Upload
abhijith-shetty
View
215
Download
0
Embed Size (px)
Citation preview
7/29/2019 Graeme Walker Design Illustration Concrete
1/20
22 - 23 November, 2010
Institution of Civil Engineers
Bridge Design to Eurocodes- UK Implementation
7/29/2019 Graeme Walker Design Illustration Concrete
2/20
Design Illustration Concrete Bridge Design
Graeme Walker, Gifford
Paul J ackson, Gifford
7/29/2019 Graeme Walker Design Illustration Concrete
3/20
Introduction
Design example prepared for the Concrete BridgeDevelopment Group
Precast, prestressed beam and slab bridge selected todemonstrate as many aspects of the codes as possible
Follows UK NAs and PDs, but makes clear the sourceof all information
7/29/2019 Graeme Walker Design Illustration Concrete
4/20
Scheme Design
2 span integral bridge, each span 20m long
7.3m wide c/way + 2m wide footways either side
Superstructure 8 standard precast, pretensioned concrete Ybeams with a 160mm deep in-situ RC deck slab; in-situ diaphragmsat abutments and pier
Substructure precast concrete piles with pile caps
7/29/2019 Graeme Walker Design Illustration Concrete
5/20
Actions
Permanent Actions
- Self weight
- Differential settlement- Differential shrinkage
Variable Actions- Wind
- Thermal
- Traffic Loads
7/29/2019 Graeme Walker Design Illustration Concrete
6/20
Traffic Loads
Positioning of the notional lanes does not have to correspond to the
position of the lane markings on the bridge. Instead, the lanes & the
remaining area are posit ioned to create the most severe load effects foreach element under consideration.
Division of carriageway into notional lanes
Carriageway width w = 7.30 m
Width of notional lanes w1 = 3.00 m
Number of notional lanes n1 = 2
Width of remaining area wr = 1.30m
7/29/2019 Graeme Walker Design Illustration Concrete
7/20
Traffic Loads Load Model 1
a) A double axleloading, referred to astandem system, or TS.
b) A uniformly
distributed load (UDL).
Normal traffic in EN 1991 is represented by (LM 1),which is the equivalent of HA loading in BD 37.
For each lane, LM1 consists of 2 parts:
7/29/2019 Graeme Walker Design Illustration Concrete
8/20
Traffic Loads Load Model 3
LM3 represents Abnormal Vehicles. The UK NAdefines a series of load models.
The vehicles are applied in the worst position and arecombined with LM1 loads at their frequent values.
4.0m
180kN 180kN 100kN
1.6m 4.4m
Direction of TravelDirection of Travel
165kN 165kN 165kN 165kN 165kN
1.2m 1.2m 1.2m 1.2m
OverallVehicleW
idth
0.35m
0
.35m
3.0m
3.0m
165kN 165kN 165kN 165kN 165kN
1.2m 1.2m 1.2m 1.2m
OverallVehicleW
idth
0.35m
0
.35m
3.0m
3.0m
OverallVehicleW
idth
0.35m
0
.35m
3.0m
3.0m
165
kN
165
kN
165
kN
165
kN
1.2m 1.2m 1.2m
Critical of1.2mor
5.0mor
9.0m
Critical of1.2mor
5.0mor
9.0m
SV 196
7/29/2019 Graeme Walker Design Illustration Concrete
9/20
Traffic Loads Load Model 1
Lanes and remaining area interchangeable for worsteffect
1,3m
Lane 1
Lane 2
Remaining Area
3m
3m
UDL = 0,61 X 9,0 =5,5kN/m2
TS Axle = 1,0 X 300 =300kN
UDL = 2,2 X 2,5 =5,5kN/m2
TS Axle = 1,0 X 200 =200kN
UDL = 2,2 X 2,5 =5,5kN/m2 No TS
7/29/2019 Graeme Walker Design Illustration Concrete
10/20
Traffic Loads Load Model 3
Lanes and remaining area interchangeable for worsteffect
SV/SOV normally replaces lane 2 (or 3+), not lane 1
1,3m
Lane 1
Lane 2
Remaining Area
3m
3m
Frequent value of LM1
Frequent value of
LM1
Frequent value of LM1
SV / SOV
7/29/2019 Graeme Walker Design Illustration Concrete
11/20
Global Design at SLS
As for most prestressed structures, SLS criteriagoverned
3 checks were required:
- Decompression (near tendons)
- Crack widths (elsewhere + in RC)
- Stress limits
7/29/2019 Graeme Walker Design Illustration Concrete
12/20
Decompression
For XD (chloride) exposure, decompression limit ischecked for the frequent load combination
All concrete within the minimum cover distance of thetendons remain in compression
7/29/2019 Graeme Walker Design Illustration Concrete
13/20
Decompression
DecompressionCheck requiredhere! (if a tendon)
Beam section showing strand position
7/29/2019 Graeme Walker Design Illustration Concrete
14/20
Decompression
Same design to BS 5400 resulted in a similar level ofprestress
Same design to EN 1992 but with no chloride exposure
allowed a 25% reduction in prestress
7/29/2019 Graeme Walker Design Illustration Concrete
15/20
Transfer and Tendon Arrangement
Tendon or rebar?
Beam section showing strand position
7/29/2019 Graeme Walker Design Illustration Concrete
16/20
Design at ULS
Flexural design differs little from BS 5400-4
More shear reinforcement required for prestressedmembers
However, interface shear governed in the designexample
(B12 @ 75mm c/f B12 @ 250mm adjacent to supports)
7/29/2019 Graeme Walker Design Illustration Concrete
17/20
Fatigue
Method 1
Cumulative fatigue damage due to the predicted cyclicload history of the structure calculated
Impractical for most structures
7/29/2019 Graeme Walker Design Illustration Concrete
18/20
Fatigue
Method 2 Simplified method
Not applicable to tendons Calculate stress range due to cyclic portion of the
frequent load combination
Allowable to EN 1992-1-1 = 70 MPa
Allowable to PD for this case = 85 MPa
Stress range under frequent load = 128 MPa
50% increase in reinforcement required over pier
7/29/2019 Graeme Walker Design Illustration Concrete
19/20
Fatigue
Method 3 Damage Equivalent Stress Range
Applicable to bars and tendons
Stress range calculated under a special load model
Stress range multiplied by factors reflecting site specificinfluences to give damage equivalent stress range
Stress range under fatigue load model 3 = 96 MPa
Damage equivalent stress range = 140 MPa
Permissible stress range = 141 MPa
No additional reinforcement required
7/29/2019 Graeme Walker Design Illustration Concrete
20/20
Conclusion
Prestressed sections designed to EN 1992 comes outvery similar to those designed to BS 5400 for normal
structures
Same design to EN 1992 but with no chloride exposure
allowed a 25% reduction in prestress