35
Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E.

Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Embed Size (px)

Citation preview

Page 1: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Grade Separation Alternative

A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive

By: Daniel Aruta, P.E.

Page 2: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Topics for Discussion:• What is a Grade Separation?

• Construction Impacts

• Traffic Analysis

• Environmental Impacts

Page 3: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

PART 1: What is a Grade Separation?• A facility which provides a physical vertical separation between two

roadways crossing each other to alleviate traffic congestion and promote safety

• One roadway passes over another crossing roadway, and both roadways do not meet

• The upper roadway crosses over the lower roadway via a bridge

• Similar to a diamond interchange on a freeway

• A Grade Separation is not a tunnel!

University Avenue in Park Slope

Page 4: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Sample of a Grade SeparationDiamond Interchange of Interstate 15 at El Cajon Blvd in San Diego

Interstate-15

El Cajon Blvd

Off

Ram

p

Page 5: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

5 Basic Elements of a Grade SeparationInterstate 15 at El Cajon Blvd in San Diego

Retaining Wall

Bridge

RetainingWall

DepressedRoadway

Ramp

Page 6: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

5 Basic Elements of a Grade SeparationInterstate 15 at El Cajon Blvd in San Diego

BridgeRetaining

Wall

RetainingWall

DepressedRoadway

Ramp

Page 7: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Genesee Ave Grade Separation at Governor Dr• Bridge on Governor Dr passes over Genesee Ave below• 2 Lanes on Genesee Ave are depressed to pass under the bridge• 4 Ramps• Inside Retaining Walls (4 each)• Outside Retaining Walls (minimum of 4 each)• Total Length from end to end = 1,787 ft.

Plan View

No

rth

Bridge

Inside Retaining Wall

Outside Retaining Wall

Depressed Roadway

Begin Walls Begin Walls

Ramp

Page 8: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Vertical Separation• Governor Dr above Genesee Ave• 2 inside lanes of Genesee Ave below Governor Dr• A bridge over a depressed roadway

Vertical Profile View

GovernorDrive

Genesee

Avenue

Depressed Roadway

Vertical Scale is Exaggerated!

Begin Grade Separation End Grade Separation

Existing Roadway

Page 9: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Section Through Bridge

• Length of Bridge (Span) = > 50 ft.• Width of Bridge = ± 110 ft.

Section where Genesee Ave passes under the bridge at Governor Dr

Section View

Page 10: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Section Through Retaining Walls

Section View

Section of Genesee Ave north and south of Governor Dr (beyond bridge)

Page 11: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Lengths of Retaining Walls

• South of Governor Dr: 731 ft. long, max height greater than16.5 ft.

• North of Governor Dr: 936 ft. long, max height greater than16.5 ft.

Inside Retaining Walls:

Plan View

731’ 936’

No

rth

Page 12: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Part 2: Construction Impacts• Utility Relocation

• Constructing the Bridge

• Constructing the Retaining Walls

• Road Closures

• Environmental Impacts

• Project Duration

Page 13: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Utility Relocation• Two 16” Water Mains• 8” Sewer• Electrical Duct Bank• Gas Line• Phone Cables

N

Water

Wate

r

Sewer

Elect

Gas

Phone

Phone

Genesee Ave

Go

vern

or

Dr

Page 14: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Constructing the Bridge• Drive Sheet Piling into the Ground

Section View

Sheet Piling

Page 15: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Constructing the Bridge• Drive Sheet Piling into the Ground

• Excavate Pit for the Bridge

Section View

Page 16: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Constructing the Bridge• Drive Sheet Piling into the Ground

• Excavate Pit for the Bridge

• Construct the Bridge

Section View

Page 17: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Constructing the Retaining Walls• Drive Sheet Piling into the Ground

• Excavate Channel

• Construct Inside Retaining Walls and Depressed Roadway

• Construct Outside Retaining Walls for Sideslopes and Outside Roadways

Section View

Page 18: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Extent of Sheet Piling in Genesee Ave

Plan View

No

rth

Sheet Piling

Depressed Roadway

For Depressed Roadway: Approx. 1,100 ft. each side of depressed roadFor Outer Retaining Walls: Lengths will vary

Page 19: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Environmental Impacts to Consider During Construction

• Noise

• Vibration

• Air Quality

• Truck Trips

• Contaminated Soils

• Backup Bells on Construction Equipment

• Driving Sheet Piling

• Diesel Exhaust from Construction Equipment

• Thousands of Truck Trips

• Soils Mitigation from 4 Gas Stations – Project Delay

Impact

Example

Page 20: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Project Duration• Utility Relocation = 6± months

• Mitigation of Contaminated Soils = ?

