Upload
wesley-lyons
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
Group16: Assembly Fixture Design and Fabrication for 6 Pole Motor Magnets and their Retaining Parts
Group Members:
Jeffrey Morton
John Pilgrim
Marcus Rothberg
November 12, 2009
Overview Introduction The Problem Product Specification The Design Concepts Design Choice and Walkthrough Experimental Calculations Cost Analysis Conclusion Future Work
Danfoss Turbocor Specializing in commercial
HVACR applications Designer and manufacturer
of world’s first oil-free refrigerant compressors
The largest compressor, that is still in development, is the TT500
The Compressor – TT500 It is currently in its
Beta phase of development
Inside the TT500 is a shaft that powers it
The shaft has a hexagonal center where six rows of magnets will be installed
The Shaft Will have six rows of
magnets secured to it via wedges
Each row of magnets will hold 9 magnets for a total of 54 magnets
The Problem Load and secure magnets and wedges onto the
shaft. Magnets need to be aligned with the poles adjacent Pole orientation alternating from column to column
Causes loading and alignment to be difficult
Magnets The difficulty in
installing the magnets is that the poles of the magnets are aligned
The repelling force of the magnets causes the installation to be difficult
Scope and Customer Needs A new method to install magnets and wedges
onto the shaft Process must be
Safe Ergonomic Accurate Time efficient Non-damaging to parts
Product Specification Budget of $1500 Load and align 9 magnets to each row Installs or allows wedges to be installed in between each row
of magnets A total of 6 rows of magnets Repeatable Completion of assembly within 45 minutes
Design 1: Plunger Fixture
Magnets placed all at once
Holds magnets for wedges and the next column of magnets to go
Initial plunger releases and moves to next column
Loads and installs magnets one at a time.
Cylindrical Sleeve retains magnets on the shaft.
Ferrous bit constrains each magnet as they are lowered onto the shaft.
Wedges may be installed as each row of magnets is installed.
Design 2: Cylinder Sleeve
AligningRings
Retaining Cylinder
FerrousBit
Design 3: Bracket and Rail
Magnets loaded one at a time. Magnets installed in rows of
nine. Magnets are aligned in rail, then
loaded into the bracket and steel fixture.
Steel with magnets is lowered onto shaft and bracket locks into fixture.
Brackets retain magnets on the shaft until wedges can be installed.
AligningRail
Magnet Clamp
Removable Ferrous Bit
Design 4: Trap Door Magnets are loaded Bar clamps and places magnets onto shaft Magnets then secured by rods Bar is removed and process is repeated
Concept Matrix
Specifications:•Precision (40%)•Ease of Use (30%)•Safety (10%)•Durability (10%)•Time (10%)
From Start to Finish Bottom collar halves and aligning cylinder are
placed
From Start to Finish Shaft is placed Top of the cylinder aligns shaft radially Edge of cylinder aligns shaft axially
From Start to Finish Top collar halves are placed
From Start to Finish Alignment cylinder is removed Collar tops are placed to retain collars
From Start to Finish Shaft is placed and located Magnets are to be loaded and placed
From Start to Finish Magnets are loaded one at a time (Part of the fixture base/frame is removed for visual
purposes)
From Start to Finish Magnet row alignment issues Cam device and wall provides solution
From Start to Finish Cam device and wall
From Start to Finish Magnets loaded and aligned with cam Magnets picked up by clamp
From Start to Finish Trap door in loader opens Clamp moves down path to place magnets on shaft
From Start to Finish Retaining rods placed on magnet row
From Start to Finish Shaft is indexed and next row of magnets is to be loaded After all 6 magnet rows are loaded, shaft is removed from
fixture
From Start to Finish Retaining wedges are installed Retaining rods and collars are no longer needed
Completion GREAT SUCCESS!!!
