31
Renewable Energy Education Project - REEP COLLEGE OF ENGINEERING – KNUST Kumasi/Ghana Short course GRID – CONNECTED SOLAR PV SYSTEM DESIGN AND INSTALLATION Ahmed Ousmane BAGRE June 2009

Grid Connected Pv Part 2

Embed Size (px)

Citation preview

Page 1: Grid Connected Pv Part 2

Renewable Energy Education Project - REEP COLLEGE OF ENGINEERING – KNUST

Kumasi/Ghana

Short course

GRID – CONNECTED SOLAR PV SYSTEM DESIGN AND INSTALLATION

Ahmed Ousmane BAGRE June 2009

Page 2: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 2

TABLE OF CONTENTS

1. GENERAL PRINCIPLE _______________________________________________________ 3

1.1. SYSTEM WITHOUT BATTERY ____________________________________________________ 3

1.2. SYSTEM WITH BATTERY ________________________________________________________ 4

1.3. COMMERCIAL BACKUP SYSTEM _________________________________________________ 5

2. METERING _______________________________________________________________ 6

2.1. NET‐METERING ______________________________________________________________ 6 2.1.1. System using a Bidirectional net‐meter _______________________________________________ 6 2.1.2. System using a Dual net‐meter ______________________________________________________ 7

2.2. A FEED – IN TARIFF ___________________________________________________________ 8

3. GRID‐CONNECTED INVERTER ________________________________________________ 9

3.1. GENERAL ___________________________________________________________________ 9 3.1.1. Inverter classification _____________________________________________________________ 9 3.1.2. Main common functions for grid inverter _____________________________________________ 10

3.2. TECHNICAL DESIGN OF PV INVERTERS ___________________________________________ 12 3.2.1. Basic inverter design _____________________________________________________________ 12 3.2.2. Different types of inverters technologies _____________________________________________ 13 3.2.3. Technologies in comparison _______________________________________________________ 14

3.3. CONFIGURATION FOR PV SYSTEM ______________________________________________ 15 3.3.1. Protection technology ____________________________________________________________ 16 3.3.2. Technical parameters ____________________________________________________________ 17 3.3.3. Inverter efficiency _______________________________________________________________ 17

4. GRID –CONNECTED SYSTEM DESIGN _________________________________________ 19

4.1. GENERAL __________________________________________________________________ 19 4.1.1. Energy efficiency ________________________________________________________________ 19 4.1.2. Documentation _________________________________________________________________ 19 4.1.3. System design steps ______________________________________________________________ 20 4.1.4. System design criteria ____________________________________________________________ 20

4.2. DESIGN TO FIT ON AVAILABLE ROOF SPACE ______________________________________ 20

4.3. DESIGN TO MEET YEARLY ENERGY USAGE ________________________________________ 28 4.3.1. Assessment ____________________________________________________________________ 28

1. PERFORMANCE PARAMETERS FOR GRID‐CONNECTED PV SYSTEM _________________ 30

1.1. Standard performances _______________________________________________________ 30

1.2. Monitoring _________________________________________________________________ 31

Page 3: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 3

1. GENERAL PRINCIPLE

1.1. SYSTEM WITHOUT BATTERY

Grid-connected or utility-interactive PV systems are designed to operate in parallel with and interconnected with the electric utility grid. The primary component in grid-connected PV systems is the inverter, or power conditioning unit (PCU). The inverter converts the DC power produced by the PV array into AC power consistent with the voltage and power quality requirements of the utility grid, and automatically stops supplying power to the grid when the utility grid is not energized. This safety feature is required in all grid-connected PV systems, and ensures that the PV system will not continue to operate and feed back into the utility grid when the grid is down for service or maintenance.

An interface is made between the PV system AC output circuits and the electric utility network, typically at an on-site distribution panel or service entrance. This allows the AC power produced by the PV system to either supply on-site electrical loads or to back-feed the grid when the PV system output is greater than the on-site load demand. At night and during other periods when the electrical loads are greater than the PV system output, the balance of power required by the loads is received from the electric utility. The system can be with battery (Figure 1a) or battery less (Figure 1b)

Figure 1a: Grid-connected system without battery configuration

AC Load(s)

PV array Inverter

Distribution

Panel

Electric

Grid

Page 4: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 4

1.2. SYSTEM WITH BATTERY

The grid-connected system with battery bank is necessary where a critical backup power supply is required for critical loads such as computer, lighting, refrigeration and other necessities. Under normal circumstances, the system operates in grid-connected mode, serving the on-site loads or sending excess power back onto the grid while keeping the battery fully charged. In the event the grid becomes de-energized, control circuitry in the inverter opens the connection with the utility through a bus transfer mechanism, and operates the inverter from the battery to supply power to the dedicated loads only. In this configuration, the critical loads must be supplied from a dedicated sub panel. Figure 18 shows how a PV system might be configured to operate normally in grid-connected mode and also power critical loads from a battery bank when the grid is de-energized.

