US Army Corps of EngineersBUILDING STRONG®
Michael B. WhiteDirector of ProgramsUSACE, Great Lakes and
Ohio River Division
11 February 2010
Great Lakes Infrastructure ~ Managing the Challenges ~
BUILDING STRONG®2
Reducing Dredging Backlog
Dredged Material Management Strategic Plan
Soo
Locks Reliability
Great Lakes Restoration Initiative
Aquatic Invasive Species Dispersal Barrier
Ongoing Critical Issues
BUILDING STRONG®3
Reducing Dredging Backlog
BUILDING STRONG®4
Path Forward to Reduce Backlog 2010-2017
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
1985 1990 1995 2000 2005 2010 2015
Cubi
c Ya
rds
Dred
ged
(x10
00)-
Blue
Lin
e
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
Cum
. Bac
klog
(100
0 cu
yds
) -
Gre
en L
ine
Annual Great Lakes Dredging 1986-2010 Average Annual Need Dredging Backlog FY11
FY11 PB
BUILDING STRONG®5
Dredging Funding Trends 2007 Dredging Funding Trends 2007 -- 20112011
0.00.51.01.52.02.53.03.54.04.5
FY07 FY09
Qua
ntity
Dre
dged
(100
0 cu
yd)
L. SuperiorRegional Provisions
CommercialRegional Provisions
Energy & Water Adds
President's
FY08
MichiganRegional Provision
5.0 ARRA(Stimulus)
5.5
3.3M Annual Reqm’t
Budget
FY10 FY11
2.2M cu yds ($26M) needed over annual reqmt to meet backlog removal plan
0.6M cu yds ($7M) needed to meet annual reqmt
BUILDING STRONG®6
Executed $63M in dredging in 2009; removed nearly 2M cubic yards of backlog
Employing innovative acquisition strategies; increasing the number of GL contractors
Increasing capacity: GL Contractor fleet added hydraulic dredging capacity in 2009
Working to improve efficiency: improved dredging efficiency in 2009 by 5%
Strategic Dredging Initiatives
BUILDING STRONG®7
Dredged Material Management Strategic Plan
BUILDING STRONG®8
DMM Historical Perspective
Dredged material nearly exclusively disposed via open water placement
1970
- River a
nd H
arbor
Act an
d
Flood C
ontro
l Act
of 19
70
(PL 9
1-611
) pas
sed
1988
- Federa
l Stan
dard
defin
ed
1996
- Sectio
n 201
of th
e 199
6 WRDA
requir
es co
st-sh
aring
45 Great Lakes CDFs constructed and/or operated by USACE at a cost of $900M
(2009 dollars)
Curren
t CRITIC
AL situ
ation
.
DMM strat
egies
mus
t be d
evelo
ped.
Execute sustainable
DMM solutions
1970 1980 1990 20001960
BUILDING STRONG®9
Current Dredged Material Management Conditions
Lake Superior
Lak
e M
ichi
gan
Lake Huron
Lake Erie
Lake Ontario
CANADA
WISCONSIN
OHIO
INDIANAILLINIOS
PENNSYLVANIA
NEW YORK
MICHIGAN
MINNESOTAGrand Marias
Two Harbors
Duluth Superior
AshlandOntonagon
Keweenaw Waterway
Presque IsleMarquette Grand
Marias St. Marys RiverChannel in Straits of Mackinac
Grays ReefLittle Bay
de Noc
Menominee
Green Bay Kewaunee
Port Washington
Milwaukee
Kenosha
Manitowoc
Sheboygan
Waukegan
Chicago River & Harbor
Calumet
Indiana Harbor
Burns Waterway
Harbor
St. Joseph Harbor
Holland
Grand Haven
Muskegon Harbor
Ludington
Manistee
Frankfort
Charlevoix
Cheboygan
Alpena
Saginaw Harbor Beach
Monroe
Channels in Lake St.
Clair
St. Clair River
Detroit River
Rouge River
Toledo Sandusky
Harbor
Huron
Lorain
Cleveland
Fairport
Ashtabula
Conneaut
Erie
Dunkirk
Buffalo Harbor
Rochester
Harbor
Oswego
Ogdensburg
800K
100K – 250K
50K – 95K
<50K
ANNUAL DREDGING REQUIREMENT (CY)
DREDGED MATERIAL MANAGEMENT STATUSCritical –
Dredged Material Management issues could severely restrict channel availability within 5 yearsPressing –
Dredged Material Management issues could severely restrict channel availability within 10 years.No pressing issues within next 10 years; continue to work on long range planning such as DMMPs.
