    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 1

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    1. INVESTIGATIONS AND

    PROSECUTION

    S

    1.1. The Director of Public Prosecutions (DPP)to set up a dedicated team to respond tothe requirements of the investigators.

    X DPP MG Done

    1.2. Analysis and isolation of possible chargeswhich are likely to be proffered on thesuspects.

    X X DPP/ACB MG On- going

    1.3. Investigators and prosecutors from Anti-Corruption Bureau (ACB), Police,Financial Intelligence Unit (FIU), MalawiRevenue Authority (MRA) and Director ofPublic Prosecutions (DPP) strategize onhow to approach these issues.

    X

    DPP MG On-going

    1.4. Strengthening of DPP office by engagingTechnical Assistance (short term and longterm).

    X X DPP Shortterm TA EU

    Long termTA yetto beidentified

    Short term TA expert in fraudand corruption cases, MrKamdoni Nyasulu, has been

    engaged for three months.

    This has been done withfinancial support fromEuropean Union

    Challenges

    Financial and human

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    2/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 2

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    resources Mobility

    1.5. Set up forensic investigation unit withinACB to work with all key stakeholders onthese emerging issues.

    X ACB MG Done

    1.6. Verification of all deleted (suspicious)transactions with suppliers of goods andservices.

    X X ACB/DPP/AGD World

    Bank

    On-going

    1.7. Profiling properties of public officersconnected with the suspicioustransactions.

    X X X ACB MG On-going

    The Bureau continues toprofile properties of suspectswhich include houses,vehicles and farms

    So far we have identified 81companies in connection withthe investigations and 60 ofthese have already beenprofiled

    Challenges

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    3/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 3

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    Timing for cases in court asthere are other competingcases

    1.8. Beefing up the investigation team at ACB. X ACB MGFurthersupportrequired

    Done

    Staff moved from ACB satelliteoffices.

    1.9. Elevation of the corruption cases to highcourt (where there are more competenciesthan in the lower courts).

    X X DPP/ACB MG On-going. Over 35 persons committed to

    High Court through DPP

    32 bail applicationsprocessed, 6 cases committedto High Court and 18 casespending committal to High

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    4/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 4

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    Court (on the Cash Gate)through ACB

    15 Suspects on bail on theK400 million AccountantGeneral Case

    1.10. ACB dialogue with Judiciary to prioritisethe corruption cases.

    X ACB MG Done

    Dialogue held on 23rdSeptember 2013

    1.11. Identification and follow up of componentsof cases that are ready for prosecutionand effecting arrests.

    X X X ACB/DPP MG On-going

    Already filed charges for someof the cases.

    Over 35 persons committed toHigh Court through DPP

    32 bail applicationsprocessed, 6 cases committedto High Court and 18 cases

    pending committal to HighCourt (on the Cash Gate)through ACB

    15 suspects on bail withregards to the AccountantGeneral K400 million Case

    Refer to separate report

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    5/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 5

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    provided

    1.12. Strengthening of the Fiscal and Fraud Unitof the Malawi Police Service bydeveloping capacity in investigations

    X X X Police Fundingyet to beidentified

    Financial and Technicalassistance required

    1.13. Develop capacity for tackling cyber basedcrimes

    X X X Police Fundingyet to be

    identified

    Police currently has nocapacity to handle cyber

    based crimes Financial and technical

    assistance required

    2. AUDITING 2.1. Internal review meeting to prepare for theforensic audit.

    X NAO MG Done

    2.2. Develop TORs for the forensic audit. X NAO DFID Done2.3. Engage a fact finding short term expert. X NAO DFID Done

    Initial comprehensiveassessment of the IFMIScontrol and operationalsystems and identification ofareas of significant risk offraud and abuse was carriedout. This helped in defining the

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    6/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 6

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    scope of the second phase(preliminary forensic audit)

    Report produced and ACBalready has started acting on it

    Way forward

    A Reference Team wasformed to provide regular

    support to the consultants andmonitor progress on the audit

    Members of the ReferenceTeam include NAO (Chair),FIU, ACB, Police, DFID, BHCand World Bank

    2.4. Undertake preliminary forensic audit X NAO DFID Audit is underway Covering 6 months from April

    2013 to September 2013. This

    could be extended to cover 90r 12 months i.e. coveringadditional 3 or 6 months inthe previous fiscal year

    Information gathering anddata analysis, which willprovide clues in how themisappropriation of cash was

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    7/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 7

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    carried out, is in progress

    The report is expected inJanuary 2014.

