Upload
kinjal-patolia
View
25
Download
1
Embed Size (px)
Citation preview
GREEN CARPET IN JUNAGADH
The purpose of this report is to identify the potential of using
renewable energy (solar, biomass) and the concept of
distributed power supply to give energy independence and
green tomorrow to Junagadh, a small town of India.
BY K. C. PATOLIA (1057047)
ENGY 710-W01
FEASIBILITY
STUDY
REPORT
SPRING-2015
1057047, K. C. PATOLIA Page 1
ACKNOWLEDGEMENT
I would like to express my special thanks of gratitude to my professor, Mr. Stanley Greenwald who
gave me the golden opportunity to do this wonderful study report on the subject “Distributed
Generation Power Plant system”, which helped me in doing a lot Research and I came to know
about so many new things. In this way, I have increased my knowledge. I am really thankful to
him.
Secondly, I would also like to thank my family and friends who helped me a lot in finishing this
study report within the limited time.
SCHOOL OF ENGINEERING & COMPUTING SCIENCE
M. S. ENERGY MANAGEMENT (SPRING 2015)
ENGY-710 – POWER PLANT SYSTEM
KINJAL C. PATOLIA (1057047)
1057047, K. C. PATOLIA Page 2
TABLE OF CONTENT
1. INTRODUCTION 3
2. JUANGADH AT GLANCE 4 3. CURRENT LOAD ANALYSIS OF JUNAGADH 6
3.1 Electric load requirement 6 3.2 Sources of electricity in Junagadh 7 3.3 Why current scenario needs transformation? 8
4. SOLAR PHOTOVOLTAIC TO AVAIL ABUNDABT ENERGY OF THE SUN 10 4.1 Introduction 10 4.2 Technical analysis 11 4.3 Plant economics and emission generation 13 4.4 Opportunities 13 4.5 Barriers 14
5. BIOMASS POWER PLANT (AGRICULTURAL RESIDUES AND MSW) 16 5.1 Introduction 16 5.2 Technical analysis 17 5.3 Plant economics and emission generation 19 5.4 Opportunities 19 5.5 Barriers 20
6. CONCLUSION 21 7. REFERENCES 22
1057047, K. C. PATOLIA Page 3
1. INTRODUCTION
As we move into a smarter and faster world, full of innovations and technology, we also face
perils of rapidly depleting sources of energy and pernicious ramifications on the environment.
Today, the entire world has been working hard to reduce the use of conventional sources of
energy and adopt cleaner and greener sources. But the success of these efforts depends on the
ideal combination of different factors like, geographical location, availability of natural
resources, government’s supportive policies, technical and economic efficiencies and carbon
footprint. In this feasibility study report ideal combination of different factors are used to avail
the natural sources of energy. Because the ultimate fact is that, “Nature is dying day by day, but
nature is the only answer to this challenge”.
1057047, K. C. PATOLIA Page 4
2. JUNAGADH AT GLANCE
FIGURE 1 [JUNAGADH ON WORLD MAP]
FIGURE 2 [GEOGRAPHY OF JUNAGADH]
1057047, K. C. PATOLIA Page 5
TABLE 1 [JUNAGADH ON WORLD ATLAS]
FIGURE 3 [SITE OF POWER PLANT]
Junagadh is located in the Gujarat, mid-western state of India. It is located at the foot of the
Girnar hills, 355km south west of state capital Gandhinagar and Ahmedabad. Junagadh is
connected to National Highway NH8d. It also comes under Western Railway zone of Indian
Railway. It has no air-port facility due to mountainous terrain. The nearest air-port is Rajkot air-
port. Junagadh has a tropical wet and dry climate with three distinct seasons observed, a mild
winter from November to February, a hot summer from March to June, and a monsoon from
July to October. Due to mountainous region and forest reserves, Junagadh lacks major
industries or plants. The economy of Junagadh is mainly based on agriculture. Junagadh is
developing rapidly in the North and in the South. There are various utility services in the city
like, water supply, waste collection facility, drainage facility, electricity and telecom services.