Figure 1b: Grid-connected system with energy storage system configuration

PV array

Inverter/ Charger

Main

Panel

Non-Critical

AC Load(s)

Electric

Grid

Critical Load

Sub Panel

Critical

AC Load(s)

Battery

Storage

Page 5: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 5

1.3. COMMERCIAL BACKUP SYSTEM The Sunny Backup system comprises one or more Sunny Backup 5000s in combination with an Automatic Switch Box (AS-Box-M, AS-Box-L or AS-Box-XL). This system is specially designed for backup applications and enables, in compliance with all standard requirements, continued operation of a grid-connected PV system in the event of grid failure. Thus, this system does not replace the conventional PV inverter (Sunny Boy), but is installed additionally. In the event of grid failure, the Sunny Backup system first ensures safe disconnection of the loads and the PV system from the public grid, and subsequently forms a stable stand-alone grid, into which the Sunny Boy can then feed solar energy. The maximum period of interruption for the loads is approximately 20 ms, which for most loads is equivalent to uninterrupted operation.

The Sunny Backup system is suitable for use in conjunction with all Sunny Boys and Sunny Mini Centrals from SMA Technologie AG. The modular structure allows the suitable construction of systems with a maximum consumer power of approximately 5 kW to 100 kW. The Sunny Backup system can be integrated into new PV system installations, and can also be retrofitted onto existing PV systems. Along with the Sunny Backup 5000 inverter and the automatic switching device, a battery is necessary as a short-term storage device, for reliable operation. During grid failure, the battery has the task of correcting the imbalance between generation and consumption. Whenever less energy is being generated than consumed (e.g. at night), the battery is discharged. Whenever more energy is being generated than consumed (e.g. during the day), the battery is charged. The intelligent battery management built into the Sunny Backup 5000 protects the battery from overcharging and deep discharge. This ensures that the battery service life stipulated by the battery manufacturer can be achieved.

Page 6: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 6

2. METERING

Following the deregulation of electricity supply markets in many countries, many electricity customers in industrialized countries installed their own electricity generating equipment and connected it to the grid. When a customer is generating more electricity than required for his own use, the surplus may be exported back to the power grid. Two main system of metering are used to control the amount of energy consumed by the customer or sent to the grid:

2.1. NET­METERING Net metering is an electricity policy for consumers who own (generally small) renewable energy facilities, such as PV system.The net metering principle consists to measure the amount of energy sent to the grid and the amount of energy consumed by the PV system owner and find the net-energy given by:

Net Energy = Energy received from the grid – Energy sent to the grid

At the end of the month, if the customer uses more energy than the PV generates, the customer pays the difference (positive net-energy). But if the customer has generated more energy than used, the grid company credits the net kilowatt-hours (negative net energy) produced at the power rate. Depending on PV size and electrical consumption, you may produce more or less than you actually use. In order to support the production of PV-generated power, some grid companies offer a better price for the kWh fed into their grid than they charge for the kWh from the grid. In other locations a one-to-one ratio is applied which means the same kWh-price for both flow directions. Net Metering can be done with or without a battery backup. Technologically speaking, two systems of net-metering exist:

2.1.1. System using a Bidirectional net­meter

In net metering system using a Bidirectional net-meter, when the PV system produces excess energy, it is sent to the grid system and the meter turns backwards. If the customer uses more power than is being produced, the energy is received from the grid system and the meter turns forwards. Meter 1 (figure 2a) is here just to get precise information on the amount of PV energy produced by the PV system and Meter 2 is the bidirectional net-meter. This option is seen as the most attractive option (no need to buy an additional meter) for the PV system owner. But, for most electricity companies in Europe, it is not satisfactory to allow the meter to simply run backwards for exported unit since this leave the meter open to fraudulent abuse. Furthermore, modern electronics meters can be programmed to run only in one direction to combat meter fraud. For all these reasons, a meter with two separate metering register is required (see figure 2a).

Page 7: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 7

Figure 2a: Bidirectional net-meter configuration

2.1.2. System using a Dual net­meter Most utilities in Europe, have adopted the net metering using a Dual net-meter. This system uses two separate, reverse blocked meters for sold (meter 3) and purchased (meter 2) electric energy. To get precise information on the amount of PV electricity produced by the solar electric system, an additional meter is recommended (meter 1, Figure 2b).

