10
Green Highland Renewables Loch Etive Hydro Developments Submarine Cable Marine Licence Application Appendix 1 – Method Statement Including Schedule of Work 1.1 Introduction This Method Statement describes how Green Highland Renewables would install a submarine cable across Loch Etive to connect a new hydro-electric installation on the Allt Easach river. The document has been prepared in support of a marine license application to MS-LOTS. Some additional information has also been provided on the operation, repair and de- commissioning of the cable should it no longer be required at some point in future. 1.2 The Proposed Submarine Cable / Route Loch Etive is a natural sea loch on the west coast of Scotland with relatively low salinity due to the constriction at the entrance caused by the Falls of Lora. Connection of the Allt Easach hydro scheme will require the installation of a 33,000V cable on the seabed of Loch Etive. In choosing a route for the cable, GHR have looked at a number of options before deciding on the proposed route. Navigational charts and sonar surveys suggested a suitable route existed between the headland on the south side of Ardmaddy Bay and the beach immediately to the west of Rhubha Bharr, approximately 19km by sea from Connel Bridge, as shown in Figure 1. The Scottish Association of Marine Science were commissioned to carry out a bathymetric and ecological survey of the seabed over the proposed route. Based on these surveys the initial design was modified slightly to allow the proposed cable route to avoid areas of cobbles and boulders where possible. This should allow the cable to sink into the soft mud seabed in time over much of the route length. Fig 1 – Location Plan for Proposed Cable Route Across Loch Etive

Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

GreenHighlandRenewables

LochEtiveHydroDevelopments

SubmarineCableMarineLicenceApplication

Appendix1–MethodStatementIncludingScheduleofWork

1.1 IntroductionThisMethodStatementdescribeshowGreenHighlandRenewableswouldinstallasubmarinecableacrossLochEtivetoconnectanewhydro-electricinstallationontheAlltEasachriver.Thedocumenthasbeenprepared in supportof amarine licenseapplication toMS-LOTS.Some additional information has also been provided on the operation, repair and de-commissioningofthecableshoulditnolongerberequiredatsomepointinfuture.1.2 TheProposedSubmarineCable/RouteLochEtiveisanaturalsealochonthewestcoastofScotlandwithrelativelylowsalinityduetotheconstrictionattheentrancecausedbytheFallsofLora.ConnectionoftheAlltEasachhydroschemewillrequiretheinstallationofa33,000VcableontheseabedofLochEtive.Inchoosingarouteforthecable,GHRhavelookedatanumberofoptionsbeforedecidingontheproposedroute.NavigationalchartsandsonarsurveyssuggestedasuitablerouteexistedbetweentheheadlandonthesouthsideofArdmaddyBayandthebeachimmediatelytothewestofRhubhaBharr,approximately19kmbyseafromConnelBridge,asshowninFigure1.TheScottishAssociationofMarineSciencewerecommissionedtocarryoutabathymetricandecologicalsurveyoftheseabedovertheproposedroute. Basedonthesesurveystheinitialdesignwasmodifiedslightlytoallowtheproposedcableroutetoavoidareasofcobblesandboulderswherepossible.Thisshouldallowthecabletosinkintothesoftmudseabedintimeovermuchoftheroutelength.

Fig1–LocationPlanforProposedCableRouteAcrossLochEtive

Page 2: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

Figure2–ProposedCableRouteAcrossLochEtiveTheNorthShoreEndPosition(NSE)is56°30.260N05°08.183W.TheSouthShoreEndPosition(SSE)is56°29.372N05°08.193W.TheCableLayingVesselhastobepositionedbetween100mand250moffshoretoavoidgroundinginshallowwater.Thevesselsspudlegsaredeployedatthesepositionstoholdpositionwhilethecableisbeingpulledashore.ThetwopositionsareknownastheNorthTransitPositionandtheSouthTransitPosition.TheNorthTransitPosition(NTP)is56°30.140N05°08.190W.TheSouthTransitPosition(STP)is56°29.401N05°08.265W.

Page 3: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

AllpositionsrelatetotheWGS84chartdatum.Thecentrelineoftheproposedroutecanbeprojectedbetweenthesefourpositions.Thecablewillbelaidwithina40mcorridorontheseabed,20moneithersideofthecentreline.1.3 CableDesignThetypeofcableproposedforuseinLochEtiveisastandardsubmarinecabledesignthathasbeenusedextensivelyaroundScotland.ThesamecablewasalsousedbyGHRwhentheyinstalledaprivatecableacrossLochTayduring2015toconnectahydroschemeatArdtalnaig.The cable is a 3 phase 33,000V cable with copper cores and crosslinked polyethyleneinsulation.Thethreecablecoresarebundledtogetherandheldinplacebypolypropyleneservingtape.Asmall3corecommunicationscableisalsoincludedwithinthecablebundleandthiscablewillbeusedtoopenandcloseacircuitbreakerat theAlltEasachsite.Thecompletecablehasaprotectivelayerofgalvanisedsteelwirearmourlaidovertheoutsidetoprotect the cable from abrasion during installation and operation. A further layer ofpolypropyleneiswoundoverthearmourtogiveablackandyellowstripedappearancewhichmakesthecableeasiertofindontheseabed.Thecompletedcableisapproximately95mmindiameter.Theapproximateweightofthecableis15.5kgpermetre.AcrosssectiondrawingoftheproposedcableisincludedasFigure3.

