentary cover is

therefore mostly postglacial in age. There is a difference in the most common sedimentary

aquifers between the older geological formation and the younger ones. In the Tertiary-

Early to Middle Quaternary regions the most common sediments are deposits left by the

retreating glaciers, river gravels, rockslides and a thin weathering cover. Principal aquifers

are the rockslides and the river gravels, some of the rockslides have extension of some

km2 and thickness of more than 10 m. Springs issuing from them have a discharge up to

some tens of litres per second, which is the same order of magnitude as that of other great

springs in the Tertiary areas.

18The bedrock in the older formation is classified as impermeable; spring–fed rivers are

rare, surface runoff is high and the rivers are liable to flooding and the gravel plains at the

valley bottoms correspondingly voluminous. In the lower courses of the rivers, as well as

on all the glacial rivers, the sediments are finer, reducing the permeability and making the

construction of wells difficult. It is characterized by strong seasonal variation in rivers as

18 Freysteinn Sigurðsson and Kristinn Einarsson (1988). Orkustofnun, National Energy Authority, Hydropower Division Reykjavik, Iceland. Groundwater Resources of Iceland- Availabilty and Demand. Jökul, No. 38, 1988. pp 40.

Page 35: GROUTING IN ROCK TUNNELLING

35

well as in the groundwater flow in the river gravels. Seasonal changes in water

temperature are also great which has the tendency of causing some difficulties during the

winter time.

In the Late Quaternary-Recent regions spring fed rivers as well as glacial rivers are

predominant. During the snowmelt in spring – early summer after rain storms most rivers

are in flood and some dry up in between due to lack of steady supply. Potential

sedimentary aquifers may also dry up, due to the high permeability of the bedrock in the

case of this; groundwater extraction is mainly carried out in springs or rocks of high

permeability.

6.2 Late Quaternary and Recent Bedrock. These formations are also of volcanic origin and mostly basaltic in composition.

Recordable numbers of central volcanoes have been active in these younger geological

periods and some are still very active.

6.3 Pyroclastics, lavafields and fissure swarms. A known characteristic of the volcanism during the glacial is the subglacial heaping up of

fragmentary rocks, tuffs, breccias and pillow lavas, due to magma extrusion under an ice

cover and rapid chilling of the lava in the subglacial/glacial meltwater. These rocks do

appear as steep-sided mountains or as extensive layers, mostly of secondary origin. Late

Quaternary and recent bedrock are characterized by high porosity, with strong variation in

permeability. The fine grained tuffs have in most cases narrow pores and low

permeability, which could be further reduced through alteration, post volcanic or due to

later geothermal activity.

The postglacial lava flows have very high permeability (conductivity 0.001-11.0 m/s).

Similarly, to their tertiary counterpart, they have a relatively low storage coefficient (0.01-

1.0). (Sigurðsson & Einarsson.1988). In comparison to the pyroclastic rocks, the

permeability of the interglacial lava flows has often been reduced by razing off of the

scoriaceous top layers, glacial tightening, and effect of deformation or rearrangement of

joints under the glacial ice cover. In general, their permeability is less than in postglacial

lavas.

Page 36: GROUTING IN ROCK TUNNELLING

36

Permeable rocks and swarms of open fissures create strong groundwater currents in the

Late Quaternary Zone and the chemistry of the groundwater may show the influence of

geothermal activity related to the silicic centres.

Figure 8. Map showing the demarcation of Iceland based on the bedrock classifications.

(Sigurðsson and Einarsson 1988).

Explanations.

1. Tertiary and Early to Middle Quaternary basalt regions.

2. Late Quaternary rocks.

3. Quaternary silicic centre.

4. Zone of fissure swarm.

Page 37: GROUTING IN ROCK TUNNELLING

37

6.4 Great springs and springs areas. Quite a number of spring areas have a discharge in the range 5-20 m3/s which is fairly

constant over the year, seasonal fluctuation is often at lesser percentage ~ 10%. Prominent

spring areas are directly or indirectly connected with active fissure zones, recent

volcanism is accompanied by swarms or zones of more or less open fissures. The

secondary permeability forming this fissuring can be very high (hydraulic conductivity

reaching up to 0.1- 1 m/s) which is of similar value with most permeable rocks or even

higher. As the fissure zones extend in the longitudinal direction for tens of km, they have a

very strong, anisotropic “draining effect”. Though to a lesser extent, the volcanic structure

of subglacially formed pyroclastics ridges acts in the same way.

The hydrogeological characteristics of the young rock formations can be summarized as

follows:

• Very strong anisotropic effect of the fissure swarms (anisotropic coefficients 1.5-2 or even more).

• Very high permeabilities, conductivity often in the range 0.001-0.1 m/s.

• A high storage coefficient in the pyroclastic rocks (0.1-0.5), but a low one in the lavaflows (0.01-0.1).

• Very strong concentration of the groundwater flow towards preferred spring areas (yield exceeding 1m3/s).

The central volcanoes in the young, recently active formations play a similar role as their

counterparts in older formations. Often irregular in structure, strongly altered rocks and

the permeability has been drastically lowered over parts of them, especially when

compared to the higher permeabilities found outsides the central volcanoes.

High-temperature geothermal areas, link to these volcanoes served as the most important

source of geothermal heat in Iceland. Fresh water is not abundant in these areas, because

of the geothermal impacts on its chemistry and the reduction in permeability. Most of

them are also situated far away from the areas of major settlements, where other sources of

fresh water are likely more abundant and better accessible.

Page 38: GROUTING IN ROCK TUNNELLING

38

19In general summary, the geologically youngest regions of Iceland, Late Quaternary and

Recent, are abundantly provided with clean and constant groundwater. The oldest regions,

Tertiary and Early to Middle Quaternary, are on the other hand usually deficient in

affluent aquifers and subject to seasonal fluctuations in groundwater flow. Unfortunately,

many settlements with very high demand of clean and ample fresh water are situated in

these geologically older regions. On the other hand, the state of things regarding the

younger formations is encouraging, as more over 70% of the total population are

concentrated on the southwestern part of the country, with an easy access to rich

groundwater basins.

Figure 9. Map

of Iceland showing great springs from the Late Quaternary and Recent Zone, most of them

in connection with fissure swarms or lava fields, (Sigurðsson and Einarsson 1988).

1. Springs or groups of springs with yield > 5 m3/s. 2. Springs or group of springs with yield 1-5 m3/s. 3. No Perennial surface runoff.

19 Freysteinn Sigurðsson and Kristinn Einarsson (1988). Orkustofnun, National Energy Authority, Hydropower Division Reykjavik, Iceland. Groundwater Resources of Iceland- Availabilty and Demand. Jökull, No. 40 1990.

Page 39: GROUTING IN ROCK TUNNELLING

39

7 Land Use Planning.

Landsvirkjun, the owner of the Kárahnjúkar Power Project, is in full support of the land

use plan being studied by the Icelandic Government, to establish a national park or a

protected area on the north side of the Vatnajökull ice cap as a part of an extended

Vatnajökull National Park. 20Landsvirkjun believes that a power project and a national

park in the area can co-exist. Hydroelectric projects and national parks are operated side

by side in many areas of the world. They claim that the project and its operation within a

protected area can establish better conditions for the operation of a protected area.

Preparation works is on-going by the Icelandic Government for the establishment of a

national park north of Vatnajökull, mostly west and southwest of the construction area.

20 Landsvirkjun website: http://www.lv.is/

Page 40: GROUTING IN ROCK TUNNELLING

40

8 Design and Construction.

8.1 Design and Construction of the project. The Head Race Tunne (HRT) is constructed from the main reservoir all the way to the

power house, It will convey the water from the Hálsón reservoir along the 40 km long

pressure tunnel and two 400 m deep vertical shafts to the underground powerhouse in the

western flank of the Fljótsdalur valley. The power house will house 6 vertical Francis

turbines with a total installed capacity of 690 MW and a rated generating flow of 144 m3/s.

The turbine water will be released to the Jökulsá í Fljótsdal river along a 1.1 km long tail

race tunnel and a 2.1 km long canal. Most of the 40 km headrace tunnel, with diameter

between 6.8 and 7.6 m was executed by three full face Tunnel Boring Machines (TBM s).

In the case of Kárahnjúkar Head Race Tunnel, 35,459,2 km and 4,167,3 km 21(VIJV

Database 2006) were excavated by Tunnel Boring Machine and Drill and Blast

respectively. Drill and Blast drives were necessary partly as counter drives to cope with

the rather tight construction schedule, the upper section of the headrace tunnel was

executed by Drill and Blast. During excavation by conventional drill and blast method, the

work face (virgin rock) is perforated by up to 5 m long drill holes. These holes are then

filled with explosives and blasted. Full face excavation means that the excavation is

performed in one operation, on the head of the Tunnel Boring Machine several rolling

cutters are mounted. The high feed pressure of the head against the face of the tunnel,

combined with a rotation of the head, leads to the crushing of the rock at the face, thus the

excavation. Full face excavation is normally a much quicker method than conventional

drill and blast. Futhermore, the mobilization cost of the TBMs are very high, thus

requiring a long tunnel in order to make the method economical. The conventional drill

and blast method provides better flexibility in handling major weakness zones.

Three construction adits was built by the contractor along the route: Adit 1 at Teigsbjarg

(lower), Adit 2 at Axará (Middle) and Adit 3 at Glúmsstaðadalur (upper). The adits are

approximately 1.4 km, 1.7 km and 2.7 km long, these will also provide permanent access

into the tunnel during operation. Based on the schedule, preparatory construction started in

21 VIJV Database December 2006. Viseningar Enginering Joint Ventures. Kárahnjúkar Hydroelectric Project Supervision Team.

Page 41: GROUTING IN ROCK TUNNELLING

41

the fall of 2002 and the main construction in springtime 2003. Impoundment of the

Hálslón reservoir started in September 2006. Electricity from the first generating unit will

begin to flow in late summer 2007, and the project is scheduled to be fully completed in

2009.22(Landsvirkjun Publication 2003)

8.2 Excavation Methods.

8.2.1 Excavation Class/Rock Support. In the TBM excavation section of the tunnel, the rock is divided into excavation classes.

There are basically four excavation classes, namely as follows:

• Excavation Class I

• Excavation Class II.

• Excavation Classs III

• Excavation Class IV.

The excavation class assigned to a particular section of the tunnel depends on the strenght

and stability of the area. It also reveals the deterioration of the rock in the area and hence,

the amount of support to be applied there. The degree of deterioration worsens from

excavation class I to IV (I<IV). In other words, areas classified as excavation class I

requires much less rock support in comparison with area classified as excavation class IV.

Below are the required activities to be carried out under each of the excavation class

according to the design and plan.

Excavation class I requires the following to be carried out:

• Spolt bolting as required.

• Sprayed concrete at least 50 mm thick with wire mesh or steel fibres.

• Drain holes 50 mm, 0.300 mm into rock at 2,0 × 2,0 or 3,0 × 3,0 spacing.

Excavation class II. requires:

• Pattern bolting, bolt lenght 2-5m long, spacing of 1,87m 23(= 1 stroke length of TBM) unless otherwise directed.

• Sprayed concrete of 50-100mm thick with wire mesh or steel fibres.

22 Landsvirkjun Publication 2003. Kárahnjúkar Hydroelectric Project and Transmission Lines FL3 and FL4. 23 Defined as the maximum advancement length of the TBM before re-gripping and advance. (Maximum advance length).

Page 42: GROUTING IN ROCK TUNNELLING

42

Excavation class III. requires:

• Pattern bolting, bolt lenght 2-5m, spacing 1,87m (= TBM stroke length) unless otherwise directed. Bolts drilled by left and right booms may be staggered ½ stroke lengths.

• Sprayed concrete of 100-150mm thick with wire mesh or steel fibres.

• U-channels where directed and rock bolts to be adjusted accordingly.

Excavation class IV requires the following:

• Rock bolting as instructed.

• Sprayed concrete of 200 250mm thick with wire mesh or steel fibres.

• Steel ribs TH 29/48, spacing 1,28m unless otherwise directed.

• Steel lagging as required.

• Rock bolts for anchoring ribs as required or instructed.

• Full circle rib if required and approved by the engineer and designer.

8.3 Bore Classes. Bore classes are used to distinguish the type of rock face been excavated at a particular

section of the tunnel, (see figure 10). Bore classes are basically divided into namely:

• Class HI.

• Class H2

• Class H3

• Class M1

Class M2.

Page 43: GROUTING IN ROCK TUNNELLING

43

Figure 10. Showing different Bore Classes, rock types and percentage of face surface.

Source: VIJV Database 2002.

Figure 11. Map showing excavation details of part of head race tunnel, (Power-intake) and

Adit 4 junction

Page 44: GROUTING IN ROCK TUNNELLING

44

TBM 1TBM 2TBM 3Jumbo 1Jumbo 2Jumbo 3Jumbo 4Jumbo 5Jumbo 6

5 km

10 km

15 km

20 km

25 km

30 km

35 km

Adit 1

Adit 2

Adit 3Adit 4

Power intake

Surge tunnel

Drainagetunnel

Jökulsá diversion tunnelø 7,2 m

Headrace tunnelø 7,6 m

Headrace tunnelø 7,2 m

Tunnel alignment

TBM 3

TBM 2TBM 1

Figure 12. Map showing the profile of the Head race tunnel, directions of the three tunnel

boring machines (TBMs) and Jumbo Drilling Machines, (Source, Landsvirkjun Database

2006).

Page 45: GROUTING IN ROCK TUNNELLING

45

Table 1. Showing the key figures of the project.

Headrace Tunnel (from Hálslon). Cross section Circular and horse shoe. (TBM and Drill and Blast). Diameter 6.8-7.6 m Lenght 39.8 km. Headrace Tunnel (from Ufsar). Cross section circular and horse shoe. (TBM and Drill and Blast). Diameter 5.5-5.8 m Lenght 13.3 km. Varying depth 100-200 m Powerhouse Type underground. Size (L ×W× H) 115 ×14 ×34 m Turbines 6 Francis units Installed capacity 6 ×115 = 690 MW. Design net head 524 m. Discharge 144m/s Power Lines. (Transmission lines FL3 and FL4). Rated voltage 420kV. Operating voltage 220kV FL3 Transm. Capacity at 220kV 915MVA. FL4 Transm. Capacity at 220kV 1,300 MVA. Lenght FL 3 49 km Lenght FL 4 53 km Number of steel towers FL3 159 Number of steel towers FL4 166 Tailrace Tunnel. Type horseshoe ross section Diameter 9 ×9 m Lenght 1,100 m Tailrace Canal. Lenght 2,100 m. Energy poduction. Annual energy 4,450 GWh

Two high tension lines connect the Kárahnjúkar Station in the Fljótsdalur valley to the

Fjarðaál aluminium smelter at Reyðarfjörður, owned by the US Company Alcoa. Each line

is about 50 km long and they go through two separate valleys for safety reasons (Snow

avalanches). The switching station in Fljótsdalur will also be connected to the national

grid,24(Landsvirkjun Publication. 2003).

24 Landsvirkjun Publication 2003. Kárahnjúkar HEP and Transmission Lines FL3 and FL4.

Page 46: GROUTING IN ROCK TUNNELLING

46

9 Monitoring Instrumentation.

Construction of a tunnel will affect the surroundings in different ways. It is of high

importance to monitor these effects to prevent damages to the surroundings as well as the

tunnel. Different types of monitoring instruments are presented below of which most of

them has been used in the construction of Kárahnjúkar Head Race Tunnel, together with a

brief description of how they work.

9.1 Deformation monitoring. Instrumentation. Application.

Borehole extensometer Rock movements around tunnel.

Pressure cell Pressure measurement in tunnel linings

Convergence tape extensometer Movement of tunnel linings.

Increx mobile extensometer Strains and deformations around tunnel

Anchor load cell Monitoring of anchor loads.

Piezo settlement column Water level and settlement control.

Embedment strain-gauge Concrete strain measurements (shotcrete).

Electrical piezometer Control of pore- water pressure.

Settlement system Monitoring of ground settlement

Surface clinometer Structural inclination movement.

Settlement column Soil settlement above tunnel.

Smach accelerograph Dynamic measurements during excavation.

9.2 Groundwater Control. Piezometers.

The measurement of the pore-water pressure in rock mass has been carried out with the

use of Piezometers. They can be installed in boreholes, from ground surface and from the

tunnel. There are several types of Piezometers. The choice of it largely depends on desired

accuracy, cost and user-friendliness. Some of the piezometer types that have been widely

used on this project are listed below:

• Standpipe piezometer.

• Pneumatic piezometer.

• Vibrating wire piezometer.

Page 47: GROUTING IN ROCK TUNNELLING

47

Dipmeters.

Dipmeters is a portable instrument for measuring the water level in wells, standpipes and

boreholes.

Flowmeter. Measures the amount of water inflows in the tunnel.

9.3 Vibration monitoring. Control of vibration is carried out on nearby constructions:

• Heavy constructions.

• Public and Private buildings

• Other structures such as concrete structures in the tunnel, transformers, as well as other structures of importance.

Page 48: GROUTING IN ROCK TUNNELLING

48

10 Grouting into the rock.

10.1 Reasons for grouting in tunnelling. Grouting is the injection of particles suspended in a fluid medium or chemical as a

solution into rock voids mainly for rock reinforcement (support), stabilization of the tunnel

strata and water tightness. Some of the reasons behind grouting are, it support tunnelling

principle such as preventing leakages, protection of groundwater against depletion and

reduces environmental degradation. It also improve stability and durability of the tunnel as

well as leads to smooth excavation.

Excavation of tunnel involves so many risks of which most are related to encountering

unexpected ground conditions. Such risks are the chances of hitting large quantities of

high pressure ground water as well as smaller inflow of ground water which are bound to

cause some problems in the tunnel as well as the surroundings. Ground water inflow

controls remain the most frequent reason for grouting in tunnels, apart from improvement

of ground stability problems. Deteriorating rock condition mostly in weak /shear zones

causing instability problems for the tunnel excavation is another reason for grouting, poor

and unstable ground can be improved by filling discontinuities with a grout material of

sufficient strength and adhesion, i.e. rock reinforcement by grout injection. 25(Garshol

2003, Raymond 1996, J. Warner 2004, C. Kutzner 1996).

In general, ground water ingress can be controlled by drainage, pre-excavation grouting

and post-excavation grouting.

Pressure grouting in rock is executed by drilling boreholes of suitable diameter, length and

direction into the rock material, placing packers near the hole opening or alternatively,

other means of providing a pressure tight connection to the borehole, connecting a grout

conveying hose or pipe between a pump and the packer and pumping a prepared grout by

overpressure into the cracks and joints of the rock surrounding the boreholes.

10.2 Comments on Pre-grouting and Post-grouting. Grouting in tunneling could be classified into two namely:

25 Knut F. Garshol (2003). Pre-Excavation Grouting in Rock Tunnelling. Raymond W. Henn. (1996) Practical Guide to Grouting of Underground Structures. James Warner (2004) Practical Handbook of grouting. Soil, Rock and Structures. Christian Kutzner (1996). Grouting of Rock and Soil.

Page 49: GROUTING IN ROCK TUNNELLING

49

• Pre-excavation grouting or Pre-grouting.

• Post-excavation grouting or Post- grouting.

• Pre-excavation grouting or pre-grouting: Involves grouting ahead of the excavation, where the boreholes are drilled from the tunnel excavation face into the virgin rock in front of the face and the grout is pumped in until refusal pressure is maintained and allows setting, before advancing the tunnel face through the injected and sealed rock volume.

The advantages of pre-grouting are:

• protection against high water inflow during excavation work,

• lowering of the groundwater table can be limited or totally prevented,

• higher grouting pressures can be used,

• strengthening of rock around the tunnel,

• less grout consumption,

• more controlled grout wandering, hence limited grout leakage to the tunnel,

• easier charging of blast or advancement of TBM stroke.

The disadvantages of pre-grouting are:

• interruption of excavation work

• blasting and deformations around the tunnel might open joints and fracture again,

• expensive if done from the surface into the tunnel,

• orienting of grouting holes might be difficult since the leaking spot is not directly seen.

Post-excavation grouting, or Post grouting: where the drilling for grout holes and

pumping in of the grout material to refusal pressure take place somewhere along the

already excavated part of the tunnel due to unacceptable water ingress beyond minimum

requirement. It is worth knowing that, post-grouting is a supplement to pre-grouting, to

seal off the remaining spot leakages if necessary most especially when the pre-grouting

has not satisfied the required average tightness within a given section of the tunnel i.e. 2

l/100 m. It is interesting to observe that post grouting is much more effective when the

same area has already been pre-injected, as the usual problem of leakage points shifting

from one tunnel location to another, without really sealing them off are in most cases

avoided. This is due to the facts that the latter process seals the open joints in the rock

Page 50: GROUTING IN ROCK TUNNELLING

50

before the water starts to flow through the dyke, discontinuities or faults, whereas with

post-grouting the water has started to flow into the tunnel and the joints have to be blocked

with the water flowing through them. One of the possible problems that have to be faced

with post-grouting is “grout wash-out”. Based on experience, it has been indicated that the

time and cost of reaching a specified result by post-grouting may be 30-60 times higher

than by pre-grouting hence, its highly recommended that in cases where large water

inrushes are expected and most especially at high ground water head, to carry out probe

drilling ahead of the face and to embark on pre-grouting if large water in flow is detected. 26(P. Tolppanen & P. Syrjanen 2003)

A few advantages of post grouting are as follows:

• does not disturb excavation work,

• easier to plan, since rock surface are visible,

• grouting can be limited to a certain area where leakage exists,

• grouting of tunnel bottom is a problem,

• lower pressure can be used,

• water usually finds a new route, and,

• Water inflows from the tunnel floor are difficult to localize.

Based on experience, it’s generally agreed that post-grouting is extremely expensive and

time consuming as well as less effective than pre-grouting. In difficult situations, it can be

close to impossible to be successful (complicated).

Other grouting activities that could be classified under post grouting activities are the

following: (Raymond W. Henn. 1996).27

• Contact grouting.

• Consolidation grouting.

• Curtain grouting.

26 P. Tolppanen and P. Syrjanen (2003). Hard Rock Tunnel Grouting Practice in Finland, Sweden and Norway – Literature Study. 27 Raymond W. Henn. (1996). Practical Guide to Grouting of Underground structures.

Page 51: GROUTING IN ROCK TUNNELLING

51

• Contact Grouting: Contact grouting involves the filling of voids between concrete

linings, cast-in-place or pre-cast, and the host geologic material. It also includes the

filling of voids behind steel and cast iron liner segments. It is also used to fill

similar voids between steel penstock lining backfill concrete and the host rock.