Figure 2b: Dual meter configuration

AC Load(s)

PV array Inverter

Utility

Grid kWh kWh kWh

1 2 3

AC Load(s)

PV array Inverter

Utility

Grid kWh kWh

1 2

Page 8: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 8

2.2. A FEED – IN TARIFF

A Feed-in Tariff (FiT, Feed-in Law, FiL,) is an incentive structure to encourage the adoption of renewable energy through government legislation. The national electricity utilities are obligated to buy renewable electricity (electricity generated from renewable sources, such as solar photovoltaic at market rates set by the government. The higher price helps overcome the cost disadvantages of renewable energy sources. The rate may differ among various forms of power generation. This system uses two separate, reverse blocked meters for sold (meter 1) and purchased (meter 2) electric energy as shown figure 2c.

Figure 2c: Feed-in tariff configuration

AC Load(s)

PV array Inverter

Utility

Grid

1 2 kWh kWh

Page 9: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 9

3. GRID­CONNECTED INVERTER

3.1. GENERAL The essential device of a grid connected photovoltaic installation is the inverter. It acts as an interface between the solar array and the utility grid. The utility-interactive inverter differs from the stand-alone unit in that it can function only when connected to the grid. This inverter converts direct current produced by the solar array into alternating current that can be fed into the distribution network. The on grid inverter not only conditions the power output of the photovoltaic array, it also serves as the system's control and the means through which the site-generated electricity enters the grid lines. It uses the prevailing line-voltage frequency on the utility line as a control parameter to ensure that the PV system's output is fully synchronized with the utility power.

3.1.1. Inverter classification Technologically speaking, there are two main types of inverters used in the grid-connected system as shown in Figure 1 The line commutated inverter uses a switching device like a commutating thyristors that can control the timing of turn-on while it cannot control the timing of turn-off by itself. Line-commutated inverters are not suitable for use in standalone systems because AC voltage from the grid is required to turn off thyristors. The self-commutated inverter uses a switching device like IGBT (Insulated Gate Bipolar Transistor), MOSFET or GTO (Gate Turn Off) thyristors and can operate without AC grid voltage. Due to advances in switching devices, most inverters for distributed power sources such as photovoltaic power generation now employ a self-commutated inverter. The Self-commutated inverters are broadly classified as:

• Voltage-Source Inverter (VSI), has a capacitor in parallel across the input and the DC side is made to appear to the inverter as a voltage source

• Current –Source Inverters (CSI), has an inductor in series with the DC input and the DC source appears as a current source to the inverter.

According to the inverter control scheme, the following classification can be done:

• Current-Controlled Inverters (CCI), • Voltage-Controlled-Inverters (VCI)

Page 10: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 10

Most inverters are voltage source (VSI) even though the PV is a current source. Because of some advantages in grid-connected inverters in most cases current control scheme is applied. The advantages are higher power factor, better transient current suppression and short circuit current is limited to rated AC current.

Figure 3: Classification of inverters

3.1.2. Main common functions for grid inverter The PV grid-connected inverter has to fulfill the basic functions in order to feed energy form a PV array into the utility grid:

• To shape the current into a sinusoidal waveform, • To invert the current into an AC current and synchronize with the grid • If the PV voltage is lower than the grid voltage, the PV array voltage has to be boosted

with a further element.

It also has to fulfill the functions below for security and performance aspect: MPPT function

The output characteristics of photovoltaic arrays are nonlinear and change with the module’s temperature and solar irradiance. For a given conditions there is a unique point in witch the array produces maximum output power. This point is called maximum power point (MPP) which varies depending of cell temperature and present irradiation level. To obtain the maximum power

Page 11: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 11

from a photovoltaic array, a maximum power point tracker (MPPT) is used. The MPPT thus help the inverter to draw peak power from the PV array to maximize the produced energy regardless module temperature and solar irradiation.

Many systems have been used and the Perturbation and observation is one of the most commonly used MPPT methods for its simplicity and ease of implementation. It operates by periodically perturbing (incrementing or decrementing) the array terminal voltage and comparing the PV output power with that of the previous perturbation cycle. If the power is increasing the perturbation will continue in the same direction in the next cycle, otherwise the perturbation direction will be reversed.