Coordinates 21.52°N 70.47°E
Country India State Gujarat Government Body Junagadh Municipal Corporation Area 59 km2(23 mile2) Elevation 107 meter(351 feet) Population 3,20,250 Density 5400/ km2 (14,000/ mile2) Time Zone IST (UTC+5:30)
SITE
1057047, K. C. PATOLIA Page 6
3. CURRENT ELECTRIC LOAD ANALYSIS OF JUNAGADH
3.1 ELECTRIC LOAD REQUIREMENT
Average area of the house (ft2) 2,200 square feet
Lighting (3W/ft2) 6,600 W 2 Small appliances (1500 W) 3,000 W 1 Dishwasher (1200 W) 1,200 W 1 Refrigerator 800 W Total 13,100 W First 10 kW of all other load has 100% demand factor (A)
10,000 W
Remainder of other load has 40% demand factor (B)
1240 W
AC @ 100 % @ 1500 W (C) 1500 W Total (A+B+C) 12,740 W No. of houses 64,000 units Total residential load 187.532 MW
TABLE 2 [RESIDENTIAL LOAD ANALYSIS]
Type of occupancy School Library Church
Lighting 3 watt 3.5 watt 2.25 watt Misc.power 1.5 watt 0.5 watt 0.5 watt Air Conditioning 4 watt 6 watt 6 watt Total 8.5 watt 10 watt 8.75 watt Area 60,000 square feet 60,000 square feet 20,000 square feet Power/unit 510 kilowatt/unit 600 kilowatt/unit 175 kilowatt/unit Number of units 30 units 3 units 10 units Growth rate 70% 35% 20% Power of units 26,010kilowatts 2,430 kilowatts 2,100 kilowatts Total institutional load
30.53 MW
TABLE 3 [INSTITUTIONAL LOAD ANALYSIS]
1057047, K. C. PATOLIA Page 7
Hospitals Stores Shops Restaurants Offices Govt. Building
Industrial
Lighting (W/ft2) 2.5 w 3.5 w 4 w 2 w 3.25 w 3.25 w 2 w
Misc.(W/ft2) 1.0 w 1 w 1 w 0.25 w 2 w 2w 1 w
A. C.(W/ft2) 6.0 w 6 w 7 w 8 w 5.5 w 5.5 w 0 w
Total(W/ft2) 9.5 w 10.5 w 12 w 10.25 w 10.75 w
10.75 w 3 w
Area(ft2) 60,000 20,000 1,000 3,000 8,000 10,000 25,000
No. of units 10 5 150 12 150 5 5
Growth rate 60 % 75% 60% 30% 60% 60% 75%
Total load (MW) 9.120 1.84 2.9 0.48 20.64 0.86 0.65
Total commercial load (MW)
36.49 MW
TABLE 4 [COMMERCIAL LOAD ANALYSIS]
TABLE 5 [TOTAL LOAD REQUIREMENT]
3.2 SOURCES OF ELECTRICITY IN JUNAGADH
In Junagadh, electricity is provided and distributed by P.G.V.C.L. which is a state run company.
The erstwhile Gujarat electricity board has been restructured into seven companies, One
generation (GSEC), one transmission (GETCO), four distribution companies and GUVNL. The
PGVCL is one of the distribution companies and area under it includes Saurashtra and Kutch
regions.
Type of unit No. of units Load requirement (megawatts)
House holds 64, 000 187.532 MW
Institutions(schools, library, church)
43 30.53 MW
Commercial 337 36.49 MW
Total 64,380 254.552 MW = 255 MW
1057047, K. C. PATOLIA Page 8
CHART 1 [DISTRIBUTION OF FOSSIL AND CLEAN SOURCES]
CHART 2 [GENERATION & REQUIREMENT OF ELECTRICITY]
3.3 WHY CURRENT SCENARIO NEEDS TRANFORMATION?
The energy policy of India is largely defined by the country’s burgeoning energy deficit and
increased focus on developing alternative sources of energy, particularly nuclear, solar and
wind energy. The growth of electricity generation has been hindered by domestic coal
shortages and as consequences, India’s coal imports for electricity generation increased by 18%
in 2010. India is largely dependent on fossil fuel imports to meet its energy demand. By 2030
India’s dependence on energy imports is expected to exceed 53% of the country’s total energy
consumption. The fact is that, cost of power generated from imported coal and domestically
produced is increasing with time.