Some excavations in rock require an initial support using pre-cast concrete

segments; steel ribs and lagging, or shotcrete followed by a cast-in-place concrete

liner. The voids left between these two lining systems often require contact

grouting. Contact grouting is otherwise known as “backfill” or “backpack”

grouting.

Cast- in- Place Concrete Lining:

The occurrence of voids between cast-in-place concrete linings and rock is not uncommon,

particularly when concrete is placed overhead, as in tunnel crowns and chamber roofs.

Voids can also form in the lower quarter-arcs in circular tunnels containing reinforcing

steel and around curved structures such as elbows that form the transition from shafts into

tunnels.

Voids in concrete placed overhead usually occur because concrete behaves like a fluid

during placement and consolidation by vibration before it takes an initial set. In its fluid

state, concrete tends to maintain a horizontal surface; therefore, a void will form at the

high point of a pour. Voids also develop due to the presence of trapped air, a poor concrete

placement procedure, insufficient concrete slump, or unstable concrete. Obstructions to

concrete flow during placement from items such as rock bolts, mine straps, embedded

conduit and piping, or steel set and lagging, could also cause voids. A predetermined

pattern is given for hole layout, spacing, depth and refusal pressure and is shown on the

contract drawing. 28(KEJV,VIJV, Raymond. Henn 1996). Two and one hole patterns on

3m centres were used in the power intake of the Head Race Tunnel. The other technical

requirements such as mix design, injection pressure and refusal pressure (3 bars) were also

specified.

28 KEJV: Kárahnjúkar Enginering Joint Ventures. Kárahnjúkar Hydroelectric Power Project Designer. VIJV: Viseningar Joint Ventures. Kárahnjúkar Hydroelectric Power Project Supervision Team.

Page 52: GROUTING IN ROCK TUNNELLING

52

• Consolidation Grouting. Consolidation grouting involves the filling of open joints, separated bedding planes,

faulted zones, cavities, and other defects in the rock up to some distance (e.g 15 m),

usually a minimum of one tunnel diameter, beyond the excavation limits. Consolidation

grouting strengthens the foundation material and reduces the flow of groundwater into the

structure. In the case of high-pressure water tunnels, consolidation grouting minimizes the

flow of water outward through the structure’s lining into the surrounding rock after the

facility has been put into service. Moreover, water and associated increase in water

pressure in the foundation material adjacent to the structure caused by the outward flow

may be unacceptable for structural, aesthetic, and even environmental reasons.

29(Raymond H.1996, Arvind Shroff & Dhananjay L. Shah.1999).

Defects in the rock surrounding the excavation may be naturally occurring, been in

existence prior to the excavation, or the defects may have developed as a result of ground

vibrations during excavation. It is also possible for existing defects to have been worsened

by the excavation process. All excavated surfaces “relax” or move, into the opening after

the rock is removed. Movement of this nature may cause once tight joints to open and

bedding planes to move a part. Additionally, the rock beyond the excavation limits is

disturbed by forces created by the act of excavating. In general, vibrations and expanding

gas pressures caused by blasting as in the case of drill and blast will disturb the rock

surrounding the excavation to a greater degree than mechanical excavation methods do

such as tunnel-boring machine (TBM).

The contract specification enclose the requirement to perform consolidation grouting, and

the need for consolidation grouting based on the decision taken by the designer will be

based upon geotechnical data that is collected during the geological site investigation

phase of the project as well as the construction methods used. A predetermined pattern,

shown on the contract drawings, is adopted for hole layout, spacing, and depth. The

specification should also contain other technical requirements, such as mix design,

injection pressure, and refusal criteria.

29 Raymond W. Henn. (1996). Practical Guide to Grouting of Underground structures. Arvind Shroff & Dhananjay L. Shah.(1999). Grouting Technology in Tunnelling and Dam Construction. 2nd Edition.

Page 53: GROUTING IN ROCK TUNNELLING

53

In general, unit pricing is used to offset pay for consolidation grouting and items such as

the depth of holes drilled (15m), the number of set-up, and the quantity of grout mixed and

placed by volume are common pay items.

• Curtain Grouting.

Curtain grouting of tunnel is made as post-grouting. It is carried out for stabilization

purposes or as sealing of visible leaks or cracks. The grouting is done as a radially fan

pattern, either perpendicular to the centre line or in a direction crossing as many cracks

and fissure planes as possible. Since curtain grouting is done as post-grouting the utilized

grout pressure is limited (low), contrary to pre-grouting where high sealing pressure can

be adopted.

Curtain grouting is also done to prevent the tunnel becoming a drainage pipe in the rock

after a few years, when temporary filled cracks will be flushed clean again. 30(Petterson

and H. Molin 1999).

Pressure grouting into the rock mass surrounding a tunnel, is a technique that has existed

for more than 5 decades, and it has developed rapidly during the last 2 decades. Much of

the development into a high-efficiency economic procedure has taken place in

Scandinavia. Pressure grouting has been successfully carried out in arrange of rock types

ranging from weak sedimentary rocks to granitic gneisses and has proofed effective

against very high hydrostatic head as well as in shallow tunnels.

Contact, consolidation and curtain grouting were intensively carried out in the power

intake stretch of the tunnel which covers the first 1-km of the Kárahnjukar Head Race

Tunnel, these section of the tunnel are with cast in place concrete lining.

10.3 Reasons behind increase in the use of pressure grouting. Some of the rationale behind the increase in the use of pressure grouting ahead of the face

in modern tunnelling works within the last two decades are the following:

• Limits on permitted ground water drainage into tunnels are now frequently imposed by concerned authorities; this is mainly due to environmental protection and sometimes to avoid settlement above the tunnel. A typical

30 Sten-Ake Petterson and Hans Molin (1999).Grouting and Drilling for Grouting: Purposes, applications, methods and equipment with emphasis on dam and tunnel Projects. Atlas Copco Crealius AB Publication.

Page 54: GROUTING IN ROCK TUNNELLING

54

effect of settlement is damage on the surface, e.g. to infrastructure like buildings, roads, drainage pipes, supply lines and cable ducts.

• The risk of unexpectedly major water inrushes can be virtually eliminated as a result of the systematic probe drilling ahead of the face which prematurely detects the possibility of hitting major water features.

• Poor ground ahead/behind the face can be substantially improved and stabilized before or after exposure by excavation. This goes a long way to improve the stability, thus reducing the risk of uncontrolled collapse in shear zone.

• Permanent sprayed concrete tunnel linings are increasingly being adopted since the saving potential in projects cost and time is of importance, this remain one of the main reason for the increased interest in permanent lining shotcrete technology. This operation can not be effective under wet conditions hence; grouting operations might become a possible solution.

• The risk of pollution into and from the tunnel can be avoided or limited. This is because once the ground has been treated with pre-grouting coupled with post-grouting if required; it becomes less permeable for stored materials to freely ingress or egress from the tunnel.

10.4 Design of grouting in rock tunnels. Design of grouting in rock tunnels encompass the development and specification of

drilling patterns, the mix design, the grout materials to be used and the methods and

procedures to be applied during execution. These variables can be controlled by grouting

engineers, geologists or specialists; these are varied depending on the actual local

conditions in the tunnel, all aiming at achieving reliable results. The success of grouting

activities could not be accurately predicted because of the nature of the technique and the

lack of details regarding ground conditions. The indirect signs and effects on water ingress

after operations are used to asess the effectiveness of the grouting operations.

The design of tunnel grouting operations depends upon the best estimates of the average

permeability of the rock through which the tunnel is to be driven. These include

calculation of the likely water ingress, drawings showing procedure such as the depth,

angle and pattern of the intended drilling, execution procedure covering all aspects of the

operation and the materials specification targeted at satisfying the required water tightness

of the tunnel.

Some basic facts to work with in the design of grouting in rock tunnels are as follows:

Page 55: GROUTING IN ROCK TUNNELLING

55

• Once the water tighteness requirements are defined, project data and all available information about rock conditions and hydrogeology can be analyzed and compared with those requirements. This involves calculation of potential ground water ingress under different typical situations. This helps in determining the sequence of steps to take to meet the required tightness of the excavated tunnel.

• Resulting tightness in terms of water ingress achieved can be measured quite accurately. This means that it is possible to move to a reasonable comparison between targeted water ingress and the actual result and pinpoint if the situation is satisfactory or not. If the results are positive, the work will continue without changes but with close monitoring of the ingress.

• In case the result is negative, i.e. too high rate of water ingress, the information should be used to decide how to modify the situation to ensure satisfactory results in comparison to the requirements for the remaining tunnel excavation. Execution in stages may be options until a satisfactory result are achieved. Post-grouting will be embarked upon for any excavated sections of the tunnel which do not meet the requirements of the specification until the overall results are acceptable. 31(K.F. Garshol 2003).

10.5 Practical basis for injection works in tunneling. Reasons for pre-injection in tunnelling are different, and the operations can be carried out

under quite variable geological- and hydro-geological conditions. These factors contribute

to the execution of pre-injection in a given case. Some common practical facts exist when

carrying out pre-injection planning and execution.

Limited working space and logistics problems are typical in tunnelling work. In order to

keep the rate of tunnel face advance high, it is highly important that all work sequences are

as rapid as possible, with as small disturbance and variation as possible, as well as with a

smooth change from one operation to the next. This is an important factor for the cost of

the tunnel, since the time associated expenses are running whether there is face advance,

or not.

Voluminous information generated during drilling of holes and during execution of the

injection itself must be treated with care in order to avoid very complicated and time

consuming decision procedures.32(K.F Garshol 1999).

31 Knut F. Garshol (2003). Pre-Excavation Grouting in Rock Tunnelling. 32 Knut. F Garshol (1999). Use of Pre-injection and Spilling in Front of hard rock TBM Excavation. Paper presented at Tenth Australian Tunnelling Conference 1999. Melbourne, Victoria 21-24 March 1999.

Page 56: GROUTING IN ROCK TUNNELLING

56

10.6 Influence of tunneling to the surrounding and the conditions inside the tunnel.

Tunnel excavation affects the immediate surrounding to some extent. This depends on the

location of the tunnel, its design and purpose, ground conditions and hydro-geological

conditions. Such influence could cause problems.

Some of the issues of importance that need evaluation are the followings:

• Location of the tunnel, especially in relation to other infrastructure, other excavation, lakes, rivers and ground water level. Most of the tunnels are below the local ground water level.

• Rock and soil cover, type and characteristics of tunnelling ground, water conductivity of the ground.

• Effects of in and out leakages on economy, environment, safety and health. It has been known that, out leakages can cause as much of damages as the other way round. The hydropower pressure conduits will loose water and electricity production and sewage may cause contamination/pollution. 33(K. F Garshol 2003).

Possible impacts of tunnel excavation on the surroundings are as follows:

• Lowering of the ground water level can cause number of effects among which are, ingress of oxygen to wood foundations which causes rotting. Some rocks, like alum shale may swell due to the creation of gypsum, causing damage to foundations and other structures. (Norwegian cases).

• Ground water resources like springs and wells may be influenced or lost and vegetation may be drastically affected and farming activities damaged.

• Out-leakages effects largely depend on the type of liquid and components in the liquid that is leaking out as well as the hydrostatic head. Some of the effects of water are splitting, jacking or washing out effects at high head and water influx at unwanted locations also at lower head. In the case of contaminated water such as sewage, hydrocarbon liquids, poisonous liquids, gases and others could lead to severe environmental problems in the surrounding.

• In general, Inflow of groundwater may cause settlement of soil deposits above the tunnel; it’s characterized with clay deposits which loose their pore pressure easily. In the case of buildings and other structures founded on clay, serious damages may result. Cases of this nature may arise at water ingress level of 1 to 5 l/min. per 100 m tunnel. (K.F. Garshol 2003).

33 Knut F. Garshol (2003). Pre- Excavation Grouting in Rock Tunnelling.

Page 57: GROUTING IN ROCK TUNNELLING

57

10.7 Condition inside the tunnel. The consequence of water ingress inside the tunnel is visible; these effects are different in

the construction phase in comparison to the operation stage.

• In the case of excavation down a decline, water tends to flow to the face and has to be pumped out. The level of acceptable quantities are usually smaller for a TBM excavation, approximately 0.5 m3/min at the face will cause problems in comparison with drill and blast (D&B) where 0.2 – 2.5 m3/min may be handled with determinant based on a number of other factors. Constant pumping of water may be required which may become an important cost factor at high pumping head/high volumes.

• Concentrated high pressure inrush, may lead to flooding and severe problems as well as delay (time loss). Conditions such as distributed water ingress and generally wet conditions will cause problems such as poor conditions for shotcrete application, concrete works, construction road works, derailing, construction phase dewatering and drainage. Water may have a high or low temperature, leading to a very poor working environment and it may also contain salt common in the case of sub-sea tunnel. Salt water produces corrosion and problems with all electrical equipment underground.

• Largely depending on rock type and quality, water can create instability, rock decomposition, and rock swelling as well as washing out.

• In the operational face of the tunnel, technical installation of different kinds will be installed such as the permanent ventilation system, electrical supply and operation systems in the case of metro tunnels. Humid conditions will over time cause corrosion and the likes of which the maintenance and repair cost may become high.

In cold climate and ventilated tunnels, water ingress can cause ice build up. This should not be allowed and has to be taken care of if it occurs. In the case of traffic tunnel, even local drips (less than 1 l/min. per 100m tunnel) of minor or no concern above the freezing point, can turn into serious problems when the frost volume is high enough.(Garshol 2003).

10.8 Issuing Of Site Instruction. Immediately after excavation, the geology of the new section is mapped and analyzed,

stating the characteristics of the rock mass and the features associated with the area. Also

considered are the results of the probe holes or core samples taken from the virgin rock

ahead of the cutter head in the case of TBM, or the blast face in drill and blast (D&B).

Observations such as the amount of water ingress and rate of penetration during drilling of

the probe hole goes a long way in guiding the engineers or specialists on the next stage of

action. In case of enormous amount of water inflow with high rate of drill rod penetration,

Page 58: GROUTING IN ROCK TUNNELLING

58

pre-grouting, if feasible cementacious type, are instructed in conjunction with rock support

depending on the excavation class. In the case of only enormous water inflow with low

rate of rod penetration/ strong bedrock, only pre-grouting often with chemicals are

instructed.

The decision is normally issued out in the form of site instruction to the contractor, which

describes and formally instructs the procedure and precautions to be followed in achieving

desired results. Information such as the orientation, diameter and depth of drilling holes,

chainages, diagram/drawing, sequence of injections, types of grout materials to be used

and equipments, general comments/precautions and closing criteria including refusal

pressure are instructed.

The results of grouting action performed are submitted for assessments including the

amount of grout intake per hole as well the effects on the amount of water ingress.

This goes a long way to determine the next line of action to be taken after settling time of

the grout perhaps to advance by few strokes in the case of TBM or one round of blast as

the case with drill and blast. 34(Tomasz Najder 2006, Peter Pitts 2006).

34 Tomasz Najder (2006). Personal Discussions. VIJV: Viseningar Joint Ventures Senior Grouting Engineer. Kárahnjúkar Hydroelectric project Supervision Team. Peter Pitts (2006). Personal Discussions. VIJV: Viseningar Joint Ventures Senior Geotechnical Engineer. Kárahnjúkar Hydroelectric project Supervision Team.

Page 59: GROUTING IN ROCK TUNNELLING

59

11 Boreholes in Rock.

Basically drilling methods can be divided into two main groups:

A. Percussive Drilling: Here the rotation of the drill bit is done during the rebound from

the rock in the bottom of the hole.

B. Rotary Drilling: Here, the rotation of the drill bit takes place while it rests against the

rock in the bottom of the hole. 35(H. Frank Eggington et al; 1996. ADITC, Petterson and

H. Molin 1999).

11.1 Top hammer percussive drilling. This is the most common drilling method in hard rock – as well as medium hard rock

tunnelling. The drill rods are attached to the drilling machine using coarse threads and the

energy from the hammer blows travel through the drill rod to the drill bit at the end.

Torque is being constantly delivered by the drilling machine for the drill rod and drill bit

rotation at certain speed which could be in the range of 80 to 160 rev. / min. with hole

diameters often above 102 mm (4 inch.) and depth limited to approximately 60 metres.

The drill rods are coupled in the case of holes length greater than the rod length (5 m.).

The commonly used borehole diameters are 51 mm, 64 mm as well as 76 mm.

Within the last two decades, the hydraulic drilling machine has completely replaced

pneumatic machines. Most of the modern hydraulic machines can penetrate at 1.5 to 2.0

m/min. even in hard granitic rock. In the case of longer grouting holes, the directional

deviation depends on a number of factors, primarily the chosen equipment and practical

procedures and secondarily on the condition of the rock. Holes drilled near horizontal have

been known with higher deviation than vertically drilled holes. By a careful and slow start

of the hole, preferably until the first drill rod length has entered into the rock and by a

slightly reduced feeder pressure, the deviation can be drastically reduced. Stiffeners could

also be applied to the first drill rod, thus further reducing the deviation. The disadvantage

with stiffeners on the drill string is the problem of ground seizing in poor ground. There is

high risk of getting the drill string stuck in the hole. 35 H. Frank Eggington et al; (1996). The Mannual of Methods, Applications and Management. 4th Edition. 1996. Australian Drilling Industry Training Committe Limited. (ADITC). Sten-Ake Petterson and Hans Molin (1999).Grouting and Drilling for Grouting: Purposes, applications, methods and equipment with emphasis on dam and tunnel Projects. Atlas Copco Crealius AB Publication

Page 60: GROUTING IN ROCK TUNNELLING

60

During the drilling of injection holes, it is important that the borehole is as circular as

possible and with the correct diameter. The packer will then have the best possible chance

to seal the hole without any problems. In order to achieve high productivity and good

economy, drilling of probe holes and injections of more than 5 m length, will require

hydraulic equipment for the handling of drill rods, including coupling and decoupling.

High productive percussive drilling requires constant water flushing for removal of the

drill cuttings, proper flushing remains very important to reduce the risk that fine materials

that may be blocking joints and cracks which are meant for effective grout penetration.

The remaining rock cuttings may also interfere with the packer seal. A secondary grinding

of particles which arises from the rotation of the couplers and the drill rods and friction

against the bore holes walls. This secondary grinding action and the risk of squeezing fines

into joints and cracks are highly reduced by sufficient water flushing. (Petterson and H.

Molin 1999).

Advantages associated with percussion drilled grout holes are:

• Much better penetration in rock than for other methods.

• Smaller and light drill rigs can be used easily moved from one hole to other on surface.

• Low drilling cost compared to rotary drilling.

• Optimization of the equipment when drilling through layers of different hardness and thickness.

Top hammers percussive drilling is the most common and generally also the least

expensive method, but it limits the hole depth and causes the greatest hole deviations

which results to increased numbers of holes and costs as well as lower quality.

11.2 Down the hole drilling. This technique is also a percusive drilling method except that, the drilling hammer works

directly on the drill bit and follows the drill bit into the borehole The drill rods serve as

feeder pressure, rotational torque and to convey the flushing medium. Due to the facts that,

the hammer blows are always directly on the drill bit, the rate of drilling is then not much

influencd by the hole lenght. The typical rotation speed is 10 to 60 rev./min. With hole

diameters of 85 mm and upward.

Page 61: GROUTING IN ROCK TUNNELLING

61

Down the hole drilling methods is not often used for drilling of injection holes in

underground works. Though, it may be considered in special cases such as if the greater

hole diameter is of benefit and a long hole with small deviation is required or if it is

necessary to use a casing for hole stabilization.

Down the hole drilling gives straighter and deeper holes, but at the same time requires a

larger hole diameter. When running at high pressures, compressors are needed.

11.3 Low speed rotary drilling. This methods works by point crushing under the rotary drill bit, due to the rotation and

axial feeding. The methods is not efficient in hard rock and the minimum diameter

necessary makes it unsuitable for injection drilling. Rotation speed will decrease with

increasing bit diameter.

Rotary cutting drilling. Rotation speed is 50-600 rev/min.

Rotary crushing drilling. Rotation speed is 50-120 rev/min

Auger drilling. (H. Frank Eggington et al; 1996).

11.4 High speed rotary drilling. (Core drilling). Core drilling is also a rotary drilling method but in this case, the drill bit is a cutting tool

and not crushing. The drill rods are steel pipes and the drill bit is a ring shaped bit with

diamonds as the cutting material. The feeding pressure and rotation torque is produced by

the drilling machine at the hole opening. The equipments are normally hydraulic and the

machine is typically powered by electricity.

Core drilling is not used for normal injection drilling, but for investigations ahead of the

tunnel face and for special case injection at greater depth. Cores of rock material that is

retrieved from the borehole are produced for inspection, laboratory testing and geological

logging. Normal hole diameters ranges from 45-56-66-76 mm as well as 86 mm.

Hole lenghts in the range of 100 to 300 m are possible, depending largely on rock

condition and equipment. Drilling capacity is usually up to 5 m/h and the deviations in the

range of 2-3% for short holes (<15 m) and around 5 % for long holes.

Page 62: GROUTING IN ROCK TUNNELLING

62

Core drilling produces round and smooth holes and typically the clogging of cracks and

joints in the rock is less (reduced), compared to percussive drilling. The cost and time

needed for core drilling is still much higher than for percussive drilling hence, it is only

used in special cases.

Some advantages of high speed rotary drilling are:

• The same equipment can be used for both investigatory and grout hole drilling.

• Continuous or intermittent exploration of the rock is possible over the whole lenght of the hole.

• Drilling can be done to greater depths.

• Straight and greater depth holes are of minimum deviation.

• Limited clogging of the rock fissures, flushing removes all cuttings from the hole.

• Wide applications in all kinds of rocks

• It is possible to use most of the power alternatives to drive the equipment.

• Good penetration speed in soft formations

• Easy packer installation into the hole

High flush water speed in the annulus does not cause cuttings to block the fissures which are to be grouted later. (Petterson and H. Molin 1999).

Requirements for grouting drillholes.

The drilling of grout holes is carried out in many different ways, depending on the

demands from the ground being dealt with, the type of grouting to be carried out, the

availability of equipment, etc.

In general, the method selected must:

• Drill a straight hole,

• Protect the hole walls from caving in,

• Produce drill cuttings of such a size, that they can be flushed out without closing the fissures in the ground or blocking the subsequent grouting,

Page 63: GROUTING IN ROCK TUNNELLING

63

• The drilling method shall be as economical as possible.36( H. Frank Eggington et al; 1996, Petterson and H. Molin 1999)

Other requirements are:

• Hole directions

• Drillhole diameters

• Hole depths

• Cleaning of grout holes

• Casing ( Rotating casing and Non-rotating casing).