• Construction of Grade Separation = 2± years

• Total Project Duration = 2.5+ years

Page 21: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Road Closures during Construction

• Genesee Ave from Radcliff La to south of University City HS

• Intersection of Governor Dr and Genesee Ave

Plan View

1,800 ft.

No

rth

• Disruption to Vehicular and Pedestrian Traffic• Loss of Access to Schools and Businesses• Economic Hardship on Local Businesses• Huge Detriment to the Community

Page 22: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

North/South Access during Construction• No Bridge on Regents Rd

• 1,800 ft. of Genesee Ave closed

• Intersection of Governor Dr and Genesee Ave closed

Police, Fire andParamedic Serviceto University City

will be severelychallenged

during construction

Page 23: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Alternate Routes during Construction• Interstate 5 Freeway

• Interstate 805 Freeway

• State Route 52

Detour!

Page 24: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Part 3: Traffic Analysis – Post Construction• Existing Traffic Movements at Intersection of Genesee & Governor

• Proposed Traffic Movements at Intersection of Genesee & Governor

• Level of Service and Lane Reductions at Split Points

• Elimination of Bus Stops

Page 25: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Existing N-S Traffic Lanes at Intersection• 2 Southbound Through Lanes• 2 Left Turns – SB Genesee to EB Governor• 1 Southbound Right Turn• 2 Northbound Through Lanes• 1 Left Turn – NB Genesee to WB Governor• 1 Northbound Right Turn

Existing Intersection

Page 26: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Proposed N-S Traffic Lanes at Intersection• 1 Southbound Combined Through/Right Turn Lane• 1 Left Turn – SB Genesee to EB Governor• 1 Northbound Combined Through/Right Turn Lane• 1 Left Turn – NB Genesee to WB Governor

Grade Separation

Page 27: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

UC Golden Says:

…and…

Do The Math:

NB: 78% of 33,000 = 25,740 ADTSB: 70% of 33,000 = 23,100 ADT

Page 28: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Street Classification and Level of Service (LOS)• Level of Service “E” = 10,000 ADT for 1 Lane• NB Traffic: 25,740 ADT > 10,000 ADT• SB Traffic: 23,100 ADT > 10,000 ADT

NB: 2.57 x Failure Volume

SB: 2.31 x Failure Volume

Page 29: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Lane Reduction at Split PointDecision: Do I take the underpass or do I take the ramp to Governor Dr?

Split Point

1 T

hro

ug

h L

ane

Ram

p to Governor D

r“Governor Dr ”

As most cars from two lanes vie for position into one lane, this will effectively create a “lane reduction” at the split point and traffic will backup!

UC Golden:

Page 30: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

3 Bus Stops on Genesee Ave are Eliminated

Post Construction

Page 31: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Part 4: Environmental Impacts – Post Const.• Noise

• Neighborhood Character

• Tree Removal

Page 32: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Noise• Sound acoustics are accentuated off retaining walls

• Increase in traffic volumes over time due to urban growth will increase ambient noise levels

Page 33: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Neighborhood Character• University City is a residential community

• Only small retail except for commercial district on Greenwich Dr

• UC is not a major traffic generator like Golden Triangle

• Grade Separation will “urbanizes” the character of the neighborhood

Should future University City appear like this?

Page 34: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

Tree Removal• 88 Conifer Trees

• 22 Eucalyptus Trees

• 5 Sycamore Trees

• 3 Others

118 trees will be removed

Page 35: Grade Separation Alternative A Feasibility Analysis of the Reconfiguration of Genesee Avenue at Governor Drive By: Daniel Aruta, P.E

The End