    The Auditor General has alsotaken on board theinvestigation of the K400

    million.

    2.5. Undertake comprehensive forensic audit. X X NAOFundingyet to beidentified

    ToRs have been developed The situation is being

    reviewed to accelerate thecommencement period forcomprehensive Forensic Auditwork to be in January 2014other than June 2014previously reported. The

    Initial discussion betweenTreasury and Auditor Generalon the funding either frominternal sources or fromDevelopment Partners willcommence this week andonce agreed will immediately

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    8/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 8

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    facilitate the realistic date forcommencement of theforensic audit.

    2.6. Identification of understudy team withinthe NAO.

    X X NAO MG/DFID??

    On- going

    The NAO Team was alreadyidentified and is working

    alongside the ForensicAuditors. The team shall beincreased to ensure smoothtransfer of skills. This will bein the next phase ofcomprehensive Forensic

    Audit.

    2.7. Transfer of the forensic audit skills. X X X NAO/Consultant WorldBank

    The plan of transferring ofskills is being worked out sothat next phase of the

    comprehensive forensic auditup to 2005 should be in place.This coincides with theappointment of the consultantunder FROIP whose terms ofreference are similar to thoseapplied in Forensic Audit.

    Among others to train staff on

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    9/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 9

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    usage of Audit ManagementSystem Software andComputer Aided AuditTechniques (CAATs) tointerrogate the IFMIS softwaresystem.

    2.8. Procure audit management system. X NAO/FROIP WorldBank

    Once the consultant is in placeit is one of his responsibility inorder to procure the IT AuditSoftware and train staff on itsusage to commence byDecember, 2013

    2.9. Undertake spot/surprise audits X DFID This will be covered on adhocbasis to facilitate surprisechecks on IFMIS and will infuture be a continuous

    process once the staff istrained on uses of AuditManagement Systems andCAATs by December, 2013.

    2.10. Acquisition of Computer- Aided Audit X NAO/FROIP World CAATs to be procured under

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    10/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 10

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    Techniques (CAATs) Bank FROIP

    2.11. Introduction of Independent AuditCommittees

    X X X OPC $261,622

    Fundingyet to beidentified

    On-going

    Decision already approved OPC to issue circular by 27th

    November, 2013

    2.12. Strengthen the role of Central InternalAudit

    X X CIAU World

    Bank

    Capacity building on going under

    FROIP e.g. IT auditors

    2.13. Institutionalize pre-auditing X CIAU/AGD MG CIAU to design somechecklists/reports and providecoaching to MDAs by mid-December, 2013 [Non auditingstaff to be doing this function].

    2.14. The Auditor General to table all reportsfrom investigations and special audits inParliament for action by PAC as soon asthey are released.

    MG The reports shall be availableas soon as they are itfinalized. They are expected tobe ready as a preliminary

    interim report by December,2013 but the final to bepresented to Parliament inJanuary, 2014

    3. ACCOUNTING 3.1. Engage the systems supplier, SofTech, to X AGD World Done and the exercise is

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    11/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 11

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    collate all suspicious transactions thathave been tempered with in the system

    Bank continuing.

    The supplier was engagedand has assisted in therecovery of suspectedfraudulent transactions for themonths of July to September2013.

    Way Forward An interim report is being

    finalised and will be submittedto OPC by end of November2013

    3.2. Recover all the transactions that havebeen deleted in the system

    X X AGD WorldBank

    On-going

    Deleted transactions from Julyto September 2013 have beenrecovered and restored back

    into the system. The affectedinstitutions will register overexpenditures that may affecttheir future paymentprocessing.

    Way forward

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    12/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 12

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    The AGD and Treasuryengage on how to remedy theover expenditure situation.

    The confirmed loss to beprocessed through the legalsystem

    3.3. Review the systems security gaps andrecommend areas of improvement X AGD WorldBank Done A preliminary report has been

    submitted. Security features enhancedWay forward

    For accountability purposes,Government and Softech tosign of all the system

    enhancements.

    There is need to conduct athorough Penetration andvulnerability Testing for theIFMIS and Interfacing withgovernment wide systems.

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    13/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 13

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    3.4. Engage the system supplier to implementthe security recommendations andenhance system controls

    X X AGD WorldBank

    Done

    Access rights have beenallocated at user level asopposed to group levelpreviously.