Hole straightness: The straightness of a drillhole depends on several factors which include;

• the drilling equipment

• the drill feed positioning

• collaring

• cracks and fissures in the rock

• hardness of the rock

• feed thrust and bit impact

• drilling angle

• drillhole inclination

• rotation speed

• the annulus gap (area difference between drillbit and drill string).

• Unstable set up of the drill rig

• Choice of drill bit.

36 H. Frank Eggington et al; (1996). The Mannual of Methods, Applications and Management. 4th Edition. 1996. Australian Drilling Industry Training Committe Limited. (ADITC). Sten-Ake Petterson and Hans Molin (1999).Grouting and Drilling for Grouting: Purposes, applications, methods and equipment with emphasis on dam and tunnel Projects. Atlas Copco Crealius AB Publication

Page 64: GROUTING IN ROCK TUNNELLING

64

12 Typical solution example for drill and blast excavation.

Drilling for grouting (20-30m) - Grouting – Drilling for blasting (3-6m) – Blasting –

Scaling – Mucking – Bolting – Shotcreting – Control.

12.1 Probing ahead of the face. In the excavation of tunnel, all information about the virgin rock condition in the face may

be scanty though, the general average conditions may fairly be well known but cases of

local features (dyke, fault, joints or cracks) that may suddenly exposed yielding enormous

litres of high water pressure. In addition to this, the striking differences between normal

hard rock tunnelling conditions and the sudden occurrence of a major shear zone

containing swelling clay and crushed rock can be catastrophes if exposed without any

warning. In most cases, this leads to delay of production.

Probing ahead of the tunnel face by percussive drilling is one of the ways of reducing

these afore-mentioned risks. Log information gathered during drilling such as the rate of

drilling rod penetration, types of drill cuttings, colour of sludge, changes in fragmentation

of the sludge, loss or reduction of flushing water, amount of water inflows among others,

all linked to depth from the tunnel and goes a long way to predict the rock conditions as

well as the hydro-geological conditions a head of the face. Based on the observations and

the resulting interpretation, decision can be made on possible action regarding additional

drilling, execution of pre-injection, embark on few strokes of the cutter head or start of

drill and blast as the case may be.

This method remains the best for investigation of water within a reasonable time and cost

frame operating from a tunnel face. In most kind of full face Tunnel Boring Machine,

custom designed percussive drilling equipment is attached for practical use. In the case

whereby additional investigation is suggested, a core hole will produce a lot more

information and more accurate data, but it takes too much time to be used as a routine tool

and off course, more expensive. 37(Knut F. Garshol 1999, Petersson and H. Molin 1999, H.

O. Honnestad & K. F Garshol 2002, P. Tolppanen, P. Syrjanen 2003).

37Sten-Ake Petterson and Hans Molin (1999).Grouting and Drilling for Grouting: Purposes, applications, methods and equipment with emphasis on dam and tunnel Projects. Atlas Copco Crealius AB Publication.

Page 65: GROUTING IN ROCK TUNNELLING

65

In drill and blast excavation, the equipment is already there and the additional effort of

drilling some of the blasting holes as overlapping to a greater depth for probing ahead is

very common. In general, Overlapping holes are drilled (20-30m) from the face covering

the perimeter of the tunnel and extending some distance beyond the blasting holes are

used. The number of probe holes required will largely depend on the size of the tunnel,

the rock type and ground water regime as well as the potential consequences of not

detected problems. The probability of problem detection increases proportionally to the

number of holes drilled. 38(H. O. Honnestad et al; 2002, Tomasz Najder 2006, Personal

Communication on site.

In the case of sub-sea tunnels, which normally lie below rivers or lakes or somewhere with

a high risk if the rock cover is shallow, the probe drilling must be targeted at more than

just detecting water but as well as water tightening or grouting holes.

The advantages of percussive probe drilling are the low cost, the speed of execution and a

fairly high probability of detecting major serious features. Disadvantages lies in the

difficulty of interpreting variation observed except in high contrast features. (Pettersson

and H. Molin 1999, H. Frank Eggington et al; 1996).

In the case of possibility of serious problem within the probing depth and more specific

information is required, a combination including core drilling is often used though, it is

more expensive and time consuming but produce rock sample for detail inspection, where

the exact location of all features can be logged and analyze.

It is also possible most especially at the preliminary stage to use borehole radar systems,

seismic tomography, electrical resistance investigations and similar sophisticated

techniques.

In conclusion, supplies of packers will be maintained in the tunnel throughout all probing

and injection operations for immediate use to seal holes should in case high water inflows

are encountered at any time while drilling. Hans O. Honnestad, K. Garshol and R. Dimmock (2002). Pre-injection in hard tunnels using Degussa Rheocem Microcement. Degussa International UGC Publication. 38 Hans O. Honnestad, K. Garshol and R. Dimmock (2002). Pre-injection in hard tunnels using Degussa Rheocem Microcement. Degussa International UGC Publication Tomasz Najder 2006. VIJV Senior Geotechnical Enginner. Personal Communication on site.

Page 66: GROUTING IN ROCK TUNNELLING

66

Figure 13a. Multi-boom drilling jumbo in operation for blasting and grouting holes.

Figure 13b. Sandvik Tamrock Axera T12 and Atlas copco Rocket Boomer WL3 C drilling

jumbos. At right, a rod changer system for the drilling jumbo (Garshol, 1999).

Page 67: GROUTING IN ROCK TUNNELLING

67

12.2 Drilling of injection holes. Length, Orientation and Number of Holes: All injection holes generally have a length of

about 20 to 30m for cement grouting or 15m for polyurethane grouting but the length may

be adjusted as necessary to meet specific requirements. All holes shall be drilled at an

angle to the tunnel direction to permit a treated grout curtain that fulfils the requirements.

There are situations with very dominating joint orientations that may call for an adapted

borehole direction.

Generally, the spacing of injection holes will be between 1 and 1.5m around the perimeter

of the tunnel. Additional holes may be drilled out from the centre of the tunnel if

considered necessary to achieve either waterproofing or face stability in zones of

weakness. All injection holes are reference numbered.

12.3 Cleaning of holes/ Flushing of boreholes for injection. The first requirement is to provide efficient water flushing during drilling of the hole. The

water pressure shall be at the maximum specified by the drilling equipment manufacturer

and shall be ensured by a special pressure booster on the drilling jumbo. In areas of rocks

with clay filled fissures/joints, carefully supervised flushing operations remain very

important.

Further cleaning of the injection holes may be prescribed as either a combination of water

and compressed air or by high pressure water cleaning. If there are zones in the borehole

that may collapse if soaked in water or if the water ingress from the hole is larger than 10

l/min then, the flushing may be omitted.

Flushing by water and compressed air should be done by a stiff plastic hose using water at

10 bar pressure, combined with some compressed air. Push the hose to the bottom of the

hole, open up the water and air and withdraw the hose while flushing is on. Flushing of

boreholes for grouting should be done as a routine matter and any necessary deviations

must be decided by the supervisor based on the borehole records. (Tomasz Najder 2006

Pers. Comm., Knut F. Garshol 1999).

Page 68: GROUTING IN ROCK TUNNELLING

68

12.4 Placement of packer. The packer is normally placed near to the borehole opening and the hole is injected over

its entire length in one single step. The packer placement depth shall be between 1.5 and

3.0m depth into the borehole, adjusted to the ground conditions and locations providing a

good sealing. However, allowance must be made for a number of possible situations that

may require a different packer placement. It is clearly important that packers are installed

with great care in order to provide effective seals within the drill holes sufficient to

withstand the subsequent grout pressure.

High ground water pressure and very poor rock may speed-up a face failure and the

appropriate action is to place the packer at greater depth (5 m). It happens sometimes that

a fissures causes water and grout backflow to the face and that the packer must be placed

at a depth larger than the depth of intersection between the borehole and this fissure. In

some cases, the borehole is locally disturbed by weak rock material and local wedge

fallout causing the packer to slide or to leak. Placing it deeper is normally the corrective

measure to solve the problem. In principle, there should be an overlap of tight rock (a

buffer either from sound rock or grouted rock from the previous injection round) of

between 5- 7 m in front of the face. Packer placement lies in this zone. 39(Hotter, K G et al,

1996, H. O. Honnestad & K. F Garshol 2002).

12.5 Water Testing/Water Pressure Testing. (WPT) Some of the rationales behind conducting water tests in connection with grouting are:

• To test the ground for stability and the need for strengthening.

• To test the leakage of water and locate the leakage route, to ascertain consequences that this may have on the surrounding structures as well as to evaluate the influence distance.

• The outcome of the afore-mentioned goes a long way to investigate how to stop the leakage of water.

39 Holter K.G et al, 1996. Tunnelling through a sand zone: Ground Treatment experiences from the Bjoroy sub sea road tunnel, Proceeding of North American Tunnelling 1996. Ed: Ozdemir, pp 249-256, Vol 1 (AA Balkema Rotterdam). Hans O. Honnestad, K. Garshol and R. Dimmock (2002). Pre-injection in hard tunnels using Degussa Rheocem Microcement. Degussa International UGC Publication

Page 69: GROUTING IN ROCK TUNNELLING

69

• Another important reason is to decide which type of grout material, method and the refusal pressure to be used.

It is advisable to combined water tests with geological and geotechnical investigations,

such as MWD (measurement while drilling) and core drilling.

Different methods to execute water tests are:

1. Natural flow from an area (Seepage test).

2. Natural flow into or out from a hole (Seepage or permeability test).

3. Pump out test (Permeability test,)

4. Pump in tests (Permeability test, WPT)

Test 1 and 2 involve free running water, test 3 and 4 are done under pressure.

Water Pressure Test (WPT) is otherwise known as “Water Loss Test” in some countries.

WPT´s are done in situ by sealing off the opening to a drill hole and pumping in a

measured volume of water under constant pressure. The flow is a measurement of the

permeability of the ground, but does not directly give a K-value for the permeability. The

result is presented as Lu (for Lugeon, after Maurice Lugeon). One lugeon is the water

intake of 1 litre per metre of drillhole length per minute at a pressure of 1 MPa (10 bars)

above the existing hydrostatic pressure head. 40(Heuer, R.E. 1995, E. Friedrich- Karl 1994,

Water Resources Commission N.S.W 1980. Grouting Manual 3rd edition, Houlsby, A.C.

1976.)

Test hole diameter is mostly in the 40 -100 mm range, but is not decisive for the

permeability test. Before starting a WPT, the hole should always be flushed clean.

Interconnection of adjacent holes with test hole should be monitored and the flow through

of water. For identification purposes, paint is used as an additive to the water pumped in.

40 Heuer, R.E. (1995). Estimating Rock Tunnel water inflow. Proceedings, Rapid Excavation and Tunnelling Conference, Society for Mining, Metallurgy, and Exploration, Inc., Cushing-Malloy, Inc., Ann Arbor, Mich., 41-60. Ewart, Friedrich-Karl, (1994). Rock Permeability and Groutability Related to Dams and Reservoirs, lecture notes, University of Paderborn, Germany, September 1994. Water Resources Commission N.S.W Australia., (1980). Grouting Manual 3rd edition, 1980. Houlsby, A.C. (1976)“ Routine Interpretation of the lugeon Water Test”, Quarterly Journal of Engineering Geology, Vol. 9, The Geological Society, 1976.

Page 70: GROUTING IN ROCK TUNNELLING

70

Water pressure testing of boreholes should not be considered as a routine activity. The

long time spent in comparison to the information value produced is the main reason for

this. There is no good reason to invest time and money in such measurement.

12.6 Choice of injection materials. In drill and blast excavation, cement grouting is the original and in general the most

common method in controlling the water inflow. In the case of Kárahnjúkar Head race

tunnel excavation, Ordinary Portland Cement (OPC) of different mix design and largest

granule size of about 125 µm were used. The thickness of the mixes varies from one

another based on the water cement content (W/C) and the typical settling time (bleeding

period) for these mixes is 2 hours under 5o-20o C, allowing work to proceed without any

delay. The range of commonly used and adopted mix design are Mix 211-05 W/C 0,5,

Mix 208-05 W/C 0,67, Mix 203-05 W/C 0,45. (VIJV- Database 2006).

Depending on the ground conditions and the required level of maximum ground water

leakage into the underground openings, chemical grout may be considered. Inflow of

ground water through joints and cracks in the face or elsewhere may cause problem of

grout washout and backflow, such problem can be solved by injection of quick foaming

polyurethane which can be used as a temporary flow blockage

12.7 Injection pressure and procedure. The decision criteria for injection to be carried out must be specified. This is in most cases

based on measured water in-leakages from the probe holes and can be a given number of

l/min from a single hole or a maximum sum leakage from all the probe holes. In general,

the balance between these criteria and the target tunnel tightness must be based on

experience and local rock conditions, with the option of feedback from actual results

during operation.

Maximum injection pressure has to be evaluated on a running basis and especially it has to

be checked against local conditions in the tunnel. Very poor rock conditions in the face

area, high hydrostatic water pressure and existing backflow will be indicators that

maximum pressure must be limited, even if the rock cover is hundreds of meters away.

Page 71: GROUTING IN ROCK TUNNELLING

71

In pre-injection, the maximum allowed pressure should be used from the beginning of

injection or alternatively until one of the following occurs:

1) No more grout is accepted by the ground at maximum allowed pumping pressure.

11) The maximum specified grout quantity for the hole has been reached, regardless of

pressure but re-grouting of the hole after settling time until refusal pressure is achieved

becomes paramount.

Allowed maximum grouting pressure should be at least 50 bars above the static ground

water head; unless there are special reasons identified requiring a lower maximum

pressure. In pressure sensitive situations, it should be recognized that the danger of

causing damage by lifting, splitting or other deformation is linked to effect of pressure and

quantity rather than to pressure alone. 41(Barton, N and Quadros, E., 2004, Arvind Shroff

& Dhananjay L. Shah.1999, Knut F. Garshol 2003, Sjostrom O.A 2003).

Injection procedure:

1) Start injection of the lowest hole in the face and work upwards. (Bottom-up approach).

11) A hole is finished when the maximum specified grout quantity per hole is reached and

the refusal pressure attained.

111) if backflow of grout and water into the tunnel is detected, this should be minimize by

reducing the pump output and adding accelerator to create a blockage of the backflow.

1V) if during the injection process two or more holes become connected as indicated by

grout backflow through the hole, close the packer in the connected hole and continue

grouting the current hole. The maximum volume of grout to be pumped before the stop

criteria are reached shall be multiplied by the number of connected holes. If the maximum

pressure is reached before the maximum quantity, then the connected holes shall be

injected as well, if they take any grout.

V) All holes that do not require injection shall be filled with a stable cement grout.

41 Barton, N and Quadros, E., (2004) “ Improved understanding of high-pressure grouting effects for tunnels in hard rock” ISRM 2003 – Technology road map for rock mechanics, South African Institute for Mining and Metallurgy. Arvind Shroff & Dhananjay L. Shah. (1999). Grouting Technology in Tunneling and Dam Construction. 2nd Edition. Knut F. Garshol (2003). Pre-Excavation Grouting in Rock Tunnelling. Sjostrom O.A. (2003). Principles and Ground water Control through Pregrouting in Rock Tunnels.

Page 72: GROUTING IN ROCK TUNNELLING

72

12.8 Injection records and quality control during injection. Records of the injections data have to be taken as a matter of routine; most of these may

be automatic by computerized recording or otherwise, there must be well prepared forms

to be used in the tunnel during work progress. It must be well defined who is responsible

for the record keeping. As a minimum, the following information must be recorded:

1) General data like tunnel chainage, date, time and shift, person who does the recording,

identification and location of all holes, measured water flow from the holes.

11) Per hole: packer placement location, type of packer, length of hole, grout mix design,

pressure at start and end, time at start and end, total grout quantity, any leakages

(backflow) and any connections to other holes.

111) Results of quality control holes.

The following quality control tests shall be carried out:

• Cup tests to ascertain setting time and bleeding.

• Marsh cone tests to indicate viscosity

The frequency of the tests will be determined by the site supervisor.

12.9 Settling of grout, time until next blast. The typical setting time for Ordinary Portland Cement (OPC) grout with additives is 2-3

hours ensuring smooth running of work. As the water pressure increase and the fissure

openings gets larger the risk of grout material failure and wash out will increase. It is

difficult to give general rules on how this situation is evaluated, but the consequences of a

failure, time required for setting, the water pressure and fissure size in the ground have to

be considered.

In the case of accelerator been used to shorten setting time, this off course is a good help

for the actually accelerated grout, but based on experience, it has been proofed that only a

part of the grout in one injection stage is normally accelerated. If the next planned activity

is drilling of boreholes for control of the injection results or for a next round of grout

holes, always start drilling in the area where the previous injection was terminated (To

allow maximum setting time). (Knut F. Garshol 2003)

Page 73: GROUTING IN ROCK TUNNELLING

73

12.10 Drilling of control holes. Control holes must be evaluated to assess the efficiency of any injection stage. Control

holes are drilled on both sides of all holes that yielded water flow above the injection

criteria. Re-injection may be necessary depending on the result of testing in the control

holes and compliance with the specified criteria.

Re-injection is carried out using a pattern of holes alternating with the previously injected

holes. This is followed by further control holes and further injection stages as necessary,

until the specified criteria are achieved.

Limited post excavation grouting may be embarked on later if necessary to achieve the

specified inflow requirements in local areas of the tunnel if it is not possible to achieve the

criteria in particular areas by pre-injection alone.

Page 74: GROUTING IN ROCK TUNNELLING

74

13 Typical solution example for Tunnel Boring Machine (TBM).

13.1 Probing a head of the face. Most of the full face Tunnel Boring Machine is equipped with custom designed

percussive drilling equipment practically used for drilling grouting holes and probe hole a

head of the cutter head. One of the visible disadvantages of this attached percussive

drilling equipment is the in-ability to drill holes close to the invert i.e. below 8 o, clock

and 5 o, clock. Overlapping probe holes are maintained during excavation in order to

ascertain the state of the virgin rock ahead of the cutter head and also to guide in taking

precautionary approach against the chances of encountering high water pressure or shear

zones which may lead to temporary delay in production.

Figure 14. Pre-grouting drilling system on a Robbins TBM (Garshol, 1999).

13.2 Drilling of injection holes. Drilling a head of a hard rock Tunnel boring machine is difficult because of the very

limited available space close to the tunnel face. The TBM occupies almost all the volume

for the first roughly 15 minutes. Typically the angle drilling is between 15o and 20o

depending on the arrangement of the drill rigs on the TBM. The length, orientation and

number of injection holes are specified and reference numbered. 42(H. O. Honnestad & K.

F. Garshol 2002, K. F. Garshol 1999, Schunnesson H. 1996).

42 Knut F. Garshol (1999). Use of Pre-injection and Spiling in Front of Hard Rock TBM Excavation. Paper Presented at Tenth Australian Tunnelling Conference 1999. Melbourne, Victoria 21-24 march 1999.

Page 75: GROUTING IN ROCK TUNNELLING

75

13.3 Cleaning of holes/ Flushing of boreholes for injection. Constant flushing of the injection holes while drilling must be ensured. The effect of

neglecting this can lead to rapid blockage of the intersected water bearing channels meant

for grout. Sludge and rock cuttings from the drilling process are forced into the openings

by the injection material as well as the pumping pressure.

13.4 Placement of packer. The packer placement depth shall be between 1.5 and 2m ahead of the TBM face. The

depth will depend on the angle of the hole and length of the cutter head. For example for a

hole collared 4m behind the cutter head face in an open TBM the packer should be at least

6m into the hole. However, allowance must be made for a number of possible situations

that may require a different packer placement. It is clearly important that packers are

installed with great care in order to provide effective seals within the drill holes sufficient

to withstand the subsequent grout pressure.

13.5 Water Pressure Testing. Water pressure test is not required in TBM excavation and not normally been carried out.

It found more application in consolidation and curtain grouting to determine the lugeon

and the procedure as well as the stages of grouting that may be required.

13.6 Choice of injection materials. The choice of injection materials largely depends on the amount of inflow from the probe

holes or the total amount of leakages from the face. In general, high inflow of water

requires a very fast reaction grout which makes chemical grout more effective. On the

other hand, cement grout with accelerator could also perform the same function by

catalyzing the setting rate as well as enhancing the stability of the zones in the case of

shear zones. In conclusion, inflow per hole greater than 5 l/sec or 15 l/sec from 2 holes

requires very fast reaction grout such as polyurethane.

Hans O. Honnestad, K. Garshol and R. Dimmock (2002). Pre-injection in hard tunnels using Degussa Rheocem Microcement. Degussa International UGC Publication Schunnesson, H., (1996). “ Probing ahead of the face with percussive drilling” Tunnels and Tunnelling, January 1996, pp 22-23.

Page 76: GROUTING IN ROCK TUNNELLING

76

13.7 Injection pressure and Procedure. In pre-injection, the maximum allowed pressure (50-110 bars) should be used from the

beginning of injection or alternatively until one of the following occurs:

I ) No more grout is accepted by the ground at maximum allowed pumping pressure.

11) The maximum specified grout quantity for the hole has been reached.

Other closing criteria are that injection should be interrupted in case of:

• Intensive leaking of non- reacted polyurethane (chemical) into the tunnel.

• The refusal pressure of approximately 110 bars is reached.

• The expanded polyurethane grout fractures the rock close to the surface.

• The packer is not set tightly in its position, but moving towards the mouth of the hole.43(Degussa UGC Europe, Tomasz Najder Personal site discussions, VIJV Database 2006)

Injection procedure:

1) Start injection of the lowest hole in the face and work upwards. (Bottom-up approach).

II) A hole is finished when the maximum specified grout quantity per hole is reached and

the refusal pressure attained.

III) if backflow of grout and water into the tunnel is detected, this should be minimize by

reducing the pump output and adding accelerator to create a blockage of the backflow.

IV) if during the injection process two or more holes become connected as indicated by

grout backflow through the hole, close the packer in the connected hole and continue

grouting the current hole. The maximum volume of grout to be pumped before the stop

criteria are reached shall be multiplied by the number of connected holes. If the maximum

pressure is reached before the maximum quantity, then the connected holes shall be

injected as well, if they take any grout.

V) All holes that do not require injection shall be filled with a stable cement grout.