Figure 4: Perturb and Observe method

Anti-islanding function Islanding is the continued operation of a grid-connected inverter in cases where the utility grid has been switched off, cut off or the distribution lines have been damaged so that no electric energy is delivered from the utility side. In such a situation the safety of persons and/or the safety of equipment might no longer be guaranteed. Thus, in the event of a loss of mains supply, grid-connected PV systems are required to automatically disconnect from the grid in order to prevent the power network from islanding. A lot of anti-islanding methods have been identified and can be divided into two main groups:

P4

P3 P2

P1 PV Gen

erator pow

er (W

)

PV Generator voltage (V)

Page 12: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 12

• Passive methods: a detection circuit monitors grid parameters (e.g. voltage, frequency,

voltage phase jumps, voltage harmonics); these methods do not have any influence on grid quality

• Active methods: a detection circuit deliberately introduces disturbances (e.g. active or

reactive power variation, frequency shift) and deduces from the reaction to these disturbances if the grid is still present.

3.2. TECHNICAL DESIGN OF PV INVERTERS

3.2.1. Basic inverter design The basic design of inverters is always very similar no matter what technology is used. The essential feature of a PV inverter is the forming of an AC voltage (grid connection) from DC voltage (PV generator). The figure 6 shows a basic design of a PV inverter where:

• B: Bridge allowing the connection of each of the two input poles via an electronic devise

such as transistor. Only two opposite switches can be closed at the same time.

• C: Capacitor functioning as energy storage and feeding continuously and uniformly the

bridge

• L: Iron core choke as current accumulator helps to get a sine-wave current to feed into

the grid

Figure 5: Basic design of a PV inverter

+

N

P

C

L

L

B

GRID

Page 13: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 13

3.2.2. Different types of inverters technologies Initially, at the inverter input, the direct current generated by the solar array is temporarily stored in a capacitor. Thus, the solar current can continually flow with maximum power, and is independent of the switching operation in the inverter. Due to the permanent opening and closing of the electronic switches, the capacitor is repeatedly discharged little by little. This causes the inverter to oscillate perpetually between two states: feeding and not feeding. With the choke as buffer at the inverter’s output, this pulsating direct current is converted to sinusoidal alternating current. However, practical use of this basic inverter is restricted due to the limit input voltage range. To feed current into the grid, the input voltage must always be above the peak of the grid voltage. For example if the grid RMS voltage is 240V, then the minimum voltage to feed a sine wave current to the grid is 339V2240x = . To solve this problem, many options are possible for adjusting or extending the input voltage range:

Figure 6a: Transformerless inverter block diagram

Figure 6b: Inverter with High Frequency Transformer block diagram

Bridge 1 RectifierP

N

GRID

+

HF Transformer

Bridge 2

-

+

N

P

Bridge

GRID

Step- up converter

Page 14: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 14

Figure 6c: Inverter with Low Frequency Transformer block diagram

3.2.3. Technologies in comparison

Characteristics 50 Hz (LF) transformer

Transformerless High frequency transformer

Semiconductor switches ++ 4 + 5/6 - - 12

Susceptibility (grid) ++ transformer + - -

Single design/Reliability ++ + -

Grid compatibility + 50 Hz - Electronic - electronic

Electromagnetic compatibility ++ -…..0 0

Efficiency + ++ -

Galvanic separation PV/Grid + - +

Weight - ++ +

L

+

C

LN

P

GRID

LF TransformerBridge

Page 15: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 15

3.3. CONFIGURATION FOR PV SYSTEM

If inverter and PV array are treated as a system, four basic configurations can be identified as shown in figure 7

a)

b)

c)

d)

Figure 7: Configuration for PV System

=

=

Page 16: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 16

System with central inverter: In this topology (Figure 7 a), the PV generator is arranged in many parallel strings that are connected to a single central inverter on the DC side. The advantage of this configuration is doubtless its high efficiency and lowest specific cost of the inverter. However, the energy yield of the PV generator decreases due to the module mismatching and partially shading conditions. Also, the reliability of the system is limited due to the dependence of power generation of a single component, the failure of the central inverter results on the shutdown of the whole plant. The central inverter is used for large PV system (> 10 kW).

System with string inverter: Similar to the central single inverter, the PV generator in this concept is divided into several parallel strings (Figure 7c). Each of PV string is connected to an inverter, the so-called “string inverter”. String inverters have the capability of separate MPP tracking of each PV string. This increases the energy yield via the reduction of mismatching and partial shading losses.

System with multi-string inverter: Multi-string inverter is an evolution concept of string technology which allows the connection of several strings with separate MPP tracking system (via DC/DC converter) to a common inverter (Figure 7b). This topology allows the integration of PV strings of different technologies and various orientations (south, west and east). The system with multi-string inverter combines the advantages of central and string technologies. The power range for this inverter is between 3 and 10 kW.