1057047, K. C. PATOLIA Page 9
CHART 3 [WORLD CARBON EMISSIONS]
The second threat is the emission of greenhouse gases. According to experts, a booming
economy coupled with rising population is adding to GHG emissions. India emitted 2,094
million tons of CO2, according to the 2006 guidelines of IPCC. Of this carbon dioxide accounted
for 72%, methane 22% and nitrous oxide 6%. The study revealed that an average Indian was
guilty of emitting 1.89 tons of CO2. Gujarat accounts for the fourth highest emission of
greenhouse gases in the country. The state, known for its chemical, pharma, and textile
industry, emitted 154.62 million tons of carbon dioxide equivalents last year.
1057047, K. C. PATOLIA Page 10
4. SOLAR PHOTOVOLTAIC TO AVAIL ABUNDANT ENERGY OF THE SUN
4.1 INTRODUCTION
India is densely populated and has high solar insolation, an ideal combination for using solar
power in India. Moreover its other resources are relatively scarce. According to a 2011 report
by BRIDGE TO INDIA and GTM research, India is facing a perfect storm of factors that will drive
solar photovoltaic adoption at a furious pace over the next five years and beyond. Government
support and ample solar resources have also helped to increase solar adoption, but perhaps the
biggest factor has been need. Particularly, Gujarat state has got both vision and advantage in
the form of topography to emerge as a world leader.
FIGURE 4 [SOLAR INSOLATION IN INDIA]
1057047, K. C. PATOLIA Page 11
FIGURE 5 [PROPOSED SOLAR PV FARM IN JUNAGADH]
4.2 TECHNICAL ANALYSIS
FIGURE 6 [SCHEMATIC DIAGRAM OF SOLAR PV PLANT]
1057047, K. C. PATOLIA Page 12
TABLE 6 [TECHNICAL DETAILS OF THE PLANT]
A photovoltaic power station, also known as a solar park, is a large-scale photovoltaic system
designed for the supply of merchant power into the electricity grid. They are differentiated
from most building-mounted and other decentralized solar power applications because they
supply power at the utility level, rather than to a local user or users. They are sometimes
referred to as solar farms or solar ranches, especially when sited in agricultural areas. The
generic expression utility-scale solar is sometimes used to describe this type of project.
Most solar parks are ground mounted PV systems, also known as free-field solar power plants.
The solar arrays are the subsystems which convert incoming light into electrical energy. They
comprise a multitude of solar modules, mounted on support structures and interconnected to
deliver a power output to electronic power conditioning subsystems. Many projects use
mounting structures where the solar modules are mounted at a fixed inclination calculated to
provide the optimum annual output profile. The modules are normally oriented towards the
equator, at a tilt angle slightly less than the latitude of the site. In some cases, depending on
local climatic, topographical or electricity pricing regimes, different tilt angles can be used, or
the arrays might be offset from the normal East-West axis to favor morning or evening output.
Solar panels produce direct current (DC) electricity, so solar parks need conversion equipment
to convert this to alternating current (AC), which is the form transmitted by the electricity grid.
The conversion is done by inverters. The system inverters typically provide power output at
voltages of the order of 480 VAC. Electricity grids operate at much higher voltages of the order
of tens or hundreds of thousands of volts, so transformers are incorporated to deliver the
required output to the grid.
