Graduation project, Shahi exports

Embed Size (px)

Citation preview

  • 8/12/2019 Graduation project, Shahi exports

    1/38

    Increasing Efficiency of Small

    Quantity Order (SQO)

    By:

    Praveen Kumar Prabhakar

    Graduation Project

    2009-13

  • 8/12/2019 Graduation project, Shahi exports

    2/38

    Acknowledgement

    Success in any endeavor calls for cooperation and

    guidance from all including seniors and environment.

    I would like to extend our deepest gratitude to industry mentor

    MR. KAMALJEET SINGH (Senior Manager, I.E Department),

    MR. K. RAM MOHAN (Asst. Prof. Nift - College Mentor) for their

    continuous and useful guidance which were the sources of

    inspiration and without which this training have hardly seen

    carried out successfully.

    I would like to extends our thanks to all our faculty and friends

    for supporting through out the way.

    It was a great privilege to work as an internee at SHAHI

    EXPORTS Pvt. Ltd. Faridabad.

  • 8/12/2019 Graduation project, Shahi exports

    3/38

    Company Profile

    NAME Shahi Exports Pvt. Ltd.

    ESTABLISHED 1974

    OWNER Mrs. Sarla Ahuja

    MANAGING DIRECTOR Mr. Harish Ahuja

    CORPORATE OFFICE Industrial Plot-1, Sector 28 Faridabad,

    Haryana

    REGIONAL PROD. UNIT Industrial Plot-1, Sector 28 Faridabad,

    Haryana

    WORK FORCE Around 85,000

    RETAIL HOUSE At Last & Co. , New York

    CAPACITY Over 3.5 million high quality garments per

    month

    FABRIC PROCESSING Sarla Fabrics, Ghaziabad

    ANNUAL TURNOVER 3000+ Crores

  • 8/12/2019 Graduation project, Shahi exports

    4/38

    Shahi Exports Pvt. Ltd., Faridabad

    This manufacturing unit was

    set up by Shahi group of

    industries in 1974.

    This plant is specialized for

    producing kids and women'swear tops.

    This plant was set up with an

    idea to meat the demand of US

    market and European market It has 50 lines with integrated

    washing unit.

  • 8/12/2019 Graduation project, Shahi exports

    5/38

    Introduction

    Production loss during building expertise iscommon but, in present scenario of frequentstyle change, small order size, complex

    specification of garments has forced us torethink about our conventional approach thatwe follow in changing from one style to other(starting new style).

    We need to be more efficient and specificabout learning period for specific style orclass of product.

  • 8/12/2019 Graduation project, Shahi exports

    6/38

    Need of the project

    Need

    FrequentStyle

    Change

    SmallOrder

    Quantity

    LabourProblem

    To ImproveProductivity

    Stiff

    Competition

    ComplexDesign

  • 8/12/2019 Graduation project, Shahi exports

    7/38

    Project Objectives

    To achieve better efficiency specially SOQ

    To reduce throughput time

    Formation of targeted efficiency matrix a/qto order quantity and SAM.

    Finding the bottle neck factor and

    developing expertise in it.

    To create a pro-active environment.

  • 8/12/2019 Graduation project, Shahi exports

    8/38

    Scope

    ofProject

    It can be used for specialization.

    Data and information can be used for

    other increasing productivity project.It can be used to identification criticaloperation and its solution.

    It can be source of information for

    need of training.

    It can be used determining incentivesscheme.. etc.

    Scope of Project

  • 8/12/2019 Graduation project, Shahi exports

    9/38

    Project Boundary

    My project will deals with only Production Planning,Industrial Engineering, and Stitching Department.

    Its assumed that other allied departments likecutting, sourcing, HR etc. are working with due co-ordination.

    Project would be for any particularly for ShahiExports Pvt. Ltd. Main unit. however it can be alsoused for others with modification as needed.

    It would purely based on information and ordersavailable at particular unit during my project.