Module integrated inverter: One inverter is used for each module, which avoid mismatching. The module integrated inverters require a complex cabling on the AC side, due to the fact that each module of the system must be connected to the 230V grid (Figure 7d). This concept is normally only used in PV systems with les power from 50 W up to 400 W

3.3.1. Protection technology

All grid-connected inverter have in common the follow protection function:

• Galvanic separation between PV generator and local grid with a transformer or through a Residual Current Detection-Surveillance (RCD) device (Transformerless’ case)

• Ground fault detection (DC side)

• Grid voltage surveillance (under and overvoltage)

• Grid frequency surveillance

• Short circuit diode to protect against pole interchanging

• Overvoltage protection with varistors on the DC side

Page 17: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 17

3.3.2. Technical parameters The most important inverter parameters are rated DC and AC power, MPP Voltage range, maximum DC/AC current and voltage and rated DC/AC current and voltage. Other parameters are power in standby mode, power in sleeping (night) mode, power factor, distortion, noise level etc. The following parameters can usually be found in inverter data sheets:

Input data Output data

Max. DC power (PDC,max) Max. AC power (PAC,max)

Max. DC voltage (UDC,max) Nominal AC output (PAC,nom)

PV voltage range, MPPT (UMPP) Harmonic distortion of the grid current

Max. input current (IPV,max) Nominal AC voltage (UAC,nom)

DC voltage ripple (Upp) Nominal AC frequency (fAC,nom)

Max. no of string (parallel) Power factor

Efficiency

3.3.3. Inverter efficiency

The output of a grid-connected PV system depends on the PV/inverter sizing ratio (Rs)1, defined as the ratio of PV array capacity at standard test conditions to the inverter's rated input capacity. Properly matching PV and inverter rated capacities improves grid-connected system performance. Under low insolation (incident solar power), a PV array generates power below its rated capacity, leading to inverter operation at partial load. Inverter efficiency drops with part-load operation: it also becomes sub-optimal when a significantly undersized inverter is made to operate mainly in conditions of overload, which result in energy loss. Figure 1 illustrates inverter efficiency under both overload and partial-load operation.

DCinput Power

ACoutput Power ηInv =

Page 18: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 18

Figure 8: Inverter efficiency

Page 19: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 19

4. GRID –CONNECTED SYSTEM DESIGN

4.1. GENERAL The design of any PV Grid connected system should consider a number of criteria such as: • Budget • Suitability of the site for safe installation of a PV Array • How much roof space is available for system installation • Potential for shading of PV Array from nearby buildings, trees or other objects • Aesthetics

4.1.1. Energy efficiency

An energy audit for the whole house/building/site should be undertaken and recommendations should be supplied to the customer with respect to electrical energy use reductions that can be achieved. For example:

• Replacing inefficient electrical appliances with new energy efficient electrical appliances • Replacing off-peak electric hot water heaters with a solar hot water system either gas or

electric boosted.( if applicable ) • Replacing incandescent light bulbs with compact fluorescents

4.1.2. Documentation When providing a quotation for the supply and installation of a PV grid connect system the minimum documentation that should be supplied to the customer with the quotation is:

• Estimate of yearly output of the PV Grid-Connected system in kWh, based on the tilt • Angle and orientation of the installed array. This is the actual energy that is supplied on

the output of the inverter. • What percentage this represents of the average current yearly energy usage by that

building/site. • The amount of money savings this represents based on current electrical energy pricing. • If possible the savings in CO2 (either tonnes or kg) should also be provided.

Page 20: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 20

4.1.3. System design steps The design of a PV grid connect system requires a number of steps. A basic design method follows:

1. Determine the main design criteria 2. Obtain relevant information based on critical design criteria. 3. Determining the size of the PV Array 4. Determining the size of the inverter 5. Determining the size of the interconnection cables to minimize system losses

4.1.4. System design criteria A PV Grid Connect system will, in general, be designed in accordance with one of the following limiting design criteria:

• Designed to meet yearly energy usage • Designed to fit on available roof space • Designed to meet a budget

At times the design will be limited by all three criteria and the final size of the PV array and therefore the size of the inverter required will be dependent on which is the dominant limiting criteria. In particular when designing a system to meet a budget or to meet the yearly energy usage, the final PV array must fit on the available roof space.

4.2. DESIGN TO FIT ON AVAILABLE ROOF SPACE

Step 1: Peak power (kWp) of the array at STC conditions Parameter 1

a) Find the approximate available roof space (m²) (south facing)

b) Choose the type of module (monocrystalline, polycrystalline or amorphous) and estimate its efficiency

Then, the nominal power P0 is obtained by the below formula:

Page 21: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 21

(kWp) ηA x x GP m00 =

Where: G0: Irradiation at Standard Test Conditions (1000 W/m² or 1 kW/m²) A: Available roof space (m²) ηm: Module efficiency Example 1: Find the nominal power of PV generator to feed a house knowing that: - Available roof space is 20 m² - Polycrystalline module with efficiency of 10%

kWp 2 10010 x 20 x 1P Array0 ==

Step 2: Number of modules for the PV generator

Parameter 2:

c) Choose the PV module (Nominal peak power Pmpp, voltage at nominal power Vmpp etc.)