Figure3–ProposedSubmarineCableCrossSection

Page 4: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

1.4 CableDelivery,LoadOutandTransittoSiteThesubmarinecabletypeusedbyGHRiscurrentlymanufacturedinJapan.ThecompletedcablewillbeshippedtotheUK inOctober2019anddeliveredbya low loadheavygoodsvehicletoCorpachBoatyard,FortWilliam.BriggsMarinewillbecontractedtoinstallthecableusingtheircableinstallationvessel“ForthGuardsman”.ThevesselwillbefittedouttoreceivethecabledrumatCorpachBoatyard,andoncecompletethecablewillbeloadedaboardusinga 300Tmobile crane. AMarineWarranty Surveywill inspect the loaded vessel and oncesatisfiedwillissueaCertificateofApproval,verifyingthattheinstallationmeetstheinsurersrequirements.TheGuardsmanwillthensaildownLochLinnieandtheLynneofLorneandpassbelowConnelBridgeintoLochEtive,arrivinglateonthefloodtidetoavoidtheworsteffectsoftheFallsofLora.ThevesselwillthensailupLochEtivetotheinstallationsite.ThetotaljourneyfromCorpachtositewilltakeapproximately8hours.OnceonsitethevesselwillmakeanumberoftransitsoverthecableroutebeforepositioningatthesouthernRhubanaStaingshoreend.1.5 CableInstallationTheGuardsmancanbefittedwithtworetractablepileswhichcanbeloweredtotheseabedinwaterlessthan10metresdeeptoholdthevesselinplace,withoutanyneedforsettingapatternofanchorsandmoorings.Thissavestimeduringthecableinstallationprocessandavoidstheneedforadditionalvesselstohandleanchors,minimisingthehazardsassociatedwiththistypeofwork.AtRubhanaStaingthevesselwillbepositionedapproximately100mfromtheshoreinwaterwithadepthofbetween5m–10m.The“spudlegs”willbedeployedtoholdherinposition.Oneendofthesubmarinecablewillbepulledashorebyasmallwinchpreviouslyinstalledonshore.Thecablewillhavefloatsattachedtopreventittouchingtheseabed.Thisoperation takesapproximately2hours.Havingcompleted theshoreend thevesselraisesthespudlegsandthentransitsacrossthelochpayingoutthecableasshegoes,totheothershoreendatRhubhaBhar.Thistransitcloselyfollowstheagreedcablerouteandthe actual “as laid” position of the cable is recorded. The maximum depth likely to beencounteredisapproximately70movertheproposedroute.ThetransitacrosstheLochwilltakeapproximately2hours.Oncethevesselisinpositionatthesecondshoreendthespudlegs are once again deployed. The vessel will be approximately 100m offshore. Ameasurement ismadebetweenthecabledrumonthevesselandasuitablepositionwellabovethehigh-watermarkashore.Thesamelengthofcableisthentakenoffthedrumandcoiledonthedeckbeforethecableiscut.Thiscableisthenwinchedashorewithfloatsjustliketheothershoreend. Thesecondshoreendwill takeapproximately2hoursto installgivingatotalof6hoursforthecompleteinstallation.

