Gravity Pipeline Outreach Meeting March 22, 2017 Regional Environmental Sewer Conveyance Upgrade

Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Gravity Pipeline Outreach Meeting

March 22, 2017

Regional Environmental

Sewer Conveyance Upgrade

Page 2: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Agenda

• Introduction (Teresa)

• Gravity Pipeline Project – Overview (Bruce)

• Procurement Process and Stages (Teresa)

• Key Parts of the RFQ (Bruce)

• Estimates, Budgets and Pricing (Teresa)

• Early Focus Areas (Stage 1) (Bruce)

• Available Information (Teresa)

• Questions (Please ask anytime)

Page 3: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Gravity Pipeline Project – Overview

• Background

• Virtual tour of alignment and shafts

– Horizontal

– Vertical

• Hydraulics

– Diurnal and Seasonal Equalization

• Status of EIR, Permits and Easements

• Availability of SVCW Funding

Page 4: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

WEST BAY SANITARY DISTRICT

SAN CARLOS

BELMONT

MENLO PARK

WOODSIDE

EMERALD HILLS

REDWOOD CITY

Page 5: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Problem we need to Solve

Joints every 12’ in RCP Force Main thru YBM

Design useful life = 25 to 50 years (ASCE; EPA)

Pipe is 45 years old

Originally designed for gravity flow (low pressure)

Currently operating at 2.5 times design pressure

64 leaks so far; rate of failure is increasing

Leaks are time-consuming, disruptive and expensive to

repair . . . potentially catastrophic.

Page 6: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Pipe cracked

(not a joint separation)

Raw sewage flowing from

separated and offset joint

Page 7: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Adjacent to airport . . .

valve bonnet blew off . . .

. . . raw sewage into the air

Page 8: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Major Failures Corrosion + Surge

Page 9: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Numerous Alternatives Considered

2013/2014 Open Cut in Street Open Cut in Levee Lay in Slough Lay in Lagoon Microtunnel (shallow)

2014/2015 Microtunnel (deep) Tunnel Boring Machine (deep) From SVCW Plant From near Airport

Sliplining (w/ bypass) Parallel Smaller Pipes Pipe Bursting (w/ bypass) Pipe Splitting (w/bypass) Swege (w/bypass) Replace in place (w/bypass)

Page 10: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 11: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 12: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Current Project

• SVCW will share all of the studies and alternatives developed to-date

• We expect to work collaboratively with the PDB during Stage 1 to refine, revise or change these concepts to best meet SVCW objectives

Page 13: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Virtual Tour

Page 14: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

“60% Permit Plans” – RLS Shaft

Page 15: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

RLS Shaft

Page 16: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

RLS Shaft

Page 17: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

RLS Shaft

Page 18: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Airport Access Shaft

Page 19: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Airport Access Shaft

Page 20: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

San Carlos Drop Structure

Page 21: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

San Carlos Drop Structure

Page 22: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

“60% Permit Plans” – Bair Island Inlet

Page 23: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Bair Island Inlet Structure

Page 24: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Bair Island Inlet Structure

Page 25: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Alignment

Page 26: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Governors Bay Alignment

Page 27: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Easement Acquisition

Page 28: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Pulgas Creek

Page 29: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Geologic Profile

Page 30: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 31: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Hydraulics

San Carlos Drop Structure

Design Storm Equalization

Diurnal Equalization

Page 32: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

EIR Status

• Draft EIR November 2016

• Comments Due January 2017 (very few comments)

• Adoption expected April 2017

Page 33: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Environmental Permits

• Environmental Permit Applications submitted December 2016

– COE under Pulgas Creek

– BCDC

– California F&WS

• Expected October 2017

Page 34: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Easements

• Affected along 3.3 miles:

– Four private owners

– Three public agencies

• Legal Descriptions being prepared

• Private acquisitions to start upon approval of EIR

• Two of public agencies are members of SVCW

• Currently leasing Airport Access Shaft staging area

Page 35: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Funding

• Currently have bond capacity to obtain bonds for entire program

• Pursuing less expensive funding

– SRF

– WIFIA

Page 36: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Procurement Process and Stages of Design-Build

• Why Progressive Design Build

• RFQ/RFP

• Stage 1/Stage 2 with Phases

• Schedule

Page 37: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Why Progressive Design Build

• Accelerate completion of overall Project relative to DBB delivery

• Promote a cooperative and collaborative relationship between SVCW and the PDB team

• Incorporate ongoing cost modeling and take a “design-to-budget” approach

• Flexibility for phased design and construction

• Early and ongoing staff involvement and training

Page 38: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

RFQ/RFP Process

• Step 1: – RFQ issuance, – Pre-submittal meeting – Interviews with selected Respondents, – Shortlisting of three (or up to four) Respondents.