  • 8/12/2019 Graduation project, Shahi exports

    10/38

    1 week

    3 weeks

    2 weeks

    Review of result and follow

    through and documentationImplementation

    Departmental

    Study

    19th May 2014

    1st May 2014

    2 weeks

    15thof April 2014

    1stof April 2014

    Study of existing

    plans and blue prints

    Project progress vs Time

    Project Timeline

  • 8/12/2019 Graduation project, Shahi exports

    11/38

    Time and Action Calendar

  • 8/12/2019 Graduation project, Shahi exports

    12/38

    Project Methodology

    ProjectMethodo

    logy

    Specialized lines for small order quantities

    Right order to right line through right prod. Planning

    Real Time information system

    Developing experts for critical operations

    Actual time study and line study for balancing of line

    Developing experts for critical operations

    Off standard time and work needs to be calculated.

  • 8/12/2019 Graduation project, Shahi exports

    13/38

    Resources Required.

    Sponsorship and manpower.

    Daily production reports.

    Information about previous andconfirmed orders.

    Skill Matrix.

    Continuous Support and

    Guidance.

  • 8/12/2019 Graduation project, Shahi exports

    14/38

    STUDY OF SAMPLE ORDERS

    Study, Problem analysis and devising solutions.

  • 8/12/2019 Graduation project, Shahi exports

    15/38

  • 8/12/2019 Graduation project, Shahi exports

    16/38

    Report U334

    Date Target

    Quantity

    Quantity

    Produced

    SAM

    Available

    SAM

    Produced

    Efficiency Over

    Time hrs

    20/02/13 453 0 19200 0 0 -

    21/02/13 453 0 19200 0 0 -

    22/02/13 453 0 19200 0 0 -

    23/02/13 453 75 19920 2504 12.62 12

    25/02/13 453 150 19800 5009 25.24 10

    26/02/13 453 200 20400 6679 32.74 20

    27/02/13 453 200 20400 6679 32.74 20

    28/02/13 453 200 20520 6679 32.52 22

    01/03/13 453 100 20400 3339 16.34 20

    02/02/13 453 112 20400 3740 18.33 20

    Summary 4530 1037 199540 34429 17.05 124

  • 8/12/2019 Graduation project, Shahi exports

    17/38

    Efficiency Curve U334

  • 8/12/2019 Graduation project, Shahi exports

    18/38

  • 8/12/2019 Graduation project, Shahi exports

    19/38

    Root Causes of Problems

    RootCausesof

    Problems

    Conventional approach towards all order.

    Longer line set-up.

    Engineered Information.

    Lack of efficiency target on basis of order size and difficulty.

    Lack of co-ordination across departments.

    Lack of R&D for smaller quantity.

    Lack of proper production planning.

    Lack of standard Quality parameters etc

  • 8/12/2019 Graduation project, Shahi exports

    20/38

    Quick Response Team

    Team based approach

    Smaller Orders and Salesman Sample

    Quick Line Setting

    Bottle neck operation instead of OT

    Way Forward

  • 8/12/2019 Graduation project, Shahi exports

    21/38

  • 8/12/2019 Graduation project, Shahi exports

    22/38

    Formation Of quick ResponseTeam

  • 8/12/2019 Graduation project, Shahi exports

    23/38

    Quick Response Team

    Identification of multi skilled operators.

    Planning of style within 20 workstation.

    Setting of line.Making Sub-Team of 4-5 members for diff.

    parts of garment.

    Setting of dedicated resources.

  • 8/12/2019 Graduation project, Shahi exports

    24/38

    Forming Quick Response Team

    (QRT)

    Selecting multiskilled

    operators.

    Preparation ofskill matrix of

    team.

    Making log ofmachinesrequired.

    Selection ofsupervisor,

    writer, helpers,QC etc.

    Communicatingthe goal ofteam to allmembers.

  • 8/12/2019 Graduation project, Shahi exports

    25/38

    Planning Layout of Line

    In this line sitting is face to

    face

    It has sub team of 4-5

    operators for each parts. It has vacant machines in

    between the line.

    It should be having narrow

    center table. It needs single over head

    line

  • 8/12/2019 Graduation project, Shahi exports

    26/38

    Operation Planning

    Operation breakdown needs to be made.