43 Degussa (BASF) UGC Europe (2006). Practical injection course UGC Europe Region Hagerbach, Switzerland, 4-5. May 2006. Tomasz Najder (2006). Senior Grouting Engineer. Viseningar Joint Ventures. Kárahnjúkar Hydroelectric Power Supervision Team. VIJV Database (2006). Viseningar Joint Ventures. Kárahnjúkar Hydroelectric Power Supervision Team.

Page 77: GROUTING IN ROCK TUNNELLING

77

Alternatively, two holes could be drilled consecutively, often opposite to each other and

grout until the required number of holes is completed.

13.8 Injection records and quality control during injection. Adequate injection data should be undertaken as a matter of routine; General information

such as:

• Tunnel chainage, date, time and shift, person who does the recording, identification and location of all holes, measured water flow from the holes.

• Per hole: packer placement location, type of packer, length of hole, grout mix design, pressure at start and end, time at start and end, total grout quantity, any leakages (backflow) and any connections to other holes.

• Results of quality control holes.

13.9 Setting of grout/ Hardening time. The setting time of Ordinary Portland Cement (OPC) grout is normally 2-3 hours and the

hardening time could be between 8-10 or even 2 days partly depending on the local

condition. Addition of additives and admixtures (accelerator) such as cemsil, sodium

silicates and industrial salts drastically reduced the setting time in order to avoid delay to

work.

In the case of chemical grouting such as polyurethane, its fast reaction time of 10-15

minutes and hardening time of maximum 5-8 hours further reduces the time waste and

hence, ensure smooth production and advancement of the Tunnel Boring Machine.

13.10 Drilling of control holes. Control holes must be evaluated to assess the efficiency of any injection stage. Control

holes are drilled on both sides of all holes that yielded water flow above the injection

criteria. Re-injection may be necessary depending on the result of testing in the control

holes and compliance with the specified criteria.

Limited post excavation grouting may be embarked on later if necessary to achieve the

specified inflow requirements in local areas of the tunnel if it is not possible to achieve the

criteria in particular areas by pre-injection alone. Further decision on additional grouting

Page 78: GROUTING IN ROCK TUNNELLING

78

or the advancement of the Tunnel Boring Machine could then be taken. 44(Knut F. Garshol

2003, H. O. Honnestad & K. F. Garshol 2002).

44 Knut F. Garshol (2003). Pre-Excavation Grouting in Rock Tunnelling. Hans O. Honnestad, K. Garshol and R. Dimmock (2002). Pre-injection in hard tunnels using Degussa Rheocem Microcement. Degussa International UGC Publication

Page 79: GROUTING IN ROCK TUNNELLING

79

14 Packers.

Packers are mechanical tools used to ensure a tight connection (seal) between the pumping

hose and the borehole drilled into the rock formation or soil for the purpose of injecting a

grout at high pressure. They are devices inserted into a grout hole that expands

mechanically or by inflation to restrict the flow of grout to a specific part of the grout hole.

A typical packer consists of a pipe with a coupling in the end as well as an elastic

expander that can be inserted into the hole and expanded against the borehole wall. The

expander will anchor the packer in place so that the injection pressure is not forcing it out

of the hole and also seal off the pressurized section of the borehole from the tunnel side.

The injection pump hose is hooked up to the pipe the pump can be put on.

Different packer types exists, most manufacturers produce in working principle the same

types of packers though, the quality, sizes and technical details may be different. The

ground condition, availability, price and a number of other factors help in selecting

packers for individual project.45(Raymond H.1996, P. Tolppanen & P. Syrjanen 2003,

James Warner 2004, Knut F. Garshol 2003, C. Kutzner 1996).

14.1 Mechanical Packers (expanders). Mechanical packers are re-usable types which are commonly used on construction sites.

The diameter of the rubber expander has to be in a certain relation to the borehole

diameter and the maximum expansion available. Mechanical packers are available in

different standard lengths, commonly from 1.0 m to 5.0 m in steps of 0, 5 m. Users can

also produce their own pipes locally and any suitable length. Connectors are used to join

standard pipe lengths for deep packer placements.

A ball valve or similar parts is normally fitted to the end of the packer-pipe, after the

completion of injection the ball valve is closed and the pump hose disconnected.

45 Raymond W. Henn. (1996) Practical Guide to Grouting of Underground Structures. James Warner (2004) Practical Handbook of grouting. Soil, Rock and Structures. Christian Kutzner (1996). Grouting of Rock and Soil. P. Tolppanen and P. Syrjanen (2003). Hard Rock Tunnel Grouting Practice in Finland, Sweden and Norway – Literature Study.

Page 80: GROUTING IN ROCK TUNNELLING

80

The valve remain closed with the packer in place until the completion of setting time to

keep the ground water pressure then, the packer may be removed and cleaned for re-use in

a different hole. Mechanical packer is applicable for both cement and polyurethane grout.

Pressurized grout would flow back into the tunnel without closing the valve. (Raymond

W.Henn. (1996).

14.2 Disposable packers. (Single application). The working principles of disposable packers are the same to re-usable counterpart

though, they are constructed so that when expanded, the expansion is automatically locked

to allow removing the inner- and outer pipes used to place the packer and expand it. The

packer has a one-way valve to keep pressurized grout in place without backflow when

releasing the pump pressure and removing the pipes.

The Mechanical packers and the disposable ones are not very effective in weak ground,

proper sealing without backflow may be difficult, they may start sliding in the hole and

sometimes they get stuck in the wrong position. 46(BASF (Degussa) Construction

Chemicals,)

46 BASF (Degussa) (2007) Construction Chemicals Europe AG.

Page 81: GROUTING IN ROCK TUNNELLING

81

Figure 15a. Showing disposable packers (With a distance of 100-150mm between the

rubber sleeves). Source BASF Construction Chemicals.

14.3 Hydraulic packers. Inflated packers are otherwise known as the hydraulic packers, the inflation is carried out

through high water pressure supplied through a separate thin line from the tunnel to the

packer location. The packer is handled through a single pipe, which is also the grouting

pipe after expansion. Hydraulic packers have a much wider expansion range and they will

seal better (lengthwise). In other words, hydraulic packers are more expensive. They are

very practical for Water pressure testing in long holes because they are very quick to

expand, deflate and remove and the low risk of backflow around them as well as the good

sealing properties in poor ground are very favourable. (Bimbar 2004, Knut F. Garshol

2003,)

A combination of a hydraulic packer and a disposable self-locking packer can be very

useful and economical under very weak conditions. The hydraulic packer allows

expansion of the disposable packer mounted in the front of it, and the hydraulic packer

Page 82: GROUTING IN ROCK TUNNELLING

82

helps to prevent backflow and sliding during injection. After completion of grout setting

time, the hydraulic packer is removed and the disposable one remains in place.

Figure 15b. Showing inflatable packers. (Source Bimbar 2004).

Page 83: GROUTING IN ROCK TUNNELLING

83

Figure 15c. Showing Inflatable Packers (Source Hany AG Equipment).

14.4 Standpipes techniques. Under poor ground condition, the placement of packer may become very difficult and the

borehole stability may also be at risk, this is very common in shear zones and highly

broken ground in hard rock tunneling. Combination of this condition with high water

pressure often leads to loss of stability and collapse. The drilling of long holes in this kind

of condition becomes a problem as the drill string could easily get stuck and will sometime

break in the bore hole.

One of the best ways of dealing with serious problems of this nature is to use the so called

stand-pipe technique. Using an oversize drill bit of 76 mm diameter to drill to a depth of 3-

4 m, then a steel pipe of suitable diameter (55 mm, 66 mm) could be easily inserted into

the hole, the pipe is then grouted with a fast setting cement grout. Once the grout has set

the pipe can be used to extend the hole by a smaller diameter hole (51 mm) diameter drill

bit. In case of any serious drilling problems of any kind, a packer is placed safely and

tightly in the steel pipe and the drill part can be injected. After completion of grout setting,

the drilling may be resumed for another step of bore hole deepening. The process is

repeated as required until a desire or instructed depth is reached. Plastic pipes could be

Page 84: GROUTING IN ROCK TUNNELLING

84

used to replace the steel pipes as described above as it does not cause any problems for

Tunnel boring machine or Road header excavators.

14.5 Tube-a-manchet. This type of methods is not commonly used in rock injection underground but found its

wide application in soil injection (mostly vertical holes). The principle is based on a

hydraulic double packer been inserted into a pre-grouted sleeve pipe which is surrounded

by a weak mortar often called a mantel grout, which is a simple cement grout with

relatively high content of Bentonite clay. The sleeve pipe has rubber sleeves (non-return

valves) at fixed distance and these valves can be activated individually by injection

pressure between the double packers. The mantel grout is designed so weak that it will

split from the injection pressure and grout can flow into the ground without any leakages

along the bore hole. The packer can then be moved as needed and a given valve can be

grouted many times. Due to the sub-horizontal orientations of most injection holes in the

tunnel, the use of mantel grout around the sleeve pipe for proper filling could be non-

effective as it results to un-wanted grout leakage along the hole. 47( Jaroslav Verfel,

1989, Raymond W. Henn,1996).

14.6 Types used on the Project. • Mechanical packers of different lengths and diameters.

• Disposable packers.

• Inflatable packers of different lengths and diameters. (Bimbar packers ½ m/ 1 m

long.)

47 Jaroslav Verfel (1989). Rock Grouting and Diaphragm Wall Construction. Development in Geotechnical Engineering 55. Elsevier Science Publishers. Raymond W. Henn. (1996). Practical Guide to Grouting of Underground structures.

Page 85: GROUTING IN ROCK TUNNELLING

85

15 Cement-Based Grouts.

15.1 Basic properties of cement grout.

15.2 Cement particle size, fineness. The two important parameters governing the permeation capability of cement are the

particle size and particle size distribution. The average particle size can be expressed as

the specific surface of all cement particles in a given quantity. The finer the grinding, the

higher is the specific surface, or Blaine value (m2/kg).

In determining Blaine value, the particle size distribution may vary and the important

factor is the maximum particle size, or as commonly expressed the d95. The d95 gives the

sieve dimension where 95% of the cement particles will pass through and the remaining

5% of the particle population is larger than this dimension. The maximum particle size

should be small in order to avoid premature blockage of fine openings, caused by jamming

of the coarsest particles and filter creation in narrow spots. 48(Houlsby, A.C. 1990, James

W. 2004, K. Bowen R. 1980, C. Kutzner 1996, K.F. Garshol 2003, Houlsby A.C 1983).

In general, cement with the highest Blaine value will normally be the most expensive, due

to finer grinding and will also give better penetration into fine cracks and openings. From

an injection perspective, this cement is characterized with the following basic properties:

• A highly ground cement with small particle size, will bind more water than a coarse cement. The risk of bleeding (water separation) in a suspension created from a fine cement counterpart is lower and a filled opening will remain more completely filled.

• The finer cements have a quicker hydration and a higher final strength but cause the disadvantages of shorter open time in the equipment. A high temperature increases the potential problems of clogging of lines and valves. Mixing of fine cements must be closely controlled, to prevent heat

48 Houlsby, A.C., (1990). Construction and design of cement grouting, a guide to grouting in rock foundations, John Wiley and Sons, New York, 1990. James Warner (2004). Practical Handbook of Grouting. Soil, Rock and Structures. John Wiley & Sons, Inc. Robert Bowen (1981). Grouting in Engineering Practice. 2nd edition. Applied Science Publishers LTD. London. Christian Kutzner (1996). Grouting of Rock and Soil. A.A Balkema /Rotterdam/ Bookfield/ 1996. Knut F. Garshol (2003). Pre-Excavation Grouting in Rock Tunnelling. MBT International Underground Construction Group. Division of MBT (Switzerland) Ltd., 2003. Houlsby A.C. (1983). Cement Grouting - A Compilation of Recent Papers. Water Resources Commission., NSW, Australia.

Page 86: GROUTING IN ROCK TUNNELLING

86

development caused by the friction in the high shear mixer, and hence even quicker setting.

The effectiveness of these characteristics largely depends on the efficiency of the mixing

process enough to separate the individual particles and properly wet them. In pure and

finer cement with the addition of water suspension, the tendency of particle flocculation is

high after mixing which is against effective production.

The effects of the water reducing admixture (or dispersing admixture) when mixing

cement could be seen on catalyzing the specific surface or Blaine value (m2/kg). Other

great effect of water reducing admixtures is the lowering of viscosity at a fixed w/c-ratio.

The importance of lowering water content is to improve final strength of grout, as well as

lowering permeability and ensure better chemical stability. More important in the cases

with higher water content is that the permeability is so high and the strength is low that

any flow of water can lead to mechanical erosion and chemical leaching out of hydroxides

(hydration products from cement reacting with water). (K.F. Garshol 2003).

Figure 16. Dispersing effect of an admixture using Micro-cement.

Page 87: GROUTING IN ROCK TUNNELLING

87

15.3 Bentonite etc. Bentonites are used to reduce the bleeding of grouts and a dosage of 3 to 5% of the cement

weight has a strong stabilizing effect. Its composition is clay containing some percentage

of clay minerals of the smectite group (usually montmorillonite) characterized by its large

volume increase on wetting.

Because of strong tendency of standard cement to separate when suspended in water,

enhanced by the normal use of water cement ratio greater than 1.0, bentonite has been

traditionally used constantly to reduce this effect and in combination with cement for

grouting of rock and soil.

Bentonite is natural clay from volcanic ashes and the main mineral is montmorillonite. It is

hydrophilic or water swelling (Brady and Clauser 1986, K.F. Garshol 2003).

Basically, two types of bentonite exist:

Sodium- bentonite (Na -)

Calcium bentonite (Ca -)

Sodium- bentonite (Na -): Because of its high stabilizing and swelling characteristic

(between 10 and 25) times the original dry volume when mixed in water, it has been

commonly used as an additive in cement grouts.

15.4 Rheological behaviour of cement grout. Cement mixed in water as a stable paste or an unstable suspension in terms of water

separation behaves according to Bingham’s Law. On the other hand, water and true liquids

have flow behaviour according to Newton’s Law. These laws are illustrated as follows:

Bingham,s Law: T = c + n dv/dx

Newton,s Law: T= n dv/dx.

Where: T= flow shear resistance (Pa).

n = Viscosity (Pa s)

dv/dx = shear velocity (s-1)

c = cohesion (Pa)

Page 88: GROUTING IN ROCK TUNNELLING

88

Figure 17. Rehological behaviour of Newton and Bingham fluids.

A cement suspension demonstrates some cohesion which has to be overcome for any flow

to be initiated as compared to the liquid counterpart. If the internal friction is negligible,

the paste will then behave in a similar manner as liquid. The rheological parameters of

cement suspensions can be affected by w/c- ratio, by chemical admixtures, by bentonite

clay and by other mineral fillers.

15.5 Pressure stability of cement grout and use of high injection pressure. The efficiency of a grouting operation is very difficult to realize since the whole operation

is carried out below ground level. In other words, it can be very well controlled by

(I) Controlling the properties of the grout,

(II) Controlling grout pressure and

(III) Controlling the rate of consumption of the grout.

Some of the precautions to be taken before starting grouting are:

(I) Ensure that the correct borehole and circulation line is connected.

(II) Grout ingredients such as clay, bentonite, additives etc are available in ample quantity

near the mixing plant and ready for use.

(III) Pump, agitator, mixers etc are working properly and have sufficient fuel.

Page 89: GROUTING IN ROCK TUNNELLING

89

(IV) Standpipe fittings and pressure gauges are operating properly

(V) Spare standby equipment is available and anything foreseeable which might interrupt

grouting. (Arvind Shroff & Dhananjay L. Shah.1999).

Refusal Criteria.

Each grout should continue until refusal is reached except

(I) When severe leakages is observed on the surface away from the hole or along the

grout pipe.

(II) When the consumption reaches a predetermined limit

(III) When there is no grout absorption at the limiting pressure specified.

(IV) When an undesirable trend develops indicating bulb formation.

The grouting operation may then be resumed after 24 hours and pressure regulated

carefully to avoid repetition of the phenomena leading to the stoppage of the grouting.

Refusal is considered to have been reached when the intact grout at the desired limiting

pressure is less than 2 litre/minute averaged over a period of 10 minutes and the pressure

greater than 3.5 kg/cm2, or 1 litre/minute when the pressure is below 3.5 kg/cm2.

Time – Pressure – Consumption Curves.

During injection the flow rate of a properly mixed grout should be constantly monitored

and plotted against the grout pressure to understand what is happening below ground. The

pressure at the grout pipe is often much less because of friction losses that occur in long

lengths of hose leading to the pipe, coupled with the existence of a large pressure drop at

all fittings and manifolds.

Typical response curves of flow rate versus pressure and flow rate versus time has been

studied and by means of these curves, one can follow closely how the rock has responded

to the grout being injected 49(Koerner, 1985, Mistry 1988).

49 Koerner, R.M. et al. (1985). Acoustic emission monitoring of grout movement issues in dam grouting. Proceeding session Geotechnical Engineering. Division of ASCE. American Society of Civil Engineer., New York, pp. 202-206. Mistry, J.F. (1988). Important Aspect of River Valley Projects. Mahajan Book Distributors, Amdavad, Gujarat, India, Vol. 2. Arvind Shroff & Dhananjay L. Shah. (1999). Grouting Technology in Tunneling and Dam Construction. 2nd Edition.

Page 90: GROUTING IN ROCK TUNNELLING

90

Based on close observation of the grouting procedure in the project, the behaviour of holes

could be classified into six different categories depending on time- consumption

(litre/minute), and time pressure data. (kg/cm2). (Arvind Shroff & Dhananjay L.

Shah.1999, Jefferies M.G et al., 1982, Baker, C. et al., 1982). These six pairs of standard

curves (A1, A2, B1, B2 and C1, C2) of which each pair indicates certain conclusions are

defined and interpreted below:

Interpretation of curves.

(1) Figure 18. (A1). Consumption drops and pressure remains constant after peak.

This pair of curves shows filling of cracks with the grout material. After reaching the

maximum pressure, a few minor cracks might open out which are again filled up. This is

clear from the curves beyond the peak, i.e. the pressure curve is approximately parallel to

the time axis while the consumption at the nearly constant pumping energy goes on

decreasing. This is the ideal curve and in such case, the procedure should be continued and

grouting completed at the specified pressure until refusal.

Jefferies M.G et al. (1982). Electronic monitoring of grouting. Proceeding. Conference. Grouting in Geotechnical. Engineering., New Orleans. W.H. Baker (ed). American Society of Civil Enginner. New York, pp 769 -780. Baker, C. et al., (1982). Use of grouting in caisson construction. Proceeding Conference. Grouting for Geotechnical Engineering. New Orleans. W.H Baker (ed). American Society of Civil Enginnering. New York, pp. 874-891.

Page 91: GROUTING IN ROCK TUNNELLING

91

(11). Figure 18 (A2). Pressure increases and consumption remain constant after Peak.

This pair of curves shows that the pressure slightly falls due to opening of the cracks.

After filling the crack, the pressure rises and the rate of consumption remain constant. If

the rate of consumption is within permissible limits, the grouting could be stopped. If the

pressure achieved is more than specified, the operation may be continued at a suitably

reduced pump speed. This is also an ideal curve (Scenario) and, in such cases, the grouting

should be continued at the specified pressure until refusal.

Page 92: GROUTING IN ROCK TUNNELLING

92

(111). Figure 18 (B1). Pressure and consumption remains constant after Peak.

This pair of curves indicates that at the peak pressure, the grout continues to travel in the

cracks unchecked. Thus, there is no control on the extent of the curtain. In this case the

grouting operation may be stopped after injecting a certain quantity of grout. The hole

should be left for a while to allow injected grout to set; grouting may then be resumed

after a lapse of about 48 hours, when the cracks will have been partly sealed by the setting

grout.

Page 93: GROUTING IN ROCK TUNNELLING

93

(1V). Figure 18 (B2). Pressure and consumption rise to some value and then fall rapidly.

The pair of curves indicates the opening out of new cracks at peak pressure. On filling of

these new cracks, the pressure and consumptions remain constant throughout, indicating

that at the second peak pressure the grout travel is continuing uncontrolled. In this case

also, the grouting operation may be stopped after injecting a certain quantity of grout (200-

300 kg of cement depending on the length). The hole should be washed thoroughly and the

injected grout allowed setting. Grouting may then be resumed after a lapse of about 48

hours.

Page 94: GROUTING IN ROCK TUNNELLING

94

(V). Figure 18 (C1). After a rise in pressure to a certain value, the pressure remains

more or less constant, while the rate of consumption goes on rising.

This pairs of curves reveals abnormal behaviour in the hole. They indicate that there may

be leakage of grout through natural strata or along the hole or some upheaval in the rock

strata. Grouting should therefore be carried out under strict supervision. Possible spots of

leakage should be located by close inspection around the area and interconnection of grout

holes, if any should also be looked for. If leakage is noticed or if the grout consumption

exceeds maximum grout take (75 kg of grout per metre depth of hole), the grouting should

be stopped and resumed only after a lapse of about 48 hours. Immediately on locating the

leakage point, it should be plugged by excavating a small pit around it and filling this with

lean cement concrete. If there is any interconnected hole through which the grout leaks,

the hole should be immediately washed by pumping water under adequate pressure so that

it does not get chocked before regular grouting is taken up in that hole. Upheaval gauges

should be closely observed to see if there has been any upheaval; if an upheaval is noticed,

grouting should be stopped forthwith. The grout hole should be thoroughly washed and

grouting resumed after about 48 hours with pressure sufficiently reduced so as not to cause

any upheaval. Sometimes grouting can be continued at a lower pressure if upheaval

remains within allowable limits. (Mistry 1988).

Page 95: GROUTING IN ROCK TUNNELLING

95

VI. Figure 18. (C2). After reaching a certain value, the pressure quickly drops while the

rate of consumption remains constant.

This pair of curves also shows abnormal behaviour of the hole. They indicate that there

may be leakages of grout through natural strata or along the hole or some upheaval in the

rock strata. Grouting should therefore be carried out under strict supervision. The

procedure as outlined for case (V) above should be followed for this case (VI) also.

15.6 Grout setting characteristics and durability of cement injection in rock. Important for the quality and durability of cement grouts is the w/c-ratio and perhaps the

grout are stable or segregating. Stable grouts and also w/c- ratio below a certain limit has

been achievable with the aid of modern grouting technology.

Stable or almost stable suspensions contain less excess water than unstable one. Hence,

grouts with low water content are advantageous in the following ways:

-During grouting.

• the risk is minimized that expelled water will damage the partially set grout.

• grouting time is shortened because little excess water has to be expelled.

• the reach and the volume of grout can be closely delineated.