TECHNICAL ANALYSIS
Type of module Crystalline silicon(German tech)
Mounting system Fixed mounting, free standing 2 angles
Azimuth/inclination 180°(south)/48°(winter), 17°(summer)
Rating of solar panel 300 Wp
DC voltage 36.72 volts
DC current 8.17 amp
Open circuit voltage 45.50 volts
Short circuit current 8.65 amp
Central inverter’s efficiency 97.5%
1057047, K. C. PATOLIA Page 13
4.3 PLANT ECONOMICS & EMISSION GENERATION
TABLE 7 [PLANT ECONOMICS & EMISSION GENERATION]
4.4 OPPORTUNITIES
With about 300 clear, sunny days in a year India’s theoretical solar power reception on
only its land area is about 5,000 trillion kilowatt-hours per year. The daily average solar
energy incident over India varies from 4 to 7 kwh/m2 with about 1500-2000 sunshine
hours per year which is far more than current total energy consumption. Gujarat has
natural advantage of barren land without shifting sand dunes.
The government of India is promoting the use of solar energy through various strategies.
The government has announced the Jawaharlal Nehru National Solar Mission and the
establishment of a clean energy fund. 51 solar power radiation resource assessment
stations have been installed across India by the ministry of new and renewable energy
(MNRE) to monitor the availability of solar energy. Data is collected and reported to the
center for wind energy technology in order to create a solar atlas.
PLANT ECONOMICS AND EMISSION GENERATION
Plant capacity 255 MW
Plant cost $1216/kw
Construction cost $310 × 106
Depreciation(straight line depreciation 5 years)
$62 × 106 /year
Interest (bond interest=3.5%) $10.85× 106 /year
Operation & Maintenance(O & M=$35.31/kw)
$9.00 × 106 /year
Fuel cost $0.00
Ash 0
Taxes 0
Carbon tax 0
Total cost $81.85 × 106 /year
Government credits 30%
Availability of source 70%
Total annual out put 1563.66 × 106 kwhr
Generation cost 3.64 ¢ / kwhr
1057047, K. C. PATOLIA Page 14
The MNRE provides 70% subsidy on the installation cost of a solar photovoltaic power
plant in north-east states and 30% subsidy on other regions. Government can also
provide subsidies for the production of PV panels in which there will be reduction in the
market price and this can lead to more usage of solar power in India. Government has
also encouraged private solar companies by reducing customs duty on solar
photovoltaic panels.
Additionally, the government has initiated a renewable energy certificate scheme, which
is designed to drive investment in low carbon energy projects. The budget also proposed
a coal tax of $1/ton on domestic and imported coal used for a power generation.
The state government is also taking initiative in providing the common
infrastructure/facilities like site preparation and leveling, power evacuation, availability
of water, access roads, security and services. Gujarat energy transmission will develop
evacuation from the identified interconnection points with solar developers. This
project is supported in part by the Asian Development Bank.
With that other benefits like carbon credits and other subsidies, moreover appreciation
in the land value. The state has signed power purchase agreements with 80 private
players worth $3billion.
4.5 BARRIERS
Land is a scarce resource in India and per capita land availability is low. Dedication of
land area for exclusive installation of solar arrays might have to compete with other
necessities that require land. The amount of land required for utility scale solar power
plants currently approximately 1 km2 for every 20-60 MW generated could pose a strain
on India’s available land resource.
The architecture more suitable for most of India would be highly distributed set of
individual roof top power generation systems, all connected via a local grid. However,
erecting such an infrastructure which does not enjoy the economies of scale possible in
mass, utility scale, solar panel deployment, needs the market price of solar technology
deployment to substantially decline, so that it attracts the individual and average family
size household consumer.
Solar does not work at night. The biggest disadvantage of solar energy is that it is not
constant. To produce solar electricity there must be sunlight. So energy must be stored
1057047, K. C. PATOLIA Page 15
or sourced elsewhere at night. Beyond daily fluctuations, solar production decreases
over winter months when there are less sunlight hours and sun radiation is less intense.
A very common criticism is that solar energy production is relatively inefficient.
Currently, widespread solar panel efficiency- how much of the sun’s energy a solar panel
can convert into electrical energy is at around 22%.Solar electricity storage technology
has not reached its potential yet. While there are many solar drip feed batteries
available, these are currently costly and bulky. Solar panels are bulky. This is particularly
true of higher-efficiency, traditional silicon crystalline wafer solar modules. These are
the large solar panels that are covered in glass. New technology thin-film solar modules
are much less bulky, and have recently been developed as applications such as solar
roof tiles and “amorphous” flexible solar modules. The downfall is that thin-film is
currently less efficient than crystalline wafer solar.