    Combining of similar machine operation.

    Increasing workstation cycle uniform.Making cycle time of each sub group

    uniform.

    Targeting on final out put rather thanindividual.

  • 8/12/2019 Graduation project, Shahi exports

    27/38

    Quick Response Team at Work

    Smaller Line Set-up

    Better control

    Team Based Approach

    Face to Face Sitting

    Spare Machines

  • 8/12/2019 Graduation project, Shahi exports

    28/38

    Quick Response Team at Work

    Better involvement of supervisor,line writer, line in charge etc.

    Motivates Team

    Lesser WIP

    More accountability

  • 8/12/2019 Graduation project, Shahi exports

    29/38

    Advantages of QRT

    Easy visibility of bottleneck operations.

    Lesser through put time.

    Face to face sitting arrangement.

    Better control and involvement of supervisor and line writer.

    Easy to maintain hourly production report.

    Lesser space required.

    Less number of helpers required.

    Better material movement.

    Healthy competitive environment and improved relation ship.

  • 8/12/2019 Graduation project, Shahi exports

    30/38

    Problems

    Supervisor don't take pride in smaller line.

    Efficiency report doesn't take consideration of

    helpers and other extra operators.

    Lack of dedicated infrastructure like proper,center table etc.

    Lack of proper skill matrix.

    Fluctuation in per day output of line.

  • 8/12/2019 Graduation project, Shahi exports

    31/38

    Outcomes

  • 8/12/2019 Graduation project, Shahi exports

    32/38

    Pilot run Quick Response Team

    Order Quantity: 2400

    Sam: 14.99 min.

    Loading Line: 23

    Manpower:

    Operator:20

    Helper: 4

    Checker: 2Avg. Eff.: 34.4%

  • 8/12/2019 Graduation project, Shahi exports

    33/38

    Second Pilot Run on Line 7

    Sam: 14.67 Min

    Average efficiency:59%

    Man Power:

    Operator: 42

    Helper: 10

    Checker: 4

    Supervisor:1

    QE- 1

  • 8/12/2019 Graduation project, Shahi exports

    34/38

    Day1

    Day2

    Day3

    Day4

    Day5

    Day6

    Day7

    Day8

    Day9

    Loss 77 55.9 36.6 28.4 25.6 35.3 40.3 41 38.6

    Efficiency 23 44.1 63.4 71.6 74.4 64.6 59.7 59 61.3

    0%

    10%20%

    30%

    40%

    50%

    60%

    70%80%

    90%

    100%

    Efficiency

    Line 7

    Comparison

    Sam: 14.99Order Quantity: 3200

    Avg. Eff.: 29.7%

    Day1

    Day2

    Day3

    Day4

    Day5

    Day6

    Day7

    Day8

    Day9

    Loss 85.8 84.7 82.1 80.1 66.5 65.3 57.4 51.4 55.8

    Efficiency 14.2 15.3 13.9 19.9 33.5 34.7 42.6 49.6 44.1

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Efficiency

    Line 10

    Sam: 14.67 MinOrder Quantity: 2800

    Avg. Eff.: 59.1%

  • 8/12/2019 Graduation project, Shahi exports

    35/38

    Pre Vs. Post Efficiency

  • 8/12/2019 Graduation project, Shahi exports

    36/38

    Conclusion

    Productivity loss at time of change over is

    among the biggest loss on production floor of

    Garment Manufacturing Unit specially when

    order quantity is small and complexity level isrelatively high.

    However it can be reduced to a great extent

    with dedicated lines, a team based approach,

    real time information, proper R&D and properPre-production planning etc.

  • 8/12/2019 Graduation project, Shahi exports

    37/38

    Bibliography

    en.wikipedia.org/wiki/Lean_manufacturi

    ng

    en.wikipedia.org/wiki/Toyota_Productio

    n_System

    www.shahi.co.in/home.htm

    www.stitchworld.net

    www.apparelresources.com

  • 8/12/2019 Graduation project, Shahi exports

    38/38

    Thank You!!!