Page 96: GROUTING IN ROCK TUNNELLING

96

• effective filling of joints, including branches.

• higher density, leads to better removal of joint water and less mixing at the grouting front. 50(Houlsby, A.C. 1990, K.F. Garshol 2003).

-After hardening.

• greater strength.

• Better durability.

• Better adhesion to joint wall

• Low permeability.

15.7 Additives and admixtures for cement injection. There are cases where unexpected backflow can occur through the face or even further

back in the tunnel, possible indications are that a borehole is in contact with extremely

large channels with a lot of high pressure water. In these situations, it is beneficial to

accelerate the cement setting and hardening by stopping the backflow and allowing further

injection of the ground without loss of material as well as, by stopping unnecessary spread

of grout outside of a reasonable distance from the tunnel. Additives and admixtures are

used in cement and non-cement-based grouts to modify their fluid and set characteristics 51(Naudts et al; 2003, Naudts 2000, P. Tolppanen & P. Syrjanen 2003).

Cement-based grout additives can be admixtures, bentonite, mineral additives, or

pozzolan, such as blast furnance slag or silica fume. Admixtures used for cementitious

grouts are are, for example:

• Plasticizers and superplasticizer to reduce the water-cement ratio.

• Accelerators to prevent grouts from leaking into the tunnel or ground surface

• Additives to reduce bleeding and shrinkage. e.g. bentonite or silica based products.

50 Houlsby, A.C., (1990). Construction and design of cement grouting, a guide to grouting in rock foundations, John Wiley and Sons, New York, 1990. Knut F. Garshol (2003). Pre-Excavation Grouting in Rock Tunnelling. MBT International Underground Construction Group. Division of MBT (Switzerland) Ltd., 2003. 51 Naudts et al., (2003). Additives and Admixtures in Cement-based Grouts. Naudts et al., (2000). “New On –site Wet milling Technology for the preparation of Ultrafine Cement-based Grout” Canadian Geotechnical Conference. Montreal. October. P. Tolppanen and P. Syrjanen (2003). Hard Rock Tunnel Grouting Practice in Finland, Sweden and Norway – Literature Study.

Page 97: GROUTING IN ROCK TUNNELLING

97

• expanding additives.

• Retarders to slow hydration.

Some of the additives used are:

• Slag

• Fly-ash

• Natural Pozzolan

• Trass: Clay-phyllosilicate

• Silica fume

• Bentonite.

• Locally available fillers.

15.8 Equipments for Cement injection.

15.8.1 Mixing equipment. (Mixer). Cement and water together with additives are fed into a mixer. Several mixer types exist;

• Normal Paddle mixers which are simple to use and rather cheap but the mixing results are not good enough for high quality grouting.

• A Turbo mixer is more suitable than a paddle mixer. A centrifugal pump circulates the grout at a high speed (1300-1400 rpm, max. 1435 rpm) in the turbo-mixing container and creates a sharing action between the fractions for good quality mixing.

• Colloidal mixer: This type of mixer produces the best result. In the colloidal type mixer shear forces are also created in the mixer housing. The shear forces may be created by high turbulence in the casing as in the case of Hany system or the shear forces are created by close tolerance between the impeller and casing 52(Pettersson & Molin, 1999, Houlsby, A.C. 1990).

The mixing time and mixing speed are important factors influencing the grout quality. A

typical mixing time for OPC is 4-5 min. The finer cements require more intense mixing.

The maximum batch size is normally 80 % of the container volume. In a colloidal mixer,

the temperature might increase several degrees due to the energy release of the shear force

52 Sten-Ake Petterson and Hans Molin (1999).Grouting and Drilling for Grouting: Purposes, applications, methods and equipment with emphasis on dam and tunnel Projects. Atlas Copco Crealius AB Publication. Houlsby, A.C., (1990). “Construction and design of cement grouting, a guide to grouting in rock foundations, John Wiley and Sons, New York, 1990.

Page 98: GROUTING IN ROCK TUNNELLING

98

braking. This might induce early hardening of the grout and should be controlled by the

agitator (Pettersson & Molin, 1999). Wearing of the mixer should as well be put in

control.

Figure 19. Mixer. 53(Photo Hany AG Equipment).

15.8.2 Agitator. In order to keep the grout at a low viscosity and to prevent sedimentation, the grout should

always be agitated. The agitator acts as a holding tank with grout ready for grouting.

Inside the slowly revolving agitator, the grout suspensions are homogenized and possible

air bubbles removed. It is normally twice the size of the mixer and rotates at

approximately 60 rpm. It is highly recommended to attach one agitator per pump and per

grout mixture.

53 Hany AG Equipment. http://www.haeny.com/geraete.html.

Page 99: GROUTING IN ROCK TUNNELLING

99

Figure 20. Agitator (Photo Hany AG Equipment).

15.8.3 Grout Pumps Market wise, two types of pumps for grouting are available;

• The progressive cavity pump (pump without valves).

• Piston pumps (the valve type pump).

The pump flow and pressure capacity must be sufficient to perform a satisfying grout

operation; these parameters should also be controllable and individually adjustable during

grouting work. The maximum practical pressures needed in tunnel grouting is 10 MPa

(100 bar). The grout flow should be high enough to avoid separation of the grout. The

maximum grain size for the pump is usually varies between 3-8 mm, and should be

checked prior to grouting work.

Page 100: GROUTING IN ROCK TUNNELLING

100

Figure 21. Grout Pump. (Maximum Pressure 100 bar).

Figure 22. Grout Pump. ( Maximum Pressure 200 bar). (Photo Hany AG Equipment).

Page 101: GROUTING IN ROCK TUNNELLING

101

15.8.4 Complete systems. This is a complete unit, a mixer, agitator, pump and even a data logger. Here, standardized

components are individually mounted onto the container or stationary plants.

Figure 23. Complete grout pump. (Photo Hany AG Equipment).

Page 102: GROUTING IN ROCK TUNNELLING

102

15.8.5 Automated mixing and grouting plants • Excellent mixing quality

• High capacity

• Accurate dosing

• Consumption record

Figure 24. Automated mixing and grouting plants. (Photo Hany AG Equipment).

Page 103: GROUTING IN ROCK TUNNELLING

103

15.8.6 Recording of grouting data. These are an automatic / computerized logging tool. An auto logger is easily use with

experience of an Excel and PC.

The logged parameters are typically flow, pressure, volume, time, real time and hole

number. All parameters are shown in real time and display, and stored on a PC card. The

logged data are store and import into standard programs for viewing and printouts.

15.8.7 HIR • Simple Recording System with chart

• Recorder for pressure and flow.

• Totalizer for accumulated flow.

• Automatic switch off of grout pump when

• Reaching the pre-adjusted pressure or

quantity

• Solid stainless steel housing (IP 65).

Grout recorder.

15.8.8 HFR • Recording System with PC software

• Recording of data of up to 8 grout lines

Simultaneously.

• Recording of data on PCMCIA Memory

Card.

• Real-Time recording on PC

• Graphical display of P+Q curves

• Flow recording by inductive flow meters or

Pump strokes.

Figure 25. Showing Recording Systems. (Photo Hany AG Equipment).

Page 104: GROUTING IN ROCK TUNNELLING

104

16 Chemical Grouts.

16.1 General. Chemical grouts are injected into voids as solutions, in contrast to cementitious grouts,

which are suspensions of particles in a fluid medium. Chemical grouts react after a

predetermined time to form a solid, semisolid, or gel. The process of injecting a

chemically reactive solution that behaves as a fluid but reacts after a predetermined time to

form either a solid, semisolid, or gel is known as chemical grouting.

Chemical grouts were developed in response to a need to develop strength and control

water flow in geologic units where the pore sizes in the rock or soil units were too small to

allow the introduction of conventional Portland-cement suspensions.

Chemical grouting technology has expanded with the addition of organic polymer

solutions and additives that can control the strength and setting characteristics of the

injected liquid. 54(EM 1110-3500. 1995, Karol R.H 1990, Karol R.H. 1983).

Commonly used chemical grouts in construction industry today include the following:

• Water reactive polyurethane.

• Silicates grouts.

• Acrylic grouts.

• Epoxy Resins.

• Bitumen (Asphalt).

Some chemical and mechanical properties that need to be evaluated in the selection of a

grout for a particular application are the following:

• Viscosity.

• Durability.

• Gel time.

• Sensitivity.

54 EM 1110-3500. (1995). EM 1110-1-3500. Engineer Manual. The U.S Army Corps of Engineers. Engineering and Design –Grouting Technology (1995). Geotechnical and Materials Branch, Engineering Division, Directorate of Civil Works (CECW-EG). Karol R.H (1990). Chemical Grouts and their properties. Marcel Dekker. Inc. New York. Karol R.H. (1983). Chemical Grouting. Marcel Decker Inc., New York.

Page 105: GROUTING IN ROCK TUNNELLING

105

• Toxicity.

• Durability.

(EM 1110-1-3500. 95).

16.2 Overview of Polyurethane grouts. Water reactive polyurethane grouts were introduced into the grouting industry during the

late sixties by the Takenaka Company in Japan under the trade name TACSS. In the 1980,

exclusive rights for TACSS was taken over as the successes in stopping major leaks in

tunnels democratize the traditional sodium silicate cement combinations as well as the

seepage control grouting (acrylamide grouting). By the mid-eighties there were more than

10 manufactureres of polyurethane grouts, coupled with era of custom-made formulations

tailored to specific project 55(Naudts, 2003). Due to the longevity problems faced by one

component water reactive hydrophilic polyurethanes, the two- component polyurethane

foams were gradually introduced into geotechnical industry and later became popular.

Polyurethane grouts are probably the most popular type of solution grouts (Chemical

grouts). It has been known to be used for close to four decades and have contributed to the

democratization of the grouting industry. Solution grouts pertains to grouts that behave

like Newtonian fluids, contrary to suspension grouts which behave like Binghamian fluids.

Solution grouts are injectable into very fine apertures, not accessible to suspension grouts

(even microfine).

Polyurethane grouts are made up of a large family of solution grouts hence, it is very

difficult to make generic statements for the whole group. Most polyurethane grouts are

non-evolutive or true solution grouts. A true solution grouts is characterised by a flat

viscosity curve, followed by a sudden increase in viscosity immediately prior to gelation

or curing. Others known example of typical true solutions are acrylamide, acrylate, epoxy

resins and silicates grouts.(Naudts, 2003).

55 Naudts A. (2003). Irreversible Changes in the Grouting Industry Caused by Polyurethane Grouting: An overview of 30 years of polyurethane grouting. Geotechnical Special Publication 2003 Issue 120; Vol 2, page 1266 – 1280.

Page 106: GROUTING IN ROCK TUNNELLING

106

Basically, polyurethane grouts are categorised into three, based on the recognition by the

construction industry:

• One component foaming grouts (Water reactive polyurethane grouts).

• Two component foaming grouts (Polyol – isocyanides combination)

• Two component polyurethane elastomers.

Water reactive polyurethane grouts is further sub-divided to two main sub-categories-

• Hydrophobic polyurethane prepolymer grouts (resins): They react with water but

repel it after the final (cured) product has been formed.

• Hydrophilic polyurethane prepolymer grouts (resins): They react with water but

continue to physically absorb it after the chemical reaction has been completed.

The aforementioned sub-categories and the two other categories are further divided into

sub-families of polyurethane grouts.

The sensitivity which defines the ability to control factors influencing the reaction or

curing pattern during the reaction of most polyurethane grouts is typically lower than the

sensitivity of cement- based suspension grouts. The longevity of the end product and its

chemical resistance are typically far superior to the cement-based counterpart (Naudts,

1990). The toxicity of most of the polyurethane grouts has been reduced to an acceptable

level as an approval for use in potable water application has been obtained for several

polyurethane categories of grouts despite some ill-conceived applications in the past. 56(Naudts, 2003, EM 1110-1-3500. 1995, Skanska Environmental Report 1997).

56Naudts A. (2003). Irreversible Changes in the Grouting Industry Caused by Polyurethane Grouting: An overview of 30 years of polyurethane grouting. Geotechnical Special Publication 2003 Issue 120; Vol 2, page 1266 – 1280. EM 1110-1-3500. (1995). EM 1110-1-3500. Engineer Manual. The U.S Army Corps of Engineers. Engineering and Design –Grouting Technology (1995). Geotechnical and Materials Branch, Engineering Division, Directorate of Civil Works (CECW-EG). Skanska AB (1997). Environmental Report. Sweden.

Page 107: GROUTING IN ROCK TUNNELLING

107

One component foaming grouts (Water reactive polyurethane grouts).

Polyurethane prepolymer grouts are characterised with the ability to react with the in-situ

groundwater to create a foam or gel that is either hydrophobic or hydrophilic. They are

component products using the underground water as a reaction partner to create the end-

product. The catalyst such as a tertiary amine is excluded as a components since it only

affects the rate and the direction of the polymer forming process 57(Hepburn, 1992,

Anderson 1998). Additional catalyst only speeds up the gelation process.

During this exothermic reaction, the hydrophobic polyurethanes expand and penetrate

pervious media: fine cracks as narrow as 8 micron as well as soil with a permeability

coefficient as low as 10-4 cm/s. The reaction and penetration is enhanced by the formation

of CO2 . Their penetrability is determined by their viscosity and reaction time, It has been

revealed that, the penetration of fine aperture is a very slow process hence, requires

multiple hole grouting to obtain an economically justifiable and technically sound

grouting operation. ( Anderson 1998). Before gelation, the viscosity of the grout

decreases due to the formation of of C02 and during gelation, the viscosity increases

substantially to prevents futher penetration. The formation of either a gel or foam during

the reaction depending largely on the amount of water they are being mixed with is the

end product.

Water-reactive prepolymer are high molecular grouting materials, primarily produced by

mixing a polyol with an excessive amount of poly-isocyanides to form a low prepolymeric

compound containing some free OCN groups. The injected resin is made up of this

prepolymer, plasticizer, diluting agents, surfactants and the amine catalyst.

The mechanism of reaction among the isocyanides, polyol and other components remain

complicated. In simple terms classification, the following happens:

• The reaction between the isocyanides and the polyol yields a pre-polyurethane.

57 Hepburn, C. (1992) Polyurethane elastomers. Elsevier Applied Science. London, New-York. Anderson, H. (1998) Chemical Rock Grouting. An experimental study on polyurethane Foams: Chalmers University of Technology, Goteborg. S-41296.

Page 108: GROUTING IN ROCK TUNNELLING

108

• The reaction of poly-isocyanides with water liberates carbon dioxide and urea

derivatives

• The reaction of poly-isocyanides with ureido develops molecular links and high

molecular formation.

These reactions occur because of the existence of the free OCN groups in the grout, which

react with the compounds containing active hydrogen atoms, such as hydroxyl, water,

amino and ureido. The hydrogen atoms move to link up with the nitrogen atoms of the

poly-isocyanides and form high molecular polymers.

Two-component Polyurethane Foam Grouts.

The result of the reaction between a polyol (R-OH) and an isocyanate (RI-NCO) known to

be toxic is the formation of polyurethane. Largely depending on the type of polyol,

blowing agents, catalysts, a wide variety of foams with different characteristics can be

formed, only differing in: density, cellular structure, compressive strength, reaction

pattern, water absorption and fire resistance.

The isocyanate has a high affinity for water and thus has a tendency to steal the

isocyanate, leaving not enough isocyanate for the polyol to form a complete reaction.

These products react with the in-situ water and expand during the exothermic chemical

reaction to release carbon dioxide. They are totally stable after reaction with limited

flexibility. The reaction time can typically be adjusted between 45 seconds up to one hour

by adding a tertiary amine-based catalyst, (Accelerator).

Figure 26a. illustrates a typical reaction curve for water reactive polyurethane

prepolymers. First there is an induction time during which the viscosity of the water and

polyurethane mix remains constants followed by the reaction time, during which the

foaming starts. The latter is associated with a decrease in viscosity followed by a very

rapid increase in viscosity before final gelation. 58(Naudts 2003, Karol R.H. 2003).

58 Naudts A. (2003). Irreversible Changes in the Grouting Industry Caused by Polyurethane Grouting: An overview of 30 years of polyurethane grouting. Geotechnical Special Publication 2003 Issue 120; Vol 2, page 1266 – 1280. Karol R.H. (2003). Chemical Grouting and Soil Stabilization. 3rd Edition. Revised and Expanded. Marcel Dekker – Taylor and Francis CRE.

Page 109: GROUTING IN ROCK TUNNELLING

109

Figure 26a. Showing typical reactive polyurethane prepolymers. (Naudts 2003).

Figure 26b. Water reactive prepolymers. (Naudts 2003).

In order to start the reaction, there is a minimum enthalpy required, which is higher, as the

pressure is higher. This indicates that, at a given pressure, if the enthalpy is too low

(temperature too low) the reaction does not start unless the products are mixed thoroughly

with the water. (Naudts 2003). Heating the grout (maximum 60oC but never directly

applying the heat to the grout containers) speeds up the rate of reaction and hence,

eliminates the possibility of grout wash-out under most circumstances, (Figure 26 b).

Above the reaction line the reaction takes place, and below this line reaction does not

occur unless mechanical agitation of in-situ water and polyurethane grout exists. The

Page 110: GROUTING IN ROCK TUNNELLING

110

turbulent flow of the urethane-water mixture through cracks and channels often provides

for enough in-situ mixing. Some of the recently developed polyurethane resins react

regardless of pressure and groundwater temperature. (e.g. Minova Carbo-Tech products).

During grouting, the carbon dioxide generated during the chemical reaction will generate

additional pressure, as the grout flows through the cracks and pore channels, pushing the

grouts into very fine cracks and crevices.

The long term durability of grouts has been deeply looked into 59(Jakubowicz, 1992;

Naudts, 1990) which revealed that in highly acidic environments; polyurethane is

anticipated not to break down more than 10% over a 100 year time period. In an alkaline

environment (such as in concrete or in limestone formations), a weight loss of 35% has

been projected over a 45 years period due to hydrolytic degradation of the cured

polyurethane. Soils grouted with polyurethane do not display signs of long- term

degradation. 60(Oshita, et al.1991; Takenaka 1976,; Landry, et al. 2000). Hence, water

reactive polyurethane grouts do not last “for ever” in highly alkaline environments but are

very durable in neutral and acidic environments.

Typical applications of two components polyurethane grouts include: stabilization of

unstable rock in mines; sealing previous formation in front of flood bulkheads; post

grouting; sealing gaps and joints around ventilation doors, etc.

59 Jakubowicz. I. (1992). Determination of long term properties for polymer based grouts. Conference proceedings. Nordiskt Symposium I berg injektering. Ed. Lundblom. Chalmers University of Technology, Goteborg. Pp 50-56. Naudts, A. (1990). “Research Project Fort Cady Minerals: Chemical resistance of modified cement-based grout and polyurethane grouts Accelerated ageing test” Unpublished. 60Oshita, T., Kitano, M., and Terashima, K. (1991) “ Long Term Durability of Sails Solidified with Hydrophobic Polyisccyanate type grout “Sociey of Materials Science. Japan. December. Pp.1552-1557. Takenaka (1976). Taccs Know-how books. Internal Publications. Landry, E, Lees, D, and Naudts A. (2000): “New Developments in Rock and Soil Grouting: Design and Evaluation” Geotechnical News. September 2000. pp 38-44.

Page 111: GROUTING IN ROCK TUNNELLING

111

Figure 27. Core showing infilling of rock cavities with polyurethane.

16.3 Adopted Products on Kárahnjúkar Head Race Tunnel. Cementitious grouts, which were the first to be injected historically continue to be the

most frequently used on the project. The two chemical grouts adopted for the grouting

activities in the Kárahnjúkar project for control of high water ingress as well as tunnel

stabilization are the following:

(a) BASF Construction Chemicals Products. (MEYCO MP 355 A3).

MEYCO MP 355 A3 is a robust two-component (A and B), solvent-free polyurethane

injection resin specifically designed for filling big voids and jointed rock, stabilization of

loose rock, and cutting of running water. The foaming reaction time is significantly

dependent on the temperature of the Polyurethane resin, the rock and the ground water.

Fields of application are:

• Stabilization of fractured rock, sands and gravels and land-fill materials.

• Void filling

• Repair of concrete structures.

• Control of high volume water structure.

Page 112: GROUTING IN ROCK TUNNELLING

112

Features and benefits of MEYCO MP 355 A3 according to manufacturers are:

• When in contact with water, the product forms rigid foam. Without the presence of

water, it forms a stiff, rubber- like material.

• Ability to react also in dry condition to cured. (With or without water).

• Sealing of running water.

• Robust rigid foam.

• Modification of the reaction can be achieved by addition of accelerator and

thixotropic agent to Component A. 61(Technical Data Sheet MEYCO MP 355/A3).

Packaging.

MEYCO MP 355/A3 is available in the following packaging:

Component A: 25kg cans or 200kg drums

Component B: 30kg drums or 240 kg drums.

Application and procedure.

Components A and B are delivered ready- to use. They are injected in the proportion of

1:1 by volume using a two component injection pump equipped with a static in-line mixer

nozzle. MEYCO MP 355 A3 Accelerator 10 and 15 are the catalyst often used.

(b) Minova CarboTech Chemical products. (CARBOPUR WFA).

CARBOPUR WFA is an extremely fast-reacting two- component- injection resin(A and

B), CFC-free and halogen free, characterize with foaming action when water added,

without water, hardens without foaming. It ensured permanent sealing against high levels

of water inflows in pits, shafts and tunnel sections.

The resin is design for:

• Sealing and consolidation in water-bearing strata.

• Sealing against strong water ingress (also seawater)

• Sealing against water under pressure e.g. from strata, dams or shaft walls.

• Stabilization and sealing works in tunnels

• Repair of old shafts and tunnels

61 Technical Data Sheet MEYCO MP 355/A3. Degussa (BASF) Construction Chemicals (Europe) AG.

Page 113: GROUTING IN ROCK TUNNELLING

113

• Stabilization of crown abutments in tunneling.

• Sealing of anchoring of sheet pilings etc in ground water.

Features and benefits of CARBOPUR WFA over others are:

• Very fast setting.

• Used for wide ranging injections.

• Stabilizing effect.

• Compatible with groundwater. B-Component slightly hazardous to water.

• Applicable at temperature between -25 and 30˚C, recommended for sealing water

at low temperature.62( Technical Data Sheet CarboPur WFA)

Packaging.

Component A 20 kg in a tin can (blue cover) or 200 kg in a drum.

Component B 24 kg in a tin can (black cover) or 240 kg in a drum.

(c ) Composition and Properties.