Example 2: The previous example gave us a total DC power (peak) of 2 kWp. What will be the number of module of Poly 170W from Schott solar with the characteristics below?

Response:

.NPP mmmpoArray =

Nm = number of modules. Thus

P

P N

mppoArray

m =

11.76 170

2.1000 Nm ==

We shall take 12 modules of 170 Wp from Schott.

The exact P0Array = 12 x170 = 2040 W or 2,04 kWp

Nominal power (Pmpp ) 170 W

Voltage at nominal power (Vmpp )

35.5 V

Current at nominal power (Impp )

4.78 A

Open circuit voltage (VOC) 44.0 V

Short circuit current (Isc) 5.30 A

Page 22: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 22

Step 3: PV array design and inverter check To optimize the annual electric output of the PV generator, it is essential to match the array size and the rated power of the inverter. The peak power of the solar module should not be much lower than the rated power of the inverter to avoid part-load operation (see figure 9). If the array is to large, energy will be lost because of the current limiting function at the inverter overload condition (see figure 9). The sizing rules for PV plants with inverter are thus:

• MPP voltage of the plant > Minima inverter input voltage • Open circuit voltage of the plant < Maximum inverter input voltage • Prefer the nominal input voltage of the inverter (maximum efficiency)

• Power ratio in the range of 90% to 110%. PVplantpower nominal

inverterpower input ratioPower =

• All connecting string must have the same voltage

Parameter 3: d) Check the inverter input voltage rating e) Check the inverter MPPT range f) Check the inverter input current range g) Check the inverter power ratio

Input data SB 2100TLL SB 2500 Max. DC power (PDC,max) 2 200 W 2700 Max. DC voltage (UDC,max) 600 V 600 V PV voltage range, MPPT (UMPP) 125 V – 600 V 224V – 600V Max. input current (IPV,max) 11 A 12 A DC voltage ripple (Upp) < 10% < 10% Max. no of string (parallel) 2 3 Output data Max. AC power (PAC,max) 2100 W 2500 W Nominal AC output (PAC,nom) 1950 W 2300 W Harmonic distortion of the grid current < 4% < 4% Nominal AC voltage (UAC,nom) 220V -240V 220V -240V Nominal AC frequency (fAC,nom) 50 Hz 50 Hz Power factor 1 1 Efficiency 96 94.1 Technology Transformerless With transformer

Example 3: Find an inverter for a PV plant of 2.04 kWp using 12 modules of 170 W from Schott Solar (for modules’ characteristics see example 2). Use the inverters given below. Inverter example: SUNNY BOY

Page 23: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 23

Checking list SB 2100TLL

SB 2500

Calculation specification Calculation specification Check inverter input voltage rating

12*Voc = 12*44 V = 528 V

< 600 V OK

12*Voc = 12*44 V = 528 V

< 600 V OK

Check inverter MPPT range

(125 V – 600 V)/12 = 10.40-50 V

(module VMPP = 35.5 V)

OK

(224 V – 600 V)/12 = 18.67-50 V

module VMPP = 35.5 V) OK

Check inverter input current rating,

1 parallel strings

1 * ISC = 5.30 A

< 11

OK

1 parallel strings

1 * ISC = 5.30 A

< 12

OK

Check the inverter power ratio

2200/2040 = 1.08 0.9 – 1.10 OK

2700/2040 = 1.32 More than 1.10

Efficiency 96 94.1 Technology Transformerless With transformer Conclusion: The inverter SB 2100 TLL achieves all the checking point and has a very good efficiency, it will better suits the project. However, some countries don’t allow the use of Transformerless inverters for grid-connected system. In this case, and in spite of the high power ration (1.38>1.10) of the inverter SB 2500, we are obliged to use it unless we look for another brand. Step 4: Determine the string configuration and therefore the number of modules that will be installed in the available roof space.

The final array configuration will be dependent on the inverter chosen. The different inverters available on the market do not have a common string configuration. Some allow a set number of modules in a string, eg 10 while others allow a range in the number of modules in the string. When a range is allowed then select the number that will minimize the number of modules required in the final array. After selecting the inverter and determining the number of modules allowed in the string the number of parallel strings is calculated as follows: Number of parallel strings = the actual maximum number of modules that can fit on roof space ÷ number of modules in each string.

