Upload
aldous-campbell
View
222
Download
0
Embed Size (px)
Citation preview
Green Dorm
Multidisciplinary Analysis
GREEN DORMMultidisciplinary Analysis
Nthando ThandiweSongya Kesler
Mikal BrewerSangWoo Cho
Ato Ulzenap
Green Dorm
Multidisciplinary Analysis
Project BackgroundThrough multidisciplinary analysis: Steel or Wood?(1) Steel + Prefab. steel framing
(2) On-site standard wood construction + platform framing, 24” on-center
Once selected, one-step further with
“Real-time 4D-based Progress Management for Schedule Reliability Analysis”
Green Dorm
Multidisciplinary Analysis
Weighted Preference (Steel vs. Wood)
Goals Weight
Environmental Performance
Low/no carbon 15
Low embodied energy 10
Day lighting 10
Economic Sustainability
First cost 10
Lifecycle cost 15
Completion date 15
Reduced earthquake losses ($) 10
Living Laboratory Research on structural performance technology 15
Sum = 100
Green Dorm
Multidisciplinary Analysis
Metrics (Steel vs. Wood)Goal -3 -2 -1 0 1 2 3
Steel Low/No Carbon
267+ TonnesSteel 229-266 Tonnes
191-228 TonnesBaseline, 190 Tonnes
189-114 Tonnes 95-115 Tonnes 0-94 Tonnes
Wood Low/No Carbon
22+ Tonnes 19.7-21 Tonnes 15-19.6 TonnesBaseline, 14 Tonnes
8.4-13 Tonnes 7-8.3 Tonnes 0-6 Tonnes
Wood Low Embodied
Energy370+ GJ 245-369 GJ 247-344 GJ Baseline, 246 GJ 245-147 GJ 146-123 GJ 0-122 GJ
Steel Low Embodied
Energy5.5+ TJ 5.05-5.4 TJ 3.7- 5.04 TJ
Baseline, 3.6 Terra Joules
3.15-2.16 TJ 2.15-0.65 TJ 0-0.64 TJ
Dayligting
15%<x<25% of the total area to be over 25 fc
25%<x<35% 35%<x<45% 45%<x<55% 55%<x<65% 65%<x<75%>75% of the total area to be over 25 fc
First Cost >$27 million $26-27 million $25-26 million $24-25 million $23-24 million $22-23 million < $22 million
Lifecycle Cost
>$250 K $225-250 K $200-225 K $175-200 K $150-175 K $125-150 K <$125 K
Completion Date
> 3.5 years 3-3.5 years 2.5-3 years2 years from construction start
1.5-2 years 1-1.5 year < 1 year
Reduced Earthquake Losses ($)
> 50% of initial cost in damages.
50% > x > 25% 25% > x > 15% 15% > x > 10% 10% > x > 5% 5% > x > 1%< 1% of initial cost in damages.
Research on Structural
Performance
Technology
Cannot think of any reason why the building should be used for research.
Little research could be done that has not already been explored.
Several test studies could be carried out.
Many test studies may be carried-out.
Excellent research potential both pre and post construction.
Green Dorm
Multidisciplinary Analysis
Structural ComparisonSteel or Wood?(1) Steel + Prefab. steel framing
(2) On-site standard wood construction + platform framing, 24” on-center
Green Dorm
Multidisciplinary Analysis
Steel Modeling In Revit Structure Based on Preliminary Steel Framing Drawings
Green Dorm
Multidisciplinary Analysis
Wood Modeling: Updated
Green Dorm
Multidisciplinary Analysis
Steel vs. Wood Structure Analysis For Structural Framing,
– Steel needs 25 different types (total 172 pieces, 4,351’ in length)– Wood needs 6 different types (total 5,540’ in length)
• 8 x 6 timber, 9 x 7 timber, 12 x 5 gluelam, etc For Structural Column,
– Steel needs 7 different types (total 27 pieces, 987’ in length)– Wood needs 7 different types (total 3270’ in length)
Green Dorm
Multidisciplinary Analysis
Wood Structure AnalysisPlatform Framing:
Light-Framing Construction: Small Apartment
Green Dorm
Multidisciplinary Analysis
Wood Structure Analysis
Roof and Floor Format
Components
-2x10 joists
-5/8” T&G plywood Und.