The main hindrance to solar energy going widespread is the cost of installing solar
panels.
1057047, K. C. PATOLIA Page 16
5. BIOMASS POWER PLANT (AGRICULTURAL RESIDUES AND MSW)
5.1 INTRODUCTION
Biomass has always been an important energy source for the country considering the benefits it
offers. It is renewable, widely available, carbon-neutral and the potential to provide significant
employment in rural areas. With the new government policy of biotechnology, Junagadh has
been identified as one of the agriculture biotechnology zone. Major crops produced in the
district are wheat, oil seeds, cotton, banana, onion and bringer. Total production of oilseeds in
the Junagadh is 4, 64,400 MT per annum which is the largest producer of groundnut and garlic
in the state contributing 26% and 36% of total production respectively. These agricultural
residues can generate a significant amount of electrical energy. Another considerable source of
energy is the municipal solid waste or garbage of the city. This type of conversion will help not
only for energy production, but it will also support “Clean India” initiative.
FIGURE 7 [CURRENT AGRICULTURAL & POLLUTION SCENARIO IN INDIA]
1057047, K. C. PATOLIA Page 17
FIGURE 8 [PROPOSED BIOMASS POWER PLANT IN JUNAGADH]
5.2 TECHNICAL ANALYSIS
FIGURE 9 [SCHEMATIC DIAGRAM OF BIOMASS POWER PLANT]
1057047, K. C. PATOLIA Page 18
TABLE 8 [TECHNICAL ANALYSIS OF BIOMASS PLANT]
The project is designed to generate electricity from biomass (surplus residues and municipal
solid waste) that is available in project region. The basic technology is combustion, where direct
combustion of biomass takes place through a multi-fuel fired boiler to generate high-pressure
and high-temperature steam, which in turn drives a turbine coupled to generate the electric
energy of rated. The major items of plant and machinery consist of a travelling grate boiler with
economizer, air pre-heater with electro static precipitator, a steam turbine with synchronous
generator, power evacuation system and fuel handling system. Other plant and equipment
includes air-cooled condenser, fuel conveyor, ash handling system, water treatment plant,
compressor units, etc. Electricity generated from biomass is a renewable source of energy; the
fuels to be used would be a mixture of surplus biomass residues, which form part of regular
carbon cycle and helps in reduction of greenhouse gases leading to sustainable development.
The project would contribute positively to the environment by reducing greenhouse gas
emissions that would have otherwise been generated by using conventional sources of energy
such as coal, lignite, gas and oil. The project utilizes surplus biomass residues, which form part
of the regular carbon cycle and hence do not contribute to additional atmospheric CO2
emission.
TECHNICAL ANALYSIS
Boiler type Travelling grate
Boiler capacity/steam flowrate 15.2 × 103 lb./hr.