Page 24: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 24

The number of modules that will be installed on the roof = number of parallel strings x number of modules in each string Objective 4: Energy EAC output Parameter 4:

h) Find the average insolation H [kWh/m2/day], based on site location (Tilt angle Azimuth). H can be obtained from forecast stations in your country or by using some software such as RetScreen, Homer, Meteonorm etc.

i) Determine the overall system efficiency h, from PV to AC grid,

E

E ηpvpeak

AC= , also

called “DC to AC derate factor”, including:

• Derating of PV nominal peak power (e.g. due to tolerances, temperature, or aging) • Module mismatches • Dirt • Shading • Losses due to wiring, blocking diodes, connectors • Efficiency, and MPP tracking performance of the power electronics (“inverter”)

Typical η = 75%. Therefore, the PV system output approximate annual energy production in kWh can be written by:

η.0ArrayPH.365.ACE =

Example 4: Find the annual energy EAC generated by a photovoltaic array with peak power of 2 kWp. The site is in Kumasi/Ghana (latitude = 6.41 N; longitude = 1.28 W). RetScreen simulation tool gives H = 4.35 kWh/m²/day for the global horizontal solar radiation or 4.35 solar hours and η = 75%. EAC = 365 x 4.35 x 2.04 x 0.75 = 2429 kWh/year Note: We didn’t take into account in this example, the PV array orientation and the tilt angle.

Page 25: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 25

Step 5: Simple cost analysis Parameter 5:

j) Find the capital cost of PV systems. For simple analysis, we can use the statistical given by some websites. On May 25th, 2009 the Website the

k) Nominal lifetime for PV systems: 20 years l) System cost :

peakPower cost x Capitalcost System =

Example 5: Find the payback time for a PV grid-connected system of peak power of 2.04 kW and produces 2429 kWh/year. We assume that the lifetime of the system is 20 years and whereas the kWh paid by the National Electricity Company is……… For the simple analysis, we can use the statistical data given by some websites. On May 25th 2009, the website,: http://www.solarbuzz.com estimated PV grid-connected system at $8/Wp and the price comprises: • Modules • BOS (balance of system) - Installation - Wiring - Power electronics “inverter” Simple cost per kWh calculation

timeLife x ACE

cost Systemcost kWh =

System cost: 8 x 2040 = $16320 ¢/kWh 33.6 20x 2429

16320cost kWh ==

Energy production cost in Ghana: • Hydro electric plant : 7 ¢/kWh • Thermal plant : 16 ¢/kWh

Page 26: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 26

Step 6: Cables sizing

The cables in an installation must be sized correctly so that:

• The current through the cable must be less than the safe current handling capability of the cables.

• The voltage drop (line losses) in the cable must be less than the value allowed by the standard (5%)

Table 1. Conductor sizes and maximum currents

Cable Size, mm2 1.5 2.5 4 6 10 16 25 35 50 70 95 120 150 185 240 300

Maximum current, A 13 21 28 36 46 61 81 99 125 160 195 220 250 285 340 395

From Ohm’s law, the voltage drop in an electrical conductor is V = I R

I = Current, amps

R = Resistance, Ohms

The electrical resistance can be derived from the properties of the conductor material.

R = ρ L / A

ρ = Resistivity, Ω mm2 /m

L = Length, m

A = Cross sectional area, mm2

Combining Ohms law with the resistance expression, we get V = I. ρ L / A

As a electrical DC circuit has 2 conductors, the voltage drop in the cable will be:

∆V = 2 ( L x I x ρ ) / A

L = route length of cable in meters I = current in amperes ρ = resistivity of copper wire in Ω / m / mm2 = 0.0183 Ω A = cross section area (CSA) of cable in mm2

For example cable at DC side

Max. input current of the inverter (IPV,max) = 11A

Max. DC voltage of the inverter (UDC,max) = 600V

Cable protection (fuse, circuit breaker)

Ipro ≥ IPV,max

Assume that we have a DC circuit breaker of Ipro = 15 A under 600 V and the length between the PV array and the inverter is 20 meters.