Page 5: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

Fig4-ForthGuardsmanwithSpudLegsDeployed(yellowcappedpiles)1.6 CableProtectionOncethecablehasbeeninstalledtheshoreendswillbeburiedtobelowthelowwatermarkto hide it from view and remove any tripping hazard for shore users. A yellowdiamondbeaconwillbeinstalledonbothshorelinestomarkwherethecablecomesashore.TheaslaidpositionofthecablewillbenotifiedtotheUKHydrographicOfficewhomarkthepositiononAdmiraltyChartsandadviseothersuppliersofmarinemappingsoftwareofthenewcable.TheEuropeanSubseaCablesAssociationandTheCrownEstatewillalsobenotified.OverahundredsimilarsubmarinecableinstallationsexistinNWScotlandwhereelectricitycablescrosssealochsorprovideconnectionstotheScottishIslands.Thesecablesaresimplylaidontheseabedandtheirlocationsmarkedonchartstoavoiddamagefromotherusers.Where the cables are laid in harbours, or on rocky shorelines,wheredamage fromwaveaction is possible, additional protection is sometimes provided using cast steel cableprotectors.Theseinterlockingunitsarefittedaroundthecableonceitisinstalled,usuallyatlowtideintheinter-tidalzone,orbyusingdiverswhenthecableisinstalledbelowthelowwatermark.Inpreparingthecontractdocumentationfortheinstallation,anoptionhasbeenincludedforfittingsteelcableprotectorsatoneorbothshoreendsdowntoadepthof10mbelowchartdatum.Inrecentyearstherehasbeengrowinginterestinthepossibleimpactsthattheoperationofsubmarinecablesmighthaveonmarineorganismsasaresultofelectro-magneticfieldsorEMFs produced by cables. In preparing this applicationGreenHighland Renewables havetakenadvicefromafisheriesscientistwhohasproducedareportwhichisincludedaspartofAppendix7.4ofthisapplication.Electricfieldsareveryunlikelytobegeneratedoutsidethescreenedcable typebeingused for thisapplication. It is likely thatmagnetic fieldswillbepresentoutside thecablealthough it isnotclearwhether thesewouldhaveanynegativeeffectonmarineorganisms.Itispossibletoreducethemagneticfieldwhichsurroundsacable

Page 6: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

by encasing it in a ferromagnetic material like steel or cast iron. The steel wire armourcoveringoftheproposedcablewillthereforereducethemagneticfield,butbyanunknownamount.Itwouldbereasonabletoassumethataddingsteelcableprotectorstocompletelysurroundthecablewillfurtherreducethemagneticfield.Onthisproject,theplanistoretrofitsteelcableprotectorsusingdiversdowntoadepthof10mtoprovideadditionalprotectioninthenearshorearea.Asaresult,anymagneticfieldproducedbythecable is likelytobereducedintheshallowwater.ManyofthemarineorganismsfoundinLochEtivetendtoswimclosetothesurface,andthisadditionalprotectionintheshallowwatershouldeliminateanyimpact to theseorganisms. Retrofittingcableprotectors indepthsexceeding10mcanbechallengingfordiversduetothelimitationsonproductiveseabedtimecausedbytheneedtode-compress.Itisnotpracticaltofittheprotectorstothecableaboardthevesselduringthecablelayprocesswithoutriskingdamagetothecable.

Figure5–SteelSubmarineCableProtectorsbeforeburialontheforeshore.Anyadditionalactivityassociatedwiththecablelaywillextendthetimetakentoconducttheoperation.Thismeansthesizeofweatherwindowrequiredincreaseswhichcouldresultinthevesselhavingtospendlongeronsitewaitingonweather.Thesedelaysarefactoredintothecontractor’scostswhichwillriseasaresult.Buryingthecablehasafurtherimpactoncosts,largelydependentontheburialmethodemployedandthedepthatwhichburialtakesplace.Thefollowingtablesgivedetailsoffourburialtechniquesandgivesanestimateofthelikelyadditional costsandanyother consideration.Allof thesemethodswill increase theenvironmentalimpactoftheproject.

Page 7: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

Mass Flow Excavation - This technique would be themostsuitableasthereisnocontactbetweentheburialequipment and the cable, so the risk of damage isreduced.Largeimpellorsfittedonthedeviceareusedtoforce sea-water downwards into the seabed whichfluidises, allowing the cables or pipelines to sink. Theexcavatedtrenchisapproximately4mwidebutitcanbedifficult to control the depth of the excavation. Thismethodcanalsobequitedestructivetotheseabedwitharelativelylargedisturbedareaaroundthetrench

This burial method would require a separatemulti-catvesselwithalargecranetodeploytherig.ThevesselshouldbeabletopassbelowtheConnel Bridge. This type of burial would addapproximately £190k to the projected cableinstallationcostsof£470k,atotalof£660k,a40%increase.

Table1–MassFlowExcavationDetailsTrencher-Thistechniqueismorehi-techandinstallsthecablemorepreciselythanMFEusingwaterjetsateachend of the rig Cable trench is approx. 0.5mwidewithmuch less environmental impact as a result. There iscontact between the device and the cable using thismethodhowever,whichincreasestheriskofdamage.

A larger DP2 vessel is required and a smallervessel may be also required for burial in theshallowerwater.ItisunlikelythevesselwouldbeabletopassbelowtheConnelbridge.Thistypeofburial would add approximately £476k to theprojectedcableinstallationcostsof£470k,atotalof£946k,a101%increase.