    Restrictions have been madeto only allow users to haveaccess to modules/ areas ofthe system where they havebeen granted access

    Processing of all transactionshas been centrally configuredto be carried out at CapitalHill. However, the remote sites

    of Mzuzu, Blantyre and Zombawill be generating vouchers ,printing cheques at theirrespective sites;

    Remote access to thedatabase has been disabledtherefore no transaction can

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    14/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 14

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    be deleted from the system.Users will only access thesystem through a web consolethrough citrix.

    Way forward

    Malawi Defence Force andState House will be engaged

    to have their transactionsprocessed centrally at CapitalHill. Alternatively, astandalone system should beimplemented.

    3.5. Enter into Service Level Agreement withSoft-tech for provision of functional andtechnical support including overseeing ITfunctions with skills transfer to localofficers

    X WorldBank/GIZ?

    Drafting a Service LevelAgreement

    3.6. Re-opening of IFMIS X AGD MG Done. Circular on allocation of user

    rights issued

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    15/26

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    16/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 16

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    granting access rights. Accesswill be granted after necessaryapprovals have been made

    3.10. Issue a circular to all MDAs on controlssurrounding processing of transactions inthe system

    X AGD MG Done.

    A circular reference numberOA/1/15/13/270 dated 19thSeptember 2013 was issued

    by the Secretary to theTreasury

    Circular issued by AccountantGeneral

    3.11. Issue and enforce internal circularemphasizing controls surroundingpayments and printing of cheques within

    Accountant General Department.

    X AGD MGDone

    3.12. Improving competencies of accountingofficers

    X X AGD World

    Bank

    AAT UK has been engaged to

    conduct training using localinstitutions to enhance ethicalaccounting principles

    Way forward,

    An MoU between GoM andICAM and AAT to be signed

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    17/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 17

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    by December 2013

    3.13. Improving competencies of relevant ICTofficers.

    X X AGD / E-Government

    Dept.

    WorldBank

    A training program has beendeveloped and submitted toFROIP for financing. However, thetraining programme has to be re-re-visited in view of the currentchanges at AGD

    3.14. Develop a comprehensive capacitybuilding plan for the team that issupporting the system

    X AGD WorldBank

    A training program has beendeveloped and submitted toFROIP for financing. However, thetraining programme has to be re-visited in view of the currentchanges at AGD

    3.15. Reconciliation of all Government accountsat RBM and commercial banks byDecember 31, 2013

    X AGD MG/WorldBank

    On-going

    Way forward A team currently working to

    clear backlog of bankreconciliation and futuretransactions in IFMIS on adaily basis.

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    18/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 18

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    A consultant being engagedthrough FROIP to assist AGDteam to set up a framework forbank reconciliation afterclearing the backlog. ToRs forthe consultant are beingdrawn. The Consultant will beplace early January 2014

    3.16. Embark on daily bank reconciliation X X X AGD MG Way Forward Engage RBM to provide bank

    statements on a daily basis

    3.17. Circulate daily IFMIS- generated chequelist to RBM and commercial banks.

    X MG Accountant General and RBM toreview the MOU including thebanking arrangements

    3.18. Develop and implement IFMIS ICTSecurity Policy

    X AGD MG/GIZ

    Way forward,

    Set a task force and engageconsultants on IFMIS SecurityPolicy by December 2013

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    19/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 19

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    3.19. Improve dialogue between RBM,Accountant General and Treasury

    X X X AGD MG On- going.

    Meetings have alreadycommenced

    3.20. Implement systems to enforce ceilings offunding with IFMIS and Reserve Bank ofMalawi.

    X AGD, RBM,Ministry ofFinance

    MG Way forward

    Put up proper structures forsegregation of duties between

    AGD, Treasury (BudgetDivision) and RBM includingappropriate internal controlsand risk managementprocedures

    3.21. Implement new enhanced IFMIS X AGD WorldBank

    1stJuly 2014

    Business Process Re-engineering has beenconcluded

    Functional requirementsbased on the revised businessprocesses have beendeveloped

    An evaluation of potentialIFMIS solutions Epicor andSerenic Navigator applications

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    20/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 20

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    have been concluded

    Way forward,

    Make recommendation togovernment of a new IFMISapplication

    3.22. Independent verification of the IFMISsystem

    3.22.1.Appoint 4- 5 consultants to theAGD to provide oversight and pre-audit services

    X EU EU has offered to finance thisaction point. The independentconsultant will work with a teamcomprising officers from CentralInternal Audit Unit.

    3.23. Carry out an independent audit forpayments made during the tenure of themanual system by end December 2013

    X $60,000

    Fundingyet to beidentified

    Central Internal Audit Unit to carryout the audit as soon as thefinancial resources are madeavailable.