Page 27: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 27

• Choose the cable size (see table 1): For Ipro = 15A, the minima cable size is 2.5 mm² (see table 1)

• Check the voltage drop using ∆V = 2 ( L x I x ρ ) / A

∆V = 2 (20 x 11 x 0.0183)/1.5 = 5.4 V

∆V% = 100 x ∆V/V = 100 x 5.4/600 = 0.9% which is below 5%

Step 7: System drawing with all the components

It is the final step of the PV system design

UTILITY ‐

LOAD

DC breaker

Sunny boy SB 2100

Overvoltage arrestors

Support structure

Grounding

F1

Wh

F2

UTILITY GRID

Wh

Page 28: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 28

4.3. DESIGN TO MEET YEARLY ENERGY USAGE Step 0: It is necessary to obtain from the customer copies of their most recent electricity accounts. As a minimum, obtain records of their last 12 months and if possible obtain records for the last few years. Use these records to estimate the average yearly energy usage in kWh. Step 1 to Step 7: See “Design to fit on available roof space

4.3.1. Assessment Design a grid-connected PV system for a residential house which energy consumption is estimated at 7200 kWh/year. The residential house is in Ouagadougou/Burkina where the daily solar radiation estimated is 5.5 kWh/m²/d. Use modules SQ85-P from Shell and inverters from Xantrex. The characteristics of the devices are given below:

Module SQ85-P Shell

Nominal power (Pmpp ) 85 W

Voltage at nominal power (Vmpp ) 17.2 V

Current at nominal power (Impp ) 4.95 A

Open circuit voltage (VOC) 22.2 V

Short circuit current (Isc) 5.45 A

Page 29: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 29

Page 30: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 30

1. PERFORMANCE PARAMETERS FOR GRID­CONNECTED PV SYSTEM

1.1. Standard performances The use of appropriate performance parameters facilitates the comparison of grid-connected photovoltaic (PV) systems that may differ with respect to design, technology, or geographic location. Three of the IEC standard 61724 performance parameters may be used to define the overall system performance with respect to the energy production, solar resource, and overall effect of system losses. These parameters are the final PV system yield, reference yield, and performance ratio: The final PV system yield Yf is the net energy output EAC divided by the nameplate DC power P0 of the installed PV array. It represents the number of hours that the PV array would need to operate at its rated power to provide the same energy. The units are hours or kWh/kW, with the latter preferred by the authors because it describes the quantities used to derive the parameter. The Yf normalizes the energy produced with respect to the system size; consequently, it is a convenient way to compare the energy produced by PV systems of differing size:

(hours)or (kWh/kW) 0P

ACEfY =

The reference yield Yr is the total in-plane irradiance H divided by the PV’s reference irradiance G. It represents an equivalent number of hours at the reference irradiance. If G equals 1 kW/m2, then Yr is the number of peak sun-hours or the solar radiation in units of kWh/m2 The Yr defines the solar radiation resource for the PV system. It is a function of the location, orientation of the PV array, and month-to-month and year-to-year weather variability.

(hours) GH

rY =

The performance ratio PR is the Yf divided by the Yr. By normalizing with respect to irradiance, it quantifies the overall effect of losses on the rated output due to: inverter inefficiency, and wiring, mismatch, and other losses when converting from DC. to AC. power; PV module temperature; incomplete use of irradiance by reflection from the module front surface; soiling; system down-time; and component failures:

Page 31: Grid Connected Pv Part 2

KNUST_Reep Short Courses June 2009 /Grid –connected Solar PV system‐Design and Installation 31

less)(dimension rYfYPR =

PR values are typically reported on a monthly or yearly basis. Values calculated for smaller intervals, such as weekly or daily, may be useful for identifying occurrences of component failures. Decreasing yearly values may indicate a permanent loss in performance

1.2. Monitoring

Most simple way to perform monitoring is display available on inverter or on inverter control unit. Other possibilities of local monitoring includes monitoring by local PC via RS232 connection and/or remote display located in living room for example (connection between inverter and display is usually wireless). For the performance analysis, the following parameters have to be monitored:

• Array voltage - VDC (V)

• Grid voltage - VAC (V)

• Array current - IDC (A)

• Grid (injected) current - IAC (A)

• Array power - PDC (W)

• Grid (injected) power - PAC (W) Module temperature - Tmodule (°C)

• Ambient temperature - Tamb (°C)

• Solar radiation - G (W/m2)

• Daily/monthly solar insolation - H (J/m2)

• Wind speed - v

Data can be stored in inverters memory or in external units (data loggers). Different solutions are available on the market. Some producers offer also additional memory increase or upgrade. Better data loggers offer monitoring functions (data logging) for various environmental and additional system related parameters what can give the user detailed overview about the whole system. Additional parameters that can be monitored are module- and ambient temperature, solar radiation, solar irradiation, wind speed etc. Temperature sensors are usually PT100 sensors. Solar radiation is measured with reference solar cells (Si-mono), analog inputs of the control equipment are usually standard 4-20 mA or 0-10 V inputs. Digital inputs are also available and can be used for net-meter/control equipment interconnection.