Table2–TrencherDetails

Page 8: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

Jetting by Divers - This technique is a very focussedmethodofburyingcableusingairlancestofluidisetheseabed and allowing the cable to sink in. Practicalsolutiondown for shorter lengthsofcabledowntoadepthof20m.There isnocontactwiththecablebutthemethoddoestendtoputalotofsedimentintothewatercolumn.

TheoperationcouldbeconductedfromaDPMulti-catvesselequippedforusebydivers.TherewouldbenoissuewithgettingundertheCoonelBridge.Thistypeofburialwouldaddapproximately£100ktotheprojectedcableinstallationcostsof£470k,atotal of £570k, a 21% increase. The cable wouldonlybepartiallyburiedhowever.

Table3–JettingbyDiversConcreteMats–Thistechniqueusesavesselmountedcrane to lower concretemats on top of the cable toprotectit.Matsareusuallyonlyusedtoprotectshortsections of cable for pipeline crossing etc. To protecttheentireroutewouldmeanlayingapprox.2506mx3matsweighing 8 tonnes each onto the cable. placingthisamountofnewmaterialontheseabedwouldbeintrusiveanddifficulttojustify.

ThismethodwoulduseadeliverybargeandaDPMulti-cat vessel with a drum crane and liftingframetoplaceupto3matsatatimeontheseabed.ThevesselsshouldbeabletopassbelowtheConnelBridge.This typeofprotectionwouldaddapproximately £430k to the projected cableinstallationcostsof£470k,atotalof£906k,a92%increase.

Table4–ConcreteCableProtectionMats

Page 9: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

1.7 CableRepairorReplacementSubmarinecablesdooccasionallybecomefaultywithmostdamageactuallycausedduringinstallationorattemptedburial.Thetypeofrepaircarriedoutonafaultedcabledependsontheageandconditionofthecableandwhereaboutsonthecableroutethefaulthasoccurred.Ifacablehasfaultedrelativelyclosetoshorethenitwouldbenormalpracticetorenewthesectionofcablefromthefaultbacktotheshore.Werethecabletofaultnearthemiddleoftherouteandthepointoffaultcanbeclearlyidentified,thenitmaybepossibletocutthecableontheseabedandbringthefaultedendtothesurface.Thefaultysectionofcableisremovedandapieceofnewcablejointedon.Theotherendisthenretrievedfromtheseabedandjointedontothenew“piecedin”section.Thecompletecableisthenreturnedtotheseabedandre-energised.Wherethecableisinverydeepwaterorcannotbecutforwhateverreasonthentheonlyoptionistoabandonthecableandlayanewoneonasimilarroute.ThisisobviouslyexpensiveandwouldmeantheoutputfromtheAlltEasachschemecouldnotbeexporteduntilthecircuitwasrestored.Thedeliveryandinstallationtimeforanewcablefromwhenanorderisplacedwouldbeapproximately1year.1.8 DecommissioningSubmarinecableshavebeeninusearoundtheUKfor150yearsandsomecablesownedbySSEarestilloperationalafter60years.GHRcannotimaginecircumstanceswhichwouldresultinahydroschemebeingcloseddown.Normallyaschemeisrefurbishedafter40yearsorso,givingitanewleaseoflife.Ifforsomereasonthecabledidbecomesurplustorequirementsthen the cable couldbe removed in a similarway tohow itwas installed. Itmayalsobeacceptabletoleavethecabledisconnectedbutstill inpositionontheseabedandthishasuntilnowbeenthegenerallyacceptedpractice.DiscussionswithMarineScotlandandTheCrownEstatewouldoccuratthetimetoagreeonasolutionbuttheschemesaroundLochEtiveareexpectedtodeliverrenewableenergytothegridindefinitely.1.9 ProjectScheduleThismarinelicenceapplicationwassubmittedduringJuly2018.TheplanningapplicationsforthethreehydroschemesweresubmittedduringMay2018,withconstructionworkplannedtocommenceinDecember2018.ThesubmarinecablewillbeorderedduringDecember2018andwillbedeliveredtotheUKinOctober2019.ThecableinstallationwilltakeplaceduringOctober2019.Thehigh-levelprojectscheduleisshowninFigure6. 2018 2019 J F M A M J J A S O N D J F M A M J J A S O N D

Marinelicenceapplicationprocess Order/manufacturesubseacable Subseacabledelivery/installation Hydroschemeconsentingprocess Hydroschemeconstructing Gridconnection

Figure6–HighLevelProjectSchedule

Page 10: Green Highland Renewablesmarine.gov.scot › sites › default › files › appendix_1_-_method_statement.pdfgrounding in shallow water. The vessels spud legs are deployed at these

1.10 LocationPhotographs

Figure7–SouthShoreEndandIndicativeCableRoute

Figure8–NorthShoreEndandIndicativeCableRoute