• Step 2: – RFP issuance to short-listed Respondents, – Pre-Proposal Meeting – Confidential Meetings with each short-listed Respondent – Reference checking – Interviews – Selection of winning Respondent – Negotiation of Stage 1 Preconstruction contract

Page 39: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Stage 1/Stage 2 with Phases

• Stage 1 – Collaboratively bring the design from a 5% to 10%

level to a 60% to 70% level

– Negotiate Stage 2 Contract Pricing and Schedule

• Stage 2 – Final design (100%)

– Construction

– Testing and Start-up

• Phases – As needed to move project forward

Page 40: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Schedule

• Issue RFQ Shortly after April 13

• SOQ Submission End of May

• Shortlist and RFP Early June

• Proposals Due Late August

• Stage 1 Approval September or October

• Stage 2 Approval 2018

Construction: Two to three years

Page 41: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Key Parts of the RFQ

• RESCU Success Factors

• Gravity Pipeline Project Objectives

• Risk Responsibility Matrix

• Required elements of SOQ

Page 42: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

RESCU Success Factors “Success” - collaboratively implementing an appropriate balance of the following: • Cost: Provide a complete functional conveyance system that meets

the goals of the Program at the lowest practical capital and lifecycle cost.

• Operations: Produce projects that are easy, efficient, and effective to operate.

• Maintenance: Produce projects that minimize required maintenance. • Safety: Implement projects that are safe to construct, operate, and

maintain. • Schedule: Place new wastewater conveyance system projects into

operation with best practical safe speed, while maintaining the present level of service with existing facilities.

• Stakeholder Impacts: Solicit, evaluate, and respond to stakeholder’s concerns, and implement a Program that best meets the combined needs of stakeholders while reaching the Program’s goals.

Page 43: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will reliably

receive, convey and equalize wastewater flows ranging from 2 mgd to 103 mgd in full compliance with environmental requirements.

• Cost: Provide a complete functional gravity pipeline and inlet facilities that meet the goals of the Project at the lowest practical capital and lifecycle cost. Provide early and ongoing total Gravity Pipeline cost predictability.

• Schedule: Achieve the best practical safe speed to complete the tunnel and inlet structures so that the existing failing pipeline and pump stations can be taken out of operation as early as reasonably possible.

• Risk: Generally assign to the Design-Builder the risks that the Design-Builder can reasonably anticipate and control. Assign to SVCW the risks that the Design-Builder cannot reasonably anticipate and control.

• Safety: Implement an effective safety program incorporating better than industry practices. • Accountability: Design-Builder to provide for a single point of accountability for

performance of all services under Stage 1 and Stage 2. SVCW to provide a single point of accountability for all direction to the Design-Builder.

• Collaboration: Implement an integrated design process that collaboratively includes SVCW management, engineering, operations and maintenance as well as the Design-Build contractor and engineer to develop a design that optimally achieves SVCW success factors and Gravity Pipeline requirements.

• Innovation: Apply proven technology from other locations to uniquely achieve Gravity Pipeline goals.

Page 44: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Risk Responsibility Matrix

• Approach: Collaboratively reduce risk and then assign to PDB what the PDB can best control

• Built from a thorough Risk Register prepared during project planning (biggest risk was cost over budget)

Page 45: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Required Elements of SOQ

• Team structure (including parties responsible for shafts, tunnel,

concrete segments)

• Key personnel

• Experience collaborating with owners

• Similar projects

• Safety

Pass fail items, financial, insurance, bonding, etc.

Page 46: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Estimates, Budgets and Pricing

• Budget vs Current Cost Estimate – design to budget

• Indicative Pricing

Page 47: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Focus Areas during early PDB Preconstruction Services (Stage 1)

• RLS shaft – coordination with FoP

• Pipe in tunnel

• Shaft construction

• Benefit of Bair Island start vs environmental/permitting delay risks

• Project cost and schedule

Page 48: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

RLS shaft – coordination with FoP

Page 49: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Pipe in Tunnel – Alternatives

• Two Pass – FRP in tunnel – HDPE lining

• One Pass – HDPE lined segments

• Field weld • Combisegments

– Multiple layers of defense • Upstream dosing • Water and air flow • Special concrete • Monitoring

Page 50: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Shaft Construction - Constraints

• Geotech – YBM, Sand, Groundwater • Airport Height limits – ~55’, ~45’, ~25’ • Protected species – Rail and Mouse • Traffic – Redwood Shores Parkway

Page 51: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Benefit of Bair Island start vs environmental/permitting delay risks

Risks • Ridgeway Rail – no night work • Mouse – no work during high

tides • New Biological opinion – 9 to

12 months • EIR amendment Benefits • Eliminate airport access shaft • No TBM relocation – one

launch • Muck spoil on site

Page 52: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Project Cost and Schedule

• Reduce GP cost by more than $40 million

• Reduce GP schedule by more than a year

• Achieve 100 year service life

• Achieve diurnal and wet weather equalization

Page 53: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

Available Information

• Current

• Future (at RFQ Issuance)

• Self-Guided Tour Maps

Page 54: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 55: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 56: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 57: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 58: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 59: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will
Page 60: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will

More questions?

Thank you for your interest!

Regional Environmental

Sewer Conveyance Upgrade