CarboPur WFA, Component A honey in colour is a mixture of various polyols and

additives which reacts with the B-component dark brown in colour to form a tough /hard

polyurethane resin. CraboPur, component B is a polyisocyanate on the basis of 4,4-

diphenylmethane diisocyanate (MDI).

The mixed resin penetrates the structures to be sealed. Most part of water in there is

displaced due to hydrophobicity and the viscosity of the resin. Traces of water make the

resin foam. Based on its contact with water, the resin foams up more or less. Thus, the

mechanical properties vary a lot. The cured resin is resistant against many acids, alkali and

salt brines as well as organic solvents.

According to the manufacturers, there are no objections against the use of CarboPur WFA

in respect of groundwater and drinking water hygiene and very compatible with concrete

and steel.

62 Technical Data Sheet CarboPur WFA. Minova CarboTech GmbH. Tunnel and Civil Engineering.

Page 114: GROUTING IN ROCK TUNNELLING

114

(d) Processing.

The two components are pumped by a two component pump at the volumetric ratio of 1:1,

they are mixed thoroughly in a static mixer unit prior to injection into the strata through a

packer installed in a previously drilled borehole. In contact with water, the resin then

foams up. When the reaction does not meet any more water it hardens without foaming to

form a pore-free material thus, a water-tight shell is formed which in turn is surrounded by

a zone consolidated by foamed-up polyurethane. This leads to a permanent sealing and

consolidation. (Minova Carbo Tech GmbH).

(e) CarboAdd Fast.

This is an accelerator for the reaction of polyurethane and silicates resins. It is a solution

of catalyst which accelerates the polyol-isocyanate-reaction. Prior to use CarboAdd Fast is

added in small amounts (0-2 %) to the bright polyol component and mixed thoroughly.

16.4 Silicate grouts. Because of silicates grouts low cost and low viscosity, sodium silicates have found its

application in soil and rock grouting for stabilization or for ground water control for

decades. It has PH of 10.5 to 11.5 making it to be quite aggressive. The working safety

and health of using silicates has been of major concern.

Liquid silicates (water glass) are produced by dissolving vitreous silicate in water at high

temperature (900o C) and high pressure. The liquid is later diluted by water to reach a

viscosity level that can be used for injection purposes in soil and fine cracks in rock. A

normal injection grout will have a viscosity of about 5 cP and the gel produced is water

rich which is weak and to some extent unstable.

The formation of gel in the ground is normally associated with release of water from the

gel and shrinkage. Due to the low gel strength, it will have limited resistance to ground

water pressure, most especially in relatively large cracks and joints.

The liquid silicates need hardener to create a gel. Acids and acidic salts (like sodium

bicarbonate, sodium aluminates) will cause such gel-formation. In recent time, chemical

systems such as methyl and ethyl di-esters are mostly used as hardener which exhibits

Page 115: GROUTING IN ROCK TUNNELLING

115

much better practical properties by improving the quality of the final grout. (Knut F.

Garshol 2003).

Because of the effects that characterize gel formation of silicates grouts in the ground,

such as release of water from the gel and some shrinkage, silicates grouting as a

permanent ground water control could not be effective as the effects can lead to new

leakage channels over time. The chemical stability also remained questionable in many

cases. Silicates grouting for temporary ground water control will mostly be the best

practical application. In rock injection, it is best advice, to ensure that cement injection to

fill up the larger channels precede silicates grout application.

The durability of silicate grouts in low PH cement- environment also remains at stake as it

is unfavorable. 63(Arvind Shroff & Dhananjay L. Shah.1999).

16.5 Acrylic grouts. Acrylates were introduced as less toxic alternatives to the toxic acrylamide compounds

that are no longer available as grout.

The acrylic grouts came into application about 5 decades ago, but for cost implications,

these were based on acrylamide. The toxic nature of acrylamide products over the years

has drastically prevented them from being used. In the Hallandsåsen tunnel excavation

Southern Sweden, addition of acrylamide and n-methylolacrylamide used as acrylic grout

in ground water control caused ground water pollution and poisoning of livestock, 64(Skanska AB Environmental Report 1997). In other words, this component could be

excluded from an acrylic grout.

Polyacrylates are gels formed in a polymerization reaction after mixing acrylic monomers

with an accelerator in aqueous solution. Polymerized polyacrylates are not dangerous for

human health and the environment. In contrast, the primary substances (monomers) can be

very dangerous before their complete polymerization. Injection materials polymerize very

quickly, sometimes before the monomers completely polymerize, a considerable amount

can be diluted by the ground water and depending on the porosity, permeability and local 63 Arvind Shroff & Dhananjay L. Shah. (1999). Grouting Technology in Tunneling and Dam Construction. 2nd Edition. 64 Environmental Report (1997). Skanska AB. Sweden.

Page 116: GROUTING IN ROCK TUNNELLING

116

geology of the area, and the action may lead to large scale contamination and pollution.

The working safety of personnel is at risk and the use of products containing acrylamide is

carcinogenic with cumulative effect in human body. (K. Garshol 2003).

Acrylics gel materials are very useful for injection into soil and rock with predominantly

fine cracks. It is usually injected with less than 20% monomer concentration in water and

the product viscosity is therefore as low as 4 to 5cP. The gel-time can typically be chosen

between seconds and up to an hour.

The strength of the gel will primarily depend on the concentration of monomer dissolved

in water, but also which catalyst system and catalyst dosage being used. Acrylic is

typically not used in areas where it is subject to wetting and drying or freezing and

thawing. 65(EM 11101-3500. 1995, Karol, R.H. 1990). In general, the chemical stability

and durability of acrylic gels are very good.

16.6 Epoxy resins. Epoxy products has found very limited use in rock injection under ground, this is due to

the cost of epoxy and the difficulty of handling and application during operation.

Epoxy resin and hardener must be mixed in the right proportions for a complete

polymerization to take place if not; the quality of the product will be negatively affected.

The reaction is exothermic and it’s not effective in filling very large cavern. Epoxy is

characterized with high viscosity except special solvent are used. The working safety and

associated environmental risk has reduced the adoption of epoxy for rock injection

underground. 66( Bruce. D. et al; 1998).

16.7 Bitumen Asphalt. Hot bitumen grouting technology has continually evolved since its early applications

almost a century ago in France, Germany and the USA to seal persistent leaks in tunnels,

65 EM 11101-3500. (1995). EM 1110-1-3500. Engineer Manual. The U.S Army Corps of Engineers. Engineering and Design –Grouting Technology (1995). Geotechnical and Materials Branch, Engineering Division, Directorate of Civil Works (CECW-EG). Karol R.H 1990. Chemical Grouts and their properties. Marcel Dekker. Inc. New York. 66 Bruce. D. et al; (1989). “ High Flow Reduction in Major Structures: Matreials, Principals, and Case Histories” Grouts and Grouting Proceedings: Geo-Congress 98. Boston, MA. Pp. 156-175.

Page 117: GROUTING IN ROCK TUNNELLING

117

below dams and for erosion protection along canals in conjunction with cement based

suspension grout.

In scenarios where others types of grout has proved less effective, heated liquid bitumen

(asphalt) could be an alternative. Selected quality of bitumen are heated to a sufficiently

high temperature (200o C to 230o C) characterized with low viscosity allowing easy

pumping. The softening point should be around 95 to 100oC. The output must be adapted

to the water head. 67(Naudts 2003, Naudts 2003, K. Garshol 2003, Jaroslav Verfel 1989).

Examples of successful field applications of hot bitumen grouting in projects such as

Lower Baker Dam, U.S.A., 1920s, 1950s, 1964 and 1982, Stewartville Dam, Ontario,

Canada – 1980s, (Deans, et al.1985), Kraghammer Sattel, Germany, 1963 (Schönian,

1999), Potash Mine, Canada -1997, Quarry in Eastern United States, 1998, Milwaukee

Tunnel, Wisconsin, U.S.A – March, 2001, and New Yung Chung Tunnel, Ilan, Taiwan

2002, has demonstrated that the application of bitumen technology is an efficient,

economical and powerful tool to prevent or stop seepage and major leaks, (Naudts 2003).

The nature of most bitumen grouting application involved emergency situations in which

very serious water inflow problems needed to be solved. Ideal bitumen quality will change

from an easily pumped fluid material to sticky, high viscous and non-fluid asphalt at the

water temperature.

As the bitumen grout comes in contact with the water, the viscosity of the grout increases

rapidly resulting in lava like flow forming a hard insulating crust at the interface between

water and bitumen and shelters the low viscosity, hot bitumen behind it. The crust or skin

is re-melted from within when hot bitumen continues to be injected. 68(Schönian, 1999).

After injection into the water stream, bitumen will rapidly loose its high temperature and

rapidly and dramatically change its rheological properties. The bitumen gets sticky and

thus gradually blocks the flow. Additional cementitious grout ensure permanent and very

stable barrier.

67 Naudts et al; (2003). Hot Bitumen Grouting: The antidote for catastrophic inflows. Jaroslav Verfel (1989). Rock Grouting and Diaphragm Wall Construction. Development in Geotechnical Engineering 55. Elsevier Science Publishers. Naudts et al., (2003). Additives and Admixtures in Cement-based Grouts. K. Garshol. (2003). Pre-Excavation Grouting in Rock Tunnelling. 68 Schönian, Erich. (1999) The Shell Bitumen Handbook. Shell International Petroleum Company Limited.

Page 118: GROUTING IN ROCK TUNNELLING

118

Some of the distinct advantages of bitumen as a grout materials to stop or control water

flow, especially under high pressure at high flow rates is that, it can be injected for a very

long time (days-even weeks) into the same grout hole without the risk of either premature

blockage due to its good insulating characteristics and absolutely no wash-out (resist

dilution) because the faster the water flows, the faster the bitumen cools off. Cement–

based suspension grout is often injected in conjunction with hot bitumen to compensate for

the associated thermal shrinkage of the bitumen; making the bitumen less susceptible to

creep; and to increase the mechanical strength of the end product. On the other hands, the

equipment and set-up are generally more complex for bitumen grouting than for the

applications involving regular cement based grouts or solution grouts. The operating

temperature of the surface pipe system needs to be in the range of 180-225˚C (356-

437˚Fahrenheit). The piping system used for grout delivery from the bitumen pumps to the

sleeve pipe “stinger” located at the end of the bitumen grout hole, must either be pre-

heated with oil, heat trace, or steam, potentially through a re-circulation system as well as

the grout been insulated and equipped with temperature sensors and pressure gauges.

(Naudts 2003).

It is noteworthy that, the apparent Lugeon value which defines the permeability coefficient

of the formation using grout as a test fluid typically decreases with time during the

execution of hot bitumen grouting contrary to cement grouting operations due mainly to

the excellent penetration properties of the bitumen into the formation. 69(Landry, et al.,

2000).

Environmental wise, “hard” oxidized blown bitumen with a high solidification point are

environmentally friendly with as well as a long history of successful use for lining

portable water reservoirs and fish hatcheries ponds in United States of America. America

Water Works Association (AWWA) has adopted oxidized bitumen proven to be in

compliance with her standards for leachate resistance of materials use in portable water

applications. In summary, if planned with sound engineered by competent contractor with

suitable equipment using appropriate type of bitumen the “hot bitumen in conjunction with

cement grouting” technique has never fails to stop high inflows. The grouting can be

69 Landry, et al., (2000). New Developments in Rock and Soil Grouting: Design and Evaluation” Geotechnical News. September 2000. pp 38-44.

Page 119: GROUTING IN ROCK TUNNELLING

119

applied safely, economically, despite adverse conditions and last but not the least, blown

oxidized bitumen grouts could be considered the most environmentally friendly grout

presently available in the market (Naudts 2003,).

Advantages and Limitations of Chemical Grouts.

Chemical grouts contain no solid particles hence; they can be injected into rock materials

containing voids that are too small to be penetrated by cementitious or other grouts

containing suspended solid particles. Chemical grouts can therefore be used to control

water movement in and to increase the strength of materials that could not otherwise be

treated by grouting. It has been used in filling voids in fine granular materials, very

effective in sealing fine fissures in fractured a rock or concrete, commonly used in

stabilization or for increasing the load-bearing capacity of fine grained materials in

foundations and for the control of water in mine shafts, tunnels, trenches and other

excavations.(see table 2 and 3).

Chemical grouts suffer from the disadvantages they are often more expensive than

particulates grouts. Large voids are often grouted with cementitious grout, and chemical

grouting is carried out as required. Chemical grouts are also restricted or totally banned in

some circumstances due to potentially toxic effects that have been observed with some of

the unreacted grout components. Potential groundwater is a major consideration in the

selection of the type of grouts to be used in many cases. (EM-1110-1-3500. 1995, Skanska

Environmental Report 1997).

Page 120: GROUTING IN ROCK TUNNELLING

120

Table 2. Ranking of Major Grout Properties.

Table 3. Ranking of Chemical Grouts by Application. (EM 1110-1-3500. 31 Jan

1995).

Page 121: GROUTING IN ROCK TUNNELLING

121

17 High Pressure Ground Water Condition.

17.1 Basic Problem. High pressure local water features creating a very high-flow water in-rush leads to

problem in the tunnel excavation by temporary delaying production. In hard rock

excavation such as granite and granitic gneiss with moderately high overburden, only few

stretch of the tunnel stands the possibility of intersecting highly jointed areas producing

large water in-rush at very high pressure. 70(Knut F. Garshol 1999, H O. Honnestad et al;

2002, Holter, K.G. 2005, Holter K.G et al, 1996, Sjostrom O.A 2003, Schunnesson, H.,

1996. K. F Garshol 2003).

Some common features that may be added to magnify the problems are but not limited to

the following:

• Weak rocks or rock zones, or heavy jointing and crushing, (shear zone).

• Too low pumping capacity for dewatering or poor drainage capacity.

• Tunnelling down slope or the access tunnel is on a down slope.

• Frequent intersection of water bearing channels.

17.2 Practical procedure in high risk areas. In practice, there are a few methods of handling water inflow problems in tunnelling

excavation, most especially in shear zones.

17.2.1 Pumping System. The capacity of the pump chosen must be based on predicted and actual project conditions,

the reserve capacity should be minimum 100%. Excavation along down gradient requires a

70 Knut F. Garshol (1999). Use of Pre-injection and Spiling in Front of Hard Rock TBM Excavation. Paper presented at Tenth Australian Tunnelling Conference 1999. Melbourne, Victoria 21- 24 March 1999. H.O. Honnestad et al; (2002). Hans O. Honnestad, Knut Garshol and Ross Dimmock, (2002). Pre-injection in hard tunnels using Degussa Rheocem microcement. Degussa International UGC Publication Holter, G.K (2005). Modern Pre-Injections in Underground Construction; Saving Time and Costs in Difficult Ground. Degussa (BASF) UGC Europe, 8048 Zuerich, Switzerland. Holter K.G et al; (1996). Tunnelling through a sand zone: Ground Treatment experiences from the Bjoroy sub sea road tunnel, Proceeding of North American Tunnelling 1996. Ed: Ozdemir, pp 249-256, Vol 1 (AA Balkema Rotterdam). K. F Garshol (2003). Knut F. Garshol (2003). Pre-Excavation Grouting in Rock Tunnelling.

Page 122: GROUTING IN ROCK TUNNELLING

122

stepwise pumping system with buffer tanks and decreasing capacity down slope has been

effective.

17.2.2 Probe drilling /coring. The effectiveness and safety effect of probe drilling is proportional with the number of

appropriately oriented holes; there are always the probabilities of executed probe drilling

not penetrating the water bearing local features/channels. In high risks zones, it is

recommended that a minimum of 4-5 drillings of 25-30 m long holes should be carried

out. (H O. Honnestad et al; 2002, K. F. Garshol 2003).

17.2.3 Injection. In the case of high water pressure found at a drilled depth smaller than the planned probe

length, additional 2-3 meters further drilling could be carried out. More holes are then

drilled into the same area and grouted. New holes to check the effectiveness of the

grouting are made from the same face position, if the contact depth is less than about 15

m. In the case of the first contact and injection made at a depth greater than 15 m, further

excavation until 5 to 10 m remains can be executed to shorten the drilling for control-and

grouting purposes.(Holter, G.K. 2005).

17.2.4 Special cases. Despite probe drilling, pre-grouting and core drillings, the probability of still intersecting

local high pressure water still remains when drilling a blast round (D&B) or control holes

(TBM). In this case, an extra round of grouting may be required. Necessary precautions

must be taken to avoid allowing high pressure water too close to the face.

In the case of a poor and jointed rock in the face area, the risks may be high that local

ruptures in the face occur, grouting may then become difficult due to the flushing out of

pumped grout materials. Time lost and cost is usually the result while trying to established

Page 123: GROUTING IN ROCK TUNNELLING

123

favorable condition for controlled grouting to be executed. 71(Holter K.G. et al; 1996, Knut

F. Garshol 1999, Skeggedal, T. 1983, Schunnesson, H. 1996).

71 Skeggedal, T. (1983). “The use of tunnel boring machines (TBM)”, Norwegian Tunnelling Society, Publication No 2, Oslo 1983. Schunnesson H. (1996). Probing ahead of the face with percussive drilling”, Tunnels and Tunnelling, January 1996, pp 22-23.

Page 124: GROUTING IN ROCK TUNNELLING

124

18 Experiences /Summaries of Case Studies.

18.1 Case study 1. Chainage 135 – 1+ 146. Power Intake. This case covers the concrete lining of the Power Intake tunnel, which is about 1 km long

from the portal at Hálslón reservoir. It was excavated by the drill and blast method and

extends to the dismantling chamber for the third Tunnel Boring Machine (TBM).

Extensive post grouting activities were carried out covering the entire section ranging

from contact grouting to seal off the membrane between the host rock and the concrete

lining, while consolidation and curtain grouting were specifically carried out to

consolidate the niche (TBM chamber) meant for the Tunnel Boring Machine 3

breakthrough which never came to reality due to a number of problems for the machine

boring the tunnel upstream.

Works were performed according to the designers 72(KEJV) drawing 14-C-2.04.012 and

Site Instructions TN-58 and TN-59 as well as additional instructions issued during the

operation. Drilling and grouting was extended to consolidate the rock close to a fault

located between chainages 1+108 and 1+111 according to Site Instruction TN-62

(upstream from the chamber).

The only target was (apart from curtain grouting) to consolidate the rock around the lined

tunnel periphery, especially close to the fault. The water leakages through the construction

joints and drainage 6” pipes connected to the fault were only observed as minor seepages

through fine cracks in the lining.

The sequence of the works was planed as follows:

1. Drilling and consolidation grouting of 5 rings (8 holes in an umbrella shape per

ring) between chainages 1+105 and 1+117 close to the fault with 15 m long holes

into the rock Ø 76 mm. The rings were located upstream from the chamber based

on the geological mapping.

2. Curtain grouting with 3 rings (12 holes per ring) between chainages 1+137 and

1+143 with 15 m long holes into the rock Ø 76 mm within the chamber.

72 KEJV. Project designer drawing 14-C-2.04.012. Headrace tunnel Ch 1 + 126 to 1 + 146. Concrete linning, plan and profile. TN denotes Site instruction serial number.

Page 125: GROUTING IN ROCK TUNNELLING

125

3. Consolidation grouting with 3 rings (12 holes per ring) between 1+125 and 1+133

with 4 m long holes in the rock Ø 76 mm within the chamber between sections as

above, (see figure 29).

In reality all bore holes drilled in the chamber were longer than 3-4 m (1 to 2 m in the fault

section) passing the reinforced lining and backfilled concrete.

In each consolidation grouting ring close to the fault (according to point 1) 8 holes were

drilled and in the consolidation and curtain grouting rings in the chamber (according to

point 2 and 3) 12 holes were drilled. The grouting holes were drilled with an alternating

pattern of 30 degrees (staggered) to prevent damages to the reinforcement.

In each section rings no. 1, 3 (or 5) were drilled and grouted first. After those rings were

completed rings in between were open. As a rule all holes in one ring were drilled first

before the grouting start and the grouting was performed from the invert up to the crown

to refusal pressure, (bottom up approach).

Grouting according to the site instructions should have been performed with cement based

grouts and thickening procedure (w/c content from 0,80 down to 0,45 to achieve the

refusal pressure of 10 bars corresponding to a grout flow of 40 l/min).

Lugeon water tests were performed at the first ring at Ch 1+105 only. There was no reason

to do further water testing in other rings due to huge water inflow from bore holes. Even in

the dry holes the pressure of 10 bars could not be achieved at the highest pump capacity of

50 l/min.

Consolidation grouting close to the fault (1)

The huge water inflows with high pressure were observed under the spring line and mostly

on the left hand side (LHS) looking downstream. In ring C (chainage 1+111) the drilling

and grouting program was revised not to open more than 2 holes at the same time from the

first appearance of water. These holes were grouted immediately one by one to stop the

huge water inflow. This inflow could risk the transportation of crushed material, sand and

gravel into the tunnel.

When the grout take exceeded 3000 l the grouting was suspended to the next day. In 3

holes with directions between 06.00 and 09.00 (using clock position), polyurethane

Page 126: GROUTING IN ROCK TUNNELLING

126

grouting was performed to stop the water and to limit the range of grout penetration within

the open feature which was probably reaching the surface under the dam and above the

Power intake. Such holes had to be re-drilled close to their previous position. 3 holes

mentioned above were re-drilled 5-9 times.

Ring B at chainage 1+108 was left to be completed as the last ring in the grouting

program.

The curtain grouting (3) and consolidation grouting (2) in the chamber.

The curtain grouting between Chainage1+137 and 1+143 was performed as the second

section. The huge water inflow and grout-take was observed in general above the spring

line and close to the crown. The restriction of number of holes drilled at the same time was

the same as in the already performed fault section but to a smaller extent.

After completion of the curtain grouting, consolidation grouting in 1+125-1+133 with

short 4 m holes in the rock was started. The main water inflow and grout-take were

observed on the RHS, mainly concentrated between 12.00 and 03.00 o’clock (opposite as

in the fault section).

The general grout consumption in this section was considerably lower than in the fault

section and curtain grouting section, (see figure 29).

During grouting for consolidation at Ch 1+129 (ring B) suddenly a huge rock fall occurred

close to the adjacent ring C at Ch 1+133 and the tunnel was evacuated (07.01.05). A new

site instruction for an additional ring was written (TN-71) and the additional 12 holes were

opened 4 m in to the rock.

Huge leakages were located between clock position 12.00 and 02.00. Considerably high

cement grout consumption was noticed above the spring line in general. Evidently a new

crack system in form of a chimney was reopened between the already grouted curtain and

the consolidation rings.