BUILDING STRONG®10
DMM Long-Term Strategy
Strategic Plan1. Extend CDF Life through Fill Management2. Aggressively pursue opportunities for beneficial use and reuse of
dredged material to create CDF capacity.3. Reduce Amount of Materials Entering Federally Maintained
Navigation Channels4. Engage State Agencies in Solutions5. Foster Partnership with USEPA to Leverage Funding for Projects
Supporting Environmental Goals and Navigation Benefits
Relying solely on new CDF construction is uncertain; we must maximize the use of the 5 strategies above.
Harbors that require immediate DMM-related solutions:►
Cleveland, Lorain, Calumet, Indiana, Toledo, Duluth-Superior, Saginaw Bay
BUILDING STRONG®11
Coordination with Other Agencies is Critical
Collaborate with USDA-NRCS, state and local agencies to leverage the Corps’
current programs such as Great Lakes Tributary Modeling to ultimately reduce the amount of material entering watersheds
that contribute to sedimentation in federally maintained navigation channels.
Engage states, USEPA, and USFWS to participate in studies to improve the scientific basis for establishing environmental dredging windows
and open lake placement decisions; develop specific strategies for each state.
Partner with USEPA to aggressively leverage authorities and funding for projects that benefit navigation and the environment -
Great Lakes Legacy Act & Great Lakes Restoration Initiative.
BUILDING STRONG®12
Soo Locks Reliability
BUILDING STRONG®13
70% of the commercial commodities transiting the Soo Locks are limited by size to the Poe Lock
•Security concerns -
foreign crews in vessels are capable of seriously damaging or destroying locks
•There is currently no redundancy for the Poe Lock
Two major efforts are underway to improve reliability of the Soo
Locks
1.
Maintain existing infrastructure through Asset Renewal Plan
2.
Add redundancy by constructing a new replacement lock with the same dimensions as the Poe Lock
•The economic impact of a 30-day unscheduled closure of the Soo Locks = $160M
The Soo Locks A Lynch Pin of the Great Lakes Navigation System
BUILDING STRONG®14
Soo Locks Asset Renewal Long-Term Plan
Asset Renewal Plan will maximize reliability and reduce risk through 2035
Full funding requires $93 million over 6 years
$19.6 M funded to date
new hydraulics, stop logs, utilities
$73M in needs from FY10-FY14
Major remaining needs:
•
New compressed air system
•
Heavy lift equipment procurement
•
Rock Cut stabilization
•
Bollard reinforcement0
5
10
15
20
25
FY08 FY09 FY10 FY11 FY12 FY13 FY14Fu
ndin
g, $
M
Funded
Needs
BUILDING STRONG®15
Great Lakes Restoration Initiative
BUILDING STRONG®16
Administration Budget Initiative for restoration of Great Lakes ecosystem
$475M in FY 2010 ($411M new funding)
Led by EPA and coordinated through GL Interagency Task Force
Budgeted through EPA Appropriations
Five-Year Action Plan (FY10 -
FY14)
Identifies five Focus Areas for restoration
Objectives, short-
and long-term goals for each Focus Area
$46.3M for USACE projects in FY10
Great Lakes Restoration Initiative Overview
BUILDING STRONG®17
Strategic Navigation Dredging (SND)
GLRI funds will be used to dredge contaminated sediments from Federal navigation channels to complement clean-up with Legacy Act
Buffalo River –
$7M in FY 2010 for removal of up to 660,000 cubic yards
Dredged Material Disposal Facility Construction
GLRI funds can be used for development of DMDFs that also provide habitat benefits
Green Bay –
DMDF will help restore 1,000 acres of coastal wetlands –
Cat Island Restoration
Great Lakes Restoration Initiative Navigation Connections
BUILDING STRONG®18
Beneficial Use of Dredged Material
GLRI funds will be used to plan, design and construct beneficial use projects
Wynn Road and Maumee Bay –
projects for dredged material from Toledo Harbor
Tributary Models
GLRI will supplement Corps’
base funding for models that support soil conservation and nonpoint source pollution prevention activities by state and local agencies
Great Lakes Restoration Initiative Navigation Connections
BUILDING STRONG®19
Aquatic Invasive Species Dispersal Barrier
BUILDING STRONG®20
BUILDING STRONG®21
Chicago Area Waterway System
21
BUILDING STRONG®22
800’
220’
Chi
cago
San
itary
and
Shi
p C
anal
Barrier I (Demo)
Lake
Mic
higa
n
Wat
er F
low
Dispersal Barriers Overview
Barrier IIB:₋ Site prep completed₋
Building construction
contract NTP issued 3 Dec
₋ Electronics design ongoing₋
Construction to be
completed 30 Sep 10
Barrier IIA:
‐
Activated @ 1 Volt/in, 5 hz, 4
ms in APR 09.