-3/8” Plywood
Figure M16.1-10: One-Hour Fire-Resistive Wood Floor/Ceiling Assembly2x10 Wood Joists 16” o.c. – Gypsum Directly Applied or on Optional Resilient Channels
Green Dorm
Multidisciplinary Analysis
Wood Structure Analysis: Quantity Takeoffs
Green Dorm
Multidisciplinary Analysis
Wood Structure Analysis: Calculations
Green Dorm
Multidisciplinary Analysis
Energy Analysis: Consumption Analysis in eQuest
Energy Assumptions
•Building is used primarily during the school year
•Major changes limited to framing
Required Specifications
•Building Size (Basic Building Envelope)
•Location
•Material Quantities (Steel and Wood)
Green Dorm
Multidisciplinary Analysis
Environmental Performance: Analysis
Created baseline Steel models in Athena, eQuest, and BEES
Embodied Energy from steel ~9.05MJ/kg
Embodied Energy from wood ~11.85MJ/kg
• *Values Included Feedstock Energy
Created baseline models of yearly energy consumption for wood and steel as well
Low Embodied Energy (Wt = 10)Low Embodied Energy (Wt = 10)
Green Dorm
Multidisciplinary Analysis
Environmental Performance
Based on steel embodied energy and Carbon Dioxide emissions, computed quantities for wood frame building
Baseline ModelsSteel Model Embodied Energy ~ 3.6 TJWood Model Embodied Energy ~ 0.246 TJ
Optimized ModelsSteel Embodied Energy ~ 2.8 TJWood Embodied Energy ~ 0.246 TJ
Green Dorm
Multidisciplinary Analysis
Environmental Performance: Analysis
Wood Low Embodied
Energy370+ GJ 245-369 GJ 247-344 GJ
Baseline, 246 GJ
245-147 GJ 146-123 GJ 0-122 GJ
Steel Low Embodied
Energy5.5+ TJ 5.05-5.4 TJ 3.7- 5.04 TJ
Baseline, 3.6 Terra Joules
3.15-2.16 TJ 2.15-0.65 TJ 0-0.64 TJ
Low Embodied Energy (Wt = 10)Low Embodied Energy (Wt = 10)
Optimized ModelSteel Embodied Energy ~ 2.8 TJWood Embodied Energy ~ 0.246 TJ
Goal -3 -2 -1 0 1 2 3
Steel Score = 1
Wood Score = 0
Green Dorm
Multidisciplinary Analysis
Environmental PerformanceLow/No Carbon (Wt = 15)Low/No Carbon (Wt = 15)
Baseline ModelsSteel CO2 Emissions ~ 190 TonnesWood CO2 Emissions ~ 14 Tonnes
Optimized ModelsSteel CO2 Emissions ~150 TonnesWood CO2 Emissions ~14 Tonnes %21 CO2 Reduction in Steel
Green Dorm
Multidisciplinary Analysis
Environmental Performance
Steel Low/No Carbon
267+ TonnesSteel 229-266
Tonnes191-228 Tonnes
Baseline, 190 Tonnes
189-114 Tonnes 95-115 Tonnes 0-94 Tonnes
Wood Low/No Carbon
22+ Tonnes 19.7-21 Tonnes 15-19.6 TonnesBaseline, 14
Tonnes8.4-13 Tonnes 7-8.3 Tonnes 0-6 Tonnes
Low/No Carbon (Wt = 15)Low/No Carbon (Wt = 15)
Optimized ModelSteel CO2 Emissions ~150 TonnesWood CO2 Emissions ~14 Tonnes
Steel Score = 1
Wood Score = 0
Goal -3 -2 -1 0 1 2 3
Green Dorm
Multidisciplinary Analysis
Let’s Go “GREENGREEN”Until we can get this 10 point by passing LEED NC2.2 Credit 8.1,Let’s improve our architectural design. We can reduce the lighting power density & energy consumptions
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Goals Weight
Environmental Performance
Low/no carbon 15
Low embodied energy 10
Daylighting 10
Economic Sustainability
First cost 10
Lifecycle cost 15
Completion date 15
Reduced earthquake losses ($) 10
Living Laboratory Research on structural performance technology 15
Sum = 100
Green Dorm
Multidisciplinary Analysis
Assumptions1) For daylight analysis in IES, there is no difference between steel and
wood structure. Same score on steel and wood options
2) Information inputs:
- Room boundary, ceiling heights, window sizes, & glazing type
3) If we enlarge window size, there should be an increase in HVAC loads, which will, in turn, result in increase of energy consumption.