The absolutely worst drillhole had direction 02.00 (clock position). This hole was grouted

in stages for 5 days – the total cement grout consumption was close to 25.000 l without

obtaining the refusal pressure of 10 bars. The hole was finally plugged with 460 kg of

polyurethane.

Page 127: GROUTING IN ROCK TUNNELLING

127

Test holes

After completion of ring B at Ch 1+108 close to the fault 2 new vertical bore holes for

testing at chainages 1+131 and 1+121 were done (TN-72). In the first one after completion

of drilling, a huge water inflow was observed and was evidently followed by two rock

falls on the lining which was heard. The water stream changed rapidly from negligible to a

maximum of ca 80 l/s during these events.

The water inflow in the hole at Ch 1+121 was moderate and stable. This hole was grouted

with standard cement grout. The hole at Ch 1+131 was finally plugged with polyurethane.

For estimation of the rock mass stability at Ch 1+131 additional 5 holes between clock

position 11.00 and 01.00 at chainages 1+127 and 1+131 were instructed (TN-74). In only

one hole at Ch 1+127 new water was observed and ca 0,50 m of empty room above the

lining while drilling. This hole was grouted with polyurethane. All the remaining 4 holes

were almost dry and plugged with standard cement grout.

Drainage pipe systems

Finally the grouting of drainage pipes located close to the invert (i.e. tunnel floor) on both

sides of the tunnel was performed with cement mixtures. The pipes were mounted to

prevent the washing out of the fresh concrete mass during the pouring of the backfill

concrete.

Two plastic 1” pipes on the left hand side (looking upstream) drained water from small

leakages from the rock and concrete backfilling along the wall. These pipes were not

connected to the pumping pit located on the right hand side and were discovered by

digging. These pipes were refilled with a moderate cement grout volume (3120 l).

The 3 steel 6” pipes on the left hand were responsible for water coming from small

leakages like on the left hand side and collecting a huge amount of water coming directly

from the fault. To minimize the cement grout-take while all pipes were indirectly

connected through the rock mass the following procedure was employed:

- each individual pipe grouting was suspended after 2000 l of thick 0,45 mixture and

next pipe was taken for grouting,

- The other ungrouted pipes were opened to flush away water, air and dissolute

grout.

Page 128: GROUTING IN ROCK TUNNELLING

128

- To decrease the range of grout penetration in the rock mass, wooden dust and

accelerator based on industrial salt were applied.

The total grout consumption to refill the drainage pipes on the right hand side was 40.470

l.

Complementary testing and grouting

During the grouting operation all leaking joints were sealed simultaneously. Only one ring

close to Ch 1+137 near the crown was still leaking in this section longitudinal cracks in

the concrete appeared probably after the rock falls.

To test the concrete’s condition and its conductivity, 2 additional core holes 4 m in to the

rock were instructed at Ch 1+137, 3 close to the leaking joint mentioned above.

The hole at 01.00 o’clock provided a small amount of water (1-2 l/s) coming only from the

backfilling concrete. The total thickness of the lining and backfilling concrete was 3, 30 m.

In general the concrete quality seamed to be poor. The 4 meter long hole in the rock was

dry – the sandstone was fractured but not affected by any grout.

The hole at direction 12.00 o’clock was dry and the quality of the concrete was estimated

as normal (no cracks). Above the backfilling concrete a 0, 45 m empty room refilled with

cement grout applied during contact grouting or curtain grouting was noticed. This hole

was later refilled with cement grout – the amount was close to the theoretical volume of

the bore hole.

The cement grouting of the leaking hole at 01.00 o’clock was suspended due to grout

losses of cement 0, 45 at a low pressure though existing cracks in the concrete lining. This

hole was completed the day after with a low pressure Polyurethane injection (ca 15 l only).

A total of 291.440 l of cement grout and 5215 l of polyurethane resin was used in this

grouting.

Page 129: GROUTING IN ROCK TUNNELLING

129

Figure 28. Showing plan of power intake, tunnel concrete lining outline and grout plan up to the gate shaft, (Ch 135- Ch 282.813). This further extends to the TBM dismantling chamber. (Ch 1+ 146)

Figure 28 shows the plan view of the power intake from the portal (Ch 135) up to the gate

shaft (Ch 282.813). Contact grouting (of two to one pattern) were carried out and four

consolidation rings of 15 m long grout holes (8 holes per ring) were made close to the gate

shaft between Ch 0+ 254.313 and Ch 0+ 272.313. This concrete lining section of the

tunnel further extends downstream (east) to the TBM dismantling chamber (Ch 1+ 146).

See figure 29.

Page 130: GROUTING IN ROCK TUNNELLING

130

Figure 29. Diagram showing extension of the power intake plan seen from above (see

figure 28), and Contact, Consolidation and Curtain grouting in the in the presently cement-

filled dismantling chamber, (Ch 1 + 105 -1+ 146).

Contact, Consolidation and Curtain grouting in TBM Chamber.Contact, Consolidation and Curtain grouting in TBM Chamber.

Page 131: GROUTING IN ROCK TUNNELLING

131

18.1.1 General remarks and recommendation.

1. The distance between the rings should not exceed 2-2, 5 m.

2. The drilling of holes with huge water leakages and material transport should be

done in ascending stages from the collar.

3. To avoid local empty rooms and “air pillows” above the backfilling concrete close

to the crown, the grout hoses with simple valves type Tube-á-manchette (sleeve

port pipes) should be mounted.

4. From the same reason as an option the conventional contact grouting through drill

holes should be performed to a refusal pressure not lower than 10 bars at the collar

related to the grout flow 40-50 l/min.

5. The core drilling through the lining should be performed in sleeves left in the

structure to prevent damages to the reinforcement and extra sleeves for additional

holes should be applied.

6. In the case of open cracks and voids thick cement grouts with lowest w/c ratio of 0,

45 are recommended with additives like sand ballast, wooden dust or chips and

accelerators like sodium silicate.

7. In huge leaking holes with lengths up to 7 m, the consolidation effect in the rock

can be achieved with Polyurethane grouting but the grout piston Polyurethane

pumps with capacity no less than 10 l/min must be applied.

8. Cold weather conditions and water temperatures below 10° C in the rock mass or

used at the mixing plant cause an uneven and ineffective grout penetration due to

very long cement grout setting time.

Accelerators like industrial salt and sodium silicate as well as water heaters are

strongly recommended.

9. In the case of Polyurethane grouting the frost sensitive components should be kept

within the temperature range of +5° C - +25° C.

Polyurethane materials from Minova – CarboTech are suitable for grouting down up to -5°

C without the need of heating as in the local Kárahnjúkar weather conditions. Therefore

they are strongly recommended instead of the commonly used Degussa-BASF PU

products. (VIJV Grouting team. VIJV- Database 2006, Tomasz Najder 2006).

Page 132: GROUTING IN ROCK TUNNELLING

132

18.2 Case study 2. Chainage 19 + 645- 19 + 595. Adit 2. ( TBM Stuck for 6-months). Extraordinary Geological Occurrence, (EGO) Section. Ch 19 +640-19+597.

This 50 m section of the tunnel is 19 km downstream the Head Race Tunnel. It

lies within the middle section called Head Race Tunnel two. This 50 m section is

characterised with three big faults, with very high leakages through the faults, and

blocky rock fall during excavation. Backfilling of voids up to 600 m3 were

experienced and the Tunnel Boring Machine (TBM) got stuck for six months

within this section before it could further advance.

Geological Description Ch19+640 to 19+597. Adit 2.

The general stratigraphical sequence between Ch 19+640 to Ch19+597 follows

that of the proceeding 20m of tunnel i.e., olivine basalt overlying tillite.

However where this section of tunnel differs is both in the quantities of water

ingress and in the nature of the fractures.

The total water ingress in this area was in the order of 100 l/sec coming from two

main areas; namely from a fracture at Ch19+620 and a second fracture at

Ch19+600. It is this water that has proved the major hindrance to backfilling and

re-boring through the faulted zones.

Structurally the area consists of several larger fractures in association with very

closely to closely spaced minor fractures. These “fractures” consist of both joints

and very small scale faulting along with faults with throws of 1 to 3m. The main

structures have a strike and dip of 220° / 85° East. There are however three other

fracture sets giving in total four fracture sets, three sub-vertical fracture sets

(striking approximately at 220° , 250° and 160°) and one fracture set with a dip of

between 0° to 30°.

There were three “problem” areas between Ch19+640 to 19+597.

The first area occurred between Ch19+640 and Ch19+630 where two faults

intersected causing a large overbreak of around 80 m3.

The second area caused more problems mainly due to large volumes of water

ingress along the fracure at Ch19+620. The highly fractured blocky nature of the

ground in this area in combination with the large water ingresses caused a void of

Page 133: GROUTING IN ROCK TUNNELLING

133

some 145 m3 to form above the tunnel crown between approximately Ch19+626

and Ch19+613.

The third area was the worst geological conditions thus far intersected on the

Project. Here we have the four joint sets mentioned earlier. These joints can be

described as very closely spaced (60 to 200mm) to closely spaced (200mm to

600mm) with a range of persistence from the minor joints of low (1 to 3m) to very

high (>20m) for the major fractures, often planar striated, sometimes open with

clay filling and with a total water ingress of up to 30 to 50 l/sec. All of this has led

to a void opening up above the tunnel crown between Ch19+610 to Ch19+597,

(the main part of the void is between Ch19+604 to Ch19+597) with a volume of

around 500 m3.

Expected geology ahead of the face.

Borehole HRT2-BH7 was drilled from headrace tunnel 2 and extends ahead of the

face to around Ch19+562. Very briefly this borehole indicates the following:

From Ch19+597 to Ch19+580 the fracture spacing is generally very close (60mm

to 200mm) to closely spaced (200mm to 600mm) and the fractures are generally

striated. The sub-horizontal joints are spaced at between 0.3m to 1.3m. A water

bearing joint thought to strike at 220° will intersect the right hand side of the tunnel

at around Ch19+591.

From Ch19+580 to Ch19+562 the geology appears to improve with the fracture

spacing increasing to widely spaced (600mm to 2000mm) and the spacing of the

sub-horizontal joint set inceases to around 6m. The joint planes are generally

planar rough.

In summary the zone from Ch19+597 to Ch19+580 must be treated with extreme

caution. Hopefully the conditions are better than the core indicates, but the

likelyhood is that the ground will want to form a void as previously. Sealing off the

water by pre-grouting will be carried out to at least try to minimise the influence of

water on the tunnel stability.

Page 134: GROUTING IN ROCK TUNNELLING

134

From the recently carried out geophysics survey we can expect to be in variable

ground conditions until Ch19+400. From Ch19+400 to Ch19+090 good ground

conditions can be expected before we encounter what may be a major lineament at

Ch19+090 to Ch19+000. Further good ground conditions are indicated from

Ch19+000 to Ch18+600. 73(VIJV- Database 2005, Peter Pitts 2005).

TBM 2 Chronology of Measures for passing Ch 19+645 to 19+595.

Due to continuing conveyor problems,TBM2 was stopped by the contractor on 24th

February 2005, in order to break out for the already delayed Drill and Blast (D&B)

Downstream Access & Jokulsa access tunnels at the Adit2 Junction area, and to re-aligned

the main tunnel conveyor.

TBM2 resumed boring on 26 March 2005, and immediately returned weekly production

figures of 218 and 274 metres/week in generally Class 1 rock conditions between Ch.

20+337 to 19+650.

By Ch.19+645, (20/04/05) the previously good Class I rock conditions started to

deteriorate rapidly, and Class IV Rock Support was being instructed from Ch. 19+640

onwards. The ground was particularly blocky with clay partings, that needed immediate

shotcreting behind the cutterhead. As a first measure the Class IV rib spacing was reduced

to 0.4m centres with full steel lagging, and cautious advance continued up to Ch. 19+622.

Following an inspection by The Engineer, the steel spiling measures described in the

Design documents were instructed in order to reduce the ravelling of the ground in front of

and above the cutterhead.

In the first week of May 2005, very slow advance of the TBM followed up with 0.4m

centred ribs, and spiling pre-reinforcement continued, the first void was now visible

behind the cutterhead, and ground loss at the cutterhead crown was continuing. The spiling

measures as described in the design were proving inadequate. Discussion on the use of

Polyurethane foam to stabilise the area were iniated by the Owners representative (VIJV)

73 VIJV (2005) Database: Viseningar Joint Ventures, Database. Construction Supervision Team. Kárahnjúkar Project Hydrelectric Power Project. Peter Pitts (2005). Personal Discussions and Internal Reports on Advancement of TBM 2. VIJV: Visen-ingar Joint Ventures. Senior Geotechnical Enginneer. Kárahnjúkar Hydroelectric project Supervision Team.

Page 135: GROUTING IN ROCK TUNNELLING

135

but not implemented until Robbins confirmed no damage to the TBM could be expected

through contact with such foams.

In the second week of May 2005 the TBM continued to be advanced slowly with full

Class IV support, however a massive 150 l/sec ingress of water was also encountered

which only exacerpated the situation and caused more ground loss above the cutterhead,

and temporary loss of rotation

On 11/05/05 a joint decision was made between Owners Representative/Landsvirkjun and

Impregilo S.P.A Iceland Branch (Contractor) to stop further advance, remove the

previously installed steel ribs and reverse the TBM 10 metres back to 19+630 to a safe

working area, and to construct a concrete bulkhead ahead of the TBM by protecting the

cutterhead with timber and polythene and then simply pumping concrete ahead into the

fault zone. Backfill concreting works continued in the third week of May 2005, however

by 17/05/05 the wash out of the concrete by the ingressing water was so severe it was

impractical to continue. The concrete backfill (621m³) had filled 80% of the tunnel

approximately, but the uppermost and critical roof section could not be filled due to the

ingress of water. Rapid reacting polyurethane foam was mobilised to site in order to seal

off the water and resume concrete backfill, drainage relief holes were also drilled. The

small amount of foam already on site was seen to be effective in sealing off the water

locally, but supplies were soon expended, by 25/05/05. Further supplies of foam did not

arrive until 31/05/05.

In the first week of June, further supplies of foam arrived and were used to seal off the

main areas of water ingress, and further concrete backfill/grouting operations were

attempted, in order to consolidate an area above the cutterhead, from which further pre-

grouting measures for the ground ahead could be collared from. On 07/06/05, the TBM

started re-excavating through the concrete plug, which continued for the next few days

again followed up with 120 steel ribs on 0.4m centres. The TBM was advanced 15m to Ch

19+614 and through the first fault by 15/06/05.

However advanced core drilling ahead of the cutterhead indicated a second and wider fault

zone lay ahead between Ch 19+610 and 19+600

Page 136: GROUTING IN ROCK TUNNELLING

136

At Ch. 19+614, drilling for pre-grouting and consolidation ahead of the face was

attempted using self-drilling injection pipes previously instructed to be brought to site by

the Owners representative. Attempts were limited by the poor rock conditions and grout

loss due to wash out. The TBM was advanced a further 2 metres and a second ring of pre-

grouting attempted, pre-grouting operations continued up until 11/07/05, and up to Ch

19+610. In this period the pre-grouting operations were hindered by the Contractors lack

of grout packers and experienced grouting operatives. The TBM resumed boring through

the pre-consolidated area on 11/07/05 again with HEB120 steel rib support and full steel

lagging support, advancing approximately 1 metre per day. By 21/07/05, the TBM had

advanced a further 13m to Ch. 19+597, and was already out of the main fault and in better

rock on the RHS of the cutterhead. At this juncture the TBM main conveyor broke down

and was not repaired until the Saturday nightshift of 23/07/05, whereupon the continuing

collapse of material during the stoppage had been found to have blocked the cutterhead

and rotation had been lost.

Further attempts to restore the rotation of the TBM head failed, and it became neccessary

to remove the previously installed ribs in order to reverse the TBM. However these ribs

where supporting loose boulders from the void above. It was necessary to consolidate

grout this area to a depth of 1.5 to 3 metres before it was safe to remove any ribs.

Consolidation grouting operations, removal of short sections of ribs, and attempts to

restore rotation continued throughout July and August. However the voided are above the

cutterhead continued to extend and ravel further, adding to the collapsed material pressing

against the cutterhead and preventing rotation. Again at the OR’s instigation, 12 m long

90mm steel pipes were installed above the cutterhead to limit further ground loss during

TBM reversal operations, but with little effect.

Into September further attempts at consolidating, removal of ribs, reversing of the TBM

continued back as far as 19+609 where rotation of the cutterhead was eventually restored

on 15/09/05. On restoration of rotation the TBM was moved forward under an overlapping

umbrella of self drilling bolts (spiles) and pre-grouting up to Ch 19+604 by 27/09/05.

However beyond this chainage the roof was again observed to be open void with

continuing loosening of the surrounding rock mass. To proceed further could have resulted

Page 137: GROUTING IN ROCK TUNNELLING

137

in a major de-stabilisation of the whole area. It was therefore jointly decided to pull back 5

m, and construct a watertight concrete bulkhead and backfill the void up to 2m above the

tunnel crown and to re-excavate through this second concreted plug.

The Bulkhead was constructed and the void backfilled up to crown level between

28/09/05 to 10/10/05. Re-boring through this second concrete plug continued to Ch.

19+605 by 12/10/05, where further void consolidation was carried out. The TBM then

advanced back to the originally achieved face at Ch 19+597, where pre-consolidation

grouting of the undisturbed ground ahead was carried out and normal TBM production

resumed. The stability of the section was restored to a large extent at this period to ensured

the stability of the tunnel and further advancement of the TBM. Additional rock support

were postponed till the finishing work period where intensive reinforcement, further

backfilling of voids and grouting of fifteen long rings of consolidation holes (12 holes per

ring) were carried out, (see figure 32) Both cement and polyurethane grouts were used.

Table 4. Summary Timeline of the operation described in Case 2.

21/04/05: Encountered first fault zone Ch.19+640

07/05/05: Advance by full class IV support measures to Ch.19+620

11/05/05: Encountered major water ingress which overcame normal pre-

grouting/consolidation techniques. cutterhead rotation lost at Ch.19+620.

13/05/05: TBM reversed to safe working area Ch 19+620 to 19+630

06/06/05: First Concrete bulkhead/plug constructed at 19+630

15/06/05: Re-excavate through concrete plug19+630 to 19+615

09/07/05: Pre-grout and consolidate second and third fault zones 19+615 to 19+600

21/07/05: Slow but steady advance by full class IV measures through collapsing

ground 19+615 to 19+597

21/07/05: Conveyor breakdowns, - 48 hour downtime

23/07/05: TBM Rotation lost at Ch 19+597

15/09/05: Consolidation grouting, removal of ribs and reversing of TBM to restore

rotation 19+597 to 19+610

27/09/05: Re-excavate through collapsing material 19+610 to 19+605

Page 138: GROUTING IN ROCK TUNNELLING

138

27/09/05: Further major collapse prevents further advance 19+605

04/10/05: Second bulkhead and plug constructed at 19+610

20/10/05: Re-excavation through plug 19+610 to 19+597

30/10/05: Consolidation grouting ahead of Ch19+597

Nov 2005: Boring Resumed.

(See figure 30).

Page 139: GROUTING IN ROCK TUNNELLING

139

Figure 30a. Diagram showing the Chronological advancement of the TBM 2 through the

faults #1, #2 and #3, (See Table 4. Summary timeline).

Page 140: GROUTING IN ROCK TUNNELLING

140

Figure 30b. Diagram showing the Chronological advancement of the TBM 2 through fault

#1, #2 and #3, (see table 4. Summary timeline).

Page 141: GROUTING IN ROCK TUNNELLING

141

Could the faulted zone have been predicted ?

According to the Site Investigation (SI), the particular area of tunnel is situated in the LA

middle suite of rocks which are predicted to occur between Ch19+200 to 21+800. The

nearest SI borehole to the fault zone is 1,5 km west at Ch 18+100 (#JB40), the nearest SI

borehole to the east is 4 km distant at Ch 23+600 (#FV47). There is a 5.5 km interval

between SI boreholes in this area, and the SI indicates an “information gap” between Ch

19+700 to 20+700. However this information gap section of tunnel was excavated mainly

in Class I rock without major geological incident.

The SI goes on to predict the likely rock class distribution to be 70% Class I, 30% Class II,

9% Class III and just 1% ( 26m) as being Class IV. Furthermore the likely risk of

encountering loose blocky ground, fault zones and sudden and major ingress of water to be

low or moderate risk.

According to this information no systematic probe drilling ahead of the TBM was being

implemented at Ch 19+640, and it is unreasonable to have expected a 45 metre wide fault

zone to have been predicted from the SI information provided. No systematic core drilling

was being made from the TBM either mainly due to the Contractors lack of suitable

equipment and experienced drillers.

With the major benefit of hindsight, surface lineations are apparent on aerial photos that

are coincident with lineations and faults encountered at Ch 19+600. Similarly, it could be

said that a 5.5 km interval between investigation boreholes was too wide for accurate

geological predictions, especially in view of using a hard rock TBM ill equipped for

dealing with soft-ground conditions. Angled boreholes on much closer spacings (say 1

km) would in retrospect have been a much more accurate way of detecting and predicting

steeply dipping fracture zones.

Since encountering the fault zone, the Owners Represeentative(OR) has suggested and

Landsvirkjun (LV) has instigated surface geophysical investigation, from which it can

now be seen that surface magnetometry is a particularly useful tool in identifying

lineations such as dykes or faults. (VIJV- Database 2005).

Other recommendations by the Owner’s Representative (OR) to improve the geological

predictions ahead of tunnel faces are:

Page 142: GROUTING IN ROCK TUNNELLING

142

• Continuous percussion probe holes ahead of the face.

• Underground core drilling, (Diamec drills).

• Desk Study, (Study topography maps).

• Surface Mapping, (Locating major faults and dykes i.e. through GPS).

• Surface Geophysics, (ISOR).

• Surface core drilling, (Angled holes).

Finishing Works.

Extraordinary Geological Occurrence, (EGO) Section. Ch 19 +640-19+597.

As part of the on-going finishing works, before filling the tunnel with water, further

reinforcement and concrete lining of this section (see figure 31) is been carried out. This is

the only section of the TBM excavation zone that is been concrete lined and thus reveals

the extent of the deterioration of the zone.

Drilling and grouting for backfilling of the voids, contact grouting to seal the membrane

between the host rock and the concrete lining and fifteen rings of consolidation holes (ring

A-N see figure 32), 12 holes per ring was instructed as part of the efforts to ensure

stabilisation of the tunnel strata.