    3.24. Verify the end June stock of arrears andmonitor thereafter

    X MG

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    21/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 21

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    4. ADMINISTRATIVE MEASURES

    4.1. Take disciplinary action on officersimplicated including interdiction anddismissal in line with the MPSR

    4.1.1.Disciplinary action, includingsuspension and administrativeinquiry, against the approvers offraudulent payments and cheque

    signatories

    X X X HumanResource Units

    in variousministries

    MG On-going.

    Upon being arrested bylaw enforcement agenciesand charged by courts oflaw, suspects areinterdicted without payuntil their cases are

    concluded

    4.2. Re-deployment and rotating of staff withinthe civil service.

    X MG

    A number of postings effected Some officers are being

    posted to fill posts in ministrieswhere suspects have beeninterdicted to close gapscreated

    In certain cases, some civilservants whose roles are notvery clear or whereinvestigations are on-going, orwhere negligence has beenproved.

    Officers are posted to otherministries to pave way for full

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    22/26

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    23/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 23

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    Conduct was produced andlaunched during the Public ServiceDay in June, 2013 and will beused during orientation.

    4.6. Independent oversight on theimplementation of this action plan

    4.6.1.Establishment of credible andeffective feedback mechanisms toallow independent monitoring andevaluation of progress achieved inimplementing the action plan

    Irish?? TORs for the independent verifiersdeveloped

    The Ministerial committee to

    endorse the TORs

    5. REFORMS 5.1. Accelerate the implementation of thePublic Finance and EconomicManagement (PFEM)Reform Program

    X X X Ministry ofFinance

    WorldBank/

    AfDB/GIZ

    On-going

    5.2. Money laundering Act amendmentincluding civil assets forfeiture regime

    X FIU/Law

    Commission/Justice

    MG On-going

    Process already started with adraft in place

    Core Team to meet end ofNovember.

    5.3. Set up a Forfeiture Unit in the DPP office X DPP/DHRMD MG/DP On-going

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    24/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 24

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    5.4. Enforce the Malawi Public Service Codeof Conduct

    X OPC/DHRMD MG/UNDP

    On-going

    Controlling Officers, with theguidance by the Departmentof Human ResourceManagement andDevelopment and theDepartment of Public Sector

    Reforms Management, areencouraged to orient their staffon the Code.

    The new office of the Ministerof responsible for GoodGovernance will take the leadin advocating ethicalbehaviour by Public Servants.

    5.5. Initiate a process of the law reviewincluding protection of whistle blowers

    X X X ACB/LawCommission

    MG

    Furthersupportrequired

    On- going

    A law review process hasbeen initiated and asubmission has been made toMinistry of Justice forprofessional scrutiny

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    25/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 25

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    Lobbying with the LegalAffairs Committee ofParliament done

    5.6. Strengthen enforcement of FinancialManagement Accountability of ControllingOfficers and other heads of Departmentand Agency, as well as enforcing personal

    accountability for wrongdoing in line withthe Public Finance Management Act,Public Audit Act, and Public Procurement

    Act.

    X X X OPC MG

    Fundingyet to beidentified

    All Principal Secretaries andControlling Officers shall begiven copies of the laws andoriented in the provisions of

    the tree Acts Independent Audit

    Committees will beestablished and rolled out

    Candidates have beenidentified

    5.7. Tabling of the Assets Declaration bill Justice MG DoneAssets Declaration bill was passedin Parliament

    5.8. Restriction of accounts and move towardsasset recovery

    X X X ACB MG

    Furthersupportrequired

    On-going

    50 bank accounts involved inillegally transactingGovernment cheques have sofar been identified andrestriction is underway

  • 8/12/2019 Government of Malawi Action Plan - 27 November 2013

    26/26

    MALAWI GOVERNMENT ACTION PLAN TO IMPROVE PUBLIC FINANCIAL MANAGEMENTAS AT 26THNOVEMBER 2 13

    P a g e | 26

    RESULT AREA ACTION TIMELINE RESPONSIBLE

    INSTITUTION

    BUDGET

    &

    FUNDING

    SOURCE

    STATUS/ REMARKS

    &

    CHALLENGES

    Short Term

    SepDec

    2013

    MediumTerm

    Jan

    Jun2014

    LongTerm

    Jul 2014onward

    AC continues to restrictaccess to related bankaccounts and the disposal ofsuch properties as houses,vehicles and land underinvestigations