ProcessLet’s do daylight analysis for original design.
Then, let’s improve design for better daylight.
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Green Dorm
Multidisciplinary Analysis
1. Original Design
Define specifications- Bldg Type: Dormitory
- Bldg System: VAV Single Duct
- Location: Mountain View, CA
- Window: Slider with Trim 6’x8’
- Glazing: Large Single Glazing (U=0.9795)
- Room Boundary (at wall center)
- Ceiling Height: 12ft
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Green Dorm
Multidisciplinary Analysis
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Building Specification Settings (Original)
Green Dorm
Multidisciplinary Analysis
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Window/Glazing Specification Settings (Original)
Green Dorm
Multidisciplinary Analysis
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Analysis Settings (Original)
Green Dorm
Multidisciplinary Analysis
LEED NC 2.2 Credit 8.1
Roomname
FloorArea
AreaAbove
thresholdPercentage
Total 12,480 5,956 47.7%
LEED NC 2.2 EQ Credit 8.1 daylight and views: FAILA pass requires 75% or more of the total area to be over the
threshold, 25fc.
Daylight Analysis of Original Design
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Goal -3 -2 -1 0 1 2 3
Dayligting
15%<x<25% of the total area to be over 25 fc
25%<x<35% 35%<x<45% 45%<x<55% 55%<x<65% 65%<x<75% >75%
Score “0”Let’s Improve the Design for Better Daylighting!
Green Dorm
Multidisciplinary Analysis
2. Improved Design
Define specifications- Bldg Type: Dormitory
- Bldg System: VAV Single Duct
- Location: Mountain View, CA
- Window: Slider with Trim 7’x9’- Glazing: Large Single Glazing
(U=0.9795)
- Room Boundary (at wall center)
- Ceiling Height: 11ft
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Green Dorm
Multidisciplinary Analysis
LEED NC 2.2 Credit 8.1
Roomname
FloorArea
AreaAbove
thresholdPercentage
Total 12,480 10,939 87.7%
LEED NC 2.2 EQ Credit 8.1 daylight and views: PASSA pass requires 75% or more of the total area to be over the
threshold, 25fc.
Daylight Analysis of Improved Design
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Goal -3 -2 -1 0 1 2 3
Dayligting
15%<x<25% of the total area to be over 25 fc
25%<x<35% 35%<x<45% 45%<x<55% 55%<x<65% 65%<x<75% >75%
Now, Score “3”We Improved the Design for Better Daylighting! Less lighting power density & energy consumptions!
Green Dorm
Multidisciplinary Analysis
Environmental PerformanceDaylighting (Wt = 10)Daylighting (Wt = 10)
Pros– Friendly interface
• Layers, Groups, Templates• More control on parameters, Detailed
– Powerful• First principle calculations• Allows for accurate simulation of custom thermal systems
Cons– Not fully compliant with Revit, our primary modeling tool
• gbXML export not foolproof• dxf does not transfer model information• Temporary Solution: Model in IES, better approach for complex models
– Does not communicate with other modeling software (Tekla, SketchUp, etc)
Future Direction– Calibrate the model using detailed operations data– Advanced training with IES
What I Learned in IES…?
Green Dorm
Multidisciplinary Analysis
Economic SustainabilityFirst Cost (Wt = 10)First Cost (Wt = 10)
Score -2 for Steel Score -1 for Wood
Goal -3 -2 -1 0 1 2 3
First Cost >$7 million $6.5-7 million $6-6.5 million $5.5-6 million $5-5.5 million $4.5-5 million < $4.5 million
Green Dorm
Multidisciplinary Analysis
Economic SustainabilityLifecycle Cost (Wt = 15)Lifecycle Cost (Wt = 15)
Goal -3 -2 -1 0 1 2 3
Lifecycle Cost >$250 K $225-250 K $200-225 K $175-200 K $150-175 K $125-150 K <$125 K
Score 0 for Wood Score 1 for Steel
Green Dorm
Multidisciplinary Analysis
First Cost – Structure (Steel)
Green Dorm
Multidisciplinary Analysis
First Cost – Uniformat (Steel)
Green Dorm
Multidisciplinary Analysis
First Cost - MasterFormat
Green Dorm
Multidisciplinary Analysis
Life Cycle Cost - Steel
Green Dorm
Multidisciplinary Analysis
Cost – Steel vs Wood
First Cost– Wood has lower first cost– Steel had a metric of -1 for First
Cost, etc– Wood had a metric of 0 for First
Cost, etc Life Cycle Cost
– Wood has lower life cycle cost
Results/Reports
Green Dorm
Multidisciplinary Analysis
Economic Sustainability
Accuracy: To Be Field-Verified– Schedule modeled after existing
schedules– Steel more accurate than wood– 4-D & Real-time Progress Management
helps validate the schedules
Completion Date (Wt = 15)Completion Date (Wt = 15)
Goal -3 -2 -1 0 1 2 3
Completion Date > 3.5 years 3-3.5 years 2.5-3 years 2 years from construction start 1.5-2 years 1-1.5 year < 1 year
Green Dorm
Multidisciplinary Analysis
More Steel vs. Wood Schedule Assumptions Both steel and wood model roughly the same pre-construction
schedule except that steel takes a little longer due to the 7-month prefabrication process
Steel frame is prefabricated while wood frame is constructed on-site The 4-D focuses on the construction process, ignoring the pre-
construction
Economic SustainabilityCompletion Date (Wt = 15)Completion Date (Wt = 15)
Green Dorm
Multidisciplinary Analysis
Steel Schedule
Although the project begins on 4/28/08, construction does not begin until 1/14/09
This results in a total construction period of 1.25 yrs.
This corresponds with a metric value of 2 (1.0-1.5 yr constr.).
Economic SustainabilityCompletion Date (Wt = 15)Completion Date (Wt = 15)
Green Dorm
Multidisciplinary Analysis
Steel 4-D
Economic SustainabilityCompletion Date (Wt = 15)Completion Date (Wt = 15)
Green Dorm
Multidisciplinary Analysis
Although the project begins on 4/28/08, construction does not begin until 1/05/09 (earlier than steel)
Total construction period of 1.75 yrs. This corresponds with a metric value
of 1 (1.5-2.0 yr constr.).
Wood Schedule
Economic SustainabilityCompletion Date (Wt = 15)Completion Date (Wt = 15)
Green Dorm
Multidisciplinary Analysis
Wood 4-D
Economic SustainabilityCompletion Date (Wt = 15)Completion Date (Wt = 15)
Green Dorm
Multidisciplinary Analysis
Economic SustainabilityReduced Earthquake Losses (Wt = 10)Reduced Earthquake Losses (Wt = 10)
Score -3 for Wood Score 2 for Steel
Goal -3 -2 -1 0 1 2 3
Reduced Earthquake Losses ($)
> 50% of initial cost in damages.
50%>x>25% 25%>x>15% 15%>x>10% 10%>x>5% 5%>x>1%< 1% of initial cost in damages.
Green Dorm
Multidisciplinary Analysis
Living Laboratory
Accuracy: Very Accurate– Conducted interviews with the professors who have
been/will be conducting the research– Interview with Prof. Dierelein & Prof. Miranda
Research On Structural Performance Technology Research On Structural Performance Technology (Wt = 15)(Wt = 15)
Goal -3 -2 -1 0 1 2 3
Research on Structural
Performance Technology
Cannot think of any reason why the building should be used for research.
Little research could be done that has not already been explored.
Several test studies could be carried out.
Many test studies may be carried-out.
The building demonstrates excellent research potential both pre and post construction.
Green Dorm
Multidisciplinary Analysis
Living Laboratory
Areas of Research– Explores likelihood of an earthquake in X-yrs– Predict the structural performance of different
systems– Investigate the benefits of performance-based
seismic design in green building design– Estimate earthquake losses– Utilize sensor for on-going structural monitoring
Research On Structural Performance Technology Research On Structural Performance Technology (Wt = 15)(Wt = 15)
Green Dorm
Multidisciplinary Analysis
Living Laboratory
Steel = 3– Focus specifically on potential benefits of steel-frame
alternatives to conventional wood shear wall construction Wood = 0
– Much has already been explored, leaving little room for cutting-edge research
Research On Structural Performance Technology Research On Structural Performance Technology (Wt = 15)(Wt = 15)
Goal -3 -2 -1 0 1 2 3
Research on Structural
Performance Technology
Cannot think of any reason why the building should be used for research.
Little research could be done that has not already been explored.
Several test studies could be carried out.
Many test studies may be carried-out.
The building demonstrates excellent research potential both pre and post construction.
Score 0 for Wood Score 3 for Steel
Green Dorm
Multidisciplinary Analysis
Money Slide (weighted)
Weighted MACDADI
-40
-30
-20
-10
0
10
20
30
40Low/no carbon
Low embodied energy
Day Lighting
First costLifecycle cost
Completion date
Reduced earthquake losses ($)
Optimized Wood Frame
Steel Rocking Frame
Green Dorm
Multidisciplinary Analysis
Stakeholder Groups:– Students– CEE Faculty– Designers– Campus Planning– Campus Housing
Data taken from “Questionnaire for Stakeholders” under previous Green Dorm Structural Decision MACDADI analysis
Stakeholders
BackgroundBackgroundGoals Students
CEE Faculty Designers
Campus Planning
Campus Housing Average
Research on sensing and monitoring systems 8.97 8.85 9.36 9.22 2.21 7.72
Research on building structure 7.97 8.35 7.07 6.89 1.71 6.40
Research on building materials 7.97 8.85 7.07 8.22 2.21 6.87
Research on design and construction process 8.31 7.60 6.79 6.89 1.71 6.26
Low/no carbon 9.64 10.35 2.95 11.22 10.83 9.00
Low embodied energy 8.64 7.60 2.02 9.89 7.83 7.20
Material efficiency and sustainable sourcing 8.64 8.60 2.05 7.89 8.83 7.20
Design for daylighting 8.64 7.35 7.50 8.22 5.83 7.51
First cost 1.74 3.43 2.41 8.22 5.13 4.19
Lifecycle cost 2.08 5.68 2.45 11.56 8.88 6.13
Completion date 1.91 2.93 1.59 6.22 5.13 3.55
Reduced earthquake losses ($) 2.08 4.18 2.09 5.56 7.38 4.25
TOTAL 76.58 83.79 53.34 100.00 67.67 76.28
Green Dorm
Multidisciplinary Analysis
StakeholdersCombined MACDADICombined MACDADI
Combined MACDADI Value Stakeholder Group Average
-40.00
-30.00
-20.00
-10.00
0.00
10.00
20.00
30.00
40.00
Research on sensing and monitoringsystems
Research on building structure
Research on building materials
Research on design and constructionprocess
Low/no carbon*
Low embodied energy Design for daylighting
First cost
Lifecycle cost
Completion date
Reduced earthquake losses ($)
Optimized Wood Frame
Steel Rocking Frame
Green Dorm
Multidisciplinary Analysis
StakeholdersCombined MACDADICombined MACDADI
Value of Design Options for Stakeholder Average
9.13
133.84
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
160.00
Average
Design Options
Re
lati
ve
Va
lue
Optimized Wood FrameSteel Rocking Frame
Value of Design Options for Students
19.85
150.42
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
160.00
Students
Design Options
Rel
ativ
e V
alu
e
Optimized Wood Frame
Steel Rocking Frame
Value of Design Options for CEE Faculty
9.03
154.05
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
160.00
180.00
CEE Faculty
Design Options
Rel
ativ
e V
alu
e
Optimized Wood Frame
Steel Rocking Frame
Green Dorm
Multidisciplinary Analysis
Final Decision . . .
Steel!!Steel!! Next step: “Real-time 4D-based Progress
Management for Schedule Reliability
Analysis”
Green Dorm
Multidisciplinary Analysis
Why Included…?- Can We VALIDATE Our Push-Driven Steel Schedule?
- Push-driven schedule: from upstream (GC) to downstream (field)- We tested other analysis (e.g. Daylight in IES, Structure in MaxBeam)- Reliability improvement: As-Planned vs. As-Built Schedules
We scored a metric value of “2” on Completion Date (1.25 yrs)
Is this really RELIABLE?
Let’s test its reliability!
Real Time 4D-based Progress Management for Schedule Reliability Analysis
Green Dorm
Multidisciplinary Analysis
How..?1) We can Test Schedule Reliability thru as-planned vs. as-built schedules
2) We can Improve Schedule Reliability thru real-time progress visualization
3) We can Improve Schedule Reliability thru real-time communication
Preparations- 3D model, RFID tags & scanners, table-PCs, hosting server, GUID settings
Manufactured Shipped Received Erected
As-Planned Quantity Complete
As-Built Quantity Complete
Internet
Internet
Real Time 4D-based Progress Management for Schedule Reliability Analysis
Green Dorm
Multidisciplinary Analysis
Assumptions1) Status is scanned thru RFID on a real-time basis.
2) Steel prefabrication includes columns, girders, and beams.
3) Seismic bracing, stud bracing, and misc. steels are on-site fabricated.
4) 1-on-1 mapping exists between schedule activities and 3D objects.
5) Schedule transition is made from WBS-oriented schedule to PBS-oriented schedule.
Information Needed1) Sequence observation
Real Time 4D-based Progress Management for Schedule Reliability Analysis
Green Dorm
Multidisciplinary Analysis
Prefab.
Attach tags Scan tags
Shipping Receiving Installing
Scan tags Scan tagsRFID
BIM
Real Time 4D-based Progress Management for Schedule Reliability Analysis
Process Diagram
Internet
InternetReal-Time
Communication
Green Dorm
Multidisciplinary Analysis
Green Dorm
Multidisciplinary Analysis
How to Transform Results into MACDADI
Real Time 4D-based Progress Management for Schedule Reliability Analysis
Original Scores -3 -2 -1 0 1 2 3
Completion Date > 3.5 years3-3.5 years
2.5-3 years
2 years from constr. start
1.5-2 years 1-1.5 year < 1 year
We scored a metric value of “2” on Completion Date (1.25 yrs)
Is this really RELIABLE?
Adjusted Scores 1 1.25 1.5 1.75 2
Variance 40% 30% 20% 10% 0%
Variance = (% of As-Planned - % of As-Built)Ex) As-Planned on the 13th week: Complete 200 LF (100%) Steel Framing Installation
However, As-Built on the week: Completed 180 LF (90%) Steel Framing Installation
Variance = 10%
Green Dorm
Multidisciplinary Analysis
What I Learned..?
Real Time 4D-based Progress Management for Schedule Reliability Analysis
Real-time Communication– Machine-to-Machine interface
– Real-time info sharing / communication through RFID+BIM
– Real-time status tracking
Schedule Reliability– Quantity-based PPC vs. Duration-based Schedule
– Reliable look-ahead schedule development
Future Direction– Links to ERP systems (cost-progress report generating)
– Increase reliability through sub’s upfront involvement
Green Dorm
Multidisciplinary Analysis
Thanks!
Any Question?