Both cement grouts and chemical counterparts are used most especially in high leaking

holes through the concrete.

Page 143: GROUTING IN ROCK TUNNELLING

143

Figure 31. Diagram showing the length of the Extraordinary Geological Section (EGO).

NB, the tunnel should be circular in the cross-section.

Page 144: GROUTING IN ROCK TUNNELLING

144

Figure 32. Diagram showing consolidation grouting rings (A-N) and backfilling of voids

as part of the rock support. NB, the tulle should be circular in the cross-section.

Page 145: GROUTING IN ROCK TUNNELLING

145

18.3 Case study 3. Chainage 1 + 468, 5. Adit 4. (Dry-dyke) Geology Mapping.

Few meters before the actual chainage of this case, the geological mapping revealed very

strong gray olivine basalt and strong scoria. Then we get strong brown conglomerate (CG)

and sandstone in the lower wall. Then moderately altered rock with coating of yellow clay

on joint surfaces with dripping of water. Then columnar dyke with columns approximately

10 cm in diameter with water seeping and dripping from several places. Altered zone with

clay filled contact on both sides of the dyke. Poor blasting results and the face is un-even.

The boundary between the dyke and host rock is clay filled.

Geological overbreak. (Ch 1+ 460 – 1+472).

Figure 33. A cross section of the tunnel showing geological mapping at the dyke.

Page 146: GROUTING IN ROCK TUNNELLING

146

Drilling of grouting holes.

Figure 34. Drawing showing drilling and grouting/plan view seen from above (lower picture).

Page 147: GROUTING IN ROCK TUNNELLING

147

Drilling and Grouting.

Drilling of series of 24 holes (diameter Ø 51 mm) spaced at 1 m intervals from the lowest

point at the invert (floor) to the crown (ceiling) on either side. The holes were at 45˚out

from the tunnel axis and collared 7 m back from the face and all holes were drilled long

enough to intersect the required feature (the dyke). A technical log kept from drilling

includes location of cavities, cracks, drill bit rate of penetration and uniformity of rotation.

Directly after drilling of each individual hole, the automatic packer BVS 40 Ø 42 – 55 mm

(Minova) with steel extension pipe were inserted and installed close to the dyke.

Grouting/ Treatment of dyke.

The rationale behind the post grouting of the dyke is to prevent leakages in and out of the

tunnel which can drastically affect the production of electricity and could as well gradually

lead to environmental degradation. Hence, consolidation of the area was jointly instructed

by the Supervising Engineer and the Designer. Grouting was performed with Polyurethane

pump type CT-GX 45-11 with the min grout delivery 25 l/min requiring approximately 7

m3/min of compressed air. Polyurethane foam CarboPur Minova (two component system)

with accelerator CarboAdd fast (added in amounts of 2% to component A) was used.

The sequence of grouting was from the lowest position (in the invert) up to the crown. All

holes were grouted to refusal pressure (110 bars) measured on the manometer at the pump.

Three hundred liters of Polyurethane were taken as the maximum injected volume per

individual hole. If refusal pressure is not reached, then an interruption of 2 minutes is

made before continuing grouting again with polyurethane (two components and

accelerator).

In the case of any individual hole with high grout-take (above total 600 liters), the

procedure above would consequently be repeated after every further 300 liters.

Closing Criteria: Some adopted criteria for interrupting the injection e.g. in case of:

• Intensive leaking of non-reacted polyurethane into the tunnel.

• The refusal pressure of approximately 110 bars is reached.

• The expanded Polyurethane grout fractures the rock or shortcrete close to the

surface.

Page 148: GROUTING IN ROCK TUNNELLING

148

• The packer is not set tightly in its position, but moving towards the mouth of the

hole.

18.4 Case study 4. Chainage 002 + 255. Adit 3. ~150- 200 l/sec. This case is located about 2 km into the tunnel from the Halslon reservoir and lies within

the Drill and Blast section of the Head Race Tunnel (Power Intake). The geological

mapping revealed a sequence of scoria above olivine basalt, discontinuity by a fault which

is grey to dark grey and very strong tholeiite basalt, grading into highly vecular/scoracious

basalt, strongly reddish to purple locally. Joints are generally widely spaced and of low to

medium persistence. Joint infill of soft brown clay is common.

Despite the information from the probe holes which revealed water bearing features, the

grouting holes were not grouted to the refusal pressure during pre-injection as instructed

by the Owners Representative. Secondly, the invert (floor) were neglected during

grouting. This resulted in enormous water inflow after blasting (150-200 l/sec) which then

required additional watertightening by post grouting. This was targeted to prevent

leakages in and out of the tunnel which goes against good tunnelling principles.

Page 149: GROUTING IN ROCK TUNNELLING

149

Figure 35. Geological Mapping showing the geological overbreak in case 4.

Page 150: GROUTING IN ROCK TUNNELLING

150

Figure 36. Diagram showing the drilling and grouting activities/plan viewed from above

(lower picture).

Drilling and grouting activities were carried out in a similar way with the above (figure 34.

Ch 1 + 468.5), and the closing criteria was the same. Coffer dam was built downstream of

the grouting area to ensure that unreacted polyurethane does not flow out of the tunnel

with the run-off water there by preventing possible pollution.

Page 151: GROUTING IN ROCK TUNNELLING

151

18.5 Case Study 5. Adit 2. Jökulsa Valve Chamber. Curtain Grouting – Plug 2.2. The Plug is a concrete structure used to permanently close the Head Race Tunnel from the

adit (Adit 2). Curtain and consolidation grouting were carried out for stabilisation reasons.

This involved 4 rings (12 holes per ring), 15 m long in an umbrella shape, spaced at 3-4 m.

Cement grouting was carried out until refusal pressure of 10 bar was reached. Figure 37a

shows the pattern of ring A, 37b shows the pattern of ring B, and 37c shows the pattern for

ring C, while ring D shows the pattern for the consolidation holes (5m).

Plug 2.2 which lies at the Jökulsa í Fljótsdal right branch, cuts across a fault (see figure

37e) of which the grouting of the area further consolidates the zone. Cement grouts are

used for the plugs in general and Plug 2.2 was observed with very low intake during

grouting. All holes were grouted to the refusal pressure of 10 bar.

Figure 37a. Sketches Showing Ring A (15m). Curtain Grouting ( 1,3,5,7,9,11,13,15,17,19,21,23).

Page 152: GROUTING IN ROCK TUNNELLING

152

Figure37b. Sketches Showing Ring B (15m). Curtain Grouting ( 2,4,6,8,10,12,14,16,18,20,22,24).

Figure 37c. Sketches Showing Ring C (15m). Curtain Grouting ( 1,3,5,7,9,11,13,15,17,19,21,23).

Page 153: GROUTING IN ROCK TUNNELLING

153

Figure37d. Sketches Showing RingD (5m). Consolidation Grouting ( 2,4,6,8,10,12,14,16,18,20,22,24).

Page 154: GROUTING IN ROCK TUNNELLING

154

Figure 37e. Curtain drilling and grouting of plug 2.2.

Page 155: GROUTING IN ROCK TUNNELLING

155

19 Discussions and summaries of lessons learned, results and conclusion.

“Grout”is defined 74(ASCE) as “a material injected into a soil or rock formation to change

the physical characteristics of the formation. Grouts can be divided into two categories, the

suspended- solid grouts, such as cement and bentonite, and those materials which are true

solutions, or chemical grouts.

Rock grouting is probably the best known of grouting practices to engineers working in

tunnel design and construction. Its application is found on most permanent dams, tunnels

and numerous other structures such as oil rigs, river barges and in mines to avoid sudden

ingress of water, and to stabilize and seal the ground ahead of excavation operations.

The purpose of grouting in rock tunnelling varies on projects but would mostly be:

• Reducing the permeability against water inflow.

• Enhancing the rock strengths.

• Filling of voids.

The importance and necessity of grouting in rock tunnelling cannot be over-estimated;

pre-grouting activities enhances the smooth running and advancement of the excavation

face in order to ensure that projects are completed within assumed time frame. This goes a

long way to safe time, money and any un-necessary claims that may come up.

Proper pre-grouting activities could almost eliminate post-grouting activities which has

been known to be time consuming, very expensive and in practice difficult in achieving

the desired and expected water tightness of the tunnel.

In shear zones, 360˚grouting pattern should be considered as this eliminates movement of

water through the other side of the feature.

A manageable grouting team is highly recommended from the beginning of any rock

tunnelling which could be increased in number with time if required. This alleviates

additional efforts that may need to be put on post-grouting thereby saving cost.

74 ASCE: American Society of Civil Enginners.

Page 156: GROUTING IN ROCK TUNNELLING

156

Grouting objectives in rock tunnelling go beyond sealing the tunnel against underground

water inflow, as to prevent any adverse environmental effect inside the tunnel, prevent un-

acceptable impact on the external environment, as well as maintaining hydrodynamic

containment but also for overall stabilization of the tunnel strata.

Post-grouting treatment in tunnelling are often necessary to consolidate the rock mass,

minimise water ingress or provide intimate contact between the tunnel lining and the rock

mass (contact grouting).

Chemical grouting has brought an irreversible development into the grouting industry

within the last five decades, with the wider application of fast reactive resins in

underground constructions such as mines and tunnels.

Effective and continuous monitoring of surrounding aquatic bodies is highly

recommended even beyond the construction period of the project.

Proper materials, equipment and technical know-how from competent and experienced

grouting practitioners remain adequate ammunition in successful rock grouting.

Multiple hole grouting is highly recommended to many problems connected with

impermeabilization and stabilization of rock tunnelling.

Up to date injection records and quality control during injection remains an important part

of successful grouting in rock tunnelling.

The three Tunnel Boring Machines (TBMs) used in the excavation of the Kárahnjúkar

Head Race Tunnel (HRT) had successful breakthroughs, despite high water inflow that

characterised parts of the tunne,l through the help of planned and successful grouting

activities (pre-grouting) ahead of the excavation face and afterwards, shear zones being

successfully consolidated (post-grouting). This has in no small measures, increased

confidence regarding the durability and overall stabilization of the tunnel strata.

Page 157: GROUTING IN ROCK TUNNELLING

157

20 References. Andersson, Helen (1998). Chemical Rock Grouting. An Experimental Study on Polyurethane Foams. Department of Geotechnical Engineering. Chalmers University of Technology S-41296 Göteborg, Sweden. ASCE (1980). American Society of Civil Engineers. The Glossary of Grouting Terms. Published by the ASCE Committee on Grouting. Journal of the Geotechnical Enginnering Division. Baker, C. et al., (1982). Use of grouting in caisson construction. Proceeding. Conference. Grouting for Geotechnical Engineering., New Orleans. W.H Baker (ed). American Society of Civil Engineering. New York, pp. 874-891. Barton, N. and Quadros, E., (2004) “ Improved understanding of high-pressure grouting effects for tunnels in hard rock” ISRM 2003 – Technology road map for rock mechanics, South African Institute for Mining and Metallurgy. Bowen, Robert (1981). Grouting in Engineering Practice. 2nd edition. Applied Science Publishers LTD. London. Broch E. (1987). Rock Tunnelling. The Past, Present and Future of Rock Tunnelling. Bruce, D., Naudts, A., and Soak, G. (1998). High Flow Reduction in Major Structures: Materials, Principals, and Case Histories. Grouts and Grouting Degussa (BASF) (2006). Practical injection course UGC Europe Region Hagerbach, Switzerland 4-5 May. Degussa (BASF) (2007). Construction Chemicals (Europe) AG. Technical Data Sheet MEYCO MP 355/A3 Edwards, D.B. Grouting for Tunnels. I.C.E. United Kingdom.

Eggington, H. Frank et al (1996). The Manual of Methods, Applications, and Management. 4th edition. Australian Drilling Industry Training Committe Limited. Drilling. Einarson, Thorleifur (1991). Geology of Iceland. Rocks and Landscape. Mál og Menning. Iceland. Ewart, Friedrich-Karl, (1994). Rock Permeability and Groutability Related to Dams and Reservoirs, lecture notes, University of Paderborn, Germany, September 1980. Freysteinn Sigurdsson (1990). Groundwater from glacial areas in Iceland. Jökull, No. 40 1990 Orkustofnun. (National Energy Authority) Reykjavik, Iceland. Freysteinn Sigurdsson. and Kristinn Einarsson (1988). Groundwater Resources of Iceland- Availability and Demand. Jökull, No. 38, 1988. Orkustofnun, National Energy Authority, Hydropwer Division Reykjavik, Iceland. Garshol, Knut F. (1999). Use of Pre-injection and Spiling in Front of Hard Rock TBM Excavation. Paper presented at Tenth Australian Tunnelling Conference, Melbourne 21-24 March.

Page 158: GROUTING IN ROCK TUNNELLING

158

Garshol, Knut F. (2003). Pre-Excavation Grouting in Rock Tunnelling. MBT International

Underground Construction Group Ltd, Switzerland.

Gíslason, S.R and Eugster, H 1987. Meteoric water – basalt interactions. 1. A laboratory study. 11: A field study in N.E. Iceland. Geochemica et Cosmochemica Acta, 51, 2827 -2855. Hepburn, C. (1992) Polyurethane elastomers. Elsevier Applied Science. London, New-York. Hany AG Equipment. http://www.hany.com/geraete.html Henn, Raymond W. (1996). Practical Guide to Grouting of Underground Structures.- Thomas Telford. Heuer, R.E. (1995). Estimating Rock Tunnel water inflow. Proceedings, Rapid Excavation and Tunnelling Conference, Society for Mining, Metallurgy, and Exploration, Inc., Cushing-Malloy, Inc., Ann Arbor, Mich., 41-60. Hjartason Á., Andersen, L.J., Kelstrup, N. And Rasmussen, J. 1980. Explanatory Notes for the international Hydrogeological Map of Europe sheet B 2 Island, 55 pp. Bundesanstalt fur Geowissenschaften und Rohstoffe, hannover, and Unesco, Paris. Holter K.G et al; (1996). Tunnelling through a sand zone: Ground Treatment experiences from the Bjoroy sub sea road tunnel, Proceeding of North American Tunnelling 1996. Ed: Ozdemir, pp 249-256, Vol 1 (AA Balkema Rotterdam). Holter, G.K (2005). Modern Pre-Injections in Underground Construction; Saving Time and Costs in Difficult Ground. Degussa (BASF) UGC Europe, 8048 Zuerich, Switzerland. Honnestad, Hans O., Knut F.Garshol and Ross Dimmock, (2002). Pre-injection in hard tunnels using Degussa Rheocem microcement. Degussa International UGC Publication. Houlsby, A.C. (1976). Routine Interpretation of the Lugeon Water Test, Quarterly Journal of Engineering Geology, Vol. 9, The Geological Society. Houlsby, A.C. (1983). Cement Grouting - A Compilation of Recent Papers. Water Resources Commission., NSW, Australia. Houlsby, A.C. (1990). Construction and Design of Cement Grouting. A guide to grouting in rock foundations. John Wiley and Sons, New York. Jakubowicz, I. (1992). Determination of long term properties for polymer based grouts. Conference proceedings. Nordiskt Symposium I berg injektering. Ed. Lundblom. Chalmers University of Technology, Goteborg. Pp 50-56. Jefferies M.G et al. (1982). Electronic monitoring of grouting. Proceeding. Conference. Grouting in Geotechnical. Engineering. New Orleans. W.H. Baker (Ed). American Society of Civil Engineer. New York, pp 769 -780. Karol, R.H. (1983). Chemical Grouting. Marcel Dekker Inc., New York. Karol, R.H. (1990). Chemical Grouts and their properties. Marcel Dekker. Inc. New York.

Page 159: GROUTING IN ROCK TUNNELLING

159

Karol R.H. (2003). Chemical Grouting and Soil Stabilisation. 3rd Ed. Revised. Marcel Dekker-

Taylor and Francis, CRE.

KEJV. Kárahnjúkar Engineering Joint Ventures. Kárahnjúkar Hydroelectric Power Project

Designer.

Koerner, R.M. et al. (1985). Acoustic emission monitoring of grout movement issues in dam grouting. Proceeding session Geotechnical Engineering. Division of ASCE. American Society of Civil Engineer., New York, pp. 202-206.

Kramer, G.J.E., Roach, M.F., Townsend, J.W. and Warren, S.T. (1998). “Grouting of TBM Rock Tunnels for the Los Angeles Subway”, ASCE – Geotechnical Special Publication #80, 1998, pp. 100 -110. Kutzner C. (1996). Grouting of Rock and Soil. A.A Balkema /Rotterdam/ Bookfield/ 1996. Landry, E, Lees, D., and Naudts, A. (2000). New Development in Rock and Soil Grouting: Design and Evaluation. Geotechnical News. September. PP 38-44. Landsvirkjun (2001). Kárahnjúkar Hydroelectric Project. Environmental Impact Assessment. Summary. Landsvirkjun (2002). Kárahnjúkar Project. Landsvirkjun’s Environmental Policy and Objectives. Landsvirkjun (2002). Kárahnjúkar – Large Scale Industry in East Iceland. Landsvirkjun’s website http://www. Karahnjukar.is. and www.lv.is Landsvirkjun (2003). Kárahnjúkar Hydroelectric Project and Transmission Lines FL-3 and FL-4. Minova CarboTech GmbH. Tunnel and Civil Engineering. Technical Data Sheet CarboPur WFA. Mistry, J.F. (1988). Important Aspect of River Valley Projects. Mahajan Book Distributors, Amdavad, Gujarat, India, Vol. 2. Najder, Tomasz (2006). Personal Discussions on site. VIJV: Viseningar Joint Ventures Senior Grouting Engineer. Kárahnjúkar hydroelectric project supervision team. Naudts, A. (1990). “Research Project Fort Cady Minerals: Chemical resistance of modified cement-based grout and polyurethane grouts Accelerated ageing test” Unpublished. Naudts, A. (1995) “ Grouting to Improve Foundation Soil” Practical Foundation Engineering Handbook. Chapter 5B. Ed Robert Wade Brown. McGraw-Hill.pp. 5.277-400. Naudts, A. (2003). Irreversible Changes in the Grouting Industry Caused by Polyurethane Grouting: An overview of 30 years of polyurethane grouting. Geotechnical Special Publication 2003 Issue 120; Vol 2, page 1266 – 1280. Naudts et al., (2000). New On –site Wet milling Technology for the preparation of Ultrafine Cement-based Grout. Canadian Geotechnical Conference. Montreal. October.

Page 160: GROUTING IN ROCK TUNNELLING

160

Naudts et al., (2003). Additives and Admixtures in Cement-based Grouts. Naudts, A. and S, Hooey. (2003). Hot Bitumen Grouting: The antidote for catastrophic inflows.

Norwegian Tunnelling Society .NTS. (2004). Publication Number 14 pp 43-46. Norconsult Publication. Rock Engineering in Tunnel Design.

Oshita, T., Kitano, M., and Terashima, K. (1991) “ Long Term Durability of Sails Solidified with Hydrophobic Polyisccyanate type grout “Sociey of Materials Science. Japan. December. Pp.1552-1557. Pettersson, Sten- Ake (2001). Atlas Copco Craelius AB, Stockholm. Development of Grouting Equipment in Scandinavian Tunnelling During the last Decade. 4th Nordic Rock Grouting Symposium Stocholm 2001 Proceedings. Pettersson, Sten-Ake and Molin, Hans (1999). Grouting and Drilling for Grouting: Purposes, applications, methods and equipment with emphasis on dam and tunnel projects. Atlas Copco Crealius AB Publication. Pitts, Peter (2006). Personal Discussions. VIJV: Viseningar Joint Ventures Senior Geotechnical Enginneer. Kárahnjúkar Hydroelectric project Supervision Team. Reina, Peter. (June 2006). Energy: Harsh Climate, Difficult Geology Temper Peace of Work. Reina, Peter. (June 2006). Energy : Iceland Digs Deep To Develop Power in the Wilderness. Roby, J. (2006). Northern Exposures. Supplying Iceland’s New hydropower Plant. Tunneling Overcome Extreme Weather and Geological Conditions. Tunnel Business Magazine. Schunnesson, H., (1996). Probing ahead of the face with percussive drilling. Tunnels and Tunnelling, January 1996, pp 22-23. Schönian, Erich. (1999) The Shell Bitumen Handbook. Shell International Petroleum Company Limited. Sjostrom O.A. (2003). Principles and Ground water Control through Pregrouting in Rock Tunnels Shroff, Arvind and Dhananjay L. Shah (1999). Grouting Technology in Tunnelling and Dam Construction. 2nd Edition. Skanska United Kingdom. Application of Grouting Techniques. Skanska AB (1997). The Halland Ridge (Pg 21). Skanska Environmental Report.

Skeggedal, T., (1983). The use of tunnel boring machines (TBM), Norwegian Tunnelling Society, Publication No 2, Oslo 1983. Saemundsson, K. (1980). Outline of the Geology of Iceland. Jökull, 29, þ.7-28. Takenaka. (1976) Taccs Know-how books. Internal Publications.

Page 161: GROUTING IN ROCK TUNNELLING

161

Tolppanen, P. and P. Syrjanen. (2003). Hard Rock Tunnel Grouting Practice in Finland, Sweden, and Norway – Literature Study by Finnish Tunnelling Association. Tómasson, H. 1982: Vattenkraft i Island och dess hydrologiska förustáttningar. Paper presented at the Nordic Hydrological Conference, Førde, 28-30. June 1982. 10 pp. Orkustofnun, mimeographed report No. OS-82059/VOD-10, Reykjavík. Tunnels and Tunnelling International (October 2005). Focus on Iceland. Extreme Tunnelling- Kárahnjúkar. U.S Army Corps of Engineers (1984). EM 1110-2-3506. Engineer Manual.. Engineering and Design –Grouting Technology. Geotechnical and Materials Branch, Engineering Division, Directorate of Civil Works (CECW-EG). U.S Army Corps of Engineers, (1995). EM 1110-1-3500. Engineer Manual. U.S Army Corps of Engineers. Engineering and Design –Grouting Technology. Geotechnical and Materials Branch, Engineering Division, Directorate of Civil Works (CECW-EG). Verfel, Jaroslav (1989). Rock Grouting and Diaphragm Wall Construction. Development in Geotechnical Engineering 55. Elsevier Science Publishers. VIJV (2006). Viseninger Engineering Joint Venture Database. Kárahnjúkar Hydroelectric Project Supervision Team. Water Resources Commission N.S.W., Grouting Manual, 3rd edition, Australia, 1980.

Warner, James (2004). Practical Handbook of Grouting. Soil, Rock and Structures. John Wiley & Sons, Inc. Hoboken, NJ.