‐
Increased to 2 Volt/in, 15 hz,
6.5 ms in AUG 09
‐Maintenance shutdown
completed 3 – 4 Dec
w/rotenone support by State
Barrier I (Demonstration):₋In continuous operationsince 2002 @ 1 Volt/in, 5 hz, 4 ms‐ Rehabilitated in Oct 2008
Barrier I (Permanent):
‐
Upgrade to a permanent
barrier authorized; plan
activation by 2013 if funded
I
IIB
IIA Barrier IIA
Other Ongoing Efforts:- Asian Carp Monitoring
-
Research on Optimum
Operating Parameters
-
Study of Solutions to
Potential Barrier Bypasses
BUILDING STRONG®23
Construction of Barrier IIB & Permanent Barrier IConstruction of Barrier IIB30 OCT 2009
Building Construction Contract Awarded
Mar 2010Electronics
Design Finalized
May 2010Building
Substantially Complete
Oct 2010Complete
Safety Testing
Dec 2009Building Notice to Proceed Issued
IIB Capabilities: Range of Operating Parameters Same As IIA
Improvements for Barrier IIB Vs. Barrier IIA
► Closed-Loop Cooling System
► All System Components Enclosed in Sealed
Building
Upgrade of Barrier I to Permanent► Similar to IIB
► Initiate Once Barrier II is Fully Operational
800’
220’
Chi
cago
San
itary
and
Shi
p C
anal
Barrier I (Demo)
Lake
Mic
higa
nW
ater
Flo
w
Sep 2010Complete Startup Testing
Aug 2010Complete
Construction
Jun 2010Begin
Electronics Installation
Barrier IIA
Barrier IIB
BUILDING STRONG®24
Efficacy Study Interim III – Modified Operations
Initial Meeting
12 Jan 10
Revision and approval of Review Plan Development of draft report and draft EA
2 Feb Initial UserEngagement
USACE timeline to ASA(CW) for Sec. 126 approvalMar 2010
Test / Implement Actions
April 10Execute
22 Jan 10Meet with IDNR / MWRD
Early Mar 10ASA(CW) Review / Approval
28 Jan 10Plan development
With agencies
27 Jan 10Vertical team
8 Feb 10NEPA –
Scoping Letters
HQ OWPR Review / Approval for
release to public
ATR of draft decision document and draft EA
Release NEPA document for public comment
Final draft documents to HQ OWPR and LRD RIT
Modify Waterway Operations (MWRD)• Lower water levels in advance of storms • Retrofit sluice gates with screens •
Use pumps instead of opening gates at Wilmette Pumping Station•
Investigate possibility of modifying water quality to distress / kill ACEstablish Control (Kill) Zones (IDNR/FWS)•
Identify areas & establish plans for “spot treatment”
using piscicide•
Identify areas and establish plans for intensive fishing operations (nets / commercial / shock)Guide AC into Control Zones (IDNR/FWS•
Herd fish into designated control zones –
directional boat mounted; electro-fish; nets•
Stationary directional barriers –
Chicago and O’Brien Locks –
deny access through locks
Modify Structural Operations (USACE)
• Close both sets of gates between lockages
• Intermittent lock operations
• Screens for flooding?
•
Screens during treatments or commercial
fishing
Uncontrolled Pathways (USACE/IDNR/FWS)
•
Intense monitoring/population control actions in
Little Cal
•
Directional / interim barriers –
Little Cal / Grand
Cal
BUILDING STRONG®25
Impact UncertaintiesFlooding: Flood Damage Reduction Structures
TARP Impacts
Property Loss / Damage ($B)
Loss of Life
Commerce / Economics: Transportation System Upset
Critical Infrastructure
Revenue Impacts
Job Impacts
Recreation / Tourism: Navy Pier
Great Lakes Shoreline
Great Lakes Fishing
Great Lakes Ecosystem: Asian Carp (AC) Adaptability
AC Impacts to Shoreline and Tributaries
AC Impacts to Great Lakes Fisheries ($B)
Water Quality: TARP Impacts
Public Health and Safety/EM: USCG/DHS/Chicago Fire and Police
BUILDING STRONG®26
We are working on many key Great Lakes navigation related issues:
►
Continuing to work toward gaining efficiencies and improving cost-effectiveness of Great Lakes dredging
►
Aggressively working multiple paths to solve the Dredged Material Management crisis –
including maximizing the beneficial reuse of dredged material
►
Continuing to assess and prioritize risks and refine needs to ensure reliability at the Soo
Locks►
Working collaboratively with EPA on important GLRI projects that will benefit Great Lakes navigation
►
Tackling the Asian Carp Barrier issues on multiple fronts –
a dynamic situation
Moving Forward
BUILDING STRONG®27
QuestionsQuestions