Fixture Exploded View
Analysis Force between two or more magnets Cam displacement polynomials Cam sva graphs Cam profile Time Analysis Material Selection Cost analysis
Magnet Testing The magnets need to be
loaded together. As the magnets get
closer together, the repelling force increases
A force of 26lbs is needed to place magnets together
Loader
Scale
Magnets
Cam Aligner Design
Action Displacement Velocity Acceleration Displacement Polynomial
Rise(0-90deg)
0 0 0
h 0 0
Dwell(90-270 deg)
h 0 0
h 0 0
Fall(270-360deg)
h 0 0
0 0 0
sd ( ) h
vr ( ) h 302
13
603
14
304
15
s.r ( ) h 10
.1
3
15
.1
4
6
.1
5
22
sf ( ) h 1 10
32
2
3
15
32
2
4
6
32
2
5
Cam Aligner SVA Graphs
0 2 4 60.5
0
0.5
1
Displacement
s ( )
0 2 4 62
1
0
1
2
Velocity
v ( )
0 2 4 60.5
0
0.5
1
Displacement
s ( )
0 2 4 63
2
1
0
1
2
3
Acceleration
a ( )
No over shoot in displacement curve.
Smooth velocity curve.
No jumps in acceleration curve.
Cam Profile From displacement curve. Profile equations:
4 2 0 2 4
4
2
0
2
4
Cam Profile
y ( )
cy ( )
x ( ) cx ( )
x ( ) Rb s ( ) sin ( ) v ( ) cos ( )
y ( ) Rb s ( ) cos ( ) v ( ) sin ( )
Center of axle equations:
cx ( ) r sin ( )
cy ( ) r cos ( )
Time Analysis
0 5 10 15 20 25 30 35 40
Ass
embl
y
Time (minutes)
Index and Secure Shaft in Inner Colars
Place and Secure Shaft in LoadingFixture
Load Six Rows of Magnets
Roll Aligning Cams Six Times
Lower and Secure Six Rows of Magnetson Shaft
Remove Shaft From Loading Fixture andInstall Wedges
Preliminary Material Selection Aluminum 6061 for most structural parts
Easy to machine Relatively cheap Noncorrosive Yield strength of 8000psi (55MPa)
Oil impregnated bronze or Teflon for loader lining Low friction Non abrasive
Brass for inner collar Low friction
Cost AnalysisPart Dimension Material Quantity Purchased? Price
Loader H=1”; w=1”; Aluminum Square
Tube 1 no $2.37
Sliding Door H=1”; w=1”; Aluminum Square
Tube 1 no $2.37
Magnet Clamp T=1/2”; L=12”; w=2” Stainless Steel 1 no $38.90
Lever D=1”; L=36” Aluminum 6061 1 no $13.33
Frame T=1/2”; W=4; L=12” Aluminum 6061 4 no $52.36
Collar D=6”; L=6” Brass 1 no $350.29
Hardware NA NA NA no $50.00
Cam D=1”; L=6” Aluminum 2024 1 no $13.34
Cam Plate T=1/4”; L&W=8” Aluminum 2024 1 no $16.38
Cam Aligner Side Plates T=1"; W=3"; L=12" Stainless Steel 1 yes $89.06
Base Plate T=1" ;W=8”; L=8” Aluminum 6061 3 yes $147.90
Other Dimensions Price per hour Quantity Purchased? Price
Machine Work NA $50/hr 10 hrs Donated $500
Total $776.30
Future Work Finalize design and do detailed drawings with
tolerances. Analyze the four bar lever. Fem Analysis of the magnetic fields and their
resulting forces. Order parts.
Acknowledgements Robert Parsons
Turbocor Machine Shop Supervisor
Clint Bencsik Turbocor Manufacturing Engineer
Alain Pepin Turbocor Mechanical Engineer Design Manager
Jean S. Cote Dr. Daudi R. Waryoba Davey Jones
Reference McMaster-Carr, www.mcmaster.com Norton, Robert L. Design of Machinery 4th
edition, 2008. McGraw Hill. Softwares – ProEngineer Wildfire,
SolidWorks, Mathcad, Microsoft Office
ANY QUESTIONS?
Comments also welcome