Steam pressure at super heater outlet 67 ata
Steam temperature at super heater outlet 480 ± 5°c
Steam turbine generator type Single cylinder impulse condensing
Capacity 10 MW
Inlet steam parameters 64 ata @ 474 °c
Generator voltage 11 kv
Frequency 50 Hz
RPM 3000
System condensing system Air-cooled
Grid voltage 66 kv
1057047, K. C. PATOLIA Page 19
5.3 PLANT ECONOMICS & EMISSION GENERATION
PLANT COST AND GENERATION EMISSION
Plant capacity 10 MW
Ground nut shells 100 tons/day
Municipal solid waste 100 tons/day
Plant cost $62/kw
Construction cost $0.43 × 106
Depreciation(straight line depreciation-15 years)
$0.03 × 106 /year
Interest (bond interest-3.5%) $0.02 × 106 /year
Operation & Maintenance(O&M=$470/kw) $4.7 × 106 /year
Efficiency 30%
HHV 7455 BTU/LB
Fuel cost($20/ton) $1.33 × 106 /year
Ash($2.91/ton) $0.19 × 106 /year
Fuel tax $0.00
Carbon tax $0.20 × 106 /year
Total cost $6.47 × 106 /year
Generation cost 7.3¢/kwh
CO2 / MWH 2949 lb. CO2 / MWH
TABLE 9 [PLANT ECONOMICS & EMISSION GENERATION]
5.4 OPPORTUNITIES
MNRE has promoted the national program for the recovery of energy from industrial
and urban wastes. Since this program seeks to promote setting up of waste to energy
plants, various financial incentives and other eligibility criteria have been proposed by
the MNRE to encourage the participation in waste to energy projects. Financial assistance is provided on the capital cost for demonstration projects that are
innovative in terms of generation of power from municipal/industrial waste. Financial
incentives are given to municipal corporations for supplying garbage free of cost at the
project site and for providing land. Incentives are given to the state nodal agencies for
promotion, co-ordination and monitoring of such projects. Financial assistance is given
for carrying out studies on waste to energy projects, covering full costs of such studies.
Assistance is given in terms of training, courses, workshops and seminars and
awareness.
1057047, K. C. PATOLIA Page 20
The project would generate employment opportunity for unemployed youth of the
local area for collection of biomass on the fields and then loading and unloading it to
the project site by transportation, there by contributing towards creation of social
capital in the region in which biomass is produced by the plant. It will create
direct/indirect employment for operating the plant as well as for transportation of
biomass material to the project plant from sources. The generation of ecofriendly power brings socio economic development of the town.
The project will help to alleviate the poverty level of poor people of town. Besides
employment, it will also bring investment in the town that will result in economic well-
being. It will generate additional income for farmers due to creation value for the commercial
value of neglected biomass in and around the region.
5.5 BARRIERS
The major barrier faced by the project is the low return on investment which reinforces
the conclusion that the project is additional and not a business-as-usual scenario.
The estimated decrease in the cost of biomass is deemed unlikely. The farmers or
suppliers may consider residues as business opportunity and increase the price of
biomass material.
Another barrier is technological risk due to use of various types of biomass residues.
The properties of biomass fuels affecting boiler performance are volatile matter,
moisture, alkali content and chlorides. The envisaged biomass fuels have high organic
alkali content, mainly the oxides of sodium and potassium which are more often
associated with sinter formation in the high temperature super-heater zones. Corrosion
due to alkali and chloride results in frequent tube failures. Furthermore the moisture
content of biomass will have an effect on the conversion efficiency and heating value.
The operation and performance of the biomass plant is highly uncertain because of the
poor characteristics of biomass material such as low bulk density, high moisture
content, etc. The project activity uses various types of biomass as fuel. Due to varied
properties of various biomass fuels, it is difficult to maintain operating parameters such
as pressure and temperature, which can be quantified and there by the carbon
revenues can be extending for the same.
Biomass power generation is not a common phenomenon in the state of Gujarat.
1057047, K. C. PATOLIA Page 21
6. CONCLUSION
In this way, the study concludes that this type of implementation of renewable energy sources
will be able to provide 70% percent electricity of the Junagadh city. As solar power is not
available 24 hours and biomass plant alone is not capable of supplying the whole demand of
the city, grid power must be available during those dark hours. However, efforts are not in vain,
because during night time the load requirement is very low. Moreover, current researches
support that in next coming decade it would be possible to implement batteries and renewable
energy together. This kind of implementation will give 100% energy independence and green
carpet to my home town, Junagadh.
1057047, K. C. PATOLIA Page 22
7. REFERENCES
http://en.m.wikipedia.org/wiki/solar-power-in-india
http://m.timesofindia.com/city/ahmedabad/gujarat-GHG-emissions
www.pgvcl.com
http://en.m.wikipedia.org/wiki/biomass
http://www.mnre.gov.in/scheme/grid-connected/bio-mass-power cogen/
http://www.eai.in/ref/ae/intelpol/policies.html
http://en.m.wikipedia.